moran-electric-service-inc-and-threaded-rod-company-inc-v ( 2014 )


Menu:
  •                                                 Apr 21 2014, 11:41 am
    FOR PUBLICATION
    ATTORNEYS FOR APPELLANT,              ATTORNEYS FOR APPELLEE,
    Threaded Rod Company, Inc.:           Indiana Department of Environmental
    Management:
    DAVID A. TEMPLE
    SEAN T. DEVENNEY                      GREGORY F. ZOELLER
    SCOTT P. FISHER                       Attorney General of Indiana
    Carmel, Indiana
    ANDREW R. FALK
    ATTORNEYS FOR APPELLANT,              TIMOTHY J. JUNK
    Moran Electric Company, Inc.:         Deputy Attorney General
    Indianapolis, Indiana
    GLENN D. BOWMAN
    NICHOLAS K. GAHL                      ATTORNEY FOR APPELLEE,
    MARC A. MENKVELD                      City of Indianapolis:
    Indianapolis, Indiana
    CAMERON GREGORY STARNES
    Office of Corporation Counsel
    Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    MORAN ELECTRIC SERVICE, INC., and     )
    THREADED ROD COMPANY, INC.,           )
    )
    Appellants-Proposed Intervenors, )
    )
    vs.                      )
    )
    COMMISSIONER, INDIANA DEPARTMENT OF )
    ENVIRONMENTAL MANAGEMENT,             )
    )
    Appellee-Plaintiff,              )
    CITY OF INDIANAPOLIS,                             )
    )
    Appellee-Intervenor,                        )   No. 49A02-1305-MI-432
    )
    ERTEL MANUFACTURING CORP.,                        )
    )
    Defendant.                                  )
    APPEAL FROM THE MARION SUPERIOR COURT
    The Honorable Michael D. Keele, Judge
    Cause No. 49D07-1002-MI-6915
    April 21, 2014
    OPINION - FOR PUBLICATION
    BARNES, Judge
    Case Summary
    Threaded Rod Company, Inc., (“Threaded Rod”) and Moran Electric Service,
    Inc., (“Moran”) (collectively, “Appellants”) appeal the trial court’s denial of their
    motions to intervene and motions for preliminary injunction in litigation between the
    Indiana Department of Environmental Management (“IDEM”), the City of Indianapolis
    (“the City”), and Ertel Manufacturing Corporation (“Ertel”). We reverse and remand.
    Issues
    Appellants raise two issues, which we restate as:
    I.     whether the trial court properly found that it did not
    have subject matter jurisdiction over Appellants’
    claims; and
    II.    whether the trial court properly denied Appellants’
    motions to intervene.
    2
    Facts
    Ertel and Appellants are the former or current owners of adjacent properties
    located in Indianapolis. The properties are contaminated with hazardous chemicals.
    There is some dispute as to whether the contaminants on the Appellants’ sites originated
    on those sites or flowed from the Ertel site. IDEM has demanded that the properties be
    remediated.
    In 2008, the City brought a civil action against Ertel to compel Ertel to reimburse
    the City for its clean-up costs. In 2009, the trial court entered summary judgment for the
    City and found that Ertel was liable to the City for cleanup costs.
    In 2010, IDEM brought a civil action against Ertel asserting claims under Indiana
    Code Chapter 13-25-4 and seeking a declaration that Ertel would be responsible to IDEM
    for past and future costs associated with the cleanup of the hazardous substances at or
    flowing from the site.    In July 2011, IDEM, the City, Ertel, and various insurance
    companies entered into an Administrative Agreed Order (“Administrative Order”) and a
    Settlement and Release Agreement (“Ertel Settlement Agreement”).
    The Administrative Order provided that the parties desired “to settle and
    compromise this matter without hearing or adjudication of any issue of fact and law . . . .”
    Appellants’ App. p. 147. One of the remedial goals of the Administrative Order was
    “reducing Contaminants of concern flowing off-site . . . .” 
    Id. at 155.
    IDEM estimated
    that it would cost $860,000 to bring “the Site conditions and any associated off-Site areas
    to [No Further Action] status.” 
