Duke Energy of Indiana, LLC v. City of Franklin, Indiana ( 2016 )


Menu:
  •                                                                   FILED
    Dec 16 2016, 8:48 am
    CLERK
    Indiana Supreme Court
    Court of Appeals
    and Tax Court
    ATTORNEYS FOR APPELLANT                              ATTORNEYS FOR APPELLEE
    John D. Papageorge                                   Lynnette Gray
    Steven C. Shockley                                   Johnson Gray & Johnson
    Jeffrey D. Stemerick                                 Franklin, Indiana
    Taft Stettinius & Hollister LLP
    Brian C. Bosma
    Indianapolis, Indiana
    Steven E. Runyan
    Keven D. Koons
    Kroger, Gardis & Regas, LLP
    Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Duke Energy of Indiana, LLC,                              December 16, 2016
    Appellant-Plaintiff,                                      Court of Appeals Case No.
    41A01-1607-CT-1549
    v.                                                Interlocutory Appeal from the
    Johnson Superior Court
    The Honorable Kevin M. Barton,
    City of Franklin, Indiana,                                Judge
    Appellee-Defendant.                                       Trial Court Cause No. 41D01-1606-
    CT-92
    Bradford, Judge.
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016           Page 1 of 24
    Case Summary
    [1]   Appellee-Defendant the City of Franklin, Indiana (“the City”), in cooperation
    with the State, has proposed a plan to revitalize and improve a stretch of
    Indiana State Road 44 (“SR 44”) that serves a major east-west artery (“the
    Traffic Plan”). The Traffic Plan includes, inter alia, a proposal to connect the
    three-way intersection of County Club Lane and Longest Drive (“the
    Intersection”) to SR 44. Appellant-Plaintiff Duke Energy of Indiana, LLC
    (“Duke”) holds a utility easement in the land underneath the proposed
    Intersection expansion and requested a preliminary injunction to prevent the
    City from completing the expansion of the Intersection, contending the City
    lacks sufficient property rights to allow it to do so and that the expansion would
    impermissibly interfere with its easement rights. The trial court denied Duke’s
    request for a preliminary injunction, and Duke now appeals. Because we
    conclude that Duke lacks standing to challenge the City’s property interests in
    the real estate at issue and that the trial court did not abuse its discretion in
    concluding that Duke does not have a reasonable probability of success at trial,
    we affirm.
    Facts and Procedural History
    [2]   The following excerpted diagram, submitted in un-excerpted form as Plaintiff’s
    Exhibit 13, is helpful to understanding the issues presented by this case.
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 2 of 24
    [3]   For a stretch in the City, Longest Drive and SR 44 (a/k/a King Street) run
    generally east-west and parallel, with Longest Drive being intersected by
    County Club Lane at the Intersection. Duke holds the Easement, which runs
    north-south, encompasses the Intersection, and includes utility pole 825-4181,
    which is adjacent to and just northwest of the Intersection. The Easement
    grants Duke the right to “construct, operate, patrol, maintain, reconstruct and
    remove an electric line, including necessary poles, wires, and fixtures attached
    thereto, for the transmission of electrical energy[.]” Plaintiff’s Exs. 18, 19.
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 3 of 24
    [4]   At issue is the Traffic Plan, by which the City intends to improve SR 44
    between SR 144 on the west side and I-65 on the east. The Traffic Plan
    includes a proposal to provide access to SR 44 from the Intersection, as shown
    below:
    Plaintiff’s Ex. 11 (excerpt).
    [5]   Early in 2016, the City presented Duke with the Traffic Plan, and Duke
    informed the City that it believed that the expansion of the Intersection would
    unreasonably interfere with its easement rights. On June 7, 2016, Duke filed
    for a preliminary injunction to prevent the City from constructing the proposed
    expansion of the Intersection. The next day, the trial court entered a temporary
    restraining order—by which the City agreed to abide—pending resolution of the
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 4 of 24
    preliminary injunction issue. On July 5, 2016, the trial court denied Duke’s
    request for a preliminary injunction, ruling that Duke had failed to establish
    unreasonable interference with its easement rights. On this basis, the trial court
    concluded that Duke had failed to show a reasonable likelihood of success at
    trial and so denied Duke’s request for a preliminary injunction. The trial
    court’s order provides, in part, as follows:
    5. The City’s project … is designed to enhance the visual
    appearance of [SR 44] so as to encourage development on the
    east side of Franklin and to provide an attractive area for
    travelers on I-65 to stop for food and lodging. By [its] design,
    the project is meant to slow traffic on [SR 44].
