15th Place Condominium Association v. South Campus Development Team, LLC ( 2014 )


Menu:
  •                                      
    2014 IL App (1st) 122292
    Nos. 1-12-2292 and 1-12-2301, Consolidated
    Opinion filed June 26, 2014
    FOURTH DIVISION
    ______________________________________________________________________________
    IN THE
    APPELLATE COURT OF ILLINOIS
    FIRST DISTRICT
    ______________________________________________________________________________
    15TH PLACE CONDOMINIUM ASSOCIATION, )                          Appeal from the
    )                          Circuit Court of
    Plaintiff-Appellant,     )                          Cook County.
    )
    v.                            )
    )
    SOUTH CAMPUS DEVELOPMENT TEAM,      )
    LLC,                                )
    )
    Defendant and            )
    Third-Party Plaintiff-   )
    Appellant                )
    )                          No. 08 L 9839
    )
    (FITZGERALD ASSOCIATES              )
    ARCHITECTS P.C., and                )
    LINN-MATHES, INC.,                  )
    )                          Honorable
    Third-Party Defendants-  )                          Raymond W. Mitchell,
    Appellees).              )                          Judge Presiding.
    PRESIDING JUSTICE HOWSE delivered the judgment of the court, with opinion.
    Justices McBride and Palmer concurred in the judgment and opinion.
    OPINION
    ¶1     In this case, third-party plaintiff-appellant South Campus Development Team (SCDT)
    appeals the trial court's order that dismissed with prejudice its third-party claims against third-
    1-12-2292)
    1-12-2301)Cons.
    party defendants Fitzgerald Associates Architects P.C. (Fitzgerald) and Linn-Mathes, Inc. (Linn-
    Mathes), on the grounds that the claims are time-barred. The third-party complaint contains
    claims of breach of contract, breach of the implied warranty of good workmanship, implied
    indemnity and express indemnity. The implied warranty of good workmanship and the express
    indemnity claims are only applicable to Linn-Mathes. In order to make a ruling in this appeal,
    we must determine three issues: (1) whether a cause of action accrual provision is enforceable to
    bar a third-party complaint against one of the contracting parties; (2) whether the trial court
    improperly resolved a disputed issue of fact when it ruled on a motion to dismiss; and (3)
    whether the 4-year limitations period applicable to construction-related activities (735 ILCS
    5/13-214(a) (West 2008)) or the 10-year statute of limitations period applicable to written
    contracts (735 ILCS 5/13-206 (West 2008)) applies to a general contractor's written promise to
    indemnify an owner against claims of defects in construction.
    ¶2     For the reasons that follow, we affirm that part of the trial court's order enforcing the
    accrual agreements and dismissing the breach of contract and implied indemnity claims as time-
    barred. We reverse the trial court's judgment dismissing the express indemnity claim against
    Linn-Mathes and remand this case for further proceedings on that claim because we find the 10-
    year limitations period for written contracts is applicable.
    ¶3                                     I. BACKGROUND
    ¶4                             A. The Underlying Cause of Action
    ¶5     SCDT was the developer of two adjacent condominium towers located at 811 and 833
    West 15th Place in Chicago, Illinois (the project). SCDT contracted with Fitzgerald for
    2
    1-12-2292)
    1-12-2301)Cons.
    architectural services and with Linn-Mathes to be the general contractor for the project. Both
    contracts contain a cause of action accrual provision which states that all causes of action against
    Fitzgerald and Linn-Mathes are to accrue when substantial completion of the project is achieved.
    The terms of both contracts state how the date of substantial completion is determined.
    ¶6     The SCDT/Fitzgerald contract provides that Fitzgerald as the architect is to have the sole
    and exclusive responsibility to determine the date of substantial completion. Section 2.6.12 of
    the SCDT/Fitzgerald contract states:
    "The Architect shall make site visits to determine the date
    or dates of Substantial Completion and the date of final
    completion, and may issue a final Certificate for Payment upon
    compliance with the requirements of the Contract Documents."
    ¶7     Similarly, section 4.2.9 of the SCDT/Linn-Mathes contract contains the following
    provisions relating to dates of substantial completion:
    "The Architect will conduct inspections to determine the
    date or dates of Substantial completion and the date of final
    completion, will receive and forward to the Owner, for the Owner's
    review and records, written warranties and related documents
    require [sic] by the Contract and assembled by the Contractor, and
    will issue a final Certificate for Payment upon compliance with the
    requirements of the Contract Documents."
    3
    1-12-2292)
    1-12-2301)Cons.
    Further, section 9.8.4 the SCDT/Linn-Mathes contract states: "When the Work or designated
    portion thereof is substantially complete, the Architect will prepare a Certificate of Substantial
    completion which shall establish the date of Substantial completion[]***." The SCDT/Linn-
    Mathes contract defines substantial completion in section 9.8.1 as follows:
    "Substantial Completion is the stage in the progress of the
    Work when the Work or designated portion thereof is sufficiently
    complete in accordance with the Contract Documents so that the
    Owner can occupy or Utilize the Work for its intended use."
