Leo Prassas v. Corick Construction, LLC (mem. dec.) ( 2015 )


Menu:
  •       MEMORANDUM DECISION
    Pursuant to Ind. Appellate Rule 65(D),
    this Memorandum Decision shall not be
    Dec 28 2015, 8:37 am
    regarded as precedent or cited before any
    court except for the purpose of establishing
    the defense of res judicata, collateral
    estoppel, or the law of the case.
    ATTORNEY FOR APPELLANT
    Gregg Romaine
    Romaine Law
    Fishers, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Leo Prassas,                                            December 28, 2015
    Appellant-Plaintiff,                                    Court of Appeals Case No.
    64A05-1508-CT-1081
    v.                                              Appeal from the Porter Superior
    Court
    Corick Construction, LLC,                               The Honorable William E. Alexa,
    Appellee-Defendant.                                     Judge
    Trial Court Cause No.
    64D02-1502-CT-891
    Bradford, Judge.
    Case Summary
    [1]   In February of 2013, Appellant-Plaintiff Leo Prassas contracted with Appellee-
    Defendant Corick Construction, LLC to have some roofing work done at his
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015      Page 1 of 13
    residence. After the work was completed, Prassas filed a small claims action
    against Corick Construction alleging that the repairs had been completed in an
    unworkmanlike manner. After the small claims court found in favor of Corick
    Construction, Prassas filed the instant lawsuit, which alleges breach of contract,
    breach of implied warranty, and deceptive practices. Corick Construction
    subsequently filed a motion to dismiss. Prassas responded to this motion and
    filed a motion for default judgment. Following a hearing on the parties’
    motions, the trial court issued an order in which it ruled in favor of Corick
    Construction.
    [2]   Prassas appealed, arguing that the trial court erred in ruling in favor of Corick
    Construction. Concluding that the trial court did not commit reversible error in
    effectively treating Corick Construction’s motion to dismiss as a motion for
    summary judgment but that issues of material fact remain that would preclude
    an award of summary judgment in Corick Construction’s favor, we reverse the
    judgment of the trial court and remand the matter to the trial court for further
    proceedings.
    Facts and Procedural History
    [3]   At all times relevant to the instant appeal, Corick Construction was under a
    voluntary-compliance order aimed at curtailing deceptive practices against
    consumers to whom it had supplied roofing services. As part of this order,
    Corick Construction was ordered to change its standard contract form to
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 2 of 13
    comply with Indiana law and to refrain from acting as a public insurance
    adjuster.
    [4]   On February 13, 2013, Prassas and Corick Construction entered into a contract
    for Corick to repair and replace Prassas’s hail-damaged roof. The contract
    entered into by the parties is the same contract as the Indiana Attorney
    General’s Office had prohibited Corick Construction from using. The contract
    failed to provide a sufficient scope of services and provided for a guaranteed
    recovery fee from the insurance proceeds even if Corick Construction did not
    complete the contracted work.
    [5]   Corick Construction worked with Prassas and his insurance company to assess
    Prassas’s damages and the associated repairs to assure that Prassas’s insurance
    company would pay for the necessary roof repairs. In completing the
    contracted work, Corick Construction replaced the shingles on the roof and
    partially replaced the gutters and downspouts. Prassas, a senior citizen, was not
    able to get up on the roof to inspect the installation of the shingles but
    repeatedly complained to Corick Construction that the downspouts were not
    replaced properly and the gutters were not angled properly to allow for the
    proper flow of water into the downspouts.
    [6]   During the fall of 2014, a neighbor approached Prassas and informed him that
    something appeared to be wrong with his roof. The neighbor, who had a
    background in construction, told Prassas that the roof looked “wavy” and that
    the shingles looked slightly curled at the edges. Appellant’s App. p. 6. During
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 3 of 13
    the late fall 2014 and early winter of 2015, Prassas had his roof inspected by
    several roofers. These roofers informed Prassas that they observed that the
    shingle spacing varied greatly, the shingles looked worn and had curled at the
    edges, and the gutters were not properly angled at the rear of the house.
    [7]   On February 4, 2015, Prassas filed a complaint for damages against Corick
    Construction alleging breach of contract, breach of implied warranty, and
    deceptive practices. In this complaint Prassas acknowledges that Corick
    Construction maintains that the roof and gutters were properly replaced and
    that there is no defect with the work performed under the contract. Prassas
    claims, however, that he will have to have the roof replaced and the gutters
    rehung as a result of Corick Construction’s allegedly faulty installation of the
    roof and gutters. Prassas claims that by acting as a public adjuster, Corick
    Construction caused Prassas to “not have a final inspection by an insurance
    representative who probably would have seen the defective workmanship.”
