NIPSCO Industrial Group v. Northern Indiana Public Service Company, Indiana Office of Utility Consumer Counselor ( 2013 )


Menu:
  • Pursuant to Ind.Appellate Rule 65(D),
    this Memorandum Decision shall not be
    regarded as precedent or cited before                        Mar 15 2013, 9:14 am
    any court except for the purpose of
    establishing the defense of res judicata,
    collateral estoppel, or the law of the case.
    ATTORNEYS FOR APPELLANT:                       ATTORNEYS FOR APPELLEES:
    BETTY J. DODD                                  Attorneys for Indiana Office of Utility
    STEVEN W. GRIESEMER                            Consumer Counselor
    JOSEPH P. ROMPALA                              RANDALL C. HELMEN
    Lewis & Kappes, P.C.                           LORRAINE HITZ-BRADLEY
    Indianapolis, Indiana                          Office of Utility Consumer Counselor
    Indianapolis, Indiana
    Attorneys for NIPSCO
    NICHOLAS K. KILE
    MARK J. CRANDLEY
    Barnes & Thornburg
    Indianapolis, Indiana
    CLAUDIA J. EARLS
    ERIN CASPER BORISSOV
    NISOURCE, INC.
    Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    NIPSCO INDUSTRIAL GROUP,                       )
    )
    Appellant-Respondent/Intervenor,        )
    )
    vs.                             )      No. 93A02-1205-EX-436
    )
    NORTHERN INDIANA PUBLIC SERVICE                )
    COMPANY,                                       )
    )
    Appellee-Petitioner,                    )
    )
    INDIANA OFFICE OF UTILITY CONSUMER             )
    COUNSELOR,                                     )
    )
    Appellee-Statutory Representative.      )
    APPEAL FROM THE INDIANA UTILITY REGULATORY COMMISSION
    IURC Cause No. 42150-ECR 19
    March 15, 2013
    MEMORANDUM DECISION - NOT FOR PUBLICATION
    MAY, Judge
    NIPSCO (Industrial Group) appeals the Indiana Utility Regulatory Commission’s
    (IURC) denial of Industrial Group’s Petition for Reconsideration regarding IURC’s final
    order in Cause Number 42150-ECR 19. That order set the allocation method for the
    Northern Indiana Public Service Company’s (NIPSCO) Environmental Cost Recovery
    Mechanism (ECRM) and Environmental Expense Recovery Mechanism (EERM) factors for
    a Qualified Pollution Control Property (QPCP) under construction. Industrial Group presents
    three issues for our consideration, one of which we find dispositive: Whether the IURC was
    required to abide by 170 IAC 4-6-15 when determining the rate allocation for the ECRM and
    EERM factors for QPCPs under construction. We affirm.
    FACTS AND PROCEDURAL HISTORY
    On December 21, 2011, the IURC issued an order on Cause Number 43969 (2011
    Rate Settlement) to settle challenges to NIPSCO’s 2010 proposed rate increase. The
    Industrial Group intervened. The parties and intervenors agreed that the issue of the rate
    allocation for ECRM and EERM factors for QPCPs under construction would be determined
    at a later date. The IURC ordered NIPSCO to propose a methodology for the rate allocation,
    which the other parties and intervenors were free to contest. In re NIPSCO, Cause No.
    2
    43969 (IURC Dec. 21, 2011).
    On February 7, 2012, NIPSCO filed its Verified Petition (ECR Petition) requesting the
    approval of its proposed rate allocations for the ECRM and EERM factors. On February 23,
    the Industrial Group filed a petition to intervene, arguing an across-the-board methodology of
    rate allocation is required by 170 IAC 4-6-15, which states: “A utility’s jurisdictional revenue
    requirement that results from the ratemaking treatment of qualified pollution control property
    under construction under this rule (170 IAC 4-6) shall be allocated among the utility’s
    customer classes in accordance with the allocation parameters established by the commission
    in the utility’s last general rate case.”
    On April 3, the Indiana Office of Utility Consumer Counselor (OUCC) filed testimony
    regarding the proposed rate allocation methodologies, one of which was a methodology
    called “12 CP,” which allocates a customer’s rate based upon the customer’s average
    contribution to the average monthly peak of utility usage. (Br. of Appellee at 2.) The
    Industrial Group reasserted its position that the IURC was required to comply with 170 IAC
    4-6-15 and the rate allocation should be based on an across-the-board methodology.