    Id. 3 One
    purpose of the Ertel Settlement Agreement was “for IDEM to conduct and
    complete future Response Actions at or in connection with the Site and close the Site,
    including any off-Site areas of Contamination . . . .” 
    Id. at 151.
    IDEM’s remedial goals
    included in the Ertel Settlement Agreement were “reducing the on-site Contaminants of
    concern to industrial default RISC cleanup levels” and “reducing Contaminants of
    concern flowing off-site in the groundwater to at or below MCLs or to a site specific risk
    level . . . .” 
    Id. at 155.
    IDEM agreed to issue a No Further Action Letter (“NFA Letter”)
    to Ertel when the remedial goals were met. 
    Id. As part
    of the two agreements, the insurance companies paid $1,000,000 to IDEM.
    The funds were placed in two escrow accounts—the first escrow account of $140,000 to
    reimburse IDEM for its past costs and a second escrow account of $860,000 for IDEM’s
    future costs. With regard to the second escrow account, IDEM agreed not to use the
    “funds for any purpose other than for Response Actions at or in connection with the
    Site.” 
    Id. Any funds
    remaining after IDEM issued the NFA Letter would be surrendered
    to the City.
    In October 2011, the trial court presiding over both civil action approved the Ertel
    Settlement Agreement in IDEM’s civil action against Ertel and the City’s civil action
    against Ertel. The Administrative Order was attached to the Ertel Settlement Agreement
    as an exhibit. In November 2012, IDEM issued the NFA Letter regarding the Ertel site.
    At that time, $846,000 remained in the second escrow account.
    On January 29, 2013, Moran filed a petition with the Indiana Office of
    Environmental Adjudication (“OEA”) seeking administrative review of the NFA Letter.
    4
    Moran argued that, in issuing the NFA Letter regarding the Ertel site, IDEM disregarded
    off-site migration of the contaminants that had occurred and was continuing to occur. On
    February 28, 2013, Threaded Rod filed a petition to intervene in Moran’s objection to
    IDEM’s issuance of the NFA Letter.1
    In January 2013, Threaded Rod filed a petition to intervene in the civil action
    between IDEM and Ertel. Threaded Rod also filed a motion for a temporary restraining
    order, motion for preliminary injunction, a request for a hearing, and alternatively, a
    motion for clarification of the trial court’s October 2011 order. Threaded Rod argued
    that the contamination on the Ertel site had migrated to the Threaded Rod site, that the
    $846,000 was intended to be used to clean up the Ertel site and other sites impacted by
    the contamination on the Ertel site, and that the funds should be preserved to address
    concerns on the neighboring properties.                   According to Threaded Rod, IDEM had
    abdicated its responsibility to clean up contaminants emanating from the Ertel site in
    violation of the trial court’s October 2011 order. Moran filed a separate motion to
    intervene and joined in Threaded Rod’s other motions. The City also filed a petition to
    intervene, which the trial court granted.
    The trial court denied Appellants’ requests for a temporary restraining order.
    IDEM and the City then filed objections to Appellants’ remaining motions. IDEM
    argued that Appellants were not entitled to intervene in the action and that the trial court
    lacked subject matter jurisdiction because the exclusive jurisdiction to review IDEM’s
    actions rested with the administrative process pursuant to the Administrative Orders and
    1
    The current status of the OEA proceedings is not evident from the record provided to us.
    5
    Procedures Act (“AOPA”). The City argued that the motions to intervene were untimely
    and, alternatively, that Appellants were not entitled to intervene.
    On April 19, 2013, the trial court issued an order denying the requests to intervene
    and the requests for a preliminary injunction. The trial court found that it lacked subject
    matter jurisdiction to address Appellants’ arguments pursuant to Indiana Department of
    Environmental Management v. Raybestos Products, Co., 
    897 N.E.2d 469
    (Ind. 2008),
    corrected on reh’g by 
    903 N.E.2d 471
    (Ind. 2009), cert. denied. The trial court ordered
    IDEM to release the funds in the second escrow account to the City. 2 Appellants now
    appeal.
    Analysis
    I. Subject Matter Jurisdiction
    Appellants argue that the trial court erred when it determined that it did not have
    subject matter jurisdiction over their claims. Because the facts relevant to this issue are
    not in dispute, it is a pure question of law that we review de novo. Ramsey v. Moore,
    
    959 N.E.2d 246
    , 250 (Ind. 2012).
