Radarsat Media, Inc. v. Taty Development, Inc. , 2021 IL App (1st) 190560-U ( 2021 )


Menu:
  •                                 
    2021 IL App (1st) 190560-U
    Order filed: June 18, 2021
    FIRST DISTRICT
    FIFTH DIVISION
    No. 1-20-0774
    NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the
    limited circumstances allowed under Rule 23(e)(1).
    ______________________________________________________________________________
    IN THE
    APPELLATE COURT OF ILLINOIS
    FIRST JUDICIAL DISTRICT
    ______________________________________________________________________________
    RADARSAT MEDIA, INC.,                           )     Appeal from the
    )     Circuit Court of
    Plaintiff-Cross-Appellant,                )     Cook County
    )
    v.                                              )
    )
    TATY DEVELOPMENT, INC. and                      )
    TATY CONSTRUCTION, INC.,                        )
    )
    Defendants-Cross-Appellees.               )
    _______________________________________________ )     17 L 013279
    TATY DEVELOPMENT, INC., and                     )
    TATY CONSTRUCTION, INC.,                        )
    )
    Counter-Plaintiffs-Appellants,            )
    )
    v.                                              )
    )
    RADARSAT MEDIA, INC.,                           )     Honorable
    )     James E. Snyder,
    Counter-Defendant-Appellee.               )     Judge, presiding.
    ______________________________________________________________________________
    JUSTICE ROCHFORD delivered the judgment of the court.
    Presiding Justice Delort and Justice Cunningham concurred in the judgment.
    ORDER
    No. 1-20-0774
    ¶1     Held: Plaintiff and defendants filed an appeal and cross-appeal from the court’s judgment
    awarding each of the parties some of their requested damages for breach of contract
    and denying defendants’ motion to dismiss plaintiff’s complaint as a sanction for a
    discovery violation. We affirmed on the appeal and on the cross-appeal, finding
    that the court’s factual findings were not against the manifest weight of the evidence
    and that the court did not abuse its discretion in denying the sanctions motion.
    ¶2     Defendants, Taty Development, Inc. and Taty Construction, Inc., retained plaintiff,
    Radarsat Media, Inc., as a subcontractor for two construction projects: the first for the construction
    of certain commercial luxury condominiums and the second for the construction of an apartment
    building. Plaintiff subsequently brought an action against defendants for breach of contract and
    quantum meruit in connection with defendants’ alleged failure to pay plaintiff for all of its work.
    Defendants counterclaimed for breach of contract, unjust enrichment, and set-off in connection
    with plaintiff’s alleged failure to timely perform all the work for which defendants paid them.
    Following a bench trial, the circuit court entered a written order awarding plaintiff $8,596. The
    court subsequently granted plaintiff’s motion for reconsideration in part, noting that the written
    order did not accurately reflect its oral judgment, and awarded plaintiff $43,304 on its breach of
    contract claims and awarded defendants $1,200 on their counterclaim for breach of contract.
    ¶3     On appeal, defendants contend that the court erred by: (1) failing to award them damages
    in the amount of $57,200 attributable to plaintiff’s delay in timely completing its work on the
    condominium and apartment projects; (2) failing to award them a setoff against the judgment
    awarded in plaintiff’s favor; and (3) failing to dismiss plaintiff’s complaint and enter a default
    judgment on their counterclaim as a sanction for a discovery violation. On cross-appeal, plaintiff
    contends the court erred by failing to award it damages for defendants’ refusal to pay it for the
    extra work performed at the condominium and apartment projects at the direction of defendants’
    agent. We affirm on the appeal and on the cross-appeal.
    -2-
    No. 1-20-0774
    ¶4       In its amended complaint, plaintiff alleged that on or about September 9, 2016, it entered
    into a written agreement with defendants whereby plaintiff agreed to provide construction and
    interior rehab services on a 13-unit apartment building at 7626-7628 South Drexel Avenue (the
    Drexel property).
    ¶5       Plaintiff and defendants also entered into four written contracts in 2016 and 2017 whereby
    plaintiff would provide internal plumbing, external plumbing, drywall installation, and steam
    shower installation for an eight-unit condominium property at 20 North Loomis Avenue (the
    Loomis property).
