Beal Bank Nevada v. NorthShore Center THC, LLC , 64 N.E.3d 201 ( 2016 )


Menu:
  •                                       
    2016 IL App (1st) 151697
    FIFTH DIVISION
    September 30, 2016
    No. 1-15-1697
    )
    BEAL BANK NEVADA,                                              )
    )    Appeal from the
    Plaintiff,                                     )    Circuit Court of
    )    Cook County
    v.                                                             )
    )
    NORTHSHORE CENTER THC, LLC, et al.,                            )
    )
    Defendants.                                    )
    )    No. 08 CH 39446
    )
    LAKE COUNTY GRADING COMPANY, LLC,                              )
    )
    Counterplaintiff-Appellant,                    )
    )
    v.                                                             )    Honorable
    )    Anthony C. Kyriakopoulos,
    FCL INVESTORS, INC., formerly known as                         )    Judge Presiding.
    FCL BUILDERS, INC.,                                            )
    )
    Counterdefendant-Appellee.                     )
    JUSTICE REYES delivered the judgment of the court, with opinion.
    Presiding Justice Gordon and Justice Lampkin concurred in the judgment and opinion.
    OPINION
    ¶1     This appeal addresses the issue of whether a contractor is liable for amounts due to a
    subcontractor if the property owner fails to make payment to the contractor for the
    subcontractor's work. The circuit court of Cook County granted summary judgment in favor of
    contractor FCL Investors, Inc., formerly known as FCL Builders, Inc. (Contractor), and against
    1-15-1697
    subcontractor Lake County Grading Company, LLC (Subcontractor) on the Subcontractor's
    breach of contract claim. Applying A.A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp., 
    132 Ill. App. 3d 325
    (1985) (Conte), the circuit court found that the provisions of the parties'
    subcontract "clearly make the receipt of payment from the [property owner] to [the Contractor],
    the condition precedent to [the Subcontractor's] payment." The circuit court concluded that the
    condition precedent has not been satisfied because the Contractor has not received payment from
    the property owner. As discussed below, we reverse the judgment of the circuit court.
    ¶2                                       BACKGROUND
    ¶3     As the circuit court proceedings were lengthy and complex, we provide only the facts
    necessary for the disposition of this appeal. In 2006, Northshore Center THC, LLC (Owner)
    borrowed funds from BankFirst, secured by notes and a mortgage, to develop real estate in
    Northbrook, Illinois. The Owner and the Contractor entered into a contract (contract), for the
    Contractor to perform certain construction work at the Northbrook site. The Contractor and
    Subcontractor entered into a subcontract (subcontract), for the Subcontractor to provide
    excavation, sewer line installation and other construction services.
    ¶4     After performing a portion of its work under the subcontract, the Subcontractor issued an
    invoice to the Contractor for $130,343.40; the said amount was tendered by the Owner. The
    Subcontractor subsequently issued additional invoices and payment requests to the Contractor
    for additional amounts totaling $775,872.60 for work performed under the subcontract.
    Although the Contractor submitted the invoices for payment to the Owner, the requests were
    refused and the Owner failed to pay. The Subcontractor recorded a subcontractor's claim for lien
    against the Contractor and the Owner on February 4, 2008, in the amount of $775,872.60. The
    Contractor recorded a contractor's claim for lien on November 26, 2008, claiming an outstanding
    2
    1-15-1697
    balance of $943,494.53 – which included the amount due to the Subcontractor.
    ¶5     BankFirst filed a foreclosure complaint against the Owner in the circuit court of Cook
    County in October 2008. The complaint also named various parties with interests in the
    mortgaged real estate as defendants, including the Contractor and the Subcontractor. The
    Subcontractor filed an answer and a counter-complaint, which included a breach of contract
    claim against the Contractor. The affirmative defense asserted by the Contractor was basically
    that the subcontract provides that payment by the Owner to the Subcontractor is a condition
    precedent to any obligation by the Contractor to pay the Subcontractor. In response, the
    Subcontractor argued that the Contractor's affirmative defense is prohibited by section 21(e) of
    the Mechanics Lien Act (770 ILCS 60/21(e) (West 2008)), discussed below.