    Appellants argued to both the trial court and the OEA that IDEM erred by issuing
    the NFA Letter. The trial court concluded that the OEA had jurisdiction, but Appellants
    argue that the trial court had jurisdiction because the trial court approved the Ertel
    Settlement Agreement. In general, the carrying out of a settlement agreement should be
    2
    IDEM includes documents in its appendix that indicate the funds were transferred to the City on April
    26, 2013. However, there is no indication that those documents were presented to the trial court.
    Consequently, it was improper to include the documents in the appendix, and we will not consider them
    on appeal.
    6
    controlled in the court that approved it, and the breaching of a settlement by one of the
    parties is actionable. Indiana Dep’t of Envtl. Mgmt. v. NJK Farms, Inc., 
    921 N.E.2d 834
    ,
    842 (Ind. Ct. App. 2010), trans. denied. The trial court disagreed with Appellants,
    finding that it did not have subject matter jurisdiction and that Appellants failed to
    exhaust their administrative remedies.
    It is well-established that, if an administrative remedy is available, it must be
    pursued before a claimant is allowed access to the courts. Town Council of New
    Harmony v. Parker, 
    726 N.E.2d 1217
    , 1224 (Ind. 2000), amended on reh’g in part, 
    737 N.E.2d 719
    (Ind. 2000).         However, the failure to exhaust administrative remedies
    deprives the trial court of subject matter jurisdiction. 
    Id. The doctrine
    of primary
    jurisdiction is also relevant here. Our supreme court has noted that:
    The doctrine [of primary jurisdiction] comes into play when a
    claim is cognizable in a court but adjudication of the claim
    “requires the resolution of issues which, under a regulatory
    scheme, have been placed within the special competence of
    [an] administrative body; in such a case, the judicial process
    is suspended pending referral of such issues to the
    administrative body for its views.” United States v. Western
    Pacific R.R. Co., 
    352 U.S. 59
    , 64, 
    77 S. Ct. 161
    , 165, 
    1 L. Ed. 2d 126
    (1956).
    Austin Lakes Joint Venture v. Avon Utilities, Inc., 
    648 N.E.2d 641
    , 645 (Ind. 1995)
    (quoting Hansen v. Norfolk & Western Ry. Co., 
    689 F.2d 707
    , 710 (7th Cir. 1982)). “The
    doctrines of primary jurisdiction and exhaustion of remedies, therefore, are related but
    significantly different.” 
    Id. “The doctrine
    of primary jurisdiction is not, in our view, jurisdictional but
    prudential; the doctrine of exhaustion of remedies, on the other hand, is jurisdictional
    7
    and, where applicable, makes a Trial Rule 12(B)(1) motion for lack of jurisdiction over
    the subject matter appropriate.” 
    Id. Under the
    doctrine of primary jurisdiction, our
    supreme court has held that “[i]f at least one of the issues involved in the case is within
    the jurisdiction of the trial court, the entire case falls within its jurisdiction, even if one or
    more of the issues are clearly matters for exclusive administrative or regulatory agency
    determination.” 
    Id. at 646.
    “Where at least one of the issues or claims is a matter for
    judicial determination or resolution, the court is not ousted of subject matter jurisdiction
    by the presence in the case of one or more issues which arguably are within the
    jurisdiction of an administrative or regulatory agency.”          
    Id. In such
    a case, while
    retaining jurisdiction, the trial court should “refer an issue or some subset of issues in the
    case to the expert agency for its opinion or final decision.” 
    Id. The heart
    of the issue is whether the trial court properly ordered the remaining
    $846,000 in funds distributed to the City, which is dependent upon whether IDEM
    properly issued a NFA Letter regarding the Ertel property. In finding that it had no
    subject matter jurisdiction, the trial court relied on Raybestos and NJK Farms.                In
    Raybestos, IDEM sent Raybestos a “Special Notice of Potential Liability” regarding the
    cleanup of PCBs. 
    Raybestos, 897 N.E.2d at 471
    . IDEM and Raybestos entered into an
    administrative agreed order approved by IDEM’s commissioner regarding the cleanup.