    ¶6       From September 2016 through August 2017, plaintiff provided carpentry, plumbing,
    electrical, drywall, and painting services to the Drexel property in accordance with the Drexel
    contract. From June 2017 through August 2017, plaintiff performed extra work and services at the
    Drexel property at defendants’ specific request, for which defendants agreed to pay plaintiff on a
    time and materials basis.
    ¶7       From July 2016 through September 2017, plaintiff performed all internal and external
    plumbing work on the Loomis property pursuant to the Loomis plumbing contracts and also
    performed extra, out-of-scope plumbing work at defendants’ request. Defendants agreed to
    compensate plaintiff for its extra plumbing work on the Loomis property on a time and materials
    basis.
    ¶8       From October 2016 through July 2017, plaintiff provided drywall services on the Loomis
    property pursuant to the Loomis drywall contract. In May and June 2017, plaintiff provided extra,
    out-of-scope drywall services on the Loomis property at defendants’ request. Defendants agreed
    to pay plaintiff on a time and materials basis for the extra drywall work.
    -3-
    No. 1-20-0774
    ¶9     From January 2017 through July 2017, plaintiff performed its steam shower installation
    work pursuant to the Loomis steam shower contract.
    ¶ 10   In count I of its amended complaint, plaintiff alleged that defendants breached the Drexel
    contract by failing to fully compensate it for all the labor and materials provided to the Drexel
    property and by failing to compensate it for the extra work on the Drexel property.
    ¶ 11   In count II, plaintiff realleged the allegations of count I and sought recovery under a theory
    of quantum meruit.
    ¶ 12   In counts III and IV, plaintiff alleged that defendants breached the Loomis internal and
    external plumbing contracts by failing to compensate it for the labor and materials provided
    pursuant to those contracts and by failing to pay it for the extra, out-of-scope plumbing work.
    ¶ 13   In count V, plaintiff alleged that defendants breached the Loomis drywall contract by
    failing to fully compensate it for the work performed under that contract including the extra
    drywall work performed at defendants’ request.
    ¶ 14   In count VI, plaintiff alleged that defendants breached the Loomis steam shower contract
    by failing to fully compensate it for the work performed under that contract.
    ¶ 15   In count VII, plaintiff realleged the allegations of counts III-VI relating to defendants’
    failure to fully compensate it for the work performed on the Loomis property and sought recovery
    under a theory of quantum meruit.
    ¶ 16   Defendants filed a seven-count counterclaim seeking recovery for plaintiff’s alleged
    breaches of the Loomis and Drexel contracts. In count I for plaintiff’s breach of the Loomis drywall
    contract, defendants alleged that plaintiff misrepresented that it installed 2,460 sheets of drywall
    for which defendants paid $63,960. In fact plaintiff only installed 1,650 sheets of drywall, for
    -4-
    No. 1-20-0774
    which $42,900 should have been charged, meaning that defendants were overcharged and
    damaged in the amount of $21,060.
    ¶ 17   In count II, defendants alleged that all payments for the Loomis contracts were
    administered through First American Title Company (FAT) and that in order to receive payment,
    plaintiff had to submit lien waivers to FAT. Plaintiff breached the Loomis internal plumbing
    contract by submitting lien waivers to FAT that were improper and inaccurate and by failing to
    fully and timely perform the work and pay its subcontractors.
    ¶ 18   In count III, defendants alleged that plaintiff breached the Loomis external plumbing
    contract by failing to fully and timely perform the work.
    ¶ 19   In count IV, defendants alleged that plaintiff breached the Drexel contract by failing to
    complete work related to the HVAC, electrical, drywall, plumbing, paint, floors, carpentry, and
    intercom.
    ¶ 20   In counts V and VI for unjust enrichment, defendants alleged that they overpaid plaintiff
    for work performed at the Loomis and Drexel properties and that plaintiff would be unjustly
    enriched if it were able to retain the overpayments. Plaintiff also failed to fully and timely play its
    subcontractors, resulting in work delays that further damaged defendants.