    ¶6     Beal Bank Nevada (bank) – substituted as plaintiff for BankFirst – filed a second
    amended complaint in November 2009. In March 2011, the Subcontractor and the bank entered
    into a settlement agreement wherein the Subcontractor agreed to release its mechanics lien in
    exchange for $475,000. As a result of the settlement, the principal balance sought by the
    Subcontractor was reduced to $300,872.60. The Contractor subsequently secured a judgment
    against the Owner in the amount of $943,494.53. By that time, however, the Owner had ceased
    its operations and had been involuntarily dissolved. Although the Contractor's counsel later
    transmitted an "assignment" of its judgment against the Owner to the Subcontractor's counsel, a
    stipulation in the record indicates that "[the Subcontractor] did not request and did not agree to
    take assignment of [the Contractor's] judgment against the Owner."
    ¶7     In June 2011, the court entered a judgment of foreclosure and sale with respect to the
    Northbrook property in favor of the bank. On the bank's motion, the court subsequently
    amended the judgment to reflect that the Contractor's liens – recorded more than four months
    3
    1-15-1697
    after the completion of work – were subordinate and inferior to the bank's mortgage.
    ¶8     In November 2013, the Contractor and the Subcontractor filed cross-motions for
    summary judgment. The Subcontractor's motion acknowledged that the parties had filed prior
    cross-motions for summary judgment, that the court previously found that certain questions of
    fact precluded judgment on the sole remaining count – breach of contract (Count III) – of the
    Subcontractor's counter-complaint, and that the parties had since engaged in substantial
    discovery and entered into stipulations in an effort to eliminate any material question of fact.
    ¶9     The circuit court subsequently entered an order denying the Subcontractor's motion for
    summary judgment and granting the Contractor's motion for summary judgment. The court
    rejected the Subcontractor's contention that the Contractor was "barred from bringing the
    condition precedent as a contractual defense due to the alleged representations and warranties
    breached by [the Contractor]," i.e., an alleged statement from the Contractor's representative to
    the Subcontractor's representative that funding had already been secured from the Owner. The
    court determined that the Contractor's "failure to confirm [the Owner's] funds before allowing
    [the Subcontractor] to begin performance" could not be considered a breach "as there is nothing
    in the four corners of the contract making [the Contractor's] confirmation of funds a term or part
    of performance."
    ¶ 10   After quoting portions of sections 5.1 and 5.2 of the subcontract, the court further found
    that Conte "is controlling on the instant case," noting that the "payment provision in the
    subcontract" in Conte was "nearly identical to the provision in the Subcontract at issue in the
    case at bar." Sections 5.1 and 5.2 provide in part:
    "[5.1] Provided Subcontractor's rate of progress and general performance
    are satisfactory to the Contractor, and provided that the Subcontractor is in full
    4
    1-15-1697
    compliance with each and every provision of the Subcontract Documents, the
    Contractor will make partial payments to the Subcontractor in an amount equal to
    90 percent of the estimated value of work and materials incorporated in the
    construction and an amount equal to 90 percent of the materials delivered to and
    suitably and properly stored by the Subcontractor at the Project site, to the extent
    of Subcontractor's interest in the amounts allowed thereon and paid to Contractor
    by the Owner, less the aggregate of previous payments, within five (5) days of
    receipt thereof from the Owner[.] ***
    [5.2] Final payment will be made within thirty (30) days after the work
    called for hereunder has been completed by the Subcontractor to the satisfaction
    of the Owner and the Contractor and the Contractor has received from the Owner
    written acceptance thereof together with payment in full for this portion of the
    work[.] ***"
    ¶ 11   The circuit court concluded:
    "The provisions outlined in the Subcontract at issue clearly make the receipt of
    payment from the Owner to [the Contractor], the condition precedent to [the
    Subcontractor's] payment. The condition precedent has not been satisfied as [the
    Contractor] has not received payment from Owner. Therefore, [the Contractor]
    did not breach the contract, and [the Subcontractor's] claim fails. Accordingly,
    [the Contractor] is entitled to summary judgment in its favor as [the
    Subcontractor] cannot recover on the subcontract."