    6. In the area of Country Club Lane, [SR 44] is now a
    well traveled limited access four lane highway. [SR 44] connects
    Franklin to Interstate 65, which is a major north-south divided
    access highway.…
    7. As part of the roadway improvement project, the City is
    opening access to Country Club Lane from both lanes of travel
    on [SR 44].… A stop sign will be added for eastbound traffic at
    Longest Drive that is entering Country Club Lane. A stop sign
    already exists for westbound traffic at Longest Drive and
    Country Club Lane.
    8. Mayor McGuinness opined that opening and closing of
    access points from [SR 44] is designed to separate the
    commercial and residential uses of property along [SR 44] and to
    remove commercial traffic from residential streets.
    9. City Engineer, Travis Underhill, testified that part of
    the goal of the overall corridor project is to safely manage
    increased traffic in the area and plan for future traffic and
    anticipated development. Mr. Underhill testified that from an
    engineering standpoint and safety standpoint, it is desirable to
    reduce commercial traffic through residential neighborhoods and
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 5 of 24
    that the direct access routes as proposed will reduce conflict
    points for motorists.
    10. A report prepared by HWC Engineering states that the
    change in access to [SR 44] is “to promote more efficient traffic
    movements along [SR 44]”. Exhibit 6.
    11. Country Club Lane provides access to a private
    country club known as Hillview Country Club. A tenant at
    Hillview Country Club is a public restaurant known as Scotty’s
    Brew[house]. Scotty’s Brew[house] opened in October of 2015.
    At all times relevant, a restaurant has been located at Hillview
    Country Club for the use of [its] members prior to the opening of
    the public restaurant. Country Club Lane is a private
    roadway.…
    12. [SR 44] has existed on the east side of the City at all
    times relevant. [SR 44] connects Franklin with the City of
    Shelbyville to the east and the City of Martinsville to the west.
    Prior to 1970, [SR 44] was a two lane roadway. Access to
    Hillview Country Club was gained directly from [SR 44]. In
    1970, the State of Indiana converted [SR 44] to a four lane
    limited access highway from I-65 to the older residential area on
    the eastside of Franklin. [SR 44] was shifted to the south. A new
    road, Longest Drive, was created to the north of [SR 44].
    Longest Drive is generally an east-west access road that is
    parallel to [SR 44]. Access to Longest Drive was gained to the
    west of Country Club Lane at a short access road known as
    Milford Drive. A portion of Longest Drive was constructed on
    the roadbed of the pre-1970 [SR 44].
    13. After the 1970 redesign, traffic to Hillview Country
    Club was required to exit [SR 44] on the north side at Milford
    Drive, immediately turn right onto Longest Drive, proceed east
    on Longest Drive to Country Club Lane and turn left or north
    onto Country Club Lane. Country Club Lane could not be
    accessed directly from [SR 44]. Longest Drive and [SR 44] were
    separated by a grassy strip.
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 6 of 24
    14. Under the current roadway project, traffic would be
    able to proceed north from [SR 44] directly to Country Club
    Lane. West bound traffic on [SR 44] would be able to turn right
    onto Country Club Lane. A break would be created in the
    existing median on [SR 44] so that east bound traffic on [SR 44]
    would be able to access Country Club Lane. Approximately
    forty feet after exiting [SR 44], traffic would encounter Longest
    Drive. Longest Drive provides access to residential areas to the
    east and to the west of Country Club Drive that have been
    constructed since the 1970 redesign of [SR 44]. A stop sign
    would be added for east bound traffic on Longest Drive. The
    result of the City’s redesign would change Longest Drive-
    Country Club Lane to a four way intersection and would be
    located just north of a three way intersection at Country Club
    Lane and [SR 44]. Traffic would be regulated by stop signs as
    opposed to use of automatic traffic control devices. The City’s
    project would also introduce a pedestrian “trail” on the north
    side of [SR 44].
    ….
    26. Utility pole 825-4181 is located at the intersection of
    Longest Drive and Country Club Lane. The pole is located
    inside the Easement and just north of the fee line of property
    acquired by the State of Indiana.
    27. The City’s project would alter the traffic flow past
    utility pole 825-4181. Traffic flow would change in the following
    manner:
    A. Traffic accessing Hillview Country Club and Scotty’s
    Brew[house] would come off of [SR 44]. Currently, traffic exits
    [SR 44] north onto Milford Drive, immediately turns right or east
    onto Longest Drive, proceeds east on Longest Drive an
    undetermined but relatively short distance and then turns left or
    north onto Country Club Lane. In addition, traffic could
    currently access Country Club Lane from an opening from [SR
    44] to the east of Country Club Lane. However, the latter option
    is a less direct route through a condominium community. As a
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 7 of 24
    result of the City’s project, traffic accessing Hillview Country
    Club and Scott[y]’s Brew[house] would proceed onto Country
    Club Lane directly from [SR 44]. The Milford Drive exit from
    [SR 44] will remain open. Traffic could still access Hillview
    Country Club and Scott[y]’s Brew[house] in the same manner as
    before, but the assumption is that the public will prefer the more
    direct route. The exit from [SR 44] to the east at Franklin Cove
    Court would be closed. However, the public could still access
    Hillview Country Club and Scott[y]’s Brew[house] from the east
    by using a new exit further to the east onto Fairway Lakes Drive.
