Village of Plainfield v. Ionia Real Properties, LLC , 2024 IL App (3d) 230304-U ( 2024 )


Menu:
  •           NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except
    in the limited circumstances allowed under Rule 23(e)(1).
    
    2024 IL App (3d) 230304-U
    Order filed November 6, 2024
    ____________________________________________________________________________
    IN THE
    APPELLATE COURT OF ILLINOIS
    THIRD DISTRICT
    2024
    THE VILLAGE OF PLAINFIELD,             )     Appeal from the Circuit Court
    )     of the 12th Judicial Circuit,
    Plaintiff-Appellee,            )     Will County, Illinois,
    )
    v.                             )     Appeal No. 3-23-0304
    )     Circuit No. 18-CH-1761
    )
    IONIA REAL PROPERTIES, LLC;            )
    JOHN ARGOUDELIS, Individually;         )
    CARRINGTON TITLE PARTNERS, LLC;        )
    DARREN BENNEFIELD, Individually;       )
    and PHOENIX FIRE SYSTEMS, INC.,        )
    )
    Defendants                     )     Honorable
    )     John C. Anderson and
    (Ionia Real Properties, LLC and John   )     Roger D. Rickmon,
    Argoudelis, Defendants-Appellants).    )     Judges, Presiding.
    ____________________________________________________________________________
    JUSTICE DAVENPORT delivered the judgment of the court.
    Justices Holdridge and Albrecht concurred in the judgment.
    ____________________________________________________________________________
    ORDER
    ¶1        Held: In this breach of contract action, the court did not err when it (1) entered summary
    judgment in plaintiff’s favor, (2) denied defendants’ motion to disqualify,
    (3) granted plaintiff’s motion for protective order and to quash subpoenas, and
    (4) entered a $45,000 judgment against defendants.
    ¶2          Ionia Real Properties, LLC (Ionia) and its sole member, John Argoudelis (collectively
    defendants), appeal the circuit court’s rulings in favor of plaintiff, the Village of Plainfield
    (Village), on the parties’ cross motions for summary judgment, defendants’ motion to disqualify
    the Village’s attorney, the Village’s discovery motion, and money damages. We affirm.
    ¶3                                             I. BACKGROUND
    ¶4          In August 2017, Ionia purchased a vacant building within the common boundaries of the
    Village and the Plainfield Fire Protection District (District). 1 In September 2017, the Village issued
    Ionia a commercial change-of-occupancy permit for the property. The permit which did not allow
    occupancy of the property, was required for the Village to begin conducting inspections for
    compliance with Village ordinances and codes.
    ¶5          On October 25, 2017, the District informed Ionia by letter of numerous fire and safety
    issues that needed to be addressed, including the installation of a fire alarm system. Per the letter,
    Ionia was required to have all fire and safety items completed by January 26, 2018.
    ¶6          On November 13, 2017, the Village inspected the property and issued a temporary
    occupancy permit to Ionia. The Village informed Ionia of several items that violated Village code
    and required “Fire Department Approval” before it would issue an occupancy permit. On January
    26, 2018, the Village invalidated the temporary occupancy permit, citing Ionia’s failure to comply
    with the District’s letter. Between February and July 2018, the Village reissued Ionia’s temporary
    occupancy permit four times only to invalidate it each time due to Ionia’s failure to install a fire
    alarm system.
    ¶7          On May 15, 2018, Argoudelis presented a bid proposal for the fire alarm system during a
    meeting with the District’s marshal and chief. On May 21, 2018, the District sent Argoudelis a
    1
    The District is its own governmental entity and is not a party to this action.
    2
    letter indicating the District had reviewed the proposal. Per the letter, Argoudelis could eliminate
    three fire alarm pull stations shown in the proposal, since his office was “a small office space.”
    The letter also addressed the fire alarm control panel and annunciator panel. It further stated,
    “The remaining items listed for your fire alarm system are required by the fire codes
    and standards and cannot be eliminated. The fire alarm system is to be installed and
    monitored by June 14, 2018. Please have your fire alarm contractor submit plans
    for review and approval prior to beginning their installation. The fire alarm system
    installation is required to comply with Plainfield Fire Protection District and
    Village of Plainfield Ordinances, the 2015 International Fire Code, [National Fire
    Protection Association (NFPA)] 72 and NFPA 70.”
    The letter did not include a list of equipment. On June 14, 2018, Ionia had not yet installed the fire
    alarm system.
    ¶8          On July 13, 2018, the temporary occupancy permit for the property expired, but Ionia
    continued to occupy the property. The Village issued violation notices and fines.
    ¶9          On August 27, 2018, the Village and Ionia executed a memorandum of agreement
    (Agreement). The Agreement provided as follows:
    “This Agreement shall be effective as of August 27, 2018 (the ‘Effective Date’).
    ***
    Whereas, the District has determined that the [fire alarm] System is required for the
    Property and has agreed to accept the System as identified in the District’s May 21,
    2018 letter to [Ionia] ***[.]