    ¶ 21   In count VII for set off, defendants alleged that plaintiff’s claims under its breach of
    contract action should be setoff by the more than $280,000 which defendants overpaid plaintiff
    and/or paid to hire new contractors to complete plaintiff’s work.
    ¶ 22   The circuit court held a bench trial over three days between September 30, 2019, and
    October 2, 2019, and heard testimony from 16 witnesses. In their briefs on appeal, the parties only
    reference small portions of some of the witness testimony. We will discuss the testimony later in
    this order when analyzing the issues on appeal.
    -5-
    No. 1-20-0774
    ¶ 23   On October 2, 2019, the circuit court entered a written order stating:
    “This cause coming to be heard for bench trial, the court hearing evidence and being fully
    advised in the premises, it is hereby ordered: judgment is entered for plaintiff Radarsat
    Media, Inc. and against Taty Development, Inc. and Taty Construction, Inc., jointly and
    severally for $8,596.”
    ¶ 24   Plaintiff filed a motion for reconsideration. On May 26, 2020, the circuit court entered a
    written order stating:
    “This matter comes before the Court on Plaintiff’s motion for reconsideration. The Court,
    being fully advised, states as follows:
    On review of the transcript of the proceedings, there was a judgment for the Plaintiff in
    part of claim on Count I for $27,000, a judgment for the Plaintiff on Count II for $16,304
    and a judgment against the Plaintiff/Counter-Defendant in favor of the Defendant/Counter-
    Plaintiff for $1,200.
    Judgment should have been entered on each of those counts. The Clerk can correct the
    court record and indicate those judgment amounts and findings on those counts for the
    proper parties. The net effect of those judgments should total as:
    Count I                       $27,000
    Count II                      $16,304
    Counter Plaintiff Judgment -$1,200
    TOTAL Plaintiff               $42,104”
    ¶ 25   The transcript of the oral findings referenced by the circuit court in which it granted
    judgment for plaintiff on count I for $27,000 and on count II for $16,304 and entered judgment for
    defendants on their counterclaim for $1,200, is not contained in the record on appeal.
    -6-
    No. 1-20-0774
    ¶ 26   On June 23, 2020, defendants appealed the May 26 order. On June 24, 2020, plaintiff cross-
    appealed the May 26 order.
    ¶ 27   Defendants’ first argument on appeal is that the circuit court erred by failing to award them
    any damages for plaintiff’s delay in completing its work on the Drexel project. Where an award of
    damages is made after a bench trial, the standard of review is whether the court’s judgment is
    against the manifest weight of the evidence. 1472 N. Milwaukee, Ltd. v. Feinerman, 
    2013 IL App (1st) 121191
    , ¶ 13. A judgment is against the manifest weight of the evidence only if the opposite
    conclusion is clear or where the trial court’s findings are unreasonable, arbitrary, or not based on
    the evidence. 
    Id.
    ¶ 28   Our review of defendants’ argument is hindered by their failure to provide us with the
    transcript of the circuit court’s oral factual findings, which were referenced in the May 26, 2020,
    order that granted plaintiff’s motion to reconsider in part and that corrected the written judgment
    so as to accord with the oral findings. Without knowing what the court’s factual findings were with
    respect to plaintiff’s alleged delay in completing work on the Drexel project, we cannot review
    whether those findings were against the manifest weight of the evidence. As the appellants,
    defendants bear the burden of providing a sufficiently complete record to support their claim of
    error and in the absence of such a record on appeal, we presume that the order entered by the circuit
    court was in conformity with the law and had a sufficient factual basis. Foutch v. O’Bryant, 
    99 Ill. 2d 389
    , 391-392 (1984). Any doubts arising from the incompleteness of the record are resolved
    against the appellant. 
    Id. at 392
    .
