Carmel Lofts LLC and Keystone Construction Corp. v. Elbrecht Investments, LLC ( 2012 )


Menu:
  •  Pursuant to Ind.Appellate Rule 65(D), this
    Memorandum Decision shall not be
    FILED
    regarded as precedent or cited before any                 Nov 20 2012, 8:52 am
    court except for the purpose of establishing
    the defense of res judicata, collateral                          CLERK
    of the supreme court,
    estoppel, or the law of the case.                              court of appeals and
    tax court
    ATTORNEYS FOR APPELLANTS:                         ATTORNEYS FOR APPELLEE:
    LAURA S. REED                                     GENE R. LEEUW
    KEVIN N. THARP                                    JOHN M. MEAD
    Riley Bennett & Egloff, LLP                       Leeuw Oberlies & Campbell, P.C.
    Indianapolis, Indiana                             Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    CARMEL LOFTS LLC and                              )
    KEYSTONE CONSTRUCTION CORP.,                      )
    )
    Appellants-Plaintiffs,                     )
    )
    vs.                                )    No. 29A05-1205-PL-266
    )
    ELBRECHT INVESTMENTS, LLC,                        )
    )
    Appellee-Defendant.                        )
    )
    APPEAL FROM THE HAMILTON SUPERIOR COURT
    The Honorable William J. Hughes, Judge
    The Honorable William P. Greenaway, Magistrate
    Cause No. 29D03-1101-PL-546
    November 20, 2012
    MEMORANDUM DECISION - NOT FOR PUBLICATION
    VAIDIK, Judge
    Case Summary
    Carmel Lofts LLC and Keystone Construction Corp. appeal the trial court’s grant
    of summary judgment to Elbrecht Investments, LLC. Concluding that there is no genuine
    issue of material fact that Keystone did not give Elbrecht proper notice pursuant to the
    parties’ subcontract to deduct a reasonable cost from Elbrecht’s payments for an alleged
    default or neglect in its work and that the amount of Elbrecht’s mechanic’s lien against
    Carmel Lofts is for the full value of its retainage, we affirm the trial court.
    Facts and Procedural History
    Carmel Lofts is the owner of a mixed-use real estate development at 110 West
    Main Street in Carmel known as the Carmel Arts District Lofts & Shoppes (“the
    project”). Keystone, a related entity, was the general contractor for the project, which
    consisted of an underground parking garage, retail space on the first floor, and four floors
    of apartments and lofts.
    On June 15, 2009, Keystone and Elbrecht entered into a Standard Form of
    Agreement Between Contractor and Subcontractor (“the Subcontract”), in which Elbrecht
    agreed to serve as a concrete subcontractor for the project. Section 3.4 of the Subcontract
    placed the following obligations on Keystone before it could deduct from sums owed to
    Elbrecht:
    If the Subcontractor defaults or neglects to carry out the Work in
    accordance with this Agreement and fails within three working days after
    receipt of written notice from the Contractor to commence and continue
    correction of such default or neglect with diligence and promptness, the
    Contractor may, by appropriate Modification, and without prejudice to any
    other remedy the Contractor may have, make good such deficiencies and
    may deduct the reasonable cost thereof from the payments then or thereafter
    2
    due the Subcontractor including any administrative or legal fees incurred by
    the Contractor.
    Appellant’s App. p. 75.
    Pursuant to the Subcontract and all change orders, the total amount due was
    $2,017,835.40.      Elbrecht began work under the Subcontract and submitted pay
    applications to Keystone totaling $2,009,835.40. Keystone paid 90% of that amount and
    held back 10%, or $200,983.54, in retainage as provided for in the Subcontract.
    On December 13, 2010, Elbrecht filed a notice of intention to hold a mechanic’s
    lien against Carmel Lofts’ real estate in the amount of $200,983.54 in order to secure
    payment of the retainage.