    ***
    3
    2. Within sixty (60) days of the Effective Date of this Agreement, [Ionia] will
    comply with the District’s May 21, 2018 letter and install the System, and all
    applicable requirements and modifications as approved by the District. (See, Letter
    attached as Exhibit A).
    ***
    4. The parties to this Agreement agree that pursuant to the Village’s Code of
    Ordinances, a fine of Five Hundred Dollars ($500.00) per calendar day shall accrue
    from the Effective Date of this Agreement until installation of the System by [Ionia]
    and acceptance of the System by the District, which shall not be unreasonably
    delayed or withheld.
    5. [Ionia] will be allowed to occupy the Property during the installation period,
    however under no circumstances shall the installation period exceed sixty (60)
    calendar days from the Effective Date of this Agreement. All fines associated with
    the Violation Notice ($500.00/day) shall be waived upon installation of the System,
    and acceptance of the System by the District, provided installation and acceptance
    occurs within sixty (60) calendar days of the Effective Date of this Agreement.
    6. The Village will issue an Occupancy Permit to [Ionia] upon acceptance of the
    System by the District, and upon inspection of the Property by an authorized
    representative of the Village.
    7. Failure of the Owner to comply with the terms of the Agreement will result in
    the imposition of the above-referenced fines ($500.00/day), forfeiture of the
    Agreement, and [Ionia] shall immediately cease all business activities at, and
    4
    occupancy of, the Property. [Ionia] agrees to immediately remit to the Village,
    payment of all fine amounts owed under the terms of this Agreement ***.
    8. Notwithstanding the foregoing, [Ionia] shall not be deemed to be in violation of
    this Agreement if [it] is unable to complete installation of the system within sixty
    (60) days of the Effective Date of the Agreement due to an excusable delay. For
    purposes of this Agreement, ‘excusable delay’ shall mean only those circumstances
    beyond [Ionia’s] reasonable control.”
    ¶ 10          The fire alarm system was not installed by October 26, 2018 (that is, within 60 days of the
    Agreement’s effective date).
    ¶ 11          On November 1, 2018, the Village filed a verified complaint and an emergency motion for
    injunctive and other relief, seeking (1) to prohibit occupancy of the property until installation and
    final approval of the fire alarm system and issuance of an occupancy permit, and (2) a money
    judgment for all fine amounts.
    ¶ 12          Phoenix Fire Systems (Phoenix) finished installing the system on November 9, 2018, and
    the Village approved it on November 27, 2018.
    ¶ 13          On June 30, 2020, the Village amended its complaint, asserting claims for breach of
    contract, breach of fiduciary duty, and other relief. Ultimately, the amended complaint proceeded
    on one count of breach of contract against Ionia and one count of unjust enrichment against
    Argoudelis individually. Defendants asserted three affirmative defenses to the Village’s amended
    complaint: (1) estoppel, (2) defendants’ substantial compliance with the Agreement, and
    (3) unclean hands.
    ¶ 14                  A. Defendants’ Motion to Disqualify Joan Meyers as Counsel for the Village
    5
    ¶ 15           In December 2021, defendants moved to disqualify Joan Meyers as counsel for the Village.
    Defendants alleged Meyers drafted the Agreement and “[t]he testimony she may provide relates
    to the agreement she negotiated and drafted.”
    ¶ 16           The Village responded the Agreement was proposed and drafted by defendants’ counsel,
    not by Meyers. Moreover, the Village argued there was no issue before the court related to
    negotiating or drafting the Agreement. Meyers averred, “I was not directly involved in, nor do I
    have personal knowledge of, any aspect of the factual allegations identified in the pleadings filed
    in this matter.”
    ¶ 17           In reply, defendants argued the Agreement would be at issue during trial and Meyers was
    the only Village witness who could provide relevant information regarding the Village’s
    perspective as to why the terms of the Agreement were drafted the way they were.
    ¶ 18           After a hearing, the court denied the motion.
    ¶ 19                      B. The Village’s Motion for Protective Order and to Quash Subpoenas
    ¶ 20           In December 2021, defendants served notices of depositions and subpoenas on current and
    former Village trustees, the former Village president, the former Village administrator, and the
    Village attorney. In January 2022, the Village moved for a protective order barring the depositions
    of the Village’s current trustees and legal counsel, and to quash subpoenas for the former trustees,
    administrator, and Village president. Each individual that defendants wished to depose averred
    they had no personal knowledge of the factual allegations identified in the pleadings.
    ¶ 21           Defendants responded that the entire lawsuit was politically motivated, guided the behavior
    of the Village staff, and was instrumental in the negotiation of the Agreement’s terms.
    ¶ 22           The Village replied defendants provided no explanation for how the Village’s motivation
    in bringing this lawsuit would somehow be relevant to whether defendants complied with the
    6
    Agreement to install the fire alarm system by the October 26, 2018, deadline. Furthermore, the
    exact terms of the Agreement were written in plain language and defendants have not challenged
    the enforceability of the Agreement.