    ¶ 29   Even addressing defendants’ argument in the absence of the court’s oral factual findings,
    we still affirm. Defendants argue that in its responses to their requests to admit, plaintiff admitted
    that it did not complete either Phase I or Phase II of the Drexel project by the contract deadlines
    -7-
    No. 1-20-0774
    and that at trial, plaintiff’s principal, Rafal Stykowski, again admitted that plaintiff did not
    complete Phase II of the Drexel project by the contract deadline. Defendants contend that the total
    delay was 286 days and that pursuant to the Drexel contract, they were entitled to a penalty
    payment of $200 per day for each of the 286 days of delay caused by plaintiff, amounting to a total
    of $57,200, which the court should have awarded them.
    ¶ 30   However, in its response to defendants’ request to admit, plaintiff stated that it failed to
    complete its work on the Drexel project by the Phase I and Phase II deadlines because cabinets
    and other items necessary for completion of the work were not delivered to it until after the
    deadlines. At trial, defendants’ principal, Calin Paunescu, admitted to the delay in the delivery of
    “the kitchens” to plaintiff until after the Phase I and Phase II deadlines. Such evidence was
    sufficient to show that the delay in completion of the Drexel project was not attributable to plaintiff
    and therefore that defendants were not entitled to any damages from plaintiff for the delay.
    ¶ 31   Next, defendants contend that the circuit court erred by failing to dismiss plaintiff’s
    complaint and enter default judgment on their counterclaim as a sanction under Illinois Supreme
    Court Rule 219(c) (eff. July 1, 2002) for plaintiff’s failure to timely comply with discovery. Rule
    219(c) provides that if a party unreasonably fails to comply with discovery, the trial court may:
    debar the offending party from maintaining any particular claim or counterclaim related to that
    discovery issue; bar a witness from testifying about that issue; or enter a default judgment or
    dismissal order against the offending party. 
    Id.
    ¶ 32    The sanctions imposed must be just and proportionate to the offense. Gonzalez v. Nissan
    North America, Inc., 
    369 Ill. App. 3d 460
    , 464 (2006). Dismissal with prejudice is a drastic
    sanction that the courts are reluctant to impose and is to be employed only as a last resort to enforce
    the rule of discovery and only when a party has shown a deliberate and contumacious disregard
    -8-
    No. 1-20-0774
    for the authority of the court. 
    Id. at 465
    . The determination of a sanction is specific to the
    circumstances of the case (id.) and will not be overturned absent a clear abuse of discretion.
    Nedzvekas v. Fung, 
    374 Ill. App. 3d 618
    , 620-21 (2007).
    ¶ 33   The alleged discovery violation at issue here related to plaintiff’s late disclosure of the so-
    called “final” lien waiver it provided to FAT on July 14, 2017, which stated that plaintiff had
    provided labor and material for the plumbing work at the Loomis project in the amount of $728,100
    and had been paid $531,640. Plaintiff was seeking a partial payment of $16,100 from FAT, leaving
    a balance due of $180,360.
    ¶ 34   In May 2018 and in January 2019, defendants served plaintiff with requests for production
    of documents seeking all lien waivers that plaintiff had submitted to FAT relating to the Loomis
    project. In response, plaintiff provided defendants with all such lien waivers except for the final
    July 14, 2017, lien waiver.
    ¶ 35   In February 2019, plaintiff issued a subpoena to FAT requesting a copy of its entire file
    relating to the Loomis project. On February 22, 2019, defendants served plaintiff with a third
    request for documents, seeking a copy of the FAT file. On March 11, 2019, plaintiff sent
    defendants the FAT file, which did not include the final lien waiver, and on April 10, 2019, plaintiff
    supplemented its responses with additional documents that did not include the final lien waiver.
    ¶ 36    On August 30, 2019, plaintiff submitted to defendants its list of trial exhibits, including
    Exhibit 14, which was titled “First American Title Company lien waiver documentation.”
    Plaintiff’s Exhibit 14 did not contain the final lien waiver.
    ¶ 37   On September 23, 2019, defendants’ counsel, Rakesh Khanna, discovered a check dated
    July 14, 2017, made out from FAT to plaintiff which indicated to him that there should be a
    -9-
    No. 1-20-0774
    corresponding lien waiver for that date. Khanna contacted plaintiff’s counsel, Paul Porvaznik, who
    subsequently emailed Khanna a copy of the final lien waiver for the first time.