    Appellant’s App. p. 8.
    [8]   On March 27, 2015, Corick Construction filed an Indiana Trial Rule 12(B)(6)
    motion to dismiss Prassas’s complaint. In this motion, Corick Construction
    alleged that the instant law suit was barred by the doctrine of res judicata because
    Prassas had filed a small claims action against Corick Construction alleging
    unworkmanlike quality of the roof replacement as it related to the same
    contract and same set of facts that were referred to in the instant action. Corick
    Construction indicated that the small claims action had been resolved against
    Prassas, with the judge specifically finding that Prassas failed to prove faulty
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 4 of 13
    workmanship in completing the contracted work. Corick Construction further
    indicated that following the small claims court’s ruling, Prassas, by counsel, had
    filed a motion to correct error and that this motion was subsequently deemed
    denied by the small claims court.
    [9]    On March 31, 2015, Prassas responded to Corick Construction’s motion to
    dismiss and moved for default judgment. Following a May 5, 2015 hearing on
    the pending motions, the trial court took the matter under advisement. The
    trial court subsequently issued an order in which it ruled in favor of Corick
    Construction. This appeal follows.
    Discussion and Decision
    [10]   Initially, we note that our disposition in the instant matter has been made more
    difficult by the fact that Corick Construction failed to submit an appellee brief.
    “Instead of imposing upon this court the burden of controverting arguments
    advanced for reversal, however, Indiana courts have long applied a less
    stringent standard of review with respect to showings of reversible error when
    the appellee fails to file a brief.” Johnson Cty. Rural Elec. Membership Corp. v.
    Burnell, 
    484 N.E.2d 989
    , 991 (Ind. Ct. App. 1985). Thus, Prassas need only
    establish the lower court committed prima facie error to win reversal. 
    Id.
     (citing
    Ind. State Bd. of Health v. Lakeland Disposal Serv., Inc., 
    461 N.E.2d 1145
    , 1145 n. 1
    (Ind. Ct. App. 1984)). “In this context, ‘prima facie’ means at first sight, on
    first appearance, or on the face of it.” 
    Id.
     (quoting Harrington v. Hartman, 
    142 Ind. App. 87
    , 88, 
    233 N.E.2d 189
    , 191 (1968)). Likewise, the statement of facts
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 5 of 13
    contained in Prassas’s brief “is deemed by us to be accurate and sufficient for
    the disposition of this appeal.” 
    Id.
     (citing Colley v. Carpenter, 
    172 Ind. App. 638
    ,
    
    362 N.E.2d 163
     (1977)).
    I. Proper Treatment of a Trial Rule 12(B)(6) Motion to
    Dismiss as a Motion for Summary Judgment
    [11]   On appeal, Prassas contends that the trial court erred in ruling in favor of
    Corick Construction. In raising this contention, Prassas asserts that the trial
    court relied on evidence outside of the pleadings. Prassas further asserts that
    the trial court effectively treated Corick’s motion to dismiss as a motion for
    summary judgment. Prassas claims that it was erroneous for the trial court to
    do so because it ruled on the motion without providing Prassas the opportunity
    to put forth evidence which he claims would show the existence of genuine
    issues of material fact.
    [12]           [Indiana Trial] Rule 12(B) provides that a motion to dismiss for
    failure to state a claim shall be treated as a motion for summary
    judgment when “matters outside the pleading are presented to
    and not excluded by the trial court.” Where a trial court treats a
    motion to dismiss as one for summary judgment, the court must
    grant the parties a reasonable opportunity to present T.R. 56
    materials. See T.R. 12(B); Biberstine v. New York Blower Co., 
    625 N.E.2d 1308
    , 1313 (Ind. Ct. App. 1993), trans. dismissed. The
    trial court’s failure to give explicit notice of its intended
    conversion of a motion to dismiss to one for summary judgment
    is reversible error only if a reasonable opportunity to respond is
    not afforded a party and the party is thereby prejudiced. Ayres v.
    Indian Heights Volunteer Fire Department, 
    493 N.E.2d 1229
    , 1233
    (Ind. 1986).