    The circuit court further observed that it did not need to consider extrinsic evidence because the
    language of the subcontract was clear, but "even if it did, [the Contractor's] and [the
    5
    1-15-1697
    Subcontractor's] course of performance is consistent with both parties' recognition that payment
    from the Owner to [the Contractor] was a condition precedent to [the Subcontractor] receiving
    payment." After the circuit court denied its motion for reconsideration, the Subcontractor filed
    this timely appeal.
    ¶ 12                                         ANALYSIS
    ¶ 13   In this appeal, we are reviewing the circuit court's ruling on cross-motions for summary
    judgment. Summary judgment is appropriate "if the pleadings, depositions, and admissions on
    file, together with the affidavits, if any, show that there is no genuine issue as to any material fact
    and that the moving party is entitled to a judgment as a matter of law." 735 ILCS 5/2-1005(c)
    (West 2014). Summary judgment rulings are reviewed de novo. Christopher B. Burke
    Engineering, Ltd. v. Heritage Bank of Central Illinois, 
    2015 IL 118955
    , ¶ 9.
    ¶ 14   The fundamental issue in this case is whether the parties' subcontract requires the
    Contractor to pay the Subcontractor. While the parties herein interpret the subcontract
    differently, such disagreement "does not suffice to establish ambiguity." Gomez v. Bovis Lend
    Lease, Inc., 
    2013 IL App (1st) 130568
    , ¶ 14. "A contract is ambiguous if it is subject to more
    than one reasonable interpretation." 
    Id. Although extrinsic
    evidence may be used to aid in the
    interpretation of an ambiguous contract, such evidence may not be used to interpret a contract
    that is unambiguous on its face. 
    Id. The construction
    of a contract presents a question of law,
    which we review de novo. Gallagher v. Lenart, 
    226 Ill. 2d 208
    , 219 (2007).
    ¶ 15   As the circuit court correctly recognized, the Conte decision is relevant to our
    interpretation of the subcontract at issue. The parties disagree regarding the applicability and
    effect of the case. In Conte, the contractor and subcontractor entered into a subcontract relating
    to excavation work. 
    Conte, 132 Ill. App. 3d at 326
    . The owner defaulted and the project
    6
    1-15-1697
    terminated; the subcontractor was owed approximately $84,000 for work already performed. 
    Id. at 326-27.
    After failing to recover on its mechanics lien claim against the Owner, the
    subcontractor sued the contractor for the $84,000. 
    Id. at 327.
    In an affirmative defense, the
    contractor argued that the parties' subcontract set forth a condition precedent to payment, i.e.,
    that the contractor must first receive payment from the owners of the project under the general
    contract before it was obligated to pay its subcontractors. 
    Id. The Conte
    subcontract included
    the following provisions:
    " 'ARTICLE 5: Material invoices submitted before the 25th of the current month
    will be paid by the 28th of the following month, provided the material so
    delivered is acceptable, and if payment for invoiced material has been received by
    [the contractor] under its general contract. ***
    ***
    ARTICLE 18: *** [I]f the work has been satisfactorily performed and invoice as
    rendered is approved and if payment for such labor and material so invoiced has
    been received by [the contractor] under its general contract, the subcontractor
    will be paid 85% of invoice as approved, less any payments previously made on
    account for previous periods. ***' " (Emphasis in original.) 
    Id. at 327-28.
    The court granted summary judgment in favor of the contractor and against the subcontractor.