    ¶ 38   Defendants filed a motion for sanctions arguing for dismissal of plaintiff’s complaint and
    entry of a default judgment on their counterclaim due to plaintiff’s belated production of the final
    lien waiver. At the hearing held on the motion, Porvaznik and his co-counsel, Christine
    McClernon, explained that their client, plaintiff, only gave them two pages of lien waivers related
    to the Loomis project, neither of which contained the final lien waiver. Porvaznik produced the
    two pages of lien waivers to defendants in response to their initial requests for production of
    documents in May 2018 and January 2019.
    ¶ 39   Porvaznik further explained that in March 2019, he subpoenaed FAT and received 1,153
    pages of documents, including draws paid to suppliers, contractors, and subcontractors on the
    Loomis project. None of the 1,153 pages of documents produced by FAT to Porvaznik contained
    the final lien waiver. Porvaznik produced the 1,153 pages of documents to defendants. Six weeks
    later, in April 2019, Porvaznik examined the documents produced by FAT and noticed a “gap”
    between Draw 27 and Draw 30. Porvaznik notified FAT, which sent him 50 additional documents
    on April 4, 2019, including (for the first time) the final lien waiver. Through “oversight,”
    Porvaznik did not immediately notify defendants of his receipt of the final lien waiver.
    ¶ 40    McClernon explained that in August 2019, she prepared Plaintiff’s Exhibit 14, the “First
    American Title Company lien waiver documentation” which did not include the final lien waiver
    because Porvaznik had not made her aware of it.
    ¶ 41   Porvaznik produced the final lien waiver to defendants in September 2019 after Khanna
    contacted him regarding some possible missing documents from the FAT file. Porvaznik reiterated
    -10-
    No. 1-20-0774
    to the court that his failure to immediately produce the final lien waiver to defendants upon his
    receipt of it in April 2019 was an “honest mistake” and unintentional.
    ¶ 42   The court inquired of Khanna as to the relevance of the final lien waiver. Khanna asserted
    that the final lien waiver showed that every single invoice prior to the final invoice had been paid
    to plaintiff, meaning that defendants owed no further monies to plaintiff. Porvaznik responded that
    the final lien waiver showed there was still an outstanding balance of $180,360 for plumbing
    services provided by plaintiff, and that the final lien waiver also did not apply to the drywall
    services for which monies were still owed to plaintiff.
    ¶ 43   The circuit court determined that Porvaznik’s failure to immediately disclose the final lien
    waiver to defendants after his receipt of it in April 2019 was a mistake and that it was not
    purposefully withheld and that the significance of the final lien waiver (i.e., how much monies
    were owed to plaintiff) was for the jury to decide. The court further noted that the appropriate
    sanction for Porvaznik’s inadvertent failure to timely disclose the final lien waiver was not to
    dismiss plaintiff’s complaint and grant a default judgment for defendants on their counterclaim but
    to “try to get [defendants] a fair trial on this.” Ordinarily, the court would consider not allowing
    the final lien waiver to come in as a sanction, but in this case, defendants wanted the final lien
    waiver to come in to show that plaintiff was not entitled to all the damages it was asserting in its
    complaint. The court allowed defendants to introduce the final lien waiver at trial, gave them the
    option of conducting additional discovery and filing a motion for summary judgment, and it also
    granted defendants their attorney fees in preparing the sanctions motion.
    ¶ 44   We find no clear abuse of discretion in the court’s order disposing of defendants’ sanctions
    motion. The court found Porvaznik’s explanations for the delay in turning over the final lien waiver
    to be credible and indicative of no deliberate and contumacious disregard of its authority and that
    -11-
    No. 1-20-0774
    the best way to give defendants a fair trial was to offer the remedies described above. Generally,
    in a trial context, we have held that the trial court acting as a fact finder is in a better position than
    this court to weigh credibility as it actually saw and heard the witnesses, whereas we are limited
    to reviewing the “cold” written record. See e.g., Racky v. Befor USA Group, Inc., 
    2017 IL App (1st) 153446
    , ¶ 107.The same rationale applies here. Having seen and heard Porvaznik, the circuit
    court was in a better position than this court to weigh his credibility and determine the appropriate
    remedies for his inadvertent discovery violation and we will not substitute our judgment therefor.