    ¶ 23          After a hearing, the court granted the motion, reasoning defendants had not identified a
    reasonable need to depose the individuals.
    ¶ 24                                            C. Depositions
    ¶ 25          During discovery, Argoudelis, James Callahan of Phoenix, and Mary Ludemann of the
    District were deposed. Their testimony is summarized below.
    ¶ 26                                      1. Argoudelis’s Deposition
    ¶ 27          Argoudelis’s attorney at the time negotiated, drafted, and executed the Agreement with the
    Village. Argoudelis knew the Agreement required the fire alarm system to comply with the
    District’s May 21, 2018, letter. He testified, “The letter’s incorporated in the agreement. I wasn’t
    focusing on the details of the letter other than—the main thing I was focused on was the equipment
    and the cost of the equipment being requested, not the process and how you get it installed and
    approved.” Ludemann never said the District needed a written plan until late October, and to his
    knowledge, the first time his contractor knew that plans needed to be submitted was in late October.
    ¶ 28          On October 2, 2018, Callahan sent Argoudelis a quote for the fire alarm installation.
    Argoudelis did not sign the quote immediately because Callahan was going to discuss it with
    Ludemann to ensure it was acceptable and they could move forward. Argoudelis believed he
    signed the quote on October 15. He did not recall Callahan telling him the quote needed to be
    signed before Callahan would prepare any plans. Argoudelis explained his email archives are
    missing all sent emails from late 2017 to early 2019, so the email he sent to Phoenix with the
    signed quote on October 15 could not be produced in discovery. On October 22, Callahan emailed
    7
    Argoudelis informing Argoudelis he still had not received the signed quote and Phoenix could not
    start work without it. Argoudelis wrote back, “I sent this to you on 10/16. Please confirm receipt.
    You did tell me last week that you would produce the drawings and submit them to [Ludemann].
    Where are you at with this? I need them submitted within a day or so since they are taking such a
    hard line.” Argoudelis knew as of October 22 that Callahan was not going to start preparing plans
    prior to having a signed quote, but he was not sure if Callahan articulated this to him before.
    ¶ 29          Argoudelis confirmed the system was not installed and accepted within 60 days as required
    by the Agreement, but he believed there was an excusable delay. Ludemann insisted on requiring
    additional equipment, and she did not give Phoenix approval to start installation until October 24
    or 25. This back and forth between Ludemann and Phoenix was not within Argoudelis’s control.
    ¶ 30                                       2. Callahan’s Deposition
    ¶ 31          Callahan was employed by Phoenix as a sales representative and project manager. His role
    was to provide fire alarm equipment for the building to meet Plainfield code and to coordinate
    installation. He contracted out actual installation of the equipment to a different company.
    ¶ 32          His first conversation with Argoudelis was on August 21 or 22, 2018. Callahan sent
    Argoudelis an installation proposal and quote on September 17, 2018, but Argoudelis did not sign
    it because it contained more devices than he wanted installed. Around October 1, Argoudelis sent
    Callahan a list of devices and asked him to revise the proposal to match this list. Callahan sent
    Argoudelis a revised quote on October 2, but Argoudelis did not immediately sign it. The two
    communicated on October 10 and 11, but Argoudelis did not tell Callahan why he did not sign the
    revised quote. Per company policy, Phoenix needed a signed quote to proceed with any work.
    ¶ 33          Callahan did not email the October 2 proposal to Ludemann because he had to submit
    drawings. The District did not review proposals and quantities; it wanted to use building layout
    8
    and see the design. In his experience, a quote or proposal for the installation of a fire alarm system
    was not sufficient to send to a fire protection district. To get a system approved, he had to send a
    fully engineered set of drawings, battery calculations, design, and descriptions of the rooms so the
    District knew what type of equipment was necessary. Ludemann would not have known whether
    the system was correctly laid out for this particular building just by looking at building material.
    ¶ 34           As of October 12, Phoenix had not prepared a drawing, but it was in the preliminary stages.
    Callahan testified,
    “We knew at some point he was going to sign the proposal. So we kind of acted
    on—because we know he had to have a system installed rather quickly. So we
    started doing some preliminary work. I was asking him for some kind of drawing,
    a building layout of his building so we can incorporate it into our drawings.”
    ¶ 35           Callahan did not recall receiving the signed quote on October 16. He received the signed
    quote for the first time on October 22. Phoenix immediately generated a set of drawings to submit
    to the District because it knew Argoudelis was under time constraints. Callahan sent the completed
    drawing plans to Argoudelis on October 23 and submitted them to the District on October 24.
    Ludemann sent Callahan a fire alarm plan review letter on October 25. This was not full approval
    because the District still required two devices to be added, but it allowed Phoenix to begin
    installation.
    ¶ 36           Phoenix completed the fire alarm system installation on November 9. The District tested
    the system on November 13. The system passed, with the stipulation to add two more devices. The
    District retested and approved the system on November 27.
