Richard Hiller d/b/a Hiller & Sons v. City of Portage (mem. dec.) ( 2019 )


Menu:
  •       MEMORANDUM DECISION
    Pursuant to Ind. Appellate Rule 65(D),                                      FILED
    this Memorandum Decision shall not be                                  Aug 13 2019, 8:12 am
    regarded as precedent or cited before any                                   CLERK
    court except for the purpose of establishing                            Indiana Supreme Court
    Court of Appeals
    the defense of res judicata, collateral                                      and Tax Court
    estoppel, or the law of the case.
    ATTORNEY FOR APPELLANT                                   ATTORNEY FOR APPELLEE
    Terry K. Hiestand                                        Steven J. Scott
    Hiestand Law Office                                      Hodges & Davis, P.C.
    Chesterton, Indiana                                      Merrillville, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Richard Hiller d/b/a Hiller &                            August 13, 2019
    Sons,                                                    Court of Appeals Case No.
    Appellant-Defendant,                                     18A-CC-3129
    Appeal from the Porter Superior
    v.                                               Court
    The Honorable Roger V. Bradford,
    City of Portage,                                         Judge
    Appellee-Plaintiff.                                      Trial Court Cause No.
    64D01-1605-CC-4460
    Friedlander, Senior Judge.
    [1]   Richard Hiller d/b/a Hiller & Sons (Hiller) appeals the trial court’s order
    denying his motion for judgment on the pleadings and granting the City of
    Portage’s (City) motion for partial summary judgment. Concluding that
    Court of Appeals of Indiana | Memorandum Decision 18A-CC-3129 | August 13, 2019                 Page 1 of 7
    genuine issues of material fact remain, we affirm in part and reverse and
    remand in part for further proceedings.
    [2]   In the early 2000’s, Hiller developed the Austin Hills Subdivision in the City.
    As part of developing the subdivision, Hiller agreed to provide the public
    improvements for each phase, including the final surfacing of roads. By 2005,
    Phases I-V were complete, and the public improvements for Phase VI, the final
    phase, were complete except the final surfacing of roads. In order to secure the
    completion of the public improvements for Phase VI, on October 17, 2005,
    Hiller provided to the City an Irrevocable Letter of Credit in the amount of
    $41,500 issued by the First State Bank of Porter (Bank). The amount of the
    Letter of Credit was based on estimates Hiller provided to the City, which the
    City found to be appropriate and accepted.
    [3]   By 2015, the final surfacing of roads for Phase VI had yet to be completed. The
    City sought bids from two contractors to perform the work, one of which
    completed the final surfacing and repair work at a cost of $146, 921. The City
    drew on the $41,500 available pursuant to the Letter of Credit and filed suit
    against Hiller in May 2016 seeking the remainder.
    [4]   In October 2017, Hiller filed a motion for summary judgment, arguing that the
    City’s complaint was not filed within any relevant statutes of limitation. The
    City filed a response, and, following a hearing, the court denied Hiller’s motion.
    Hiller sought and received from the trial court certification of its order for
    Court of Appeals of Indiana | Memorandum Decision 18A-CC-3129 | August 13, 2019   Page 2 of 7
    interlocutory appeal; however, this Court denied his motion to accept
    jurisdiction of the appeal.
    [5]   In September 2018, the City filed its motion for partial summary judgment as to
    liability, claiming that Hiller had agreed to complete the final layering of the
    road in Phase VI, that after ten years he had not completed the final layering,
    and that he was liable for the cost the City incurred in having the work
    completed. In response, Hiller filed a motion for judgment on the pleadings,
    arguing that the City failed to state a claim upon which relief can be granted
    and that the City’s claims are time-barred. The court treated Hiller’s motion as
    a response to the City’s motion for summary judgment. In November,
    following a hearing, the court granted the City’s partial motion for summary
    judgment as to liability and denied Hiller’s motion. Hiller now appeals.
    [6]   Given that Hiller presented matters outside the pleadings in support of his
    motion for judgment on the pleadings, we will treat his motion as one for
    summary judgment, as did the trial court, and review it accordingly. See Ind.
    Trial Rule 12(C). We review de novo a trial court’s ruling on summary
    judgment. Morris v. Crain, 
    71 N.E.3d 871
    (Ind. Ct. App. 2017). We apply the
    same standard of review as the trial court: summary judgment is appropriate
    only where the designated evidentiary matter shows there is no genuine issue as
    to any material fact and that the moving party is entitled to judgment as a
    matter of law. Young v. Hood’s Gardens, Inc., 
    24 N.E.3d 421
    (Ind. 2015); see also
    Ind. Trial Rule 56(C). Appellate review of a summary judgment is limited to
    those materials specifically designated to the trial court, and all facts and
    Court of Appeals of Indiana | Memorandum Decision 18A-CC-3129 | August 13, 2019   Page 3 of 7
    reasonable inferences drawn from those facts are construed in favor of the
    nonmovant. Sheehan Const. Co., Inc. v. Cont’l Cas. Co., 
    938 N.E.2d 685
    (Ind.
    2010). Summary judgment is not a summary trial, and it is inappropriate
    merely because the nonmoving party appears unlikely to prevail at trial. Morris,
    
    71 N.E.3d 871
    . Finally, that the parties made cross motions for summary
    judgment does not alter our standard of review; rather, we consider each
    motion separately to determine whether the moving party is entitled to
    judgment as a matter of law. Pond v. McNellis, 
    845 N.E.2d 1043
    (Ind. Ct. App.
    2006), trans. denied.