    
    Id. at 328.
    On appeal, the subcontractor argued that the provisions were a limitation only as to
    the time of payment and urged the court to examine factors outside of the subcontract to
    determine the parties' understanding and intent. 
    Id. The contractor
    responded that the provisions
    created a condition precedent to payment and there was no ambiguity in the subcontract. 
    Id. ¶ 16
      In affirming the judgment of the circuit court, the Conte appellate court stated: "We do
    7
    1-15-1697
    not believe that the record supports [the subcontractor's] claim that its right to payment by [the
    contractor] was absolute and not in anyway contingent upon [the contractor's] receiving payment
    from the owners under the general contract." 
    Id. at 329.
    Although the court acknowledged that
    "conditions precedent are not generally favored, and courts will not construe stipulations to be a
    condition precedent when such a construction would result in forfeiture," it found that the "plain,
    unambiguous language" in the subcontract "binds the parties to a condition precedent." 
    Id. ¶ 17
       The dissenting opinion in Conte discussed section 227 of the Restatement (Second) of
    Contracts, "Standards of Preference with Regard to Conditions," which states: "(1) In resolving
    doubts as to whether an event is made a condition of an obligor's duty, and as to the nature of
    such an event, an interpretation is preferred that will reduce the obligee's risk of forfeiture, unless
    the event is within the obligee's control or the circumstances indicate that he has assumed the
    risk." Restatement (Second) of Contracts § 227 (1981). The dissent wrote that comment (b) to
    section 227 of the Restatement states "that the word 'forfeiture' is used to refer to the denial of
    compensation that results in such a case." 
    Conte, 132 Ill. App. 3d at 330
    (Jiganti, J., dissenting),
    citing Restatement (Second) of Contracts § 227, comment b, at 175 (1981). The dissent noted
    that the "very first illustration" for comment (b) to section 227 "is a virtual reiteration of the facts
    in the instant case." 
    Conte, 132 Ill. App. 3d at 330
    -31. The illustration states:
    "1. A, a general contractor, contracts with B, a sub-contractor, for the plumbing
    work on a construction project. B is to receive $100,000, 'no part of which shall
    be due until five days after Owner shall have paid Contractor therefor.' B does
    the plumbing work, but the owner becomes insolvent and fails to pay A. A is
    under a duty to pay B after a reasonable time." Restatement (Second) of
    8
    1-15-1697
    Contracts § 227, comment b, at 176 (1981). 1
    The dissent concluded that the Restatement (Second) of Contracts, and cases from other
    jurisdictions that ruled in accordance with the Restatement, "mandate[d] a finding consistent
    with their conclusions." 
    Conte, 132 Ill. App. 3d at 331
    .
    ¶ 18      The Contractor here contends that the "interpretive principle" set forth in section 227 of
    the Restatement "comes into play only if the court has doubts as to whether the contract language
    specifies a condition precedent." Illinois courts have defined a condition precedent as "an event
    which must occur or an act which must be performed by one party to an existing contract before
    the other party is obligated to perform." Maywood Proviso State Bank v. York State Bank &
    Trust Co., 
    252 Ill. App. 3d 164
    , 168 (1993). "The obligations of the parties end in the event that
    a condition precedent is not satisfied." 
    Id. ¶ 19
         According to the Contractor, the language of the subcontract in this case – like the
    language at issue in Conte – was "clear and unambiguous in setting out a condition precedent,"
    i.e., because the Owner did not pay, the Contractor is not obligated to pay the Subcontractor. As
    we do not read the parties' subcontract as establishing such a condition precedent, we reject the
    Contractor's position. Section C of the parties' subcontract provides that "[t]he Contractor agrees
    to pay the Subcontractor for the full, faithful and complete performance of this Subcontract the
    sum of $817,000 subject to additions and deductions for changes agreed upon in writing signed
    by FCL BUILDERS, INC or determined as hereinafter set forth, and further agrees to make all
    partial and final payments on account thereof solely in accordance with the terms and provisions
    of the Subcontract Documents including, but without restriction thereto, the provisions of
    Section D, Article 5 of this Subcontract." (Emphasis added.) Based on the "and further agrees"
    1
    We quote the illustration, which was paraphrased by Justice Jiganti in his Conte dissent.