    The result of the changes would mean that traffic accessing
    Hillview Country Club and Scott[y]’s Brew[house] will proceed
    straight past pole 825-4181 as opposed to turning at the pole.
    Inasmuch as vehicles de[]ccelerate to turn, traffic would be
    proceeding faster past pole 825-4181 after completion of the
    City’s project.
    B. The success of Hillview Country Club is dependent
    upon expansion of membership. The success of Scotty’s
    Brew[house] is dependent upon attracting customers. Scott[y]’s
    Brew[house] has placed information signs and directional signs
    on Interstate 65. Mayor McGuiness testified that the City’s
    project is designed to create a situation for the improvement of
    business and commercial development on the east side of
    Franklin. Inasmuch as access to Hillview Country Club and
    Scott[y]’s Brew[house] will be easier for the public, there may be
    increased traffic flow past pole 825-4181 as a result of the City’s
    project. Development on the eastside of Franklin will also cause
    an increase in traffic past pole 825-4181 without regard to
    whether access is directly provided from [SR 44].
    C. A residential development is being developed to the
    northwest of Hillview Country Club. The residential
    development will be accessed from Eastview Drive, which is the
    first major arterial road that is accessed from [SR 44] west of the
    area at issue. A road will connect the residential development to
    a parking lot at Hillview Country Club and Scott[y]’s
    Brew[house]. Although Country Club Lane is a private
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 8 of 24
    roadway, the public could utilize Country Club Lane and the
    parking lot to access the new residential development as well as
    Eastview Drive. Accordingly, traffic could increase past pole
    825-4181 by reason of the connection of the residential
    development to the Hillview Country Club parking lot.
    However, the traffic flow caused by the residential development
    would likely be minimal inasmuch as Eastview Drive would offer
    a more favorable route of travel.
    28. Duke asserts that the creation of the four way and
    three way intersections in immediate proximity to each other
    with the increased volume and speed of traffic proceeding past
    pole 825-4181 increases the hazard to which [its] repair and
    maintenance crews are exposed. The City asserts that the
    elimination of the two ninety degree turns required to access
    Country Club Lane will create a safer condition. Engineer Travis
    Underhill opined that turning a vehicle created a more hazardous
    condition than operating the vehicle in a straight line.
    29. No evidence was submitted of vehicular collisions or
    collisions between a vehicle and utility pole 825-4181 or other
    poles in the area.
    30. Duke’s witness, Gary McNamee, acknowledged that
    the change proposed by the City’s project will not affect Duke’s
    use of the easement for the transmission and distribution of
    electricity except as it relates to the repair and maintenance of the
    electric lines.
    31. Testimony was presented as to repair and
    maintenance work that would be required to be performed.
    Repairs would need to be made if a pole was damaged as a result
    of a collision by a motor vehicle or if an electrical line should
    come down as a result of a collision by a vehicle with a pole or
    weather related occurrences. Poles may need to be replaced due
    to deterioration of the pole.
    32. In order to maintain and to repair electric lines, Duke
    utilizes bucket trucks and line trucks. The bucket trucks can
    reach a height of eighty (80) feet and have outriggers that
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 9 of 24
    stabilize the vehicle while in use. Due to the outriggers, the truck
    would occupy more space than the truck would occupy without
    deployment of the outriggers. Stringing trucks could be required
    to hold a still energized line while the line is repaired. In
    instances in which a pole must be replaced, a crane may be
    utilized to lift a new pole into place. A flatbed truck would be
    required to transport the new pole. As part of the process of
    repairing or replacing a pole or an electric line, traffic in
    proximity to the pole would be subject to control so as to reduce
    the risk of harm to Duke’s repair crews.
    33. An increase in the speed and/or volume of traffic
    would increase the size and extent of the area that would be
    controlled so that Duke’s maintenance or repair crew could
    safely perform their job.
    34. Mr. McNamee testified that the more directions from
    which traffic is approaching a work zone, the more people that
    are required to control traffic. The more traffic that there is from
    different directions, the greater is the risk that the traffic cannot
    be controlled as well. Record, 6/14/2016, 10:56. The placement
    of a pole in proximity to a street means that a repair crew would
    be working in the street. Id., 11:14.