    [7]   In his motion for judgment on the pleadings and in his brief to this Court, Hiller
    maintains that the City’s complaint was untimely filed. “The defense of a
    statute of limitation is peculiarly suitable as a basis for summary judgment.”
    Del Vecchio v. Conseco, Inc., 
    788 N.E.2d 446
    , 449 (Ind. Ct. App. 2003), trans.
    denied. As per Indiana’s discovery rule, a cause of action accrues, and the
    statute of limitation begins to run, when a claimant knows or in the exercise of
    ordinary diligence should have known of the injury. Barrow v. City of
    Jeffersonville, 
    973 N.E.2d 1199
    (Ind. Ct. App. 2012), trans. denied. For an action
    to accrue, it is not necessary that the full extent of the damage be known or
    even ascertainable but only that some ascertainable damage has occurred. 
    Id. “The exercise
    of reasonable diligence means simply that an injured party must
    act with some promptness where the acts and circumstances of an injury would
    put a person of common knowledge and experience on notice that some right of
    his has been invaded or that some claim against another party might exist.” 
    Id. Court of
    Appeals of Indiana | Memorandum Decision 18A-CC-3129 | August 13, 2019   Page 4 of 7
    at 1206. The discovery rule applies to both tort and contract claims. Del
    Vecchio, 
    788 N.E.2d 446
    .
    [8]    As we discuss below, the City’s claim appears to be based on an oral contract.
    The statute of limitation for an oral contract is six years. Ind. Code § 34-11-2-
    7(1) (1998). Hiller points to October 2005 as the date any cause of action may
    have accrued. This claim rests on the issuance date of the Letter of Credit,
    which states it was established to guarantee completion of the public
    improvements to Phase VI of the Austin Hills Subdivision should there be any
    “performance deficiency.” Appellant’s App. Vol. 2, p. 29. There is also some
    evidence that Sandy McDaniel, project manager for the City, had some type of
    communication with Hiller in 2009 concerning a possible timeframe in which
    the final layering would be complete. On the other hand, the City claims it was
    not aware of its injury, and thus a cause of action did not accrue, until the time
    the final layer of asphalt was applied to the Phase VI roads in 2015.
    [9]    We cannot say when, as a matter of law, the limitation period began to run
    because the evidence is in conflict. When there is a factual issue concerning the
    date on which a cause of action accrues, the question is generally one for the
    finder of fact. Custom Radio Corp. v. Actuaries & Benefit Consultants, Inc., 
    998 N.E.2d 263
    (Ind. Ct. App. 2013). Therefore, summary judgment premised on
    the expiration of the statute of limitation would have been inappropriate.
    [10]   We turn now to the City’s motion for summary judgment. The City refers only
    to an “agreement,” but the gist of its claim against Hiller sounds in contract. In
    Court of Appeals of Indiana | Memorandum Decision 18A-CC-3129 | August 13, 2019   Page 5 of 7
    order to recover for a breach of contract, a plaintiff must prove (1) a contract
    existed, (2) the defendant breached the contract, and (3) the plaintiff suffered
    damage as a result of the defendant’s breach. Alexander v. Linkmeyer Dev. II,
    LLC, 
    119 N.E.3d 603
    (Ind. Ct. App. 2019).
    [11]   No written contract was designated by the City, and, at most, the
    uncontradicted designated evidence demonstrates some type of oral agreement
    between Hiller and the City. In his 2016 deposition, Hiller testified that work
    on Phase VI began in approximately 2005 and that his construction company
    was responsible for certain public improvements that he identified as sewer
    lines, water lines, street base, curbs, and two layers of asphalt. He further
    testified that he had agreed to complete all of these public improvements for
    Phase VI, including the final layer of asphalt for the roads.
    [12]   As to a breach of any such agreement, there is a genuine dispute. The City’s
    designated evidence merely shows that by 2015 Hiller had not yet completed
    the final layering of roads in Phase VI. In the designated portion of her
    deposition, McDaniel testified that in 2015 the City was having some individual
    paving projects done, and the mayor asked for bids for the final layering of
    Phase VI. The City obtained two bids for the job and hired the contractor that
    submitted the lowest bid. However, McDaniel also testified that she was
    unaware of any notifications to Hiller after 2009 with regard to the final
    layering of Phase VI. In the designated portion of his deposition, Hiller testified
    that he typically waited until 90% of the lots in the phase had homes built on
    them before he completed the final layering.
    Court of Appeals of Indiana | Memorandum Decision 18A-CC-3129 | August 13, 2019   Page 6 of 7
    [13]   The City has not produced any evidence demonstrating the terms of any
    agreement it had with Hiller. Consequently, there is no evidence outlining the
    parties’ obligations or duties under the agreement, such as a time period within
    which Hiller was to have completed the final layering. Without some evidence
    of the terms of the parties’ agreement, there can be no showing of a violation of
    such terms. The designated evidence clearly establishes a question of fact on
    the issue of whether Hiller breached any agreement by not completing the final
    layering by 2015. Accordingly, we cannot say the City was entitled to
    judgment as a matter of law.
    [14]   For the reasons stated, we conclude that genuine issues of fact remain which
    preclude entry of judgment as a matter of law. Accordingly, we affirm the trial
    court’s denial of Hiller’s motion for judgment on the pleadings and reverse and
    remand for further proceedings on the trial court’s grant of the City’s motion for
    partial summary judgment.
    [15]   Judgment affirmed in part and reversed and remanded in part.
    Bailey, J., and Pyle, J., concur.
    Court of Appeals of Indiana | Memorandum Decision 18A-CC-3129 | August 13, 2019   Page 7 of 7