    ¶ 45    Defendants also argue that McClernon committed a fraud on the court by representing that
    Plaintiff’s Exhibit 14 contained all the lien waivers when, in fact, it did not include the final lien
    waiver. Defendants cite out-of-state cases holding that such fraud merits dismissal of plaintiff’s
    cause of action. As discussed earlier in this order, McClernon explained that when she prepared
    Plaintiff’s Exhibit 14, Porvaznik had not yet made her aware of the final lien waiver. The court
    committed no abuse of discretion in finding that McClernon’s failure to include the final lien
    waiver in Plaintiff’s Exhibit 14 was a mistake and not fraud and that dismissal of plaintiff’s
    complaint was not an appropriate sanction.
    ¶ 46    Next, defendants argue that the circuit court erred by failing to grant them a setoff of
    $69,769.91 from the judgment entered against them on plaintiff’s breach of contract action. The
    term “setoff” is used in two distinct ways. One type of setoff refers to when a defendant has a
    distinct cause of action against the same plaintiff who filed suit against him and is subsumed
    procedurally under the concept of counterclaim. Thornton v. Garcini, 
    237 Ill. 2d 100
    , 113 (2010).
    The other type of setoff refers to defendant’s request for a reduction of the damages award because
    a third party has already compensated plaintiff for the same injury. 
    Id.
    -12-
    No. 1-20-0774
    ¶ 47     The setoff at issue here is of the first type, as it was brought as a counterclaim against
    plaintiff. Specifically, defendants claim that plaintiff overcharged them for plumbing supplies
    which one of plaintiff’s suppliers, Crawford Supply Group, Inc. (Crawford) provided to another
    subcontractor, DND Plumbing, Inc. (DND) and that the amount of the overcharge should be used
    to setoff plaintiff’s judgment. In support, defendants note that the final lien waiver that plaintiff
    provided to FAT on July 14, 2017, shows that defendants gave plaintiff $195,948.16 for payment
    to Crawford for plumbing supplies, but that Crawford subsequently sent a mechanics lien notice
    stating that it had only received $95,545.24 and was owed an additional $30,633.01. At trial, the
    parties entered into a written stipulation that plaintiff subsequently paid Crawford the $30,633.01
    due under the mechanics lien notice. That leaves $69,769.91 remaining from the original
    $195,948.16 which defendants gave to plaintiff to pay to Crawford. Defendants contend that the
    $69,769.91 constitutes an overpayment by them to plaintiff and should have been returned.
    Defendants request that the judgment entered against them on plaintiff’s breach of contract action
    be setoff by the $69,769.91 overpayment 1.
    ¶ 48     Although the ultimate determination of whether defendants are entitled to a setoff is a
    question of law subject to de novo review (id. at 115-116), the resolution of this issue necessarily
    involves a factual finding as to whether defendants overpaid plaintiff $69,769.91 for the plumbing
    supplies which Crawford provided to DND. As discussed, though, defendants did not provide us
    1
    In their appellants’ brief and at points in their supplemental reply brief, defendants argue for a setoff of
    $100,402.92, which represents the difference between the $195,948.16 they provided to plaintiff to pay over to
    Crawford for plumbing supplies and the $95,545.24 represented to have been paid to Crawford pursuant to the final
    lien waiver. On pages 11-12 of their supplemental reply brief, though, defendants acknowledge that the additional
    $30,633.01 payment made by plaintiff to Crawford pursuant to the mechanics lien notice lowers the alleged setoff
    amount to $69,769.91.
    -13-
    No. 1-20-0774
    with a transcript of the court’s oral factual findings, and therefore any doubts are resolved against
    them. Foutch, 
    99 Ill. 2d at 392
    .
    ¶ 49   Even addressing the issue on the merits, we still affirm.
    ¶ 50    Defendants argue that the final lien waiver and the written stipulation amount to a judicial
    admission by plaintiff that of the $195,948.16 it received from defendants for payment to Crawford
    for plumbing supplies, plaintiff only made two payments to Crawford of $95,545.24 and
    $30,633.01, for a total of $126,178.25, meaning that defendants overpaid plaintiff $69,769.91.