    35. Mr. McNamee testified that the poles used in
    transmission lines are bigger. The trucks that carry the poles are
    bigger. The equipment used to install the poles is bigger. Due to
    the size of the pole and the position that it has to take as the pole
    is raised, it is more likely that both lanes of traffic must be shut
    down. Record, 6/14/2016, 10:57.
    36. In a letter to City Engineer Travis Underhill and
    Mayor Joe McGuinness, Mr. McNamee stated that Duke does
    not allow intersections within [its] easements. He articulated the
    reasons as follows:
    “Intersections consume more space in the Duke Energy
    right-of-way, leaving less room for the line to be rebuilt or
    for use to add a line in this right-of-way should it be
    needed. Intersections reduce our ability to use the space
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 10 of 24
    that has [been] purchased for current transmission lines
    and possible future new lines, whether they be permanent
    or temporary due to storm damage.
    Intersections create a heavier traffic flow of vehicles and
    increase the risk of injury to Duke Energy crew members
    when they are working on power transmission lines. Any
    time utility work is performed in a vehicular traffic area, it
    increases the risk of injury. An intersection increases
    traffic and adds to the number of directions from which
    that traffic may approach the working crews.
    Some intersections require more signage and traffic
    signals, which are also not permitted in the Duke Energy
    right-of-way. When a Duke Energy line is damaged, the
    intersection will likely need to be blocked during long
    repair times, and this would close access for some traffic.
    Repairing damaged transmission lines takes longer than
    repairing lower-voltage distribution lines due to their size
    and the fact that the equipment to do the work is not
    always in the immediate location of the damage.”
    Exhibit 25.
    37. Marty Dickey, Manager of Transmission for Duke,
    testified that if pole 825-4181 were to be replaced, it would be
    replaced with a steel pole of either one or two pieces. The steel
    pole would be taller and weigh more than the existing wooden
    pole. A “lay down” area for preparation of the steel pole for
    installation would be required. Mr. Dickey opined that pole
    replacement would require closure of the roads in proximity to
    the pole, to-wit: Country Club Lane and Longest Drive, but he
    did not believe that the work would require closure of [SR 44].
    Record, June 14, 2016, 1:17. If an intersection were installed at
    Country Club Lane, access to the area off of [SR 44] would need
    to be shut off as part of the closure. Id.
    38. Mr. Dickey testified that the “more complex” the
    traffic situation, the more traffic control would be required. Mr.
    Dickey referred to a distance required for management of traffic
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016     Page 11 of 24
    as defined by the speed and volume of traffic. He testified that
    traffic management could require directional signs and traffic
    control personnel to control traffic as opposed to use of traffic
    cones. However, Mr. Dickey did not render specific opinion as
    to how the proposed intersection would change traffic control.
    39. Mr. Dickey referred to a pole replacement on Madison
    Avenue in Greenwood. The pole replaced carried both
    transmission and distribution lines. Distribution to customers in
    the area was not shut down. The pole replacement required that
    Madison Avenue, a major arterial street in Greenwood, be
    closed. So as to accommodate the desire of the City of
    Greenwood to minimize the disruption caused by closure of a
    major arterial street, the work was performed at night. The work
    was performed without endangerment to Duke crews.
    40. No evidence was submitted of repairs or maintenance
    that had been conducted to pole 825-4181 or to the lines or other
    poles in proximity to pole 825-4181.
    41. If warranted to protect [its] maintenance or repair
    crews, Duke will close a roadway so as to permit repairs or
    maintenance to be safely performed. Although the City has not
    been consulted on those occasions in which a road has been
    closed by Duke to repair an electric line or pole, the City was not
    opposed to closing roads to create a safe work environment for
    utility maintenance and repair crews. Three occasions were cited
    in which Duke had closed a public street for repairs.
    42. Mr. McNamee also opined that the placement of the
    trail in proximity to a utility pole could be a safety factor. The
    trail should be at least twenty-five (25) feet from the utility pole.
    The weight from a bucket truck, line truck or crane could damage
    asphalt for a trail that is not constructed to handle the weight of
    such equipment. The damage would be a safety factor to
    pedestrians and bicycle traffic. No evidence was presented that
    the trail would affect Duke’s use of the easement for the
    transmission and distribution of electricity or constitute a hazard
    to Duke’s maintenance or repair crews.
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 12 of 24
    43. The proposed trail would come no closer than seventy
    to eighty feet from pole 825-4181 but would pass underneath
    Duke’s transmission lines. Exhibit 18. The trail would be further
    than 25 feet from pole 825-4181.
    CONCLUSIONS
    ….
    32. Duke adopted a policy in 2008 to exclude the
    introduction of intersections within [its] easements.
    ….