    Carmel Lofts filed a complaint against Elbrecht in January 2011. Carmel Lofts
    alleged that because Elbrecht had not fully performed the Subcontract (Elbrecht allegedly
    still needed to pour concrete for a staircase and a pool deck), Elbrecht’s mechanic’s lien
    slandered Carmel Lofts’ title to the real estate. Pursuant to Indiana Code section 32-28-
    3-11, which allows substitution of a surety in place of a mechanic’s lien, see Bailey v.
    Holliday, 
    806 N.E.2d 6
    , 10 (Ind. Ct. App. 2004), the trial court released the mechanic’s
    lien, and Carmel Lofts posted a surety bond in the amount of $225,000. Appellant’s App.
    p. 59.
    In February 2011, Elbrecht filed a counterclaim against Carmel Lofts and
    Keystone for breach of the Subcontract, foreclosure of its mechanic’s lien (by proceeding
    against the bond instead of the real estate), and unjust enrichment.
    Although Elbrecht had requested a “punch list” for the project in December 2010,
    it was not until May 6, 2011, that Keystone presented Elbrecht with a punch list of items
    3
    that needed to be corrected. Id. at 217-18. The twenty-four-item punch list was created
    by the project architect, CSO Architects, and was entitled “Field Observation.” Elbrecht
    worked on the punch-list items in May and June 2011. Elbrecht’s project manager, Jason
    Kiser, then met with Keystone’s project director, Bob Crowder, at the project site on July
    5, 2011, to discuss the punch list. Although the parties dispute what was discussed at the
    meeting, it is undisputed that following the meeting, Crowder thought that “it was
    pointless for Keystone to ask Elbrecht to return to fix deficiencies in [its] work, or to give
    notice to Elbrecht that Keystone was hiring replacement contractors to perform
    Elbrecht’s work.” Id. at 302 (supplemental affidavit of Crowder). Thereafter, Keystone
    supplemented Elbrecht’s work to address some of the alleged deficiencies.
    In late November 2011, CSO Architects and Crowder performed a walk through at
    the project site, and CSO Architects, with Crowder’s input, issued a revised punch list.
    Elbrecht was not notified of or invited to participate in this walk through.
    Also in November 2011, Elbrecht moved for summary judgment. Carmel Lofts
    and Keystone filed a cross-motion for summary judgment. Following a hearing, in May
    2012, the trial court entered summary judgment in favor of Elbrecht. Specifically, the
    trial court found:
    6. Keystone presented Elbrecht with a punch list dated May 6, 2011.
    Elbrecht worked on the items listed on the punch list in May and June,
    2011, and met with Keystone’s project director, Bob Crowder, on July 5,
    2011.
    7. Keystone did not give the written notice required by the Subcontract
    Agreement following the July 5, 2011, meeting that it intended to
    commence correction of any claimed default or neglect on the part of
    Elbrecht.
    4
    Id. at 7. Accordingly, the court said that Elbrecht was entitled to recover from Keystone
    the sum of $200,983.54 plus prejudgment interest of $11,100.60. Finding that Elbrecht’s
    notice of intention to hold a mechanic’s lien “was timely recorded and create[d] a valid,
    enforceable lien against the property,” the court concluded that Elbrecht was “entitled to
    judgment in rem against Carmel Lofts and foreclosure of its mechanic’s lien against the
    property in the sum of $200,983.54,” plus prejudgment interest of $11,100.60, post-
    judgment interest, and attorney’s fees of $23,129.30. Id. at 7, 10. The court released the
    mechanic’s lien bond with Hudson Insurance Company. Id. at 10. The court denied
    Carmel Lofts and Keystone’s cross-motion for summary judgment.
    Carmel Lofts and Keystone obtained a stay of execution of the final judgment
    pending their appeal by posting a $265,000 letter of credit. Id. at 327.