    9
    1-15-1697
    language, we read this provision as reflecting two separate obligations of the Contractor: to pay
    an amount to the Subcontractor for "full, faithful and complete performance" of the subcontract
    and to make partial and final payments on account thereof solely in accordance with the
    subcontract documents, including Article 5 of the subcontract.
    ¶ 20   Section 5.1 in Section D, Article 5 provides, in part, that "the Contractor will make partial
    payments to the Subcontractor in an amount equal to 90 percent of the estimated value of work
    ***, to the extent of Subcontractor's interest in the amounts allowed thereon and paid to
    Contractor by the Owner, less the aggregate of previous payments, within five (5) days of receipt
    thereof from the Owner[.]" Section 5.2 of the subcontract provides, in part: "Final payment will
    be made within thirty (30) days after the work called for hereunder has been completed by the
    Subcontractor to the satisfaction of the Owner and the Contractor and the Contractor has
    received from the Owner written acceptance thereof together with payment in full for this portion
    of the work[.]" Unlike in Conte, wherein the subcontractor would be paid "if" the contractor was
    paid by the owner, there is no express language in the subcontract at issue which plainly and
    unambiguously establishes payment by the Owner as a condition precedent to the Contractor's
    obligation to pay the Subcontractor. Consistent with section C of the subcontract, we interpret
    the language of sections 5.1 and 5.2 as addressing the amounts and timing of payments, but not
    the threshold obligation of the Contractor to compensate the Subcontractor for its work under the
    subcontract. Such interpretation is further bolstered by section 5.4 of the subcontract, which
    provides that "[n]otwithstanding the amounts and times of payments set forth above, the
    Contractor at any time may make advance payments to the Subcontractor if, in the Contractor's
    sole discretion, such advances will aid the Subcontractor in the performance of this Subcontract."
    (Emphasis added.) Section 5.4 supports the interpretation that sections 5.1 and 5.2 address the
    10
    1-15-1697
    mechanics of payment, but not the fundamental requirement that the Contractor pay the
    Subcontractor.
    ¶ 21   Citing Killianek v. Kim, 
    192 Ill. App. 3d 139
    (1989), and Coey v. Lehman, 
    79 Ill. 173
    (1875), the Contractor argues that "[w]here a construction contract specifies an event that is to
    occur before a payment obligation arises, the specified event is deemed a condition precedent to
    the payment obligation." In Killianek, a homeowner's contract with a contractor provided:
    " 'Final payment, constituting the entire unpaid balance of the Contract Sum, shall be paid by the
    Owner to the Contractor when the work has been completed, the contract fully performed, and a
    final Certificate for Payment has been issued by the Architect.' " 
    Killianek, 192 Ill. App. 3d at 141
    . The homeowner argued that "inasmuch as the contractor has not provided him with a final
    certificate for payment" pursuant to their contract, "the lack of compliance therewith amounts to
    an unfulfilled condition precedent, and there is no obligation on him to perform," i.e., to make
    the final payment under their contract. 
    Id. The appellate
    court agreed with the homeowner,
    finding that the parties "were bound by the underlying agreement, save that the obligation of the
    owner to make final payment is not binding as it was the subject matter of a condition precedent
    which was never satisfied." 
    Id. at 143.
    ¶ 22   In Coey, the contract between the contractor and certain subcontractors provided that
    85% of the contract price was to be paid as the work progressed and the 15% balance was to be
    paid upon acceptance of the work by the superintending architect. 
