Parkway Developers Construction, LLC v. Lang, Feeney & Associates, Inc., and Terance D. Lang ( 2013 )


Menu:
  • Pursuant to Ind.Appellate Rule 65(D),
    this Memorandum Decision shall not be
    regarded as precedent or cited before                           Jul 26 2013, 8:27 am
    any court except for the purpose of
    establishing the defense of res judicata,
    collateral estoppel, or the law of the case.
    ATTORNEYS FOR APPELLANT:                            ATTORNEYS FOR APPELLEES:
    JULIA BLACKWELL GELINAS                             TIMOTHY J. ABESKA
    MAGGIE L. SMITH                                     ALICE J. SPRINGER
    Frost Brown Todd LLC                                Barnes & Thornburg LLP
    Indianapolis, Indiana                               South Bernd, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    PARKWAY DEVELOPERS                                  )
    CONSTRUCTION, LLC,                                  )
    )
    Appellant-Plaintiff,                         )
    )
    vs.                                  )      No. 71A03-1212-PL-526
    )
    LANG, FEENEY & ASSOCIATES, INC.,                    )
    and TERANCE D. LANG,                                )
    )
    Appellees-Defendants.                        )
    APPEAL FROM THE ST. JOSEPH SUPERIOR COURT
    The Honorable Michael P. Scopelitis, Judge
    Cause No. 71D07-0905-PL-133
    July 26, 2013
    MEMORANDUM DECISION - NOT FOR PUBLICATION
    ROBB, Chief Judge
    Case Summary and Issues
    Parkway Developers Construction appeals the trial court’s judgment ordering Lang
    Feeney & Associates to pay Parkway interest on late payments under a contract. Parkway
    raises three consolidated and restated issues on appeal: 1) whether the trial court erred in
    determining that a memorandum agreement was enforceable, and in agreeing with Lang on
    the terms of the agreement; 2) whether the trial court erred in granting summary judgment to
    Lang on three of the claims in Parkway’s complaint; and 3) whether the trial court abused its
    discretion in denying Parkway’s motion to amend its complaint. Concluding that the trial
    court did not err in interpreting the contract, that the trial court did err in granting summary
    judgment but that such error was harmless, and that the trial court did not abuse its discretion
    in denying Parkway’s motion to amend, we affirm.
    Facts and Procedural History
    In 2005, Parkway hired Lang to do surveying and other work for a subdivision project
    that Parkway was developing. In 2007, Parkway realized that Lang had made surveying
    errors and miscalculated the amount of dirt available on the property. Lang acknowledged
    that errors had been made, and the parties met several times to come to an agreement to
    remedy the errors. There is some disconnect between the parties and in the record as to who
    played what role in the drafting of the final agreement. It seems that both parties worked on
    drafting the contract, and from both the record and the poor draftsmanship of the contract, it
    appears that lawyers were not involved in its drafting; the record indicates though that
    Parkway had the advice of an attorney before signing the contract.
    2
    The Memorandum of Agreement (the “Agreement”) was signed on January 16, 2008.
    The Agreement states, in relevant part:
    Lang, Feeney & Associates agree to pay Parkway Developers Construction
    $55,631.00 in Cash, Surveying and related work to be performed under this
    agreement and existing invoices previously presented to Parkway Developers
    Construction, all in installments as follows:
     First installment of $5,000.00 before December 31, 2007;
     Starting March 31, 2008 payments of $5,000.00 per month. (Interest
    occurring at 1% per month for late payments.)
     Dirt to be filled in lots 2, 4, and 5 to make lots uniform for all home
    models. All expenses for earthwork not to exceed a quantity of 2,075
    cubic yards of earth in conjunction with lots 2, 4 and 5, and correcting
    all surveyors [sic] errors to be paid by Lang, Feeney & Associates.
     All work and seeding to be done no later than June 2008 (Weather
    permitting).
     This Contract also includes first two approvals of the second phase of
    Country Farm Estates. With all expenses incurred including, but not
    limited to, any legal or attorney fees to be paid by Lang, Feeney &
    Associates.
     It is further agreed that any monies currently due to Lang, Feeney &
    Associates from Parkway Developers Construction is now applied to
    satisfaction of this agreement by Lang, Feeney & Associates.
     Subject to the terms and conditions set forth in paragraph 5 of this
    Agreement, Parkway . . . does hereby release . . . Lang . . . from any and
    all claims . . . arising from or relating to the Survey Errors.
    ***
     Notwithstanding anything to the contrary in the Agreement, the parties
    specifically acknowledge that the liability for any claims of Parkway
    Developers Construction LLC against Lang, Feeney and Associates, Inc
    arising from the Survey Errors shall only be finally discharged after (a)
    Parkway Developers Construction LLC has received the total sum, in
    cash and work equity of Lang, Feeney and Associates, Inc, of
    $55,631.00 plus any applicable interest, as calculated and designated
    herinabove [sic].
    Appendix at 88-89.