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 6 of 13
    Our review of the relevant cases discloses at least four
    considerations pertinent to a determination of whether a trial
    court’s failure to give express notice deprives the nonmovant of a
    reasonable opportunity to respond with T.R. 56 materials. First,
    we consider whether the movant’s reliance on evidence outside
    the pleadings should have been so readily apparent that there is
    no question that the conversion is mandated by T.R. 12(B). See
    Duran v. Komyatte, 
    490 N.E.2d 388
    , 391 (Ind. Ct. App. 1986),
    trans. denied (noting that the operation of T.R. 12(B) is “well
    known” and a “clear mandate” of which counsel should be
    cognizant). Second, we consider whether there was ample time
    after the filing of the motion for the nonmovant to move to
    exclude the evidence relied upon by the movant in support of its
    motion or to submit T.R. 56 materials in response thereto. See
    Biberstine, 625 N.E.2d at 1314. Third, we consider whether the
    nonmovant presented “substantiated argument” setting forth
    how she “would have submitted specific controverted material
    factual issues to the trial court if [she] had been given the
    opportunity.” Ayres, 493 N.E.2d at 1233 (citing Macklin v. Butler,
    
    553 F.2d 525
    , 528 (7th Cir. 1977)).
    Azhar v. Town of Fishers, 
    744 N.E.2d 947
    , 950-51 (Ind. Ct. App. 2001) (first set of
    brackets added, footnote omitted).
    [13]   In Azhar, we concluded that the trial court did not commit reversible error by
    treating the Defendants’ motion to dismiss as a motion for summary judgment
    because the Defendants’ reliance on evidence outside the pleadings was
    unmistakable and “given the mandatory wording of Trial Rule 12(B), Azhar
    should have known that the trial court was compelled to convert the motion to
    a summary judgment motion.” 
    Id. at 951
    . We also noted that the approximate
    three-month period between the filing of the motion to dismiss and the hearing
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 7 of 13
    thereon was ample time to allow Azhar to “(1) move to exclude the evidence
    relied upon by the Defendants; (2) file a motion for additional time to conduct
    discovery to ascertain the evidence in opposition to the motion; and/or (3)
    submit materials in opposition thereto.” 
    Id.
     We last noted that Azhar had
    “failed to show, either in the hearing below or in her appellate briefs, what
    specific additional material she would have presented if express notice had been
    given.” 
    Id.
    [14]   Here, similar to Azhar, we must conclude that the trial court did not commit
    reversible error by considering the evidence outside the pleadings submitted by
    Corick Construction and effectively treating Corick Construction’s motion to
    dismiss as a motion for summary judgment. Again, “[t]he trial court’s failure to
    give explicit notice of its intended conversion of a motion to dismiss to one for
    summary judgment is reversible error only if a reasonable opportunity to
    respond is not afforded a party and the party is thereby prejudiced.” 
    Id. at 950
    .
    Upon review, we cannot say that Prassas was prejudiced or denied a reasonably
    opportunity to respond.
    [15]   As in Azhar, Corick Construction’s reliance on evidence outside the pleadings
    was unmistakable. Thus, given the mandatory wording of Indiana Trial Rule
    12(B), Prassas should have known that the trial court was compelled to convert
    the motion into a motion for summary judgment. The record reflects that
    counsel for Prassas did, in fact, make such realization, acknowledging that
    because Corick Construction attached the small claims court judgment to its
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 8 of 13
    motion, the motion should have been treated as a motion for summary
    judgment.
    [16]   We also believe that Prassas had ample time to (1) move to exclude the
    evidence relied on by Corick Construction, (2) file a motion for additional time
    to conduct discovery, or (3) to submit materials in opposition thereto. The
    record reveals that Prassas responded to Corick Construction’s motion. Over
    one month later, the trial court conducted a hearing on the pending motions.
    During this hearing, counsel for Prassas presented argument before the trial
    court stating Prassas’s opposition to Corick Construction’s motion. In doing
    so, counsel for Prassas acknowledged that Corick Construction’s motion was,
    in effect, a summary judgment motion. Counsel for Prassas also presented
    argument akin to what would be argued during a summary judgment hearing,
    i.e., argument aimed at showing that an issue of material fact existed with
    regard to whether Prassas’s claims were barred by the doctrine of res judicata.
    Specifically, Prassas argued that the issues raised in the instant matter were not
    the same as those raised in the small claims action but rather represented
    separate and distinct allegations of inadequate workmanship by Corick
    Construction. Prassas has not indicated what specific additional information he
    would have presented if express notice that the motion to dismiss would be
    treated as a motion for summary judgment had been given.