    34. Duke had identified to the City the reasons for
    objecting to the intersection within the easement as a reduction in
    the usable area of the easement, increase of traffic and the risk of
    injury to repair crews and the introduction of signage and traffic
    controls within the easement. The evidence focused upon the
    increased risk of harm to repair crews.
    35. The creation of a four point intersection in proximity
    to a three point intersection does increase the number of variables
    that are subject to being controlled. The volume and the speed of
    traffic will increase. In the event that repairs or maintenance
    must be performed to pole 825-4181 or in proximity to the pole,
    the risk to repair and maintenance crews is now controlled by
    road closure. In the event that repairs or maintenance must be
    performed to pole 825-4181 or in proximity to the pole after the
    introduction of the intersection into the easement, Duke would
    still regulate the risk of harm to repair and maintenance crews by
    road closure. The introduction of the intersection into the
    easement would necessitate additional traffic control measures,
    including blocking access to the area from [SR 44].
    36. Duke asserts that the introduction of the intersection
    into the easement will increase the risk of harm to [its] repair
    crews. Intuitively, the placement of a four point intersection in
    such close proximity to a three point intersection and which is
    not regulated by an automatic traffic control device would seem
    to increase the risk of harm to people and property occupying the
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 13 of 24
    intersection. Mr. Underhill, the City Engineer, opined that safety
    would be improved by eliminating the two ninety (90) degree
    turns for traffic going to Hillview Country Club and Scott[y’s]
    Brew[house] and by keeping commercial traffic out of the
    residential area. However, Mr. Underhill did not specifically
    address the issue raised by Duke that the new intersection would
    create new variables so as to increase the risk of harm.
    Presumably, HWC Engineering and Mr. Underhill, as the
    engineers responsible for public safety, have determined that the
    new design does not unreasonably increase the risk of harm to
    people and property within the redesigned intersection.
    37. The Court does not find that the ability of Duke to
    repair or to maintain [its] transmission lines would be affected by
    the introduction of the intersection into the easement. In order to
    repair or to maintain [its] electric lines, Duke may close a street.
    The most likely maintenance issue cited by Duke would be the
    replacement of pole 825-4181. Mr. Dickey testified that pole
    replacement would require that Longest Drive and Country Club
    Lane would need to be closed based upon the size of the
    equipment and the space required. He did not believe that [SR
    44] would be impacted. The City’s redesign would introduce a
    new point of access from [SR 44]. The new point of access
    would need to be blocked. Inasmuch as the repairs and
    maintenance would require the closure of the road, the ability of
    Duke to perform repairs and maintenance would continue as
    before.
    ….
    41. Indiana has recognized that a titleholder of the
    servient interest can use the easement in any manner that does
    not “materially impair or unreasonably interfere with the use of
    the easement by the dominant estate holder.” Brown v.
    Heidersbach, 
    172 Ind. App. 434
    , 442, 
    360 N.E.2d 614
    , 620 (Ind.
    Ct. App. 1977)(citing Smith v. Holloway, 
    124 Ind. 329
    , 
    24 N.E. 886
     (1890)).
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 14 of 24
    42. Indiana has not recognized Section 4.12 of the
    Restatement of the Law, Third, Property (Servitudes). The City’s
    interference with Duke’s Easement is not measured by the City
    coming upon Duke’s Easement but whether the City interferes
    with the grant of use, including repair and maintenance, under
    the Easement. The limitation upon the titleholder is that the
    titleholder not “materially impair or unreasonably interfere” with
    the use of the easement. Logically, those who hold right of use
    under the titleholder, including a public right-of-way, would be
    subject to the same standard for interference with Duke’s right of
    use under grant of Easement of material impairment or
    unreasonable interference. The unreasonable interference
    standard is the same as set forth in the Restatement of the Law,
    Third, Property (Servitudes).
    43. The Court does not conclude that there has been a
    showing of material impairment, unreasonable interference or
    irreconcilable conflict. As noted, the risk of harm is subject to
    traffic regulation through road closure. The risk of harm is also
    subject to regulation by the time at which the work would be
    performed. Country Club Lane serves a private country club and
    a public restaurant with set operating hours. The repair and
    maintenance work can be carried out at time when the businesses
    are closed. Inasmuch as Duke can and does close an area to
    traffic to perform repairs and maintenance, Duke is essentially
    arguing that the proposed intersection could increase the
    disruption to the public from the closure of the road to perform
    repairs or maintenance. Duke’s assertion may be valid, however,
    the issue is the interference with Duke’s right of use under grant
    of easement. At best, additional traffic control measures may be
    required. The Court does not conclude that this rises to the level
    of material impairment, unreasonable interference or
    irreconcilable conflict. Insofar as the changed public right of way
    is affected by the Duke easement by additional traffic control
    measures, these factors are considerations by the City in
    determining whether to change the public right-of-way.