    ¶8     In April 2005, after a number of condominium units were sold, SCDT turned over control
    of the condominiums to its owners and the 15th Place Condominium Association (the
    Association). Following the turnover, the board of directors of the Association discovered
    numerous design and workmanship defects related to the balconies, masonry, and garage. The
    Association hired an engineering company that confirmed the presence of design and
    workmanship defects, and the Association filed a lawsuit against SCDT on September 4, 2008.
    The complaint included claims of breach of the implied warranty of fitness and habitability,
    breach of fiduciary duty, and negligence. The complaint alleged that SCDT knew or should have
    known that the defects existed; SCDT failed to have any of the defects fixed; and SCDT failed to
    disclose the defects to buyers.
    ¶9                                    B. Third-Party Action
    4
    1-12-2292)
    1-12-2301)Cons.
    ¶ 10   On March 9, 2009, SCDT entered into a written tolling agreement with Fitzgerald and
    Linn-Mathes that tolled "any and all claims or causes of action" between the parties that "had not
    expired as of the date of this [tolling] Agreement."
    ¶ 11   On June 21, 2011, SCDT filed a third-party complaint against Fitzgerald and Linn-
    Mathes. The third-party complaint alleged claims for breach of contract and, alternatively,
    implied indemnity against Fitzgerald, and claims for breach of contract, breach of implied
    warranty of good workmanship, express indemnity and, alternatively, implied indemnity against
    Linn-Mathes.
    ¶ 12                                  C. Motions to Dismiss
    ¶ 13   On July 27, 2011, Fitzgerald filed a motion to dismiss the third-party complaint pursuant
    to section 2-619.1 of the Code of Civil Procedure (the Code) (735 ILCS 5/2-619.1 (West 2008)).
    In its motion, Fitzgerald argued that SCDT's third-party complaint was time-barred or, in the
    alternative, SCDT's implied indemnity claim had to be dismissed for failing to state a cause of
    action pursuant to section 2-615 of the Code. 735 ILCS 5/2-615 (West 2008). Fitzgerald argued
    in the motion that all causes of action SCDT had against it accrued on the date of substantial
    completion, which occurred on May 16, 2003 for the first tower and on October 11, 2004 for the
    second tower. Applying those accrual dates to the four-year statute of limitations applicable to
    construction-related activity (735 ILCS 5/13-214(a) (West 2008)), Fitzgerald argued that SCDT's
    claims against it were time-barred because Fitzgerald and SCDT did not enter into the tolling
    agreement until March 9, 2009, which was more than four years following the latest possible
    date on which substantial completion could have occurred, October 11, 2004. Fitzgerald
    5
    1-12-2292)
    1-12-2301)Cons.
    attached to its motion to dismiss an affidavit of Michael DeRouin, president of Fitzgerald and
    project manager of Fitzgerald at the time of the development project, stating that substantial
    completion had occurred on May 16, 2003 and October 11, 2004. The affidavit incorporated a
    letter and a certificate of substantial completion, which indicated the same dates of substantial
    completion, May 16, 2003 and October 11, 2004, respectively.
    ¶ 14   On December 5, 2011, Linn-Mathes also filed a motion to dismiss pursuant to section 2-
    619(a)(5) of the Code (735 ILCS 5/2-619(a)(5) (West 2008)), or in the alternative, to dismiss
    pursuant to section 2-615 of the Code (735 ILCS 5/2-615 (West 2008)). Linn-Mathes also
    argued that under the provisions of the cause of action accrual agreement any claims SCDT had
    against it accrued on the date of substantial completion which occurred in May 2003 and October
    2004. As such, Linn-Mathes argued: (1) the claims against it were barred by the four-year
    statute of limitations applicable to construction matters (735 ILCS 5/13-214(a) (West 2008)) and,
    as a result, all claims were time-barred when it entered into the cause of action tolling agreement
    in 2009; (2) SCDT failed to verify the third-party complaint; and (3) the claims alleged against
    Linn-Mathes failed to state a cause of action. Linn-Mathes also attached to its motion the
    affidavit of Michael DeRouin, which was identical to the affidavit attached to Fitzgerald's
    motion to dismiss.
    ¶ 15   On December 27, 2011, SCDT filed its response. SCDT disputed the date of substantial
    completion and argued that the date of substantial completion occurred in 2006. SCDT attached
    the affidavit of Vincent Forgione to its response. In the affidavit, Forgione testifies that he "has
    not been able to locate certificates of substantial completion for Phase I and Phase II of the
    6
    1-12-2292)
    1-12-2301)Cons.
