Diane Seiwert and 19942 Longview Drive, LLC v. Ty Brown and Brown Roofing Co. (mem. dec.) ( 2018 )


Menu:
  • MEMORANDUM DECISION
    Pursuant to Ind. Appellate Rule 65(D),
    this Memorandum Decision shall not be
    regarded as precedent or cited before any                                  FILED
    court except for the purpose of establishing                           Jul 10 2018, 8:44 am
    the defense of res judicata, collateral                                    CLERK
    estoppel, or the law of the case.                                      Indiana Supreme Court
    Court of Appeals
    and Tax Court
    APPELLANT PRO SE                                          ATTORNEYS FOR APPELLEES
    Diane Seiwert                                             Joseph W. Votaw, III
    Lawrenceburg, Indiana                                     Votaw and Schwarz
    Lawrenceburg, Indiana
    Susan M. Salyer
    Ruggiero & Salyer, LPA
    Cincinnati, Ohio
    IN THE
    COURT OF APPEALS OF INDIANA
    Diane Seiwert and 19942                                   July 10, 2018
    Longview Drive, LLC,                                      Court of Appeals Case No.
    Appellants/Defendants/Cross-Claim                         15A01-1707-PL-1616
    Appeal from the Dearborn
    Plaintiffs,                                               Superior Court
    The Honorable Jonathan N.
    v.
    Cleary, Judge
    Trial Court Cause No.
    Ty Brown and Brown Roofing
    15D01-1611-PL-74
    Co.,
    Appellees/Plaintiffs/Cross-Claim
    Defendants.
    Court of Appeals of Indiana | Memorandum Decision 15A01-1707-PL-1616 | July 10, 2018           Page 1 of 6
    Bradford, Judge.
    Case Summary
    [1]   Diane Seiwert and 19942 Longview Drive, LLC (“Seiwert”) appeal the trial
    court’s judgment in favor of Ty Brown and Brown Roofing Company
    (“Brown”). We affirm.
    Facts and Procedural History
    [2]   On June 16, 2016, Seiwert contracted with Brown for the installation of copper
    gutters and downspouts. The parties’ contract provided that the cost of
    installation of the gutters and downspouts would be $7000.00. After Brown
    had installed the gutters but before he could install the downspouts, Seiwert
    decided that she was not satisfied with the aesthetics of the gutters, ordered
    Brown to stop work, and informed him that she would not be paying for the
    work done to that point. Brown filed suit in the small claims court seeking
    payment in the amount of $5531.83. The requested amount covered both the
    cost of the gutters and the labor for the installation. Seiwert filed a
    counterclaim alleging breach of contract and negligence. The matter was
    transferred to the trial court. Following a multi-day trial, the trial court rejected
    Seiwert’s counterclaim and entered judgment in favor of Brown in the amount
    of $5531.83.
    Discussion and Decision
    Court of Appeals of Indiana | Memorandum Decision 15A01-1707-PL-1616 | July 10, 2018   Page 2 of 6
    I. Whether the Contract was Void
    [3]   Seiwert contends that the trial court erred as it should have found the contract
    at issue to be void because it lacked a start and completion date in violation of
    the Home Improvement Contracts Act (“HICA”).1 The HICA provides that a
    home improvement contract must contain the “approximate starting and
    completion dates of the real property improvements.” Ind. Code § 24-5-11-
    10(a)(6). The purpose of the HICA “is to protect consumers by placing specific
    minimum requirements on the contents of home improvement contracts.”
    Benge v. Miller, 
    855 N.E.2d 716
    , 720 (Ind. Ct. App. 2006). We have previously
    concluded that “the General Assembly did not intend that every contract made
    in violation of HICA to automatically be void.” Imperial Ins. Restoration &
    Remodeling, Inc. v. Costello, 
    965 N.E.2d 723
    , 729 (Ind. Ct. App. 2012).