    ….
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 15 of 24
    47. In determining that the proposed intersection would
    not interfere with Duke’s ability to repair or to maintain [its]
    transmission lines, the Court notes that no evidence was
    submitted of the frequency or length of time required for repairs
    or maintenance. No evidence was submitted that repairs had
    ever been performed in proximity to pole 825-4181. Based upon
    deterioration of physical equipment over time and technological
    change, it is reasonable to assume that repairs are required. No
    evidence was presented as to the frequency of repairs or
    maintenance except for it being an eventual possibility. Evidence
    was not presented as to the length of time to conduct repairs.
    The most likely maintenance required was the replacement of the
    pole. The pole on Madison Avenue in Greenwood was replaced
    during a night time project.
    ….
    53. The appropriate standard for a preliminary injunction
    is that “the moving party must demonstrate by a preponderance
    of the evidence: (1) a reasonable likelihood of success at trial; (2)
    the remedies at law are inadequate; (3) the threatened injury to
    the movant outweighs the potential harm to the nonmoving party
    from the granting of an injunction; and (4) the public interest
    would not be disserved by granting the requested injunction.
    (Citations omitted).” Central Indiana Podiatry, P.C. v. Krueger,
    
    882 N.E.2d 723
    , 727 (Ind. 2008).
    54. For the reasons hereinabove set forth, the Court does
    not find that Duke has established a reasonable likelihood of
    success at trial.
    IT IS THEREFORE ORDERED BY THE COURT, That
    the Plaintiff’s Motion for Preliminary Injunction is DENIED.
    Order pp. 2-5, 8-13, 21-22, 23-24, 25, 26-27.
    Discussion and Decision
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 16 of 24
    [6]   “The grant or denial of a preliminary injunction rests within the sound
    discretion of the trial court, and our review is limited to whether there was a
    clear abuse of that discretion.” Ind. Fam. & Soc. Servs. Admin. v. Walgreen Co.,
    
    769 N.E.2d 158
    , 161 (Ind. 2002) (citing Harvest Ins. Agency, Inc. v. Inter-Ocean Ins.
    Co., 
    492 N.E.2d 686
    , 688 (Ind. 1986)).
    When determining whether or not to grant a preliminary
    injunction, the trial court is required to make special findings of
    fact and state its conclusions thereon. Ind. Trial Rule 52(A).
    When findings and conclusions are made, the reviewing court
    must determine if the trial court’s findings support the judgment.
    The trial court’s judgment will be reversed only when clearly
    erroneous. Findings of fact are clearly erroneous when the
    record lacks evidence or reasonable inferences from the evidence
    to support them.
    Hydraulic Exch. & Repair, Inc. v. KM Specialty Pumps, Inc., 
    690 N.E.2d 782
    , 785
    (Ind. Ct. App. 1998) (citations omitted). We also determine whether the trial
    court’s conclusions are contrary to law. See Carson v. Ross, 
    509 N.E.2d 239
    , 241
    (Ind. Ct. App. 1987), trans. denied. “We consider the evidence only in the light
    most favorable to the judgment and construe findings together liberally in favor
    of the judgment.” Hydraulic Exch. & Repair, 
    690 N.E.2d at 785
    . Although we
    defer substantially to the trial court’s findings of fact, we review questions of
    law de novo. Mayer v. BMR Props., Inc., 
    830 N.E.2d 971
    , 978 (Ind. Ct. App.
    2005).
    [7]            In order to obtain injunctive relief, appellee had the burden of
    showing that: 1) its remedies at law were inadequate, thus
    causing irreparable harm pending resolution of the substantive
    action; 2) it had at least a reasonable likelihood of success at trial
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 17 of 24
    by establishing a prima facie case; 3) its threatened injury
    outweighed the potential harm to appellant resulting from the
    granting of an injunction; and 4) the public interest would not be
    disserved.
    Harvest Ins. Agency, 492 N.E.2d at 688. “If the movant fails to prove any of
    these requirements, the trial court’s grant of an injunction is an abuse of
    discretion.” Ind. Fam. & Soc. Servs. Admin., 769 N.E.2d at 161.
    [8]    Duke makes two claims related to its contention of a reasonable likelihood of
    success on the merits should the matter proceed to trial: (1) the City should not
    be able to expand the Intersection because it does not have adequate property
    interests in portions of the land and (2) the proposed expansion of the
    Intersection unreasonably burdens its rights pursuant to the Easement.