    ¶ 51   A judicial admission, which is conclusively binding, is a deliberate, clear, unequivocal
    statement by a party about a concrete fact within that party’s knowledge. In re Estate of Rennick,
    
    181 Ill. 2d 395
    , 406 (1998). Although the final lien waiver and written stipulation show that
    plaintiff made two payments to Crawford in the amounts of $95,545.24 and $30,633.01 for
    plumbing supplies, they make no deliberate, clear, unequivocal statement amounting to a judicial
    admission that those were the only payments plaintiff ever made to Crawford or that plaintiff kept
    the remaining $69,769.91 it received from defendants without ever paying it to Crawford. See In
    re Marriage of Hundley, 
    2019 IL App (4th) 180380
    , ¶ 118 (a judicial admission cannot be a matter
    of inference or uncertain summary). Accordingly, we must look elsewhere in the record for
    evidence as to whether plaintiff paid over to Crawford the entire $195,948.16 it received from
    defendants or whether plaintiff retained $69,769.91 of that amount for itself.
    ¶ 52   Plaintiff directs us to the trial testimony of its principal, Stykowski, who testified that the
    complete balance of $195,948.16 which defendants provided plaintiff to pay Crawford for
    plumbing supplies was in fact paid to Crawford through DND. Stykowski testified:
    “Q. Now, on this lien waiver, you have a line item here as of July 14, 2017, for Crawford.
    And on that it says the amount paid to date was $195,948.16, isn’t that correct?
    -14-
    No. 1-20-0774
    A. Correct.
    Q. And it’s your testimony here today that as of July 14, 2017, [plaintiff] paid Crawford
    $195,948.16 for the supplies that Crawford provided on Loomis?
    A. Correct. I paid to DND and DND paid to Crawford.”
    ¶ 53   Stykowski’s testimony was sufficient for the court to find that all of the $195,948.16 which
    defendants gave to plaintiff for payment to Crawford for plumbing supplies was ultimately paid to
    Crawford through DND, meaning that there was no overpayment by defendants and therefore that
    they were not entitled to a setoff.
    ¶ 54   Next, we address plaintiff’s cross-appeal. Plaintiff contends that the court erred in rejecting
    its contention that defendants breached the Loomis and Drexel contracts by failing to pay plaintiff
    hundreds of thousands of dollars for extra work it performed at those properties pursuant to verbal
    change orders made by defendants’ property manager, Richard Swiech. Plaintiff acknowledges
    that the contracts expressly provide that all change orders must be in writing but argues that it
    relied on Swiech’s apparent authority to make verbal change orders and that defendants waived
    the requirement that the change orders be in writing. The existence and scope of an agency
    relationship is typically a question of fact (McNerney v. Allamuradov, 
    2017 IL App (1st) 153515
    ,
    ¶ 64) and the court’s determination thereof following a bench trial will not be reversed on appeal
    unless against the manifest weight of the evidence. Staes and Scallan, P.C. v. Orlich, 
    2012 IL App (1st) 112974
    , ¶ 35.
    ¶ 55   To hold a principal liable under an apparent agency theory, the aggrieved third party must
    prove: the principal’s consent to or knowing acquiescence in the agent’s exercise of authority; the
    third party’s knowledge of the facts and good-faith belief that the agent possessed such authority;
    and the third party’s detrimental reliance on the agent’s apparent authority. Saletech, LLC v. East
    -15-
    No. 1-20-0774
    Balt, Inc., 
    2014 IL App (1st) 132639
    , ¶ 14. With respect to the first element, the principal’s consent
    or knowing acquiescence in the agent’s exercise of authority, plaintiff contends that the record on
    appeal contains five emails showing Swiech’s principal, Paunescu, consenting to Swiech making
    verbal change orders to the Loomis and Drexel contracts. Instead of citing us the specific pages of
    the record where those five emails are located, plaintiff informs us that they can be found
    somewhere on pages 1146-1290 of volume 2. The failure to cite to the specific pages of the record
    where the emails may be found violates Illinois Supreme Court Rule 341(h)(7) (eff. Oct. 1, 2020)
    (providing that “reference shall be made to the pages of the record on appeal where evidence may
    be found”). We are not required to comb the record searching for evidence supporting the
    appellant’s argument. See Thrall Car Manufacturing Co., 
    145 Ill. App. 3d 712
    , 719 (1986) (“[t]he
    appellate court is not a depository in which the appellant may dump the burden of argument and
    research”). Plaintiff’s argument could be found forfeited for its failure to comply with Rule
    341(h)7). Wells Fargo Bank, N.A. v. Sanders, 
    2015 IL App (1st) 141272
    , ¶ 43.