    ¶ 37           It took approximately two and a half weeks to install the system. Argoudelis’s failure to
    sign the quote delayed the installation.
    9
    ¶ 38                                        3. Ludemann’s Deposition
    ¶ 39             Ludemann worked for the District as an inspector and marshal. On May 15, 2018,
    Argoudelis met with her and the District’s chief. They discussed Argoudelis’s bid proposal. This
    was not an actual plan submission. Ludemann testified, “there was no drawing submitted, so there
    was no way for me to know with that bid proposal what was going where. I needed a plan review
    in order to determine if the system was sufficient.”
    ¶ 40             On May 21, the chief sent Argoudelis a letter stating plans needed to be submitted for
    review and approval, and the system needed to comply with all codes, standards, and ordinances.
    The District was trying to work with Argoudelis by omitting some of the items as specified in the
    letter.
    ¶ 41             Ludemann had no input in drafting the Agreement.
    ¶ 42             Phoenix submitted the plan drawings on October 23. Ludemann reviewed them and sent
    Phoenix a plan review letter the next day. Normally, this is a 14-day turnaround, but she turned
    this around right away to avoid any further delays. The plan review letter did not reject Phoenix’s
    plans but required two additional devices to be added to what Phoenix submitted. According to
    Ludemann, “They weren’t shown on the plans, it’s not above and beyond, it’s the basic minimum
    requirements. Why they weren’t shown, I can’t answer.” These were the only plans she received,
    and the only plan review she conducted was based on these plans. During the deposition, defense
    counsel showed Ludemann the two quotes from Phoenix. She testified,
    “The point is what you are showing me is nothing to do with anything I would
    review, it’s between the client and their contractor. The plans that were sent to me
    were reviewed, there was a requirement for a strobe in the bathroom and a strobe
    10
    in the basement with a horn per code that wasn’t on the plans for whatever reason
    and that was requested to be added per code and that’s that.”
    ¶ 43           The District tested the system on November 13 and found that two devices, required by
    code, were still missing. The system was retested on November 27, after the required devices were
    installed.
    ¶ 44                          D. The Parties’ Cross Motions for Summary Judgment
    ¶ 45           In April 2022, the Village moved for summary judgment, arguing as follows. It was
    undisputed the Agreement was enforceable and required Ionia to install a code-compliant fire
    alarm system within 60 days of the Agreement’s effective date, that is, by October 26, 2018.
    Further, Ionia agreed to pay the Village a fine of $500 per day, which would be waived only if
    installation and approval of the fire alarm system occurred by October 26, 2018. Ionia failed to
    install the system by October 26, 2018, and, moreover, there was nothing to excuse Ionia’s
    noncompliance. Lastly, the evidence revealed Argoudelis was solely responsible for delaying
    installation by failing to timely execute a quote with Phoenix.
    ¶ 46           Defendants also moved for summary judgment. They argued as follows. The Agreement
    required the Village to waive all fines upon acceptance of the fire alarm system because the 60-
    day deadline was a nonmaterial clause and did not affect the parties’ bargained-for objective. The
    Agreement reflected a compromise where the Village and Ionia were not tied to one specific
    completion date. The Agreement’s purpose was to ensure the installation of a fire alarm system at
    the property; because the system has been installed, any fines constituted an unenforceable penalty.
    Moreover, the Village’s breach of contract claim failed because the Village suffered no damages.
    ¶ 47                             E. The Court’s Summary Judgment Rulings
    11
    ¶ 48          On June 24, 2022, the court granted the Village’s motion for summary judgment and denied
    defendant’s motion. Thus, only the issue of damages remained pending.
    ¶ 49                                               F. Damages
    ¶ 50          On August 23, 2022, defendants filed a brief regarding damages. They argued the purpose
    of paragraph 7 of the Agreement was to secure performance or punish nonperformance. According
    to paragraph 7:
    “Failure of [Ionia] to comply with the terms of the Agreement will result in the
    imposition of the above-referenced fines ($500.00/day), forfeiture of the
    Agreement, and [Ionia] shall immediately cease all business activities at, and
    occupancy of, the Property. [Ionia] agrees to immediately remit to the Village,
    payment of all fine amounts owed under the terms of this Agreement ***.”
    Defendants contended the fine provision resulted in a windfall recovery for the Village and was
    not a credible estimate of damages.
    ¶ 51          The Village responded the fines would have been owed by Ionia regardless of whether the
    Agreement was executed, because the fines were imposed pursuant to Village code. The Village’s
    agreement to waive Ionia’s fines in exchange for Ionia installing the fire alarm system within 60
    days and then the Village’s refusal to waive the fines when Ionia breached the Agreement did not
    somehow transform the fines into an unenforceable penalty.
    ¶ 52          On November 1, 2022, the court found paragraph 7 of the Agreement was an unenforceable
    penalty clause.