    Pursuant to the agreed order, Raybestos prepared a risk assessment, which concluded that
    the PCB levels posed no human health risk, and IDEM approved the risk assessment.
    IDEM suggested that Raybestos perform a “hot spot” removal rather than clean the entire
    site. 
    Id. A successor
    IDEM commissioner disagreed, and IDEM determined that the risk
    8
    assessment had been approved in error. IDEM and Raybestos were unable to agree on a
    cleanup level, and Raybestos filed a petition for administrative review with the OEA.
    The OEA concluded that Raybestos had waived its right to seek review of IDEM’s
    actions, but on judicial review, the trial court disagreed and ordered IDEM to reinstate its
    approval of the risk assessment. IDEM did not appeal that order.
    During this time, IDEM also encouraged the EPA to require a more complete
    cleanup, and the EPA issued an order requiring a cleanup of the site that was substantially
    more expensive than the “hot spot” removal. 
    Id. at 472.
    Raybestos then filed a civil
    complaint claiming that IDEM had breached its contract, i.e., the agreed order.
    Raybestos sought damages from IDEM for the more expensive cleanup and future
    expenses. The trial court found that IDEM’s communications with EPA had breached the
    agreed order, and the trial court ordered IDEM to pay more than $16,000,000 in damages.
    On appeal, our supreme court noted that the AOPA “establishes the exclusive
    means for judicial review of an agency action.” 
    Id. at 474
    (citing Ind. Code § 4-21.5-5-
    1). Although several agencies and agency actions are exempt from the AOPA, neither
    IDEM nor the agreed order is among them. 
    Id. (citing I.C.
    §§ 4-21.5-2-4, -5). The court
    found that IDEM was “plainly” an agency and that the agreed order and the
    communications with the EPA were agency actions. 
    Id. Consequently, our
    supreme
    court concluded that the exclusive means for review of the agency’s actions was by a
    petition for review to the OEA.3 The court remanded to the trial court with instructions to
    3
    The court also concluded that the alleged breach of the agreed order did not support a judgment for
    money damages and that IDEM could properly communicate with the EPA.
    9
    vacate the trial court’s judgments in favor of Raybestos and dismiss the complaint for
    lack of subject matter jurisdiction.
    Similarly, in NJK Farms, after NJK Farms filed a petition for judicial review
    regarding a landfill permit application, IDEM and NJK Farms entered into a settlement
    agreement filed with the trial court, and the trial court action was stayed pending
    completion of certain provisions of the settlement agreement. Under the agreement, NJK
    Farms was allowed to submit a complete permit application. After NJK Farms submitted
    its application and during the public comment period, the legislature passed a new statute
    applicable to landfills and the county where the proposed landfill was located passed
    comprehensive zoning regulations, which included regulations for landfills. IDEM then
    informed NJK Farms that it would have to submit a new application to comply with those
    requirements. Instead, NJK Farms filed a motion with the trial court alleging that IDEM
    had breached the settlement agreement.            IDEM then denied the existing permit
    application, and NJK Farms filed a petition for review with the OEA. The trial court
    found that it had exclusive jurisdiction of the claims based on its control of the settlement
    agreement and advised the OEA of its decision. The trial court also found that IDEM had
    breached the settlement agreement, set the matter for a trial on damages, and certified the
    order for interlocutory appeal.
    On appeal, we noted that, generally, the “carryout out of a settlement agreement
    should be controlled in the court that approved it.” NJK 
    Farms, 921 N.E.2d at 842
    .
    However, we also noted that “a settlement agreement that must be filed with and
    approved by a regulatory agency ‘loses its status as a strictly private contract and takes on
    10
    a public interest gloss.’” 
    Id. (quoting Citizens
    Action Coalition of Ind. v. PSI Energy,
    664 N.E.2d 401,406 (Ind. Ct. App. 1996)).
    We concluded that IDEM was an agency subject to AOPA and that IDEM’s
    actions regarding the settlement agreement were “agency actions” under AOPA. 
    Id. at 844;
    see I.C. § 4-21.5-2-4, -5. NJK Farms attempted to distinguish Raybestos because
    the settlement agreement arose out of a judicial, not administrative, proceeding.