    Project," but that based on his "experience" and "SCDT's schedule of contractor draw payments,"
    "[b]ecause substantial completion typically occurs after the general contractor has completed the
    majority of the work, based on the contractor draw schedule, substantial completion most likely
    occurred in early 2006." SCDT also argued that it was unreasonable to interpret the contract to
    apply the contract accrual agreement to the implied indemnity claims because the limitation
    period applicable to the implied indemnity claims could expire before SCDT even knew it had a
    claim for implied indemnity. SCDT also argued that the express indemnity claim against Linn-
    Mathes was subject to the 10-year statute of limitations applicable to written contracts.
    ¶ 16   Fitzgerald filed a motion to strike the affidavit of Vincent Forgione, and Linn-Mathes
    joined in Fitzgerald's motion. The motion argued that Forgione was not qualified to give the
    opinions in the affidavit, that his use of the term "substantial completion" was improper because
    his definition differed from the definition of "substantial completion" specifically contained
    within the contracts, and that his opinions within the affidavit were irrelevant and immaterial to
    the matters at issue.
    ¶ 17                                   D. Trial Court's Ruling
    ¶ 18   On March 8, 2012, the trial court initially denied Linn-Mathes' motion to dismiss, finding
    that the private contract limitations period that the parties had agreed upon in their respective
    contracts did not apply in this case because this was a third-party action. The court made a
    similar ruling with respect to Fitzgerald's motion to dismiss and denied Fitzgerald's motion to
    strike the affidavit of Vincent Forgione.
    7
    1-12-2292)
    1-12-2301)Cons.
    ¶ 19   On April 12, 2012, Fitzgerald filed a motion seeking interlocutory appeal pursuant to
    Illinois Supreme Court Rule 308 (eff. Feb. 26, 2010) regarding the trial court's denial of the
    motions to dismiss. On April 24, 2012, at the hearing for Fitzgerald's motion seeking
    interlocutory appeal, the trial court sua sponte decided to consider Fitzgerald's motion as a
    motion to reconsider and provided SCDT an opportunity to file a supplemental brief.
    ¶ 20   On June 20, 2012, the trial court entered a written order reconsidering its March 8, 2012
    order, and made a finding that the private statute of limitations accrual period in the parties’
    contracts applied to the third-party action. Therefore, because the court applied the four-year
    statute of limitations applicable to construction-related matters to the third-party claims, and
    determined that the date of substantial completion occurred on October 11, 2004 at the latest,
    thus triggering the running of the statute of limitations, SCDT's third-party claims against Linn-
    Mathes and Fitzgerald had to be dismissed with prejudice because they were time-barred.
    Specifically, the court stated:
    "After reconsideration, the Court finds that Guzman is inapposite.
    Guzman addresses when the cause of action accrues for a claim of
    indemnity. The contract at issue in this case expressly addresses
    accrual. It states that causes of action between the parties accrue
    upon the substantial completion of the work. The contractual
    provision at issue contains no limiting language as to what causes
    of action might be encompassed. This language is sufficiently
    broad to include a claim for indemnity. In Guzman, the court was
    8
    1-12-2292)
    1-12-2301)Cons.
    dealing with section 13-214 and interpreting how the discovery
    rule applied as to third party indemnity claims. It found that the
    discovery rule tolled the statute of limitation for indemnity action
    because the third party claim could not be determined before
    liability was established [on] the underlying claim. The
    contractual provision at issue here expressly eliminates the effect
    of the discovery rule. Instead of accruing at the point of discovery
    as most causes of action in Illinois do, the parties in this case
    pegged accrual of causes of action to the point of substantial
    completion."
    ¶ 21   On July 9, 2012, the trial court modified its June 20, 2012 order to state that "there was
    no just reason for delaying the appeal of this order pursuant to Illinois Supreme Court Rule
    304(a)," and SCDT timely filed a notice of appeal.
    ¶ 22                                   II. ANALYSIS
    ¶ 23   In this appeal, we consider whether the trial court erred in dismissing SCDT's third-party
    complaint against Linn-Mathes and Fitzgerald. Accordingly, we must determine: (1) whether the
    trial court erred when it determined the accrual agreements in the SCDT/Linn-Mathes and
    SCDT/Fitzgerald contracts are enforceable on third-party claims; (2) whether in ruling on the
    motion to dismiss the trial court improperly resolved a disputed issue of fact when it determined
    the dates of substantial completion; and (3) whether the 4-year limitations period applicable to
    9
    1-12-2292)
    1-12-2301)Cons.
    construction-related activity or the 10-year limitations period applicable to written contracts
    applies to an express indemnity agreement contained within a construction contract.
    ¶ 24   Our review of a section 2-619 motion to dismiss (735 ILCS 5/2-619 (West 2008)) is de
    novo. Porter v. Decatur Memorial Hospital, 
    227 Ill. 2d 343
    , 352 (2008).