    Coey, 79 Ill. at 175
    . The
    architect ultimately found the work and materials to be unsatisfactory and thus did not provide
    the certificate for payment of the 15% balance. 
    Id. at 175-76.
    The trial court ruled in favor of
    the subcontractors. 
    Id. at 174.
    The Illinois Supreme Court reversed, noting that "where the
    parties to a building contract agree that the superintendent shall pass upon the work, and certify
    11
    1-15-1697
    to the payments to be made, his decision is binding, unless fraud or mistake on his part shall be
    shown." 
    Id. at 176.
    ¶ 23   Killianek and Coey do not guide our analysis herein. In both cases, the condition
    precedent was approval by the architect. The imposition of such a requirement as a condition
    precedent to a payment obligation appears logical and practical: a contractor or homeowner
    presumably should not be obligated to pay for work or materials that may be unsafe or otherwise
    unsatisfactory. Furthermore, the proper completion of work in Killianek and Coey likely was
    within the control of the party subject to the condition precedent. Conversely, the parties herein
    have stipulated that "[the Subcontractor] performed, in a good and workmanlike manner, all the
    work and provided all the materials requested by [the Contractor] in connection with the
    Subcontract." As stated by the Conte majority, "[c]onditions precedent are not generally
    favored, and courts will not construe stipulations to be a condition precedent when such a
    construction would result in forfeiture," i.e., denial of compensation. 
    Conte, 132 Ill. App. 3d at 329
    ; accord Premier Electrical Construction Co. v. American National Bank of Chicago, 276 Ill.
    App. 3d 816, 824-25 (1995). Without clear language indicating the parties' intent that the
    Subcontractor would assume the risk of non-payment by the Owner, we will not construe the
    challenged language in the subcontract as a condition precedent.
    ¶ 24   Although not binding, the decision of the Seventh Circuit Court of Appeals in BMD
    Contractors, Inc. v. Fidelity and Deposit Co. of Maryland, 
    679 F.3d 643
    (7th Cir. 2012), sets
    forth a useful framework for our analysis. The BMD court, applying Indiana law, considered
    whether a contractor's 2 surety was obligated to pay a subcontractor after the owner's bankruptcy
    triggered "a series of payment defaults to flow down the levels of contractors and
    2
    The BMD "contractor" was itself a subcontractor in the multi-tiered construction project. For
    clarity purposes, we refer to this entity as the "contractor."
    12
    1-15-1697
    subcontractors." 
    Id. at 645.
    The subcontract at issue provided, in part: "IT IS EXPRESSLY
    AGREED THAT OWNER'S ACCEPTANCE OF SUBCONTRACTOR'S WORK AND
    PAYMENT TO THE CONTRACTOR FOR THE SUBCONTRACTOR'S WORK ARE
    CONDITIONS PRECEDENT TO THE SUBCONTRACTOR'S RIGHT TO PAYMENTS
    BY THE CONTRACTOR." (Emphasis in original.) 
    Id. at 647.
    The Seventh Circuit held that
    because the contractor was never obligated to pay the subcontractor, the subcontractor could not
    recover against the surety on the payment bond. 
    Id. at 646.
    In so holding, the court discussed
    the distinction between "pay-if-paid" and "pay-when-paid" provisions:
    " *** Two increasingly common contractual provisions address distinct kinds of
    payment risk in construction subcontracting: pay-if-paid clauses and pay-when-
    paid clauses.
    A pay-when-paid clause governs the timing of a contractor's payment
    obligation to the subcontractor, usually by indicating that the subcontractor will
    be paid within some fixed time period after the contractor itself is paid by the
    property owner. A typical clause might say: 'Contractor shall pay subcontractor
    within seven days of contractor's receipt of payment from the owner.' Robert F.
    Carney & Adam Cizek, Payment Provisions in Construction Contracts and
    Construction Trust Fund Statutes, 24 CONSTRUCTION LAW, Fall 2004, at 5, 5.