    However, we did not find the distinction persuasive. We noted:
    Although the agreed order in Raybestos was entered
    into during the administrative proceeding rather than after the
    petition for judicial review was filed, we see no practical
    difference between the circumstances in Raybestos and the
    circumstances here. Under NJK’s interpretation, if the parties
    enter into an agreement to resolve issues during the
    administrative process, the AOPA would apply and damages
    could not be awarded for a breach of the agreement; but if the
    parties entered into an agreement to resolve issues after a
    petition for judicial review was filed, the AOPA would not
    apply and the agency could be liable for damages under
    Indiana Code Section 34-13-1-1. Such an interpretation
    would lead to illogical results contrary to the purpose of the
    AOPA.
    Finally, we also note that, under NJK’s interpretation,
    the trial court would have had exclusive jurisdiction over
    NJK’s entire permit application process as a result of the
    Settlement Agreement. However, under that interpretation,
    the trial court would have immediate jurisdiction to review
    IDEM’s denial of NJK’s permit on any basis, such as a denial
    based upon technical engineering requirements. The purpose
    of administrative review of agency decisions is to allow the
    agency “to correct its own errors, to afford the parties and the
    courts the benefit of [the agency’s] experience and expertise,
    and to compile a [factual] record which is adequate for
    judicial review.” Austin Lakes Joint Venture v. Avon Util.,
    Inc., 
    648 N.E.2d 641
    , 644 (Ind. 1995) (quoting Weinberger v.
    Salfi, 
    422 U.S. 749
    , 765, 
    95 S. Ct. 2457
    , 2467, 
    45 L. Ed. 2d 11
                  522 (1975)). Clearly, it is better for such issues to be
    presented in the typical administrative review process prior to
    consideration by the trial court. The administrative review
    process allows IDEM to correct its own mistakes and allows
    those with the requisite expertise a first look at the issues.
    NJK 
    Farms, 921 N.E.2d at 844
    (footnote omitted). We concluded that NJK Farms had
    failed to exhaust its administrative remedies and that the trial court did not have subject
    matter jurisdiction. 
    Id. at 845.
    Here, Appellants argue that the Ertel Settlement Agreement is not an agency
    action. However, it is not the Ertel Settlement Agreement that is at issue; rather, IDEM’s
    issuance of the NFA Letter and request that the trial court disburse the remaining
    $846,000 are at issue. AOPA provides that an “agency action” is any of the following:
    “(1) The whole or a part of an order; (2) The failure to issue an order; (3) An agency’s
    performance of, or failure to perform, any other duty, function, or activity under this
    article.” I.C. § 4-21.5-1-4.
    We begin our analysis by noting that the trial court approved the Ertel Settlement
    Agreement pursuant to the statutes governing the Hazardous Substances Response Trust
    Fund, Indiana Code Chapter 13-25-4. This code chapter establishes a trust fund to
    finance the prevention and cleanup of hazardous substance releases. The chapter allows
    the IDEM commissioner to “proceed in court” or “issue an administrative order” to
    “compel a responsible person to undertake a removal or remedial action with respect to a
    release or threatened release of a hazardous substance from a facility or site in Indiana.”
    I.C. § 13-25-4-9. The commissioner may also “proceed in the appropriate court to
    recover costs and damages for which a responsible person is liable to the state . . . .” I.C.
    12
    § 13-25-4-10. Finally, the commissioner may also “enter into an agreement with one (1)
    or more potentially responsible persons concerning removal and remedial action at a site
    in Indiana.” I.C. § 13-25-4-23(a). Such an agreement may be established: “(1) in an
    administrative order issued by the commissioner; or (2) by a consent decree entered in an
    appropriate court.” I.C. § 13-25-4-23(e). Under the above statutes, only the trial court
    can order the recovery of damages, but both the trial court and the agency can address
    remedial action.
    We first address the issuance of the NFA Letter. As in NJK Farms, Appellants’
    interpretation of AOPA would lead to inconsistent results and possible forum shopping.