    ¶ 53                                  G. The Village’s Motion to Reconsider
    ¶ 54          On November 18, 2022, the Village moved to reconsider the November 1 order. The
    Village asserted by finding the Agreement contained an unenforceable penalty clause, the court
    12
    failed to consider (1) the undisputed facts regarding the drafting of the Agreement, (2) the
    bargained-for consideration that was the basis of the Agreement, (3) the Village’s code mandating
    the amount of fines imposed for violations, and (4) the fines that Ionia already accrued by the time
    the Agreement was executed. The Village also argued by granting its motion for summary
    judgment but then finding paragraph 7 of the Agreement to be unenforceable, it was impossible to
    reconcile the two rulings: that judgment should be entered in favor of the Village, but the Village
    was not entitled to recover the fines set forth in the Agreement.
    ¶ 55          In response, defendants asserted the Village had not brought any newly discovered
    evidence, no changes in existing law, and had not pointed out any errors in the court’s application
    of existing law.
    ¶ 56          On June 12, 2023, the court granted the Village’s motion to reconsider with respect to the
    breach of contract claim and entered judgment against Ionia in the amount of $45,000. The court
    denied the motion to reconsider with respect to the unjust enrichment claim against Argoudelis.
    Defendants appealed.
    ¶ 57                                             II. ANALYSIS
    ¶ 58          On appeal, defendants argue the circuit court erred when it (1) granted the Village’s motion
    for summary judgment, (2) denied defendants’ motion for summary judgment, (3) denied
    defendants’ motion to disqualify, (4) granted the Village’s motion for protective order and to quash
    subpoenas, and (5) entered a judgment for $45,000, against Ionia.
    ¶ 59          As an initial matter, the Village argues defendants’ brief should be stricken and the appeal
    dismissed because the brief does not comply with Illinois Supreme Court Rule 341(h)(6) (eff. Oct.
    1, 2020) in that their statement of facts does not provide this court with a complete picture of the
    proceedings. The Village previously filed a motion to strike the brief on this same basis, and we
    13
    denied the motion. While that ruling is not binding, we conclude defendants’ violation does not
    hinder our review to the point that dismissing the appeal would be appropriate. See Ittersagen v.
    Advocate Health & Hospitals Corp., 
    2021 IL 126507
    , ¶ 37.
    ¶ 60                          A. The Parties’ Cross Motions for Summary Judgment
    ¶ 61          Defendants argue the circuit court erred in granting the Village’s motion for summary
    judgment, because there was a question of material fact on the issue of excusable delay.
    Specifically, they maintain the record shows the delay was at least in part caused by the District.
    First, defendants point out the District required Ionia to add equipment above and beyond the
    original agreed-upon system, which resulted in the installation delay. Second, defendants note they
    did not control Phoenix or the physical installation of the fire alarm system, and defendants
    communicated to Phoenix there was a completion deadline. In addition, defendants point to their
    verified denials of 27 paragraphs of the Village’s complaint and assert the circuit court failed to
    take defendants’ affirmative defenses into account.
    ¶ 62          Defendants also contend the circuit court erred in denying their motion for summary
    judgment. Defendants argue the 60-day installation deadline was a nonmaterial clause, the alleged
    breach did not deprive the Village of the benefit of its bargain, and it did not result in any damages
    to the Village. According to defendants, the Agreement’s bargained-for objective was to have the
    fire alarm system installed at the property and for the property to receive an occupancy permit
    within a reasonable amount of time. The fines were never a bargained-for objective but rather a
    potential consequence if the system was not installed. Further, they argue the fines were an
    unenforceable penalty to coerce performance rather than a valid liquidated damages provision.
    Therefore, defendants allege, the fines result in a windfall to the Village.
    14
    ¶ 63          The Village argues defendants’ claims are unsupported by the evidentiary record, and the
    circuit court properly granted its motion for summary judgment. The Village asserts defendants
    have not cited any evidence to suggest the District required Ionia to install a fire alarm system that
    was above and beyond what was required under law and what was agreed to by the parties.
    Moreover, the Village asserts Argoudelis alone delayed the fire alarm installation through his
    failure to agree to and execute a quote with Phoenix in a timely manner. Argoudelis did not execute
    the quote that would allow Phoenix to initiate the work until October 22, 2018, just 4 days before
    the Agreement’s 60-day deadline. According to the Village, defendants ignore Callahan’s
    deposition testimony that Argoudelis’s failure to sign the quote caused the delay.
    ¶ 64          The Village argues the circuit court also properly denied defendants’ motion for summary
    judgment. According to the Village, defendants’ argument that the Agreement’s 60-day deadline
    was immaterial is disingenuous. The Village maintains the timing of the installation was the
    precise consideration that was bargained for and the essential objective of the Agreement.