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 9 of 13
    II. Propriety of Judgment in Favor of Corick
    Construction
    [17]   Prassas appears to alternatively contend on appeal that, even assuming the trial
    court correctly treated Corick Construction’s motion to dismiss as a motion for
    summary judgment, the trial court’s ruling in favor of Corick Construction was
    erroneous. Thus, having concluded that the trial court did not commit
    reversible error by considering Corick Construction’s motion to dismiss as a
    motion for summary judgment, we must next consider whether summary
    judgment is appropriate.
    The purpose of summary judgment is to end litigation about
    which there can be no factual dispute and which may be
    determined as a matter of law. LeBrun v. Conner, 
    702 N.E.2d 754
    ,
    756 (Ind. Ct. App. 1998). The moving party bears the burden of
    making a prima facie showing that there are no genuine issues of
    material fact. Ind. Trial Rule 56(C); Campbell v. Criterion Group,
    
    613 N.E.2d 423
    , 428 (Ind. Ct. App. 1993), on reh’g 
    621 N.E.2d 342
    . It is only after the moving party makes a prima facie
    showing of the non-existence of a genuine issue of material fact
    that the burden shifts to the non-moving party to set forth specific
    facts showing the existence of a genuine issue for trial. T.R.
    56(E); Campbell, 
    613 N.E.2d at 428
    .
    Id. at 952.
    [18]           Four elements determine whether a judgment has res judicata
    effect: 1) the former judgment must have been rendered by a
    court of competent jurisdiction; 2) the matter now in issue was,
    or might have been, determined in the former suit; 3) the
    particular controversy previously adjudicated must have been
    between the parties to the present suit or their privies; and 4) the
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 10 of 13
    judgment in the former suit must have been rendered on the
    merits. Cox v. Ind. Subcontractors Ass’n, Inc., 
    441 N.E.2d 222
    , 225
    (Ind. Ct. App. 1982).
    Moreton v. Auto-Owners Ins., 
    859 N.E.2d 1252
    , 1254 (Ind. Ct. App. 2007)
    (emphasis added). The parties do not appear to dispute that the small claims
    judgment was rendered by a court of competent jurisdiction, that the particular
    controversy previously adjudicated was between the same parties as the instant
    matter, or that the small claims judgment was rendered on the merits.
    [19]   However, Prassas argued below, and again on appeal, that the issues presented
    in the instant law suit were not the same as those raised in the small claims
    action. Prassas specifically asserts on appeal that although Corick Construction
    claims that he was “trying to take two bites at the apple, it’s just not true.” Tr.
    p. 12.
    [20]   The documents designated by Corick Construction and the argument offered by
    Prassas indicate that the small claims action involved allegations of faulty
    workmanship relating to the installation of a soffit. The complaint filed in the
    instant matter, however, involves the allegedly improper installation of shingles,
    gutters, and downspouts. Specifically, the complaint alleges that Corick
    Construction committed a breach of contract and breach of implied warranty
    with regard to the allegedly improper installation of the shingles, gutters, and
    downspouts. The complaint also contains the claim that the allegedly improper
    installation was not noticed upon final inspection because Corick Construction,
    in violation of a voluntary-compliance order that it had entered into with the
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 11 of 13
    Indiana Attorney General, worked with Prassas’s insurance company to assess
    Prassas’s damages, the associated necessary repairs, and the sum of funds that
    would be paid out for the completed repairs.
    [21]   In addition, the complaint alleges that Prassas did not learn of the full extent of
    the allegedly improper installation of the shingles, gutters, and downspouts
    until he had his roof inspected by several roofers in late 2014 and early 2015.
    The designated documents demonstrate that the small claims court trial was
    conducted on November 21, 2014, and the court’s decision issued on December
    3, 2014. Thus, the pleadings and designated documents present an issue of
    material fact as to whether Prassas was aware of the allegedly improper
    installation of the shingles, gutters, and downspouts at the time he filed the
    small claims court action. It is reasonable to assume that if he did not know of
    the improper installation, he could not have included such claims in the small
    claims action.
    [22]   Given that Prassas need only make a prima facie case of error, we conclude that
    the record indicates that an issue of material fact exists as to whether the claims
    raised in the instant lawsuit were the same as those raised before the small
    claims court. Because issue of material fact remains, we conclude that the trial
    court erred in ruling in Corick Construction’s favor and dismissing the instant
    lawsuit.
    [23]   The judgment of the trial court is reversed and the matter remanded to the trial
    court for further proceedings.
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 12 of 13
    Baker, J., and Pyle, J., concur.
    Court of Appeals of Indiana | Memorandum Decision 64A05-1508-CT-1081 | December 28, 2015   Page 13 of 13