    Appellants’ concern is whether IDEM properly remediated neighboring properties
    allegedly contaminated by Ertel. Under Indiana Code Chapter 13-25-4, IDEM can enter
    into both administrative orders or obtain trial court orders regarding remedial action at
    sites. Under Appellants’ interpretation, if an action concerning remediation was brought
    in the trial court, the trial court would enforce it; if an administrative order was entered
    into, the OEA would enforce it. This would lead to conflicting and inconsistent results.
    Moreover, here, both an administrative order and a trial court approval of the settlement
    were entered, and petitions to enforce the agreements were filed with both the OEA and
    the trial court. IDEM’s performance in remediating the properties involves complex
    environmental engineering concepts that are better suited to review in the administrative
    process. As in Raybestos and NJK Farms, we conclude that IDEM’s action in issuing the
    NFA Letter constitutes an agency action in the context of the AOPA. Consequently, the
    issue was required to be presented to the OEA.
    13
    We reach a different conclusion regarding the distribution of the remaining escrow
    funds. Under Indiana Code Section 13-25-4-10, only the trial court had the ability to
    control the recovery of damages. “An Indiana court obtains subject matter jurisdiction
    only through the Constitution or a statute.” Parkview Hosp., Inc. v. Geico Gen. Ins. Co.,
    
    977 N.E.2d 369
    , 372 (Ind. Ct. App. 2012), trans. denied. The trial court obtained
    jurisdiction over the funds pursuant to statutory authority. Consequently, we conclude
    that Raybestos and NJK Farms are distinguishable here with respect to the distribution of
    the remaining escrow funds.
    This case is similar to Fratus v. Marion Community Schools Board of Trustees,
    
    749 N.E.2d 40
    (Ind. 2001).       There, retiring teachers filed a complaint against the
    teachers’ union, alleging that it had breached its duty of fair representation, and the
    school board, alleging that it had breached its contract with the teachers. Our supreme
    court determined that the teachers’ claim against the union was a matter for “exclusive”
    determination by the Indiana Education Employment Relations Board (“IEERB”).
    
    Fratus, 749 N.E.2d at 45-46
    . However, the trial court had jurisdiction over the teachers’
    claim against the school board. Our supreme court invoked the doctrine of primary
    jurisdiction and held that, “although the trial court must refer to the IEERB that portion of
    [t]eachers’ complaint asserting claims against the [u]nion, the trial court nonetheless
    retains jurisdiction over the entire case until the IEERB reaches a final decision.
    Thereafter the trial court may address all claims properly before it.” 
    Id. at 46.
    Thus, the
    trial court was required to “suspend any action on the merits until the IEERB renders a
    final decision on [t]eachers’ claim against the [u]nion.” 
    Id. at 47.
    14
    Here, pursuant to the doctrine of primary jurisdiction, because the trial court has
    jurisdiction over one issue in the case and the OEA has jurisdiction over a second, related
    issue, the trial court should retain jurisdiction over the entire case until the OEA reaches a
    final decision on Appellants’ petitions. At that point, the trial court may make a decision
    regarding the disbursement of the remaining escrowed funds. We conclude that the trial
    court erred when it determined that it did not have subject matter jurisdiction.
    II. Intervention
    Having concluded that the trial court had subject matter jurisdiction, we address
    Appellants’ argument that the trial court erred by denying their petitions to intervene.
    The grant or denial of a petition to intervene is within the discretion of the trial court and
    is reviewed for an abuse of that discretion. Granite State Ins. Co. v. Lodholtz, 
    981 N.E.2d 563
    , 566 (Ind. Ct. App. 2012), trans. denied. An abuse of discretion occurs when
    the trial court’s decision is clearly against the logic and effect of the facts and
    circumstances before the court or the reasonable and probable inferences to be drawn
    therefrom. 
    Id. Indiana Trial
    Rule 24 governs intervention as of right and provides, in part:
    Upon timely motion anyone shall be permitted to intervene in
    an action:
    *****
    (2) when the applicant claims an interest relating to a
    property, fund or transaction which is the subject of the action
    and he is so situated that the disposition of the action may as a
    practical matter impair or impede his ability to protect his
    interest in the property, fund or transaction, unless the
    15
    applicant’s interest is adequately represented by existing
    parties.