    Moreover, the Village argues, even in the absence of the Agreement, Ionia would have been
    required to install the fire alarm system. The only consideration the Village received was that the
    installation must occur within 60 days. The specific date the installation needed to be completed
    for the fines to be waived was negotiated by Ionia’s attorney and agreed to by Ionia. Further, the
    Village argues, the inclusion of an excusable delay provision would have been unnecessary if the
    timing of the installation was an immaterial term. The Village maintains that despite defendants’
    representations, it is not imposing a $500 per day fine on Ionia as a penalty for installing the fire
    alarm system 14 days late. To the contrary, this fine was imposed pursuant to Village code, the
    Village began issuing violation notices in August 2018, and Ionia would have owed the fines
    regardless of whether the Agreement was executed. Defendants presented no facts or legal
    15
    authority to support its argument that by failing to waive Ionia’s fines, the Village is imposing an
    unenforceable penalty. Finally, the Village contends Ionia had in fact delayed installing a fire alarm
    system for over a year.
    ¶ 65          Summary judgment will be granted if the “pleadings, depositions, and admissions on file,
    together with the affidavits, if any, show that there is no genuine issue as to any material fact and
    that the moving party is entitled to a judgment as a matter of law.” 735 ILCS 5/2-1005(c) (West
    2020). “A summary judgment, interlocutory in character, may be rendered on the issue of liability
    alone although there is a genuine issue as to the amount of damages.” 
    Id.
     “When parties file cross-
    motions for summary judgment, they agree that only a question of law is involved and invite the
    court to decide the issues based on the record.” Pielet v. Pielet, 
    2012 IL 112064
    , ¶ 28. “However,
    the mere filing of cross-motions for summary judgment does not establish that there is no issue of
    material fact, nor does it obligate a court to render summary judgment.” 
    Id.
     “In reviewing a trial
    court’s grant of summary judgment, we do not assess the credibility of the testimony presented
    but, rather, determine only whether the evidence presented was sufficient to create an issue of
    material fact.” Lau v. Abbott Laboratories, 
    2019 IL App (2d) 180456
    , ¶ 37. We review the circuit
    court’s decision to grant a motion for summary judgment de novo. Shaw v. U.S. Financial Life
    Insurance Co., 
    2022 IL App (1st) 211533
    , ¶ 26.
    ¶ 66          After careful review of the record, we find there is no genuine issue as to any material fact
    and the Village was entitled to judgment as a matter of law. Defendants’ claims are not supported
    or are outright contradicted by the record. Defendants’ argument that the District required
    additional equipment above and beyond the Agreement is misguided. The Agreement itself states
    Ionia “will comply with the District’s May 21, 2018 letter and install the System, and all applicable
    requirements and modifications as approved by the District.” (Emphasis added). The District in
    16
    its May 21 letter did not agree to accept the system as is; a formal review and approval process
    was still required. Additionally, defendants never presented any evidence that shows the
    equipment exceeded that which was required by the Village’s code.
    ¶ 67          Admittedly, defendants did not have control over Phoenix or the physical installation. But
    it is undisputed Argoudelis did not return a signed quote to Phoenix until four days before the
    installation deadline. Even if Argoudelis returned the signed quote on October 15, as he testified,
    that left only 12 calendar days for the fire alarm system to be reviewed, approved, installed, tested,
    and pass final inspection. The District informed Argoudelis in the October 25, 2017, letter that
    installation of a fire alarm system takes more than 30 days to complete. Callahan testified
    Argoudelis caused the delay, and defendants submit nothing to refute that. Because signing the
    quote with Phoenix was entirely within Argoudelis’s control, it was Argoudelis alone that caused
    the delay. Thus, there was no “excusable delay” as defined in the Agreement.
    ¶ 68          Defendants also emphasize their verified denials of 27 paragraphs of the Village’s amended
    complaint. However, “[i]f the party moving for summary judgment supplies facts that, if not
    contradicted, would warrant judgment in its favor as a matter of law, the opponent cannot rest on
    his pleadings to create a genuine issue of material fact.” Harrison v. Hardin County Community
    Unit School District No. 1, 
    197 Ill. 2d 466
    , 470 (2001). This is true even if the pleading is verified.
    Fryison v. McGee, 
    106 Ill. App. 3d 537
    , 539 (1982). Defendants’ denials, with nothing more, are
    not enough to create a genuine issue of material fact. Moreover, defendants’ defenses provide
    nothing that create a genuine issue of material fact because the defenses rely on the same arguments
    and facts that are undisputed by the record.
    ¶ 69          Defendants’ reasoning in their argument that the court erred in denying its motion for
    summary judgment wholly ignores the Agreement’s plain language. “If the words in the contract
    17
    are clear and unambiguous, they must be given their plain, ordinary and popular meaning.”
    Thompson v. Gordon, 
    241 Ill. 2d 428
    , 441 (2011). “A court will not interpret a contract in a manner
    that would nullify or render provisions meaningless, or in a way that is contrary to the plain and
    obvious meaning of the language used.” 
    Id. at 442
    . The Agreement is clear that defendants had 60
    days to install the system, a $500 per day fine would be imposed if Ionia did not comply with the
    Agreement, and that fine would be waived only if the system was installed within 60 days. Only
    an excusable delay outside Ionia’s control would excuse Ionia’s untimely performance. We fail to
    see how the 60-day deadline was not a material provision in the Agreement. If the timeline was
    immaterial, the fine and excusable-delay provisions would be rendered meaningless, thus
    rendering the entire Agreement meaningless. We decline to read the 60-day deadline provision as
    an immaterial term.