    Discussion and Decision
    Carmel Lofts and Keystone argue that the trial court erred in entering summary
    judgment in favor of Elbrecht and asks us to remand the case for trial. In reviewing an
    appeal of a motion-for-summary-judgment ruling, we apply the same standard applicable
    to the trial court. Presbytery of Ohio Valley, Inc. v. OPC, Inc., 
    973 N.E.2d 1099
    , 1110
    (Ind. 2012), reh’g denied.     Summary judgment is appropriate where the designated
    evidence “shows that there is no genuine issue as to any material fact and that the moving
    party is entitled to a judgment as a matter of law.” Ind. Trial Rule 56(C). Review is
    limited to those facts designated to the trial court, T.R. 56(H), and “[a]ll facts and
    reasonable inferences drawn from those facts are construed in favor of the non-moving
    party.” Presbytery of Ohio Valley, 973 N.E.2d at 1110 (quotation omitted). The fact that
    5
    each party sought summary judgment does not alter our analysis.           Id.   Rather, we
    consider each motion separately construing the facts most favorably to the non-moving
    party in each instance. Id.
    I. Notice under the Subcontract
    Carmel Lofts and Keystone first argue that the trial court erred in entering
    summary judgment for Elbrecht because the punch list was sufficient notice to Elbrecht
    pursuant to Section 3.4 of the Subcontract. See Appellant’s Br. p. 14 (“In concluding that
    Section 3.4 required that Keystone give Elbrecht a second notice after the Punchlist, the
    trial court misinterpreted Section 3.4.”). This issue requires us to examine the provisions
    of the Subcontract.
    The interpretation of contract provisions is a question of law. Niccum v. Niccum,
    
    734 N.E.2d 637
    , 639 (Ind. Ct. App. 2000). Unless contract terms are ambiguous, they are
    given their plain and ordinary meaning. 
    Id.
     Controversy between the parties regarding
    interpretation of contract terms does not necessitate ambiguity in the contract. 
    Id.
     When
    provisions of a contract are clear and unambiguous, they are conclusive and we will not
    construe the contract or look at extrinsic evidence; rather, we will merely apply the
    contractual provisions. 
    Id.
     Our paramount goal in interpreting a contract is to ascertain
    and effectuate the intent of the parties. Bernel v. Bernel, 
    930 N.E.2d 673
    , 682 (Ind. Ct.
    App. 2010), trans. denied.
    Section 3.4 of the Subcontract provides:
    If the Subcontractor defaults or neglects to carry out the Work in
    accordance with this Agreement and fails within three working days after
    receipt of written notice from the Contractor to commence and continue
    correction of such default or neglect with diligence and promptness, the
    6
    Contractor may, by appropriate Modification, and without prejudice to any
    other remedy the Contractor may have, make good such deficiencies and
    may deduct the reasonable cost thereof from the payments then or thereafter
    due the Subcontractor including any administrative or legal fees incurred by
    the Contractor.
    Appellant’s App. p. 75. The plain language of the Subcontract requires Keystone to take
    three actions in the event that Elbrecht defaults or neglects to carry out the work in
    accordance with the parties’ agreement: (1) issue written notice to Elbrecht to commence
    and continue correction of any default or neglect with diligence and promptness 1; (2) give
    Elbrecht three working days after receipt of written notice to make corrections; and (3) if
    Elbrecht fails to make the corrections, then issue the “appropriate Modification” to the
    contract, all before it can deduct the reasonable cost of correcting the deficiencies from
    Elbrecht’s payments. The trial court found that the Keystone failed to comply with the
    first step. We agree.
    The evidence shows that CSO Architects visited the project site on May 6, 2011,
    for an observation and then created a document entitled “Field Observation” that
    contained twenty-four items that needed to be corrected.2 Id. at 217-18. Notably, the
    document is not addressed to Elbrecht, and “Elbrecht” is not even named in the
    document. CSO Architects sent the document to Keystone on May 6, and Keystone
    emailed it to Elbrecht that same day. Id. at 299.
    1
    Contrary to Carmel Lofts and Keystone’s argument in their reply brief, see Appellant’s Reply
    Br. p. 5 n. 2, we find that the written notice must inform Elbrecht to “commence and continue correction”
    of any alleged “default or neglect with diligence and promptness,” Appellant’s App. p. 75, and further
    inform Elbrecht that if Elbrecht does not correct the deficiencies within three working days, then
    Keystone may fix the deficiencies and deduct the reasonable cost from Elbrecht’s payments.