    3
    After the Agreement was signed, Lang made payments to Parkway, several of which
    were late; forgave money that Parkway owed to Lang; and performed certain work under the
    Agreement, including obtaining the first two approvals of the second phase of Country Farm
    Estates.
    In 2009, Parkway filed suit against Lang, ultimately including four claims: claims one
    through three were for negligence and breach of contract relating to Lang’s initial surveying
    errors, and claim four was for breach of contract relating to the Agreement. Lang filed for
    summary judgment, arguing that it had met its obligations under the Agreement and thus was
    released from any claims relating to the initial surveying errors. The trial court granted
    summary judgment as to claims one through three, but found that there were material facts in
    dispute as to claim four, and so claim four proceeded to trial.
    In July 2012, Parkway moved to amend its complaint to add a claim for fraud. The
    trial court denied the motion. In October 2012, a bench trial was held on claim four, and
    following the trial the parties were instructed to file post-trial briefs. In November 2012, the
    trial court issued its order and judgment, and sua sponte included findings of fact and
    conclusions of law. The court found that the Agreement required Lang to provide Parkway
    with combined cash and services totaling $55,631, plus interest for any late payments. The
    court found that Lang had paid Parkway $35,000 in cash, had forgiven $8,213 in debt, and
    had performed services totaling $13,574, for a total of $56,787. The court also found that
    Lang had not properly seeded or placed dirt as outlined in the Agreement and so was not
    entitled to any credit for services performed for those items, but that because Lang had
    4
    otherwise exceeded the monetary requirement of the Agreement, there was no breach of
    contract. Finally, the court ordered Lang to pay Parkway $247.31 as interest on cash
    payments that were made late. This appeal followed. Additional facts will be supplied as
    necessary.
    Discussion and Decision
    I. Memorandum of Agreement
    A. Standard of Review
    When, as here, findings of fact and conclusions of law are entered by the trial court,
    we will not set aside the judgment unless it is clearly erroneous. AmRhein v. Eden, 
    779 N.E.2d 1197
    , 1206 (Ind. Ct. App. 2002). Clear error leaves us definitely and firmly
    convinced the trial court committed error. 
    Id.
     The evidence must support the findings, and
    the findings must support the judgment. 
    Id.
     We defer to the trial court when evidence
    conflicts, and we will not reweigh the evidence or reassess the credibility of witnesses. 
    Id.
    We will affirm if there is sufficient evidence of probative value to support the decision,
    viewing the evidence most favorable to the judgment and the reasonable inferences drawn
    therefrom. 
    Id.
     Conclusions of law are reviewed de novo. 
    Id.
    B. Release Requirements in Agreement
    Parkway does not contest a finding that Lang submitted a combination of cash,
    services, and forgiven debt that exceeded $55,631. Parkway argues instead that the
    Agreement required Lang to pay $55,631 in cash, and to perform all of the services outlined
    in the Agreement, and to forgive Parkway’s debt. Parkway further argues that because the
    5
    parties disagree as to how the dollar amount in the Agreement is to be interpreted, there was
    no meeting of the minds, and thus the contract is void, and Parkway should be free to pursue
    its claims against Lang related to the initial surveying errors.
    Parkway contends that there was no meeting of the minds because the parties disagree
    as to whether the Agreement was supposed to cap Lang’s costs or whether it was meant to
    outline several things, all of which Lang was required to complete. However, it is unclear
    what suggests that there was no meeting of the minds, other than afterthought. While it is
    true that a meeting of the minds is required for the formation of a contract, the relevant intent
    “is not the parties’ subjective intents but their outward manifestation of it.” Zimmerman v.
    McColley, 
    826 N.E.2d 71
    , 77 (Ind. Ct. App. 2005) (“A court does not examine the hidden
    intentions secreted in the heart of a person; rather it should examine the final expression
    found in conduct. The intention of the parties to a contract is a factual matter to be
    determined from all the circumstances.” (citation omitted)). The trial court found that the
    Agreement required Lang to provide Parkway with cash and services totaling $55,631, plus
    interest for late payments. We agree that the Agreement is not ambiguous on its face: twice
    it states that the amount due from Lang is to come from a combination of cash and services.
    The Agreement begins with, “Lang, Feeney & Associates agree to pay Parkway Developers
    Construction $55,631.00 in Cash, Surveying and related work to be performed under this
    agreement and existing invoices previously presented to Parkway Developers Construction,”
    and then later reiterates that “Lang, Feeney and Associates, Inc arising from the Survey
    Errors shall only be finally discharged after (a) Parkway Developers Construction LLC has
    6
    received the total sum, in cash and work equity of Lang, Feeney and Associates, Inc, of
    $55,631.00.” App. at 88-89 (emphasis supplied). While Parkway testified to a different
    interpretation than Lang, that does not necessarily mean that there was no meeting of the
    minds. It was up to the trial court to weigh the evidence and witness credibility, and there
    was sufficient evidence to support the trial court’s finding that the Agreement required Lang
    to provide cash and services totaling $55,631.