    Instead, we apply a balancing approach and examine the factors
    that courts use to determine whether or not a contract
    contravenes declared public policy. The considerations to be
    balanced are (1) the nature of the subject matter of the contract,
    (2) the strength of the public policy underlying the statute, (3) the
    likelihood that refusal to enforce the bargain or term wi[ll] further
    that policy, (4) how serious or deserved would be the forfeiture
    suffered by the party attempting to enforce the bargain, and (5)
    the parties’ relative bargaining power and freedom to contract.
    1
    We note that Seiwert’s entire argument relating to this contention appears to be a block-quote from an
    uncited prior opinion of either this court or the Indiana Supreme Court. Despite Seiwert’s failure to make
    any argument relating to the facts and circumstances surrounding this case, we have nonetheless addressed
    the merits of her contention.
    Court of Appeals of Indiana | Memorandum Decision 15A01-1707-PL-1616 | July 10, 2018             Page 3 of 6
    
    Id. (internal citations
    omitted).
    [4]   The contract at issue involved two parties of seemingly equal bargaining power
    and freedom to contract. The parties contracted for the installation of copper
    gutters and downspouts. Brown began work and completed installation of the
    gutters before being instructed by Seiwert to stop. Brown did not remove the
    gutters from Seiwert’s home after being instructed to stop work and the gutters
    remain in Seiwert’s possession. To void the contract after partial completion of
    the contracted work would result in a windfall for Seiwert as it would leave
    Brown deprived of both compensation for the work completed and the cost of
    the materials themselves. Further, the record reveals that the underlying claims
    do not allege any issue related to the start or completion date of the project. For
    these reasons, we cannot conclude that the parties’ agreement should be
    unenforceable against Seiwert.
    II. Breach of Contract
    [5]   Seiwert also contends that the trial court erred in finding in favor of Brown on
    the parties’ competing breach of contract claims. Seiwert appeals from a
    general judgment.
    A general judgment will be affirmed if it can be sustained upon
    any legal theory consistent with the evidence. In making that
    determination we neither reweigh the evidence nor judge the
    credibility of witnesses. Rather, we consider only the evidence
    most favorable to the judgment together with all reasonable
    inferences to be drawn therefrom. In reviewing a general
    judgment, we must presume the trial court correctly followed the
    law. A general judgment will be affirmed unless the
    Court of Appeals of Indiana | Memorandum Decision 15A01-1707-PL-1616 | July 10, 2018   Page 4 of 6
    uncontradicted evidence leads to a conclusion opposite that
    reached by the trial court.
    Conseco Fin. Servicing Corp. v. Friendly Vill. of Indian Oaks, 
    774 N.E.2d 87
    , 92
    (Ind. Ct. App. 2002) (internal citations omitted).
    [6]   Seiwert does not dispute that she instructed Brown to stop work or that she did
    not pay Brown for the work completed. Nevertheless, Seiwert argues that the
    trial court should have found that it was Brown who first breached the parties’
    contract. In making this argument, Seiwert does not assert that the gutters were
    not properly affixed to the home or that the gutters did not function properly.
    She merely claims that Brown damaged the aesthetics of the gutters during the
    installation process. Specifically, Seiwert asserts that she expected Brown to
    “ensure [that] the money [she] spent resulted in adding aesthetic value to her
    home.” Appellants’ Br. p. 22. The trial court considered the evidence
    presented by the parties and determined that the alleged damage to the
    aesthetics of the gutters did not amount to a breach of the parties’ contract.
    Seiwert has failed to convince us of such on appeal. As such, given that Seiwert
    does not dispute that she both instructed Brown to stop work before the
    downspouts were installed and failed to pay for the installation of the gutters,
    Court of Appeals of Indiana | Memorandum Decision 15A01-1707-PL-1616 | July 10, 2018   Page 5 of 6
    we conclude that the trial court did not err in finding that Seiwert breached the
    parties’ contract.2
    [7]   The judgment of the trial court is affirmed.
    Baker, J., and Kirsch, J., concur.
    2
    Seiwert also raises the issue that the trial court erred in failing to specifically address her counterclaim in its
    ruling. We see no merit in this argument in that the trial court’s ruling implicitly rejects her counterclaim.
    Court of Appeals of Indiana | Memorandum Decision 15A01-1707-PL-1616 | July 10, 2018                     Page 6 of 6