    ¶ 56   Despite plaintiff’s failure to comply with Rule 341(h)(7), we have examined pages 1146-
    1290 of volume 2 of the record and found the referenced emails, one from December 7, 2016, two
    from February 14, 2017, and February 20, 2017, one from March 23, 2017, and one from May 8,
    2017. The December email was from Swiech to an unidentified person named Mayra Quintana
    and merely states that plaintiff “is going to install the alarm,” but does not indicate in any way that
    the installation of the alarm was a change made verbally by Swiech which was then authorized by
    Paunescu. The February emails show Paunescu communicated directly with plaintiff to make
    certain changes to the Loomis and Drexel properties, but they do not show him authorizing any
    verbal change orders made by Swiech. The March email is from Swiech to Quintana and Paunescu
    and references a change order to the interior plumbing contract at the Loomis property, but it does
    -16-
    No. 1-20-0774
    not indicate that the change order was made verbally by Swiech and then authorized by Paunescu.
    The May 8 email is from an unidentified woman named Maria Maris to Swiech but it does not
    indicate any verbal change orders by Swiech that were then authorized by Paunescu. Thus, none
    of the five emails referenced by plaintiff show that Paunescu consented or knowingly approved of
    any verbal change orders made by Swiech.
    ¶ 57   Plaintiff cites the testimony of Phyllis Zecevic, the owner of DND, but she merely testified
    that she had worked on projects in the past where verbal change orders were made; she did not
    testify to Paunescu approving verbal change orders on the Loomis and Drexel projects at issue
    here. Plaintiff also cites the testimony of its owner, Rafal Stychowski, but the cited portion of his
    testimony does not relate to Paunescu’s approval of any of Swiech’s verbal change orders.
    ¶ 58   Finally, plaintiff cites Swiech’s testimony that Paunescu approved of his verbal change
    orders on the Loomis and Drexel projects. Paunescu testified to the contrary, stating that Swiech
    could make a change order only if he authorized it “in writing.” Paunescu further testified:
    “Q. So if Richard Swiech says that change orders were verbally approved routinely
    on Loomis, you’re saying that that’s not accurate?
    A. Correct.”
    ¶ 59    It was for the court as the trier of fact to consider the credibility of the witnesses and
    resolve conflicts in the evidence. Siguenza-Brito, 235 Ill. 2d at 228. Paunescu’s testimony was
    sufficient to show that he did not waive the contractual requirement that all change orders be in
    writing and did not consent or knowingly acquiesce in Swiech’s exercise of authority in issuing
    the verbal change orders. The court’s finding in favor of defendants on plaintiff’s apparent agency
    theory was not against the manifest weight of the evidence.
    -17-
    No. 1-20-0774
    ¶ 60   Next, plaintiff cursorily contends that the court should have granted its motion to
    reconsider and awarded it more monies based on Swiech’s apparent agency when making verbal
    change orders. For all the reasons discussed, the court committed no error in denying plaintiff’s
    motion to reconsider based on its apparent agency theory of recovery.
    ¶ 61   For all the foregoing reasons, we affirm the circuit court.
    ¶ 62   Affirmed.
    -18-
    

Document Info

Docket Number: 1-19-0560

Citation Numbers: 2021 IL App (1st) 190560-U

Filed Date: 6/18/2021

Precedential Status: Non-Precedential

Modified Date: 5/17/2024