    ¶ 25                           A. Contract Accrual Agreements
    ¶ 26    We will first consider whether the contract accrual provisions apply to third-party claims
    between the contracting parties. SCDT’s contracts with both Linn-Mathes and Fitzgerald
    contain a cause of action accrual agreement that provides that all causes of action accrue on the
    date of substantial completion of the project. The accrual agreement appears in both the
    SCDT/Fitzgerald contract and the SCDT/Linn Mathes contract, with minor differences. SCDT
    argues that the accrual provisions do not apply to third-party claims and that its third-party
    claims against Linn-Mathes and Fitzgerald did not accrue until it was served with summons by
    the plaintiff in the underlying case. See Guzman v. C.R. Epperson Construction, Inc., 
    196 Ill. 2d 391
    , 401 (2001). SCDT further argues it was unreasonable for the trial court to enforce the
    accrual agreement contained in the contracts because enforcing the accrual agreement clauses
    contained in the contracts at issue could result in a situation where the limitations period
    applicable to implied indemnity claims would expire before an actual case of implied indemnity
    had arisen. For the reasons that follow, we disagree with this argument and find that the trial
    court properly enforced the contract accrual agreement provisions at issue here.
    ¶ 27   The relevant language in the SCDT/Fitzgerald contract states:
    10
    1-12-2292)
    1-12-2301)Cons.
    "8.3 Causes of actions between the parties to this
    Agreement pertaining to acts or failures to act shall be deemed to
    have accrued and the applicable statutes of limitations shall
    commence to run not later than either the date of Substantial
    Completion for acts or failures to act occurring prior to Substantial
    Completion, or the date of issuance of the final Certificate for
    Payment for acts or failures to act occurring after Substantial
    Completion."
    The relevant language in the SCDT/Linn-Mathes contract states:
    "As to acts or failures to act occurring prior to the relevant
    date of substantial completion, any applicable statute of limitations
    shall commence to run and any alleged cause of action shall be
    deemed to have accrued in any and all events not later than such
    date of Substantial Completion."
    ¶ 28   "It is well settled that a contractual limitation requiring suit to be brought within a
    specific period of time is valid if reasonable even though the period provided by general statute
    of limitations *** is longer." Florsheim v. Travelers Indemnity Co. of Illinois, 
    75 Ill. App. 3d 298
    , 303 (1979). A limitation period is enforceable even where it may bar a meritorious claim.
    See 
    id. at 304.
    Further, "'parties to a contract may agree upon a shortened contractual limitations
    period to replace a statute of limitations, so long as it is reasonable.'" Federal Insurance Co. v.
    Konstant Architecture Planning, Inc., 
    388 Ill. App. 3d 122
    , 126 (2009) (quoting Medrano v.
    11
    1-12-2292)
    1-12-2301)Cons.
    Production Engineering Co., 
    332 Ill. App. 3d 562
    , 566 (2002)). Illinois public policy strongly
    favors the freedom to contract. Stevens v. Rooks Pitts & Poust, 
    289 Ill. App. 3d 991
    , 998 (1997).
    ¶ 29    In Konstant Architecture Planning, Inc., the court upheld a contract clause regarding an
    accrual time for all statutes of limitations that is nearly identical to the one at issue here. In
    Konstant Architecture Planning, Inc., the accrual clause agreed upon by the parties stated:
    "'Causes of action between the parties to this Agreement pertaining
    to acts or failures to act shall be deemed to have accrued and the
    applicable statute of limitations shall commence to run not later
    than either the date of Substantial Completion, or the date of
    issuance of the final Certificate for Payment for acts or failures to
    act occurring after Substantial Completion.'" Konstant
    Architecture Planning, 
    Inc., 388 Ill. App. 3d at 124
    .
    In construing these contract terms, the Konstant Architecture Planning, Inc. court noted that the
    court's "primary objective is to give effect to the intent possessed by the parties at the time they
    entered the agreement." 
    Id. at 128.
    Accordingly, the Konstant Architecture Planning, Inc. court
    found the above accrual clause to be clear and unambiguous in that the parties contracted to
    create a date of accrual for all statutes of limitations that effectively eliminated the discovery
    rule. 
    Id. ¶ 30
       Here, like in Konstant Architecture Planning, Inc., we find that the terms of accrual
    agreement contained within both contracts were clear and unambiguous. Where there is no
    ambiguity in the contract terms, the parties' intent must be drawn from the language of the
    12
    1-12-2292)
    1-12-2301)Cons.
    written instrument itself. Quake Construction, Inc. v. American Airlines, Inc., 
    141 Ill. 2d 281
    ,
    288 (1990). SCDT, Linn-Mathes and Fitzgerald, who were sophisticated parties entering into
    contracts involving more than $34 million in construction work, clearly intended to create an
    accrual date for all statutes of limitations in an effort to limit liability and eliminate the effect of
    the discovery rule. Had the parties intended to limit this clause in any way, they could have done
    so. However, as plainly written, the clause applies to any and all claims. Thus, the plain
    language of the clause in each contract makes it clear that the parties intended to limit potentially
    unlimited liability and eliminate the discovery rule by creating a fixed accrual limitations date for
    any and all causes of action, which began to run on the date of substantial completion.