    These clauses address the timing of payment, not the obligation to pay. They do
    not excuse a contractor's ultimate liability if it does not receive payment by the
    property owner, so they do not transfer the risk of 'upstream' insolvency from
    contractor to subcontractor and on down the chain.
    In contrast, a pay-if-paid clause, as the name suggests, provides that a
    13
    1-15-1697
    subcontractor will be paid only if the contractor is paid and thus ensures that each
    contracting party bears the risk of loss only for its own work. A typical clause of
    this type might say: 'Contractor's receipt of payment from the owner is a
    condition precedent to contractor's obligation to make payment to the
    subcontractor; the subcontractor expressly assumes the risk of the owner's
    nonpayment and the subcontract price includes the risk.' 
    Id. at 5-6."
    (Emphasis in
    original.) BMD 
    Contractors, 679 F.3d at 648-49
    .
    Determining that the subcontract language is "properly construed as a pay-if-paid clause" (id. at
    645), the Seventh Circuit concluded that "the condition-precedent language is clear and sufficient
    on its face to unambiguously demonstrate the parties' intent" that the subcontractor would not be
    paid unless the contractor was paid. 
    Id. at 649.
    ¶ 25   Applying the foregoing framework, sections 5.1 and 5.2 of the parties' subcontract
    include pay-when-paid – not pay-if-paid – provisions. Although neither "if" nor "when" is used
    in the relevant portions of those sections, the sections address the timing of payment, not the
    obligation to pay. Furthermore, there is no clear indication in the subcontract of any intent to
    "transfer the risk of 'upstream' insolvency from contractor to subcontractor." BMD 
    Contractors, 679 F.3d at 649
    .
    ¶ 26   We recognize that the contractual provisions at issue in Conte have occasionally been
    referred to as "pay-when-paid" provisions (e.g., Brown & Kerr Inc. v. St. Paul Fire & Marine
    Insurance Co., 
    940 F. Supp. 1245
    , 1249 (N.D. Ill. 1996)). We believe the Conte provisions are
    more accurately termed "pay-if-paid" clauses. Ultimately, however, we need not categorize the
    language of Conte. Instead, we observe that the Conte majority considered the plain and
    unambiguous language of the subcontract as providing that the subcontractor would be paid only
    14
    1-15-1697
    if the contractor is paid "and thus ensure[d] that each contracting party [bore] the risk of loss only
    for its own work." BMD 
    Contractors, 679 F.3d at 649
    .
    ¶ 27   The Contractor argues that the Subcontractor "asks this Court to 'disavow' Conte
    [citation] and to instead adopt a new set of principles whereby conditions precedent will not be
    enforced if they are outside the control of the obligee or if the language of the contract does not
    include the literal label 'condition precedent.' " Citing two Illinois Supreme Court decisions
    addressing the doctrine of stare decisis – Vitro v. Mihelcic, 
    209 Ill. 2d 76
    , 81-82 (2004) and
    Wakulich v. Mraz, 
    203 Ill. 2d 223
    , 230 (2003) – the Contractor discourages departure from
    precedent, i.e., the majority decision in Conte. However, we do not "disavow" Conte, but rather
    distinguish its facts from those of this case. We agree with the Contractor that there are no
    "magic words," and we consider the determination of the contracting parties' intent from the
    clear and ordinary language contained within the subcontract as requiring case-by-case analysis.
    Our decision herein does not "overhaul" Illinois law, as the Contractor suggests.
    ¶ 28   Although not necessary for our analysis, we observe that courts in other jurisdictions
    have recognized the distinction between pay-if-paid and pay-when-paid provisions and have
    treated such provisions differently. For example, in Evans, Mechwart, Hambleton & Tilton, Inc.
    v. Triad Architects, Ltd., 
    965 N.E.2d 1007
    , 1014 (Ohio Ct. App. 2011), the Court of Appeals of
    Ohio reversed the lower court's grant of summary judgment in favor of a contractor that
    disclaimed any obligation to pay its subcontractor because the owner had not paid the contractor.