    2
    For example, the first item states: “On the first floor, east end there is a cold joint at the far
    southeast corner that extends approximately 8’ into the building. There are many areas of this cold joint
    that need to be ground flat between the two pours.” Appellant’s App. p. 217.
    7
    While Keystone may have used the punch list as a tool to inform Elbrecht to fix
    certain items at the project site, the punch list does not satisfy Keystone’s obligation to
    provide the notice required by Section 3.4 of the Subcontract that would then allow
    Keystone to modify the Subcontract, have someone else fix the deficiencies, and then
    deduct the reasonable cost from Elbrecht’s payments. Notably, the punch list does not
    tell Elbrecht (1) “to commence and continue correction” of its “default or neglect with
    diligence and promptness” and (2) that it has “three working days after receipt of written
    notice” in which to correct the deficiencies. That is, the punch list contains no directive
    from the general contractor, Keystone; rather, it is a document prepared by the architect,
    CSO Architects, with whom Elbrecht has no contractual relationship. The punch list also
    gives no notice to Elbrecht that Keystone may correct the deficiencies and then deduct
    the reasonable cost from Elbrecht’s payments. Despite Carmel Lofts and Keystone’s
    argument on appeal that the Subcontract did not require Keystone to give a second notice
    to Elbrecht, we find that Keystone did not give any notice to Elbrecht pursuant to Section
    3.4 of the Subcontract that would justify its attempts to deduct from Elbrecht’s retainage.
    The effect of Keystone’s failure to give proper notice to Elbrecht pursuant to Section 3.4
    of the Subcontract is that Keystone had no objections to Elbrecht’s work and therefore
    Keystone could not deduct from Elbrecht’s retainage. The trial court properly entered
    summary judgment in favor of Elbrecht on the issue of notice.
    In light of this holding, we do not need to address any of Carmel Lofts and
    Keystone’s arguments regarding the costs Keystone incurred to fix the alleged
    8
    deficiencies, including whether certain portions of Crowder’s affidavit are admissible to
    help establish these costs.3
    II. Mechanic’s Lien
    Carmel Lofts and Keystone next argue that the trial court erred in entering
    summary judgment for Elbrecht, a subcontractor, on its mechanic’s lien claim against
    Carmel Lofts because the reasonable value of Elbrecht’s work is far less than the
    $200,983.54 it claimed.
    “The historical origin and purpose of mechanic’s lien statutes was to make a
    property owner an involuntary guarantor of payments for the reasonable value of
    improvements made to real estate by the physical labor or materials furnished by laborers
    or materialmen.” Premier Invs. v. Suites of Am., Inc., 
    644 N.E.2d 124
    , 130 (Ind. 1994).
    The purpose of a mechanic’s lien is to prevent the inequity of a property owner enjoying
    the benefits of the labor and materials furnished by others without recompense. 
    Id.
    Where a subcontractor of a general contractor seeks a lien on property where he has
    furnished labor and materials, a contract exists between the contractor and subcontractor,
    3
    Carmel Lofts and Keystone make a separate argument that Elbrecht is not entitled to “final
    payment” pursuant to Section 12.1 of the Subcontract, which provides:
    Final payment, constituting the entire unpaid balance of the Subcontract Sum, shall be
    made by the Contractor to the Subcontractor when the Subcontractor’s Work is fully
    performed in accordance with the requirements of the Subcontract Documents, the
    Architect has issued a certificate for payment covering the Subcontractor’s completed
    Work and the Contractor has received payment from the Owner in accordance with the
    terms of the Prime Contract.
    Appellant’s App. p. 29. But Keystone cannot use this provision of the Subcontract to excuse its duty to
    give proper notice to Elbrecht to correct its deficiencies – and thus fully perform – under another
    provision of the Subcontract.
    As for the parties’ dispute about how much should be deducted for the pool deck that Elbrecht
    never completed, we find that $8000 was properