Howell v. Empire State Surety Co. , 183 Ill. App. 220 ( 1913 )


Menu:
  • Mr. Justice Fitch

    delivered the opinion of the court.

    7. Interest, § 24*—payment vexatiously delayed. Where plaintiff is advised before signing a contract that defendant would not make a certain payment, the mere fact that defendant contested the claim to such payment does not constitute an unreasonable or vexatious delay, justifying an allowance of interest.

Document Info

Docket Number: Gen. No. 17,883

Citation Numbers: 183 Ill. App. 220

Judges: Fitch

Filed Date: 11/20/1913

Precedential Status: Precedential

Modified Date: 11/8/2024