    Ind. Trial Rule 24(A).      Indiana cases addressing Indiana Trial Rule 24(A)(2) have
    traditionally adopted the three-part test followed by the Federal courts in their
    interpretation of its counterpart in the Federal Rules of Civil Procedure. Granite 
    State, 981 N.E.2d at 566
    . This test requires that intervenors show: (1) an interest in the subject
    of the action; (2) disposition of the action may as a practical matter impede the protection
    of that interest; and (3) representation of the interest by existing parties is inadequate. 
    Id. Whether a
    particular factual situation satisfies this three-part test is within the discretion
    of the trial court. 
    Id. The first
    element of the test is whether Appellants have “an interest” in the subject
    of the actions between Ertel, IDEM, and the City. IDEM and the City seem to argue that
    Appellants have no interest here because the Ertel Settlement Agreement and
    Administrative Order provide that there are no third-party beneficiaries to the
    agreements. However, IDEM and the City cite no relevant authority for the proposition
    that Appellants must be third-party beneficiaries to the agreements to have an interest in
    the subject of the action. Rather, our courts have required that a proposed intervenor
    claim “an immediate and direct interest in the proceedings.” In re Paternity of E.M., 
    654 N.E.2d 890
    , 893 (Ind. Ct. App. 1995).
    Appellants are adjacent property owners to the Ertel property, and they allege that
    their properties were contaminated by Ertel. Clearly such contamination could affect the
    value of their properties in many ways. In both the Ertel Settlement Agreement and the
    16
    Administrative Order, IDEM agreed to conduct remediation of the Ertel contaminants
    that flowed off-site, which would presumably include Appellants’ properties. However,
    IDEM issued a NFA Letter without, according to Appellants, addressing the off-site
    contaminants. As such, we conclude that Appellants had an immediate and direct interest
    in the proceedings. See, e.g., In re Remonstrance Appealing Ordinance Nos. 98-004 98-
    005, 98-006, 98-007 & 98-008, of Town of Lizton, 
    737 N.E.2d 767
    , 769 (Ind. Ct. App.
    2000) (holding that landowners had an immediate and direct interest in remonstrators’
    litigation where the landowners’ property was annexed by the town); Heritage House of
    Salem, Inc. v. Bailey, 
    652 N.E.2d 69
    , 74 (Ind. Ct. App. 1995) (holding that nursing home
    owners had “an interest in protecting their remaining non-certified beds from becoming
    Medicaid certified and the litigation regarding the validity of the CON Program directly
    affected that interest”), trans. denied.
    The second element is whether the “disposition of the action may as a practical
    matter impede the protection” of Appellants’ interest. T.R. 24(A). IDEM issued the
    NFA Letter and requested that the trial court approve distribution of the remaining
    $846,000 pursuant to the Ertel Settlement Agreement and Administrative Order. As
    Appellants point out, if the escrowed funds “are distributed to the City without being
    used for their intended and ordered purpose,” Appellants “may be prevented from
    recapturing those funds to clean up Ertel’s contamination that is present on and below
    Threaded Rod’s property and beyond.” Appellants’ Brief p. 19. Thus, the distribution of
    the remaining funds, which were to be used to remediate contaminants, including
    contaminants that flowed off-site, would impede the protection of Appellants’ properties.
    17
    The final element is whether “representation of the interest by existing parties is
    inadequate.” T.R. 24(A). The current parties of the two civil actions are IDEM, the City,
    Ertel, and various insurance companies. Ertel, having been released from liability, has no
    incentive to represent Appellants’ interests. IDEM’s and the City’s interests in issuing
    the NFA Letter and distributing the remaining escrowed funds to the City also appear to
    conflict with Appellants’ interests in using the remaining escrowed funds to remediate
    Appellants’ properties. Consequently, we conclude that the representation of Appellants’
    interests by the existing parties is inadequate. In sum, we conclude that the trial court
    abused its discretion by denying Appellants’ motions to intervene.
    Conclusion
    The trial court erred when it determined that it did not have subject matter
    jurisdiction. However, under the doctrine of primary jurisdiction, this action should be
    stayed until the administrative action is final. We also conclude that the trial court erred
    by denying Appellants’ motions to intervene. We reverse and remand for proceedings
    consistent with this opinion.
    Reversed and remanded.
    ROBB, J., and BROWN, J., concur.
    18