    ¶ 70          The fine provision in the Agreement was a valid liquidated damages clause, not an
    unenforceable penalty. “It is a general rule of contract law that, for reasons of public policy, a
    liquidated damages clause which operates as a penalty for nonperformance or as a threat to secure
    performance will not be enforced.” Jameson Realty Group v. Kostiner, 
    351 Ill. App. 3d 416
    , 423
    (2004). Three elements must be met to validate a liquidated damages clause:
    “(1) the parties intended to agree in advance to the settlement of damages that
    might arise from the breach; (2) the amount of liquidated damages was reasonable
    at the time of contracting, bearing some relation to the damages which might be
    sustained; and (3) actual damages would be uncertain in amount and difficult to
    prove.” 
    Id.
    The parties agreed to the daily fine. The amount was reasonable, because pursuant to the local
    ordinance, “[t]here shall be an automatic five hundred dollars ($500.00) fine per day if the structure
    18
    is occupied prior to receiving a temporary occupancy permit or an occupancy permit.” Plainfield
    Building Code § 2.5-15 (approved Jan. 4, 2016). Actual damages would be uncertain because it is
    dependent on the number of days defendants are in violation. Moreover, without the Agreement,
    the Village could have collected fines for the entire time defendants occupied the property without
    an occupancy permit or temporary occupancy permit, from July 13, 2018, to November 27, 2018.
    By our calculation, those fines would have amounted to $68,500. Instead, by entering into the
    Agreement with defendants, the Village forfeited the right to collect fines incurred before August
    27, 2018.
    ¶ 71          Additionally, the fines the Village seeks pursuant to the Agreement are not a windfall. The
    entire purpose of the Agreement was for defendants to install a fire alarm system that they had
    failed to do for nearly a year, in violation of local ordinances. Although defendants did not comply
    with the Agreement, they still benefited as the Village waived the fines incurred before the
    Agreement.
    ¶ 72          The court did not err in granting the Village’s motion for summary judgment nor in denying
    defendants’ motion for summary judgment.
    ¶ 73                                  B. Defendants’ Motion to Disqualify
    ¶ 74          Defendants also argue the circuit court erred when it declined to disqualify the Village’s
    counsel, Joan Meyers. According to defendants, Meyers negotiated the Agreement on behalf of
    the Village. Defendants maintain they should have been allowed to depose Meyers because she
    negotiated the Agreement.
    ¶ 75          “The advocate-witness rule precludes an attorney from acting as an advocate and as a fact
    witness in the same case.” Cushing v. Greyhound Lines, Inc., 
    2013 IL App (1st) 103197
    , ¶ 317.
    But “disqualification is regarded as a drastic measure [citation] which courts should grant only
    19
    when the movant can show that the lawyer’s testimony is likely to prejudice the testifying lawyer’s
    own clients.” Weil, Freiburg & Thomas, P.C. v. Sara Lee Corp., 
    218 Ill. App. 3d 383
    , 396 (1991).
    “[A] motion to disqualify is addressed to the sound discretion of the trial court, and its
    determination will not be disturbed absent a showing of abuse of that discretion.” Macknin v.
    Macknin, 
    404 Ill. App. 3d 520
    , 530 (2010). “An abuse of discretion occurs where no reasonable
    person would agree with the position adopted by the trial court.” Schwartz v. Cortelloni, 
    177 Ill. 2d 166
    , 176 (1997).
    ¶ 76          The Village argues the court properly denied defendants’ motion to disqualify because
    defendants never presented a valid reason to call Meyers as a witness. The Village maintains
    Meyers did not participate in, and has no personal knowledge of, the factual allegations identified
    in the pleadings. She did not draft the Agreement; the Agreement was proposed and drafted by
    defendants’ counsel. More importantly, the negotiation or drafting of the Agreement was never at
    issue. We agree with the Village.
    ¶ 77          Defendants did not show how Meyers’ testimony would likely prejudice the Village. The
    record clearly establishes Meyers did not draft the Agreement and she was not personally involved
    in the fire alarm system installation. Disqualification, a drastic measure, was not appropriate under
    the circumstances. The court did not abuse its discretion.
    ¶ 78                  C. The Village’s Motion for Protective Order and to Quash Subpoenas
    ¶ 79          Defendants contend the circuit court erred in granting the Village’s motion for protective
    order and to quash subpoenas. “The applicable standard of review for rulings on discovery issues
    is the abuse of discretion standard.” Illinois Environmental Protection Agency v. Illinois Pollution
    Control Board, 
    386 Ill. App. 3d 375
    , 390 (2008). “We review a circuit court’s decision to quash a
    subpoena for abuse of discretion.” Parkway Bank & Trust Co. v. Korzen, 2013 IL App (1st)
    20
    130380, ¶ 62. Defendants argue the information sought in their discovery requests, specifically the
    negotiation of Agreement terms, are relevant to the issues in this case. According to defendants,
    they should have been able to depose the people responsible for negotiating, drafting, and
    approving the Agreement, including the former Village president who signed the Agreement.
    ¶ 80          The Village argues that, while defendants claim these current and former Village
    employees may have information pertaining to the negotiation of the Agreement and the meaning
    of the terms in the Agreement, none of those issues were in dispute in the litigation. Further, it
    contends, defendants have not articulated how any of these individuals had any relevant
    information to the litigation. We agree with the Village.
    ¶ 81          Of the list of Village employees defendants subpoenaed, only one individual—the former
    Village president—had even a remote connection to the Agreement: he signed the agreement. But
    there is no evidence to suggest he was any more involved than that. Defendants were interested in
    deposing the people responsible for negotiating, drafting, and signing the Agreement, yet neglected
    to depose the only individual who actually drafted the Agreement. Argoudelis himself testified
    that his attorney at the time drafted the Agreement. There is nothing in the record that suggests
    any other Village employees, past or present, were involved in executing the Agreement. The court
    did not abuse its discretion.
    ¶ 82                                   D. Money Judgment Against Ionia
    ¶ 83          Finally, defendants claim the circuit court erred in entering a money judgment of $45,000
    against Ionia because there was no hearing on damages and an evidentiary hearing was necessary
    to calculate the amount of damages. Defendants again argue the Agreement’s excusable-delay
    provision limited the amount of damages to delays caused by Ionia. Defendants now argue the
    time period between Phoenix installing the system and the District approving the system was
    21
    beyond Ionia’s reasonable control and therefore fell within the excusable-delay provision.
    According to defendants, the court should have heard testimony to determine how much of this
    time period was an excusable delay.
    ¶ 84          The Village argues the judgment was proper and no evidentiary hearing was required. They
    assert no factual issues required resolution before damages could be imposed. According to the
    Village, the motions for summary judgment fully briefed the issues of whether there was an
    excusable delay and whether the Agreement contained a liquidated damages clause, and
    defendants point to no facts or evidence to suggest an excusable delay existed. Under the
    Agreement, Ionia agreed to pay $500 per day in fines from the effective date of the Agreement
    until the District approved the fire alarm system’s installation. Defendants admit the fire alarm
    system was not installed and approved until November 27, 2018, well past the Agreement’s 60-
    day deadline. According to the Village, the time between the effective date of the Agreement and
    the date the fire alarm system was installed and approved, results in $45,000 in fines.
    ¶ 85          “A trial court’s assessment of damages will not be disturbed unless it is against the manifest
    weight of the evidence.” Amalgamated Bank of Chicago v. Kalmus & Associates, Inc., 
    318 Ill. App. 3d 648
    , 658 (2000). “A damage award is against the manifest weight of the evidence if the
    trial court ignores the evidence or the measure of damages is erroneous as a matter of law.” 
    Id.
    ¶ 86          The Agreement is clear that the $500 per day fine would accrue from the Agreement’s
    effective date until the system was installed by Ionia and accepted by the District. It is undisputed
    that the system was finally approved on November 27, 2018. The record is also clear there was no
    excusable delay outside of Ionia’s control that would excuse some or all of the fines, as Argoudelis
    alone caused the delay.
    22
    ¶ 87          Moreover, according to the Agreement, “[f]ailure of [Ionia] to comply with the terms of
    the Agreement will result in the imposition of the above-referenced fines ($500.00/day), forfeiture
    of the Agreement, and [Ionia] shall immediately cease all business activities at, and occupancy of,
    the Property.” (Emphasis added). The Village chose not to invoke the forfeiture provision. Had
    the Village invoked the forfeiture provision, Ionia would have owed all fines accruing from July
    13, 2018, to November 27, 2018.
    ¶ 88          We agree with the Village that there were no factual issues to be resolved in calculating
    damages, and a hearing was therefore unnecessary. However, both parties miscalculated damages.
    The total number of days from the effective date of the Agreement (August 27, 2018) to the date
    the system was finally approved (November 27, 2018) is 92 days. A $500 fine for 92 days amounts
    to $46,000. The Village’s reliance on 60 days in its calculation in its brief appears to be in error.
    Defendants provide no clear calculations. Yet, throughout the record, the Village only requested
    $45,000 in damages. Thus, the circuit court did not err in entering a $45,000 judgment against
    Ionia, and we affirm the court’s calculation of damages.
    ¶ 89                                           III. CONCLUSION
    ¶ 90          The judgment of the circuit court of Will County is affirmed.
    ¶ 91          Affirmed.
    23
    

Document Info

Docket Number: 3-23-0304

Citation Numbers: 2024 IL App (3d) 230304-U

Filed Date: 11/6/2024

Precedential Status: Non-Precedential

Modified Date: 11/6/2024