    I. Whether Duke Has Standing to Challenge the City’s
    Interests to Land Involved in the Traffic Project
    [9]    Duke is claiming that the City may not expand the Intersection because it does
    not have sufficient property rights in the land at issue. Put another way, Duke
    is essentially pursuing an ejectment action against the City based on alleged
    trespass. The City argues that, even if one assumes that it does not have rights
    sufficient to allow it to expand the Intersection, Duke, as a mere easement
    holder, may not exclude the City on that basis.
    [10]   It is settled law that “in a trespass claim a plaintiff must prove that he was in
    possession of the land and that the defendant entered the land without right.”
    Aberdeen Apts. v. Cary Campbell Realty All., Inc., 
    820 N.E.2d 158
    , 164 (Ind. Ct.
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 18 of 
    24 App. 2005
    ) (citation and quotation marks omitted), trans. denied. “We are also
    mindful of the traditional rule that an action for trespass to real estate ‘cannot
    be maintained for an invasion of a right of way or easement.’” Ind. Mich. Power
    Co. v. Runge, 
    717 N.E.2d 216
    , 227 (Ind. Ct. App. 1999) (quoting State ex rel.
    Green v. Gibson Circuit Ct., 
    246 Ind. 446
    , 449, 
    206 N.E.2d 135
    , 137 (1965)).
    “‘This rule is based upon the principle that trespass actions are possessory
    actions and that the right interfered with is the plaintiff’s right to the exclusive
    possession of a chattel or land.’” 
    Id.
     (quoting Green, 
    246 Ind. at 449
    , 
    206 N.E.2d at 137
    ). Duke does not dispute that its interest in the parcels at issue is
    non-possessory, nor does it argue that cases such as Indiana Michigan Power and
    Green are no longer good law. Whatever defects in the City’s title may exist,
    Duke may not exclude the City (or any other entity) from the Intersection or
    challenge the construction of the Intersection on that basis.
    II. Whether the Traffic Plan Would Unreasonably
    Burden Duke’s Enjoyment of its Utility Easement
    [11]   The only remaining question is whether expanding the Intersection would
    impose an impermissible burden on Duke’s easement rights.
    Indiana cases clearly have held that the owner of an easement
    possesses all rights necessarily incident to the enjoyment of the
    easement, and that he may make such repairs, improvements, or
    alterations as are reasonably necessary to make the grant of the
    easement effectual. Board of Commissioners of Vanderburgh County
    v. Joeckel, (1980) Ind. App., 
    407 N.E.2d 274
    , trans. denied; Holding
    v. Indiana & Michigan Electric Co., (1980) Ind. App., 
    400 N.E.2d 1154
    ; Mercurio v. Hall, (1924) 
    81 Ind. App. 554
    , 
    144 N.E. 248
    .
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 19 of 24
    Although these cases involve controversies between the
    dominant and servient owners, we believe they are applicable to
    the present dispute between co-owners of an easement.
    The general rule appears to be that where there are several
    owners in common of an easement, each owner has a right to
    make reasonable repairs, alterations, and improvements to the
    easement so long as such do not injuriously affect his co-owner.
    Hultzen v. Witham, (1951) 
    146 Me. 118
    , 
    78 A.2d 342
    ; Mehene v.
    Ball, (1959) 
    22 Misc. 2d 577
    , 
    194 N.Y.S.2d 28
    ; Cain v. Aspinwall-
    Delafield Co., (1927) 
    289 Pa. 535
    , 
    137 A. 610
    ; Stifel v. Hannan,
    (1924) 
    95 W.Va. 617
    , 
    123 S.E. 673
    . Stated conversely, an owner
    in common of an easement may not alter the land in such a
    manner as to render the easement appreciably less convenient
    and useful for one of his co-owners. Goss v. Johnson, (1976) Iowa,
    
    243 N.W.2d 590
    ; Big Cottonwood Tanner Ditch Co. v. Moyle, (1946)
    
    109 Utah 213
    , 
    174 P.2d 148
    ; 25 Am. Jur. 2d, Easements, § 88
    (1966). Thus, the issues to be examined are the reasonable
    necessity to the enjoyment of the easement and the injurious
    effect on other co-owners, the latter being of significance because
    courts have not interfered with alterations or improvements
    unless it was made to appear that the objecting party would be
    seriously inconvenienced in his own use of the easement.
    Hultzen.
    Litzelswope v. Mitchell, 
    451 N.E.2d 366
    , 369-70 (Ind. Ct. App. 1983).
    [12]   At the very least, the City claims a right-of-way to construct the Intersection on
    the real estate at issue, which, as mentioned, is a claim Duke lacks standing to
    challenge. The issues we must examine, then, are the reasonable necessity of
    the Intersection to the City and the injurious effect it would have on Duke.