    Parkway also argues that Lang breached the Agreement and therefore was not released
    from liability stemming from the original surveying errors. However, this argument circles
    back to Parkway’s interpretation of the requirements under the Agreement. Parkway does
    not argue that the trial court wrongly found that Lang supplied cash and services totaling
    more than $55,631, but continues to argue that the trial court wrongly interpreted the
    requirements of the Agreement. The record supports the trial court’s finding that Lang met
    that cap within the Agreement. The trial court nevertheless addressed the possibility of a
    breach by Lang, stemming from Lang’s failure to complete all of the services outlined in the
    Agreement.1 The court found that, while Lang had failed to complete some of the services,
    because Lang otherwise met and exceeded the dollar cap as set out in the Agreement, there
    was no breach for failure to complete additional services. The evidence supports the trial
    court’s findings that Lang did not breach the Agreement.
    Concluding that evidence supports the trial court’s findings that the Agreement
    required only that Lang supply cash and services totaling $55,631 and that Lang met that
    1
    For example, the Agreement included dirt filling and seeding work that the court determined
    Lang had not completed properly, if at all.
    7
    obligation and did not breach the Agreement, we also conclude that the trial court’s findings
    support the judgment requiring Lang to only pay $247.31 as interest on late payments.2
    II. Summary Judgment
    A. Standard of Review
    Our standard of review for a grant of summary judgment is the same as that used in
    the trial court: summary judgment is appropriate only where the evidence shows that there is
    no genuine issue of material fact, and the moving party is entitled to judgment as a matter of
    law. In re Bender, 
    844 N.E.2d 170
    , 176-77 (Ind. Ct. App. 2006), trans. denied. The moving
    party bears the burden of designating sufficient evidence to eliminate any genuine factual
    issues and, once the moving party has fulfilled this requirement, the burden shifts to the
    nonmoving party to come forth with contrary evidence. 
    Id. at 177
    . On appeal, we do not
    reweigh the evidence, but we liberally construe all designated evidentiary material in the light
    most favorable to the nonmoving party to determine whether there is a genuine issue of
    material fact for trial. 
    Id.
     The party that lost in the trial court has the burden to persuade the
    appellate court that the trial court erred. 
    Id.
     We are not limited to reviewing the trial court’s
    reasons for granting summary judgment as the judgment may be affirmed upon any theory
    supported by the designated materials. 
    Id.
    B. Parkway’s Claims One Through Three
    Parkway contends that the trial court erred when it granted Lang’s motion for
    summary judgment on claims one through three of Parkway’s complaint. We conclude that
    2
    Neither party contests the court’s calculation of interest owed.
    8
    any error in the grant of summary judgment was harmless. The trial court may not pick and
    choose at the summary judgment stage, and here it is at least possible that there were issues
    of material fact regarding claims one through three, which related to Lang’s initial surveying
    errors. Because there were issues of material fact relating to Lang’s possible breach of the
    Agreement, if the court had determined that Lang breached the Agreement such that Lang
    was not released from liability for the surveying errors, then the court may have needed to
    reach claims one through three. Therefore, summary judgment on claims one through three
    was in error. However, because of the trial court’s resolution of the remaining claim that
    went to trial (claim four), and our conclusion that the trial court’s judgment was proper and
    Lang—having met the dollar requirement in the Agreement—was released from liability for
    the original surveying errors, summary judgment as to claims one through three was
    harmless.
    Because of the nature of this case, claims one through three were subsumed into the
    judgment for claim four. According to the terms of the contract, Parkway bargained in the
    Agreement for a sum total dollar amount in cash and work, and received that total, and
    therefore Lang met its part of the contract and was released from suit regarding the initial
    survey errors. Lang is not liable for the original surveying errors and therefore claims one
    through three are moot.
    9
    III. Motion to Amend Complaint
    The decision whether to grant or deny a motion to amend is within the discretion of
    the trial court and may be reversed only upon a showing of abuse of discretion. Kelly v.
    Bennett, 
    792 N.E.2d 584
    , 586 (Ind. Ct. App. 2003), trans. denied.
    Parkway’s original complaint was filed in May 2009. In December 2009, Parkway
    filed a motion to amend, which was granted. The motion to amend which is at issue here was
    first filed in April 2012, nearly three years after the initial complaint was filed. Objections
    and further proposed amendments followed, and in August 2012 the trial court held a hearing
    on the motion to amend and then denied the motion. Two months later, the bench trial took
    place.
    Parkway’s argument does not focus on any abuse of discretion by the trial court, but
    instead reads as if the court had granted summary judgment on the additional claim. We
    conclude that the trial court here did not abuse its discretion in denying a motion to amend
    nearly three years after the initial complaint was filed.
    Conclusion
    Concluding that the judgment of the trial court is not clearly erroneous, that any error
    in granting summary judgment was harmless, and that the trial court did not abuse its
    discretion in denying a motion to amend the complaint, we affirm.
    Affirmed.
    FRIEDLANDER, J., and CRONE, J., concur.