    On April 14, the IURC held a hearing on the matter. On May 2, the IURC issued its
    order on the ECR Petition, approving the 12 CP rate allocation methodology. On May 22,
    the Industrial Group filed a Petition for Reconsideration, arguing the IURC’s decision
    violated 170 IAC 4-6-15, and the 12 CP rate allocation methodology discriminated against
    those customers who deducted a portion of their charges based on their willingness to have
    their service interrupted when the system is at peak usage. On August 15, the IURC denied
    3
    the petition, finding the Industrial Group was precluded from arguing a violation of 170 IAC
    4-6-15, and the IURC’s earlier decision sufficiently addressed the discrimination issue. This
    appeal ensued.
    DISCUSSION AND DECISION
    When reviewing administrative decisions:
    Our review . . . is limited to whether the agency based its decision on
    substantial evidence, whether the agency’s decision was arbitrary and
    capricious, and whether it was contrary to any constitutional, statutory, or legal
    principle. PSI Energy, Inc. v. Indiana Office of Utility Consumer Counsel, 
    764 N.E.2d 769
    , 774 (Ind. Ct. App. 2002), trans. denied. We are not allowed to
    conduct a trial de novo, but rather, we defer to an agency’s fact-finding, so
    long as its findings are supported by substantial evidence. 
    Id.
    The first stage of our review examines whether the agency’s “decision
    contain[s] specific findings on all of the factual determinations material to its
    ultimate conclusions,” which is especially important when the agency’s
    decision is a rate order. 
    Id.
     Basic findings of fact are important because they
    enlighten us as to the agency’s “reasoning process and subtle policy
    judgments” and allow for “a rational and informed basis for review,” which
    lessens the likelihood that we would substitute our “judgment on complex
    evidentiary issues and policy determinations” better decided by an agency with
    technical expertise. 
    Id.
     Requiring an agency to set forth basic findings also
    assists the agency “in avoiding arbitrary or ill-considered action.” 
    Id.
    The second stage of the review process examines whether there is
    substantial evidence in the record to support the agency’s basic findings of
    fact. 
    Id.
     To determine whether there was substantial evidence sufficient to
    support the agency’s determination, we must consider all evidence, including
    that evidence supporting the determination as well as evidence in opposition to
    it. 
    Id.
     We may set aside agency findings of fact only when we determine, after
    a review of the entire record, that the agency’s decision clearly “lacks a
    reasonably sound basis of evidentiary support.” 
    Id.
    Additionally, however, it is well established that the substantial
    evidence test cannot be utilized to analyze the reasonableness of the
    conclusions of ultimate fact inferred by an agency from its findings of basic
    fact. 
    Id.
     Therefore, even though an agency’s findings of fact may represent
    inferences drawn by the agency and thus not be susceptible to scrutiny for
    evidentiary support, the reasonableness of the agency’s inferences is an
    appropriate judicial determination. 
    Id.
     Moreover, any agency determination
    4
    that is not in accordance with the law may be set aside because we owe no
    deference to an agency’s conclusions of law. 
    Id.
    Citizens Action Coal. of Ind., Inc., v. N. Ind. Pub. Serv. Co., 
    804 N.E.2d 289
    , 294 (Ind. Ct.
    App. 2004). Additionally, “[a]n interpretation of a statute by an administrative agency
    charged with the duty of enforcing the statute is entitled to great weight, unless the
    interpretation would be inconsistent with the statute itself.” LTV Steel Co. v. Griffin, 
    730 N.E.2d 1251
    , 1257 (Ind. 2000).
    The Indiana Administrative Code section regarding the ratemaking treatment of
    QCPCs states, “A utility’s jurisdictional revenue requirement that results from the ratemaking
    treatment of qualified pollution control property under construction under this rule (170 IAC
    4-6) shall be allocated among the utility’s customer classes in accordance with the allocation
    parameters established by the commission in the utility’s last general rate case.” 170 IAC 4-
    6-15. The Industrial Group argues the IURC was required to use the “last general rate
    increase,” pursuant to 170 IAC 4-6-15, to determine the rates in ECR Petition for the ECRM
    and EERM from QCPCs under construction. We disagree.
    In addressing the method by which it determined the appropriate rates for ECRM and
    EERM from QCPCs under construction, the IURC found:
    The 2011 Settlement and 2011 Rate Order specifically left open the
    question of the appropriate allocation method for NIPSCO’s ECRM and
    EERM factors. Accordingly 170 IAC 4-6-15 provides no guidance with
    respect to the allocation ordered in Cause No. 43969 given the express
    language in the 2011 Rate Order that the allocation of QPCP would be
    determined based upon proposals presented in this Cause. Further, we do not
    believe that the negotiated revenue allocations that formed the basis of the
    2011 Settlement should be applied to allocation of the ECRM revenue
    requirement in a contested case.