    [13]   The trial court made several findings regarding the reasonable necessity of the
    expansion of the Intersection:
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 20 of 24
    (1) the Traffic Plan, of which the Intersection expansion is a part,
    is designed to enhance the visual appearance of SR 44 to
    entice travelers on I-65 to stop for food and lodging;
    (2) the Traffic Plan is designed to slow traffic on SR 44 and
    separate commercial and residential traffic in the area, which
    are positive developments from an engineering and safety
    standpoint;
    (3) additional access points on SR 44 would reduce conflict
    points for motorists;
    (4) access to Scotty’s Brewhouse and Hillview County Club from
    SR 44 would be more direct and faster;
    (5) the Traffic Plan is designed to spur business and commercial
    development on the east side of the City; and
    (6) the Intersection would provide better access, via County Club
    Lane, to a residential development northwest of the Hillview
    Country Club.
    In summary, the Intersection expansion is one part of a City effort to beautify
    the SR 44 corridor on the east side, enhance motorist safety, and spur
    commercial and business growth. Denying the City the ability to expand the
    Intersection would prevent it from fully implementing the Traffic Plan. Taken
    together, the findings support a conclusion that the Traffic Plan in general, and
    the proposed expansion of the Intersection in particular, are reasonably
    necessary uses of the City’s right-of-way as they relate to implementation of the
    Traffic Plan.
    [14]   The other side of the coin is the injurious effect the expansion of the
    Intersection would have on Duke. Duke’s argument in this regard focuses
    primarily on its claims that any repair to or replacement of its equipment near
    the Intersection would be more expensive and also more hazardous to its
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 21 of 24
    employees were the Intersection to be expanded. The trial court made the
    following findings related to Duke’s claims:
    (1) no evidence was submitted of any repair or maintenance that
    had been done to pole 825-4181 or any nearby equipment;
    (2) Duke had in the past, when warranted, closed roadways
    temporarily in order to perform maintenance, a practice to
    which the City has no objections;
    (3) should pole 825-4181 have to be replaced at some point,
    Country Club Lane and Longest Drive, but not SR 44, would
    have to be closed;
    (4) replacement of pole 825-4181 would, however, require
    closure of access from the Intersection to SR 44 if the
    Intersection were expanded;
    (5) the Manager of Transmission for Duke testified that traffic
    management of the expanded Intersection could require
    directional signs and personnel but did not render a specific
    opinion on how the proposed expansion would change traffic
    control;
    (6) working at night, Duke replaced an electrical pole in
    Greenwood which required the closure of Madison Avenue, a
    major arterial roadway, a procedure that did not endanger
    repair crews; and
    (7) the location of a proposed bicycle and pedestrian trail would
    not be close enough to pole 825-4181 to be a safety risk.
    [15]   Based on the above findings, the trial court concluded that Duke’s ability to
    repair and maintain its transmission lines would not be affected by expansion of
    the Intersection. The trial court noted that the most likely maintenance would
    be replacement of pole 825-4181, which would require closing the entire
    Intersection whether or not it was connected to SR 44. The trial court also
    noted that Country Club Lane served Hillview Country Club and Scotty’s
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 22 of 24
    Brewhouse, both businesses with set hours, meaning that maintenance could be
    scheduled when both were closed and traffic in the area was diminished. The
    trial court concluded that Duke’s ability to maintain its property in its easement
    would be unaffected with the possible exception that some additional traffic
    control measures may be required. The record, however, contains no solid
    evidence on the additional costs or risks of temporarily closing a four-way
    intersection as opposed to a three-way.
    [16]   Under the circumstances of this case, we cannot say that the trial court’s
    conclusion amounts to an abuse of discretion. On the whole, the trial court’s
    findings, which were all supported by evidence in the record, were more than
    enough to support a conclusion that the reasonable necessity of the
    Intersection’s expansion outweighed whatever injurious effect that expansion
    would have on Duke’s enjoyment of its easement. Because the trial court did
    not abuse its discretion in concluding that Duke did not establish a reasonable
    likelihood of success at trial, it also did not abuse its discretion in denying its
    request for a preliminary injunction.
    Conclusion
    [17]   We conclude that Duke, as a mere utility-easement holder, lacks standing to
    maintain an ejectment action against the City on the basis that the City does not
    have sufficient property rights to expand the Intersection. Moreover, we
    conclude that the trial court did not abuse its discretion in determining that
    Duke failed to show a reasonable likelihood of success at trial. Consequently,
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 23 of 24
    the trial court did not abuse its discretion in denying Duke’s request for a
    preliminary injunction against the City.
    [18]   We affirm the judgment of the trial court.
    Pyle, J., and Altice, J. concur.
    Court of Appeals of Indiana | Opinion 41A01-1607-CT-1549 |December 16, 2016   Page 24 of 24