    ¶ 31    SCDT argues that enforcing the accrual limitations clause in each of the contracts in this
    case will violate public policy as it had been found to do so in "cases dealing with automobile
    insurance policies that set the accrual date for uninsured or underinsured motorist claims at the
    time the accident occurred" and "cases involving employee benefit plans that set the accrual date
    at the date the claim for benefits was filed." While courts will not enforce an agreement that is
    contrary to public policy, a contract should not be deemed illegal unless it is expressly contrary
    to the law or public policy. American Country Insurance Co. v. Cline, 
    309 Ill. App. 3d 501
    , 506
    (1999). The laws and public policy of the State of Illinois permit freedom of contracting
    between competent parties. 
    Id. In addition,
    construction of a contact that renders the agreement
    enforceable rather than void is preferred. 
    Id. at 507.
    As a result, the issue as to whether a
    contract is contrary to public policy depends on the facts and circumstances of the case. 
    Id. 13 1-12-2292)
    1-12-2301)Cons.
    ¶ 32    We do not find the public policy concerns recognized in uninsured/underinsured
    automobile policy claims and employee benefits claims have any bearing in this case where
    sophisticated parties contracted to and agreed to terms that trigger the running of all statutes of
    limitations on the date of substantial completion.1 The cases cited by SCDT all involve contracts
    between sophisticated and unsophisticated parties. Further, the terms of the contract at issue in
    each of the cases cited by SCDT were not negotiated and agreed upon by both parties, rather they
    were offered to the unsophisticated party in a take it or leave it manner. Here, as stated above,
    the contract terms regarding the accrual date for all claims were bargained for and agreed upon
    by sophisticated parties engaged in a multi-million dollar construction project. Accordingly, we
    find no good reason to disturb these contract provisions that were bargained for by sophisticated
    parties, and affirm the trial court's finding enforcing the contractual accrual date in both the
    SCDT/Fitzgerald and SCDT/Linn-Mathes contracts.2
    ¶ 33                          B. Date of Substantial Completion
    1
    Of note, none of the cases cited by SCDT state, or even suggest, that it is against public
    policy for two sophisticated parties to agree to contract terms that eliminate the effect of the
    discovery rule. In fact, as stated above, our courts have specifically found that this is permitted.
    See Konstant Architecture Planning, 
    Inc., 388 Ill. App. 3d at 126
    .
    2
    We also find that SCDT's reliance on Guzman in this argument misplaced, as the facts
    of Guzman dealt with the application of the default statute of limitations, which incorporated the
    discovery rule, and not a modified statute of limitations that sets a trigger date for all claims, like
    the one we are presented with here.
    14
    1-12-2292)
    1-12-2301)Cons.
    ¶ 34   SCDT argues that the trial court erred in determining that substantial completion, the
    contract trigger date for the running of any statute of limitations, occurred on May 16, 2003 and
    October 11, 2004. SCDT argues that it submitted a rebuttal affidavit in its response to the
    motion to dismiss and offered testimony that suggests that substantial completion occurred
    sometime in early 2006, thereby creating a genuine issue of material fact as to the date of
    substantial completion, i.e., the contract accrual date. If the cause of action accrued in 2006,
    SCDT had viable breach of contract claims against Linn-Mathes and Fitzgerald at the time the
    tolling agreement was signed in March 2009. As such, SCDT argues the trial court improperly
    decided a material question of fact when it determined the date of substantial completion of the
    two towers to be May 16, 2003 and October 11, 2004 respectively.
    ¶ 35   The purpose of a motion to dismiss under section 2-619 of the Code is to dispose of
    issues of law and easily proved issues of fact at the outset of a case. Zedella v. Gibson, 
    165 Ill. 2d
    181, 185 (1995); 735 ILCS 5/2-619(c) (West 2008). When ruling on a section 2-619 motion,
    the court admits as true all well-pleaded facts and the legal sufficiency of the complaint. King v.
    City of Chicago, 
    324 Ill. App. 3d 856
    , 859 (2001). If grounds for dismissal do not appear on the
    face of the pleading attacked, the motion shall be supported by affidavit, and the nonmoving
    party has the opportunity to file a counteraffidavit. 735 ILCS 5/2-619(c) (West 2008). The
    relevant question is whether there exists a genuine issue of material fact precluding dismissal, or
    absent an issue of material fact, whether dismissal is proper as a matter of law. Fuller Family
    Holdings, LLC v. Northern Trust Co., 
    371 Ill. App. 3d 605
    , 613 (2007).
    15
    1-12-2292)
    1-12-2301)Cons.
    ¶ 36   Here, Fitzgerald and Linn-Mathes attached to their motions to dismiss the affidavit of
    Michael DeRouin, the president of Fitzgerald and the project manager of Fitzgerald during the
    development project. In his affidavit, DeRouin testifies that he was "directly responsible for the
    architectural services provided" during the development project. Further, he testifies in his
    affidavit that the first tower was substantially completed on May 16, 2003 and the second tower
    was substantially completed on October 11, 2004. In support of these two dates, DeRouin
    attaches a letter that was written to SCDT on May 16, 2003 indicating that substantial
    completion had occurred with respect to the first tower, and a certificate of substantial
    completion that is signed by him and dated October 11, 2004 with respect to the second tower.
    ¶ 37   In SCDT's response to the motions to dismiss, it attached a counteraffidavit of Vincent
    Forgione. Forgione is an employee of Frontier Management Corporation, which is an affiliate of
    SCDT. Forgione states in his affidavit that he "has not been able to locate certificates of
    substantial completion for Phase I and Phase II of the Project," but that based on his "experience"
    and "SCDT's schedule of contractor draw payments," "[b]ecause substantial completion typically
    occurs after the general contractor has completed the majority of the work, based on the
    contractor draw schedule, substantial completion most likely occurred in early 2006." Thus,
    Forgione uses the date of the final contractor draw payment, December 2006, to predict when
    "the majority of the work" was completed to then estimate that substantial completion occurred
    in early 2006.
    ¶ 38   Here, all parties entered into contracts stating that the date of substantial completion
    would be determined by the architect (Fitzgerald) and would be reflected in a certificate of
    16
    1-12-2292)
    1-12-2301)Cons.
    substantial completion. DeRouin's affidavit states that Fitzgerald determined that the first tower
    was substantially completed on May 16, 2003, and the second tower was substantially completed
    on October 11, 2004. In support of these two dates, DeRouin also attached a letter that was
    written to SCDT on May 16, 2003 indicating that substantial completion had occurred with
    respect to the first tower, and a certificate of substantial completion that is signed by him and
    dated October 11, 2004 with respect to the second tower. As a result, Forgione's affidavit, which
    estimates when substantial completion occurred based upon draw payments and when the final
    draw payment was made, does not contradict the testimony of DeRouin who testifies that
    substantial completion, pursuant to the contracts signed by the parties, was achieved on May 16,
    2003 and October 11, 2004. Safeco Insurance Co. v. Jelen, 
    381 Ill. App. 3d 576
    , 583 (2008)
    (where facts asserted in an affidavit are not refuted by counteraffidavit, the court will take those
    facts as true notwithstanding any contrary unsupported allegations in the plaintiff's pleadings).
    Further, any evidence regarding when substantial completion may have occurred that does not
    comport with the terms that were contracted to by the parties is not material and cannot create a
    material issue of fact. Therefore, because we find that the Forgione affidavit did not contradict
    the evidence stated in the DeRouin affidavit and did not raise a genuine issue of material fact, it
    follows that there is no genuine issue of material fact and the trial court properly concluded the
    dates of substantial completion occurred on May 16, 2003 and October 11, 2004. See
    Bloomingdale State Bank v. Woodland Sales Co., 
    186 Ill. App. 3d 227
    , 232 (1989) (where there
    are no genuine issues of material fact, the court may grant a section 2-619 motion to dismiss).
    ¶ 39                       C. Statute of Limitations on SCDT's Claims
    17
    1-12-2292)
    1-12-2301)Cons.
    ¶ 40       Since we have concluded that the trial court properly enforced the cause of action
    accrual agreement and also properly determined the date of substantial completion of the project
    to be May 16, 2003 and October 11, 2004, we can now determine whether the statute of
    limitations expired on SCDT's claims against Linn-Mathes and Fitzgerald.
    ¶ 41              a. Implied Indemnity Claims and Breach of Contract Claims
    ¶ 42      With respect to the implied indemnity claims, the applicable statute of limitations states
    that a party has two years from being served with process in the underlying action or two years
    from the date the party knew or reasonably should have known of an act or omission giving rise
    to the action for indemnity, whichever period expires later. 735 ILCS 5/13-204(b) (West 2008).
    However, in this case, because of the existence of the cause of action accrual agreement, the two-
    year period began to run on the date of substantial completion. Because substantial completion
    occurred at the latest on October 11, 2004, the limitation period on SCDT's claims for implied
    indemnity against the third-party defendants expired on October 11, 2006, well in advance of the
    March 9, 2009 tolling agreement, and are therefore time-barred. With respect to the breach of
    contract claims, which the parties agreed were governed by the four-year statute of limitations
    period applicable to construction-related activity, those claims are also time-barred as the statute
    of limitation on those claims expired on October 11, 2008, which again was prior to the March 9,
    2009 tolling agreement. Accordingly, we affirm the judgment of the trial court dismissing the
    breach of contract and implied indemnity claims against the third-party defendants as being time-
    barred.
    ¶ 43                             b. Express Indemnity Claim
    18
    1-12-2292)
    1-12-2301)Cons.
    ¶ 44   SCDT argues that its express indemnity claim against Linn-Mathes was improperly
    dismissed by the trial court because it was governed by the 10-year statute limitations applicable
    to written contracts rather than the 4-year statute limitations applicable to construction matters.
    Section 13-206 of the Code states:
    "Except as provided in Section 2-725 of the 'Uniform Commercial
    Code', actions on bonds, promissory notes, bills of exchange,
    written leases, written contracts, or other evidences of indebtedness
    in writing and actions brought under the Illinois Wage Payment
    and Collection Act shall be commenced within 10 years next after
    the cause of action accrued***." 735 ILCS 5/13-206 (West 2008).
    ¶ 45   Linn-Mathes argues that the trial court properly determined that its express promise to
    indemnify SCDT for breaches related to the construction work is governed by the four-year
    statute of limitations applicable to construction-related activity, and that the trial court properly
    dismissed SCDT's claim as time-barred under that statute. 735 ILCS 5/13-214(a) (West 2008).
    Section 13-214(a) of the Code states:
    "Actions based upon tort, contract or otherwise against any person
    for an act or omission of such person in the design, planning,
    supervision, observation or management of construction, or
    construction of an improvement to real property shall be
    commenced within 4 years from the time the person bringing an
    action, or his or her privity, knew or should reasonably have
    19
    1-12-2292)
    1-12-2301)Cons.
    known of such act or omission. Notwithstanding any other
    provision of law, contract actions against a surety on a payment or
    performance bond shall be commenced, if at all, within the same
    time limitation applicable to the bond principal." 735 ILCS 5/13-
    214(a) (West 2008).
    ¶ 46    We agree with SCDT that the 10-year statute of limitations applies to its express
    indemnity claim. Our decision is based upon our supreme court's ruling in Travelers Casualty &
    Surety Co. v. Bowman, 
    229 Ill. 2d 461
    (2008), which found that a written agreement to
    indemnify was not one of the activities protected under the 4-year statute of limitations
    applicable to construction matters and was instead subject to the 10-year statute of limitations
    applicable to written contracts. See 735 ILCS 5/13-206 (West 2008).
    ¶ 47    In Travelers, Travelers Casualty & Surety Company (Travelers) filed suit against James
    A. Bowman and Barbara B. Bowman, the president and sole shareholder, respectively, of a metal
    working firm, Carlson, for breach of a written indemnity agreement relating to performance
    bonds. 
    Travelers, 229 Ill. 2d at 464
    . The Bowmans became liable to Travelers under the
    indemnity agreement when Carlson failed to perform certain construction work. 
    Id. Our supreme
    court found that the 4-year statute of limitations did not apply to Travelers' claim and
    that the 10-year statute of limitations applied instead. 
    Id. at 465.
    In coming to this conclusion,
    the Court stated that "'[t]he determination of the applicable statute of limitations is governed by
    the type of injury at issue, irrespective of the pleader's designation of the nature of the action.'"
    
    Travelers, 229 Ill. 2d at 466
    (quoting Armstrong v. Guigler, 
    174 Ill. 2d 281
    , 286 (1996)). The
    20
    1-12-2292)
    1-12-2301)Cons.
    court further stated that the "essence of any contractual action is found in the agreement's
    promissory language" and "[a]s long as the gravamen of the complaint rests on the
    nonperformance of a contractual obligation, section 13-206 applies." (Internal quotation marks
    omitted.) 
    Id. at 467
    (quoting 
    Armstrong, 174 Ill. 2d at 291
    ). In finding that the type of injury at
    issue in Travelers was contract related rather than construction related, the court stated:
    "Here, the liability at issue emanates not from construction-
    related activity but, rather, from the breach of a contractual
    obligation to indemnify. ***
    *** The Bowmans' liability to Travelers does not, however,
    emanate from Carlson's breach of the construction contracts.
    Rather, the Bowmans' liability emanates from the refusal to
    perform their obligation of indemnification under the written
    indemnification agreement after claims were made against the
    underlying performance bonds." 
    Travelers, 229 Ill. 2d at 469
    .
    Further, in Armstrong, which was relied upon in Travelers, the court stated:
    "The essence of any contractual action is found in the agreement's
    promissory language. Thus, it is only where liability emanates
    from a breach of a contractual obligation that the action may be
    fairly characterized as 'an action on a written contract.' The focus
    of the inquiry is on the nature of the liability and not on the nature
    of the relief sought." 
    Armstrong, 174 Ill. 2d at 291
    .
    21
    1-12-2292)
    1-12-2301)Cons.
    In sum, the Travelers court concluded that "[b]ecause the claim at issue is based on a breach of
    express indemnification provisions in a written agreement, it is subject to the 10-year limitations
    period in section 13-206." 