    5
    Instead we find that our Order in Cause No. 43526 [is] instructive. In
    that Cause, we determined that the 12 CP allocation was appropriate, and
    ordered NIPSCO to design its rates using that allocation. While rates under
    Cause No. 43526 never became effective, we should not ignore our allocation
    determination from less than two years ago. We note that the Commission did
    consider the P&A methodology in Cause No. 43526, and did not approve its
    use in that Cause, and we do not do so here.
    (Industrial Group App. at 13.) The order regarding the 2011 Settlement stated:
    The Settlement is silent as to the allocation of costs in the ECRM and EERM
    and the Settlement does not preclude the Commission from deciding the proper
    allocation in a subsequent proceeding. Therefore, for purposes of its
    compliance filing in this proceeding, NIPSCO should allocate costs from the
    ECRM and EERM consistent with the way it is currently allocating them, and
    the Commission finds that in its first ECRM and EERM following issuance of
    this Order (to be filed in February 2012) NIPSCO shall propose an allocation
    methodology, which all parties are free to contest.
    In re NIPSCO, Cause No. 43969 at 66.
    The statement leaving the determination of the ECRM and EERM rates open to
    proposal suggests the IURC did not intend to strictly comply with 170 IAC 4-6-15, which
    requires the ECRM and EERM rates to be based on the allocation method used in the last
    general rate increase. We have found strict compliance with 170 IAC 4-6-15 illogical when
    that compliance results in an inaccurate allocation of costs amongst customer classes.
    Citizens Action, 
    804 N.E.2d at 304
    . See also Robinson v. Gazvoda, 
    783 N.E.2d 1245
    , 1250
    (Ind.Ct.App.2003) (instead of requiring an inaccurate allocation of costs amongst consumer
    classes, we prefer to look to the legislative intent underlying the statute and to construe the
    statute in such a way as to prevent absurdity and hardship and to favor public convenience; in
    so doing, we consider the objects and purposes of the statute, as well as the effects and
    6
    consequences of such an interpretation), trans. denied.
    As the Industrial Group agreed to the settlement, it cannot now complain there is
    error. See Stolberg v. Stolberg, 
    538 N.E.2d 1
    , 5 (Ind. Ct. App. 1989) (appellant precluded
    from complaining of error in settlement agreement to which she acquiesced). Because the
    Industrial Group agreed to such a deviation as part of its ratification of the 2011 Settlement,
    it therefore, is precluded from complaining that the IURC deviated from 170 IAC 4-6-15 in
    its order setting the rates for ECRM and EERM factors for QCPCs under construction.1
    Accordingly, we cannot find error in the IURC’s failure to follow 170 IAC 4-6-15, and we
    affirm the IURC’s decision.2
    Affirmed.
    ROBB, C.J., and PYLE, J., concur.
    1
    The Industrial Group also argues the IURC erred when it determined, in its order denying the Industrial
    Group’s Petition for Reconsideration, that the Industrial Group was precluded from arguing the IURC violated
    170 IAC 4-6-15 because it did not object to the methodology prescribed by the IURC in the 2011 Settlement
    Order. As we come to the same conclusion, we find no error.
    2
    The Industrial Group also argues the IURC discriminated against its “interruptible” customers by failing to
    allow for the deduction of their times of interrupted service as part of the approved 12 CP rate allocation. 
    Ind. Code § 8-1-2-4
     requires a public utility “avoid discrimination in rates between classes of customers[.]”
    However, we have recognized the ratemaking statutes do not “prohibit differing rates for differing classes or
    types of service . . . The charging of different rates for service rendered under different conditions and under
    different circumstances is not unlawful or unduly preferential.” Capital Improvement Mgrs. of Marion Cty. v.
    Pub. Serv. Comm’n, 
    176 Ind. App. 240
    , 263, 
    375 N.E.2d 616
    , 633 (1978). As there was evidence to support
    the IURC’s decision to exclude from its order any special consideration of the “interruptible” customers, we
    cannot say the act of doing so was discriminatory. See Citizens Action, 
    804 N.E.2d at 294
     (we will not reverse
    if the IURC’s decision is supported by substantial evidence).
    7