    Citing section 227 of the Restatement (Second) of Contracts, the appellate court concluded that
    the subcontract contained pay-when-paid and not pay-if-paid provisions, and thus the contractor
    breached its contractual duty to pay the subcontractor within a reasonable time. 
    Id. at 1014,
    1017. See also Lemoine Co. of Alabama, L.L.C. v. HLH Constructors, Inc., 
    62 So. 3d 1020
    ,
    15
    1-15-1697
    1026-27 (Ala. 2010) (discussing paid-if-paid and pay-when-paid clauses); Otis Elevator Co. v.
    Hunt Construction Group, Inc., 
    859 N.Y.S.2d 850
    , 851 (N.Y. App. Div. 2008) (stating that "the
    pay-when-paid clause in the subcontract merely regulated the time of payment, and did not shift
    the risk of owner nonpayment to plaintiff"); Koch v. Construction Technology, Inc., 
    924 S.W.2d 68
    , 71 (Tenn. 1996) (noting that the "overwhelming majority of jurisdictions do not construe"
    pay-when-paid clauses "so as to release the general contractor from all obligation to make
    payment to the subcontractor in case of nonperformance by the owner").
    ¶ 29    Furthermore, we note that a federal district court applying Illinois law in Brown & Kerr
    Inc. v. St. Paul Fire & Marine Insurance Co. found that a "pay when paid" clause in a
    subcontract did not preclude payment under a surety bond when the subcontractor had
    satisfactorily performed its obligation under the subcontract. Brown & 
    Kerr, 940 F. Supp. at 1250
    . The court opined that the dissent in Conte "was later codified" in section 21(e) of the
    Illinois Mechanics Lien Act, which provides, in part, that "[a]ny provision in a contract,
    agreement, or understanding, when payment from a contractor to a subcontractor or supplier is
    conditioned upon receipt of the payment from any other party including a private or public
    owner, shall not be a defense by the party responsible for payment to a claim brought under
    Section 21, 22, 23, or 28 of this Act against the party." 770 ILCS 60/21(e) (West 2014).
    "Although this provision applies only to cases brought under the Illinois Mechanic's Lien Act,"
    the district court stated, "it illustrates the Illinois Legislature's concern with construing a 'pay
    when paid' clause as a condition precedent to a subcontractor's payment." Brown & Kerr, 940 F.
    Supp. at 1250.
    ¶ 30    In sum, the subcontract herein requires the Contractor to pay the Subcontractor and does
    not impose any condition precedent on such a fundamental obligation. It does not contain any
    16
    1-15-1697
    plain and unambiguous statement sufficient to overcome our disfavor for conditions precedent,
    particularly as to payment obligations. We view this result as consistent with Illinois policy and
    law.
    ¶ 31   In light of our holding, we need not consider the Subcontractor's contention that the
    incorporation of the contract into the subcontract imposed obligations upon the Contractor to
    have confirmed irrevocable or unconditional financing. Furthermore, we need not consider the
    Subcontractor's argument that the Contractor "is barred from asserting that the unavailability of
    funds releases it from liability to" the Subcontractor because the Contractor "knew it
    misrepresented that it confirmed irrevocable and unconditional financing." We observe,
    however, that Contractor presumably was better positioned than the Subcontractor to confirm the
    Owner's financial viability. Absent an expression in the subcontract indicating the parties' clear
    intent to allocate the risk of nonpayment to the Subcontractor, we will not interpret the
    subcontract so as to create or shift such risk.
    ¶ 32                                    CONCLUSION
    ¶ 33   The judgment of the circuit court of Cook County granting summary judgment in favor of
    the Contractor and against the Subcontractor is hereby reversed. This matter is remanded to the
    circuit court for further proceedings consistent with this order.
    ¶ 34   Reversed; remanded.
    17