    Travelers, 229 Ill. 2d at 476
    .
    ¶ 48    Here, like in Travelers, the express indemnity claim against Linn-Mathes arose from
    Linn-Mathes' refusal to perform its obligation to indemnify SCDT pursuant to an express
    promise to indemnify SCDT contained in the contract between the parties. Because the nature of
    the claim was Linn-Mathes' refusal to indemnify, any potential liability arises out of Linn-
    Mathes' failure to indemnify SCDT rather than any acts or omissions relating to construction-
    related activity.
    ¶ 49    Further, our supreme court has held that the four-year statute of limitations relating to
    construction matters protects only certain enumerated activities, specifically, "the design,
    planning, supervision, observation or management of construction." (Internal quotation marks
    omitted.) People ex rel. Skinner v. Hellmuth, Obata & Kassabaum, Inc., 
    114 Ill. 2d 252
    , 261
    (1986); see 735 ILCS 5/13-214(a) (West 2008); see also Konstant Architecture Planning, 
    Inc., 388 Ill. App. 3d at 125-26
    (the four-year statute of limitations applicable in construction-related
    activities, "applies only if the defendant is being sued for its act or omission of one of the
    enumerated construction-related activities"). Indemnification is not one of those enumerated
    activities protected under the four-year statute of limitations. As such, section 13-214(a) does
    not protect Linn-Mathes' actions or inactions as an indemnitor. Therefore, the 10-year statute of
    limitations applicable to written contracts applies to SCDT's express indemnity claim against
    Linn-Mathes.
    22
    1-12-2292)
    1-12-2301)Cons.
    ¶ 50   Linn-Mathes argues that the four-year statute of limitations governing construction
    activity should apply here because the express indemnity clause at issue is contained within the
    construction contract and is not its own separate contract. However, we see no requirement that
    express indemnity clauses must be contained in a separate written document in order to apply the
    10-year statute of limitations for written contracts. To the contrary, as made clear in Travelers,
    "it is the nature of the plaintiff's injury rather than the nature of the facts from which the claim
    arises which should determine which limitations period should apply." (Internal quotation marks
    omitted.) 
    Travelers, 229 Ill. 2d at 466
    (quoting 
    Armstrong, 174 Ill. 2d at 286-87
    ). The nature of
    SCDT's claim against Linn-Mathes is indemnification, regardless of the fact that the
    indemnification clause is contained within the overall construction contract.
    ¶ 51   Further, while Linn-Mathes also argues that the holding in Guzman requires the four-year
    construction statute of limitations to be applied to the express indemnity claim at issue here, we
    cannot see how the holding in Guzman is applicable. Guzman only dealt with implied indemnity
    claims and not an express indemnity claim like the one at issue in this case. See Guzman, 
    196 Ill. 2d 391
    . As pointed out in Travelers, the Guzman court "was not presented with the issue of
    whether section 13-204 applied to an express indemnity agreement and it did not, therefore,
    examine that issue." 
    Travelers, 229 Ill. 2d at 476
    . Further, the Guzman court ultimately found
    that section 13-204 applied to the implied indemnity claims in that case, and our courts have held
    that "[s]ections 13-204(a) and 13-204(b) are not applicable when the basis for indemnity rests on
    a written indemnity agreement." 
    Travelers, 229 Ill. 2d at 473
    . Thus, because this appeal deals
    with an express indemnity claim, which was not addressed in Guzman and which is an entirely
    23
    1-12-2292)
    1-12-2301)Cons.
    different animal than the implied indemnity claims that were addressed in Guzman, Guzman is
    inapplicable here.
    ¶ 52   Accordingly, we find that SCDT's express indemnity claim against Linn-Mathes must be
    governed by the 10-year statute of limitations applicable to written contracts because the nature
    of that claim is for the failure to indemnify rather than any act or omission relating to
    construction activity. We therefore reverse the trial court's finding that the four-year statute of
    limitations applies to SCDT's express indemnity claim against Linn-Mathes and the dismissal of
    that claim. Since less than 10 years elapsed between the dates of substantial completion (May
    2003 and October 2004) and the time the statute of limitations tolling agreement was signed in
    2009 and the third-party complaint was filed in 2011, we reverse the dismissal of the express
    indemnity claim as time-barred and remand this case to the trial court for further proceedings on
    SCDT's express indemnity claim against Linn-Mathes.
    ¶ 53                                   III. CONCLUSION
    ¶ 54   For the above reasons, we affirm the trial court's enforcement of the contractual accrual
    agreement and the dismissal of the implied indemnity and breach of contract claims against the
    third-party defendants because they are time-barred; we reverse trial court's dismissal of the
    express indemnity claim against Linn-Mathes and this case is remanded for further proceedings
    on that claim only.
    ¶ 55   Affirmed in part and reversed in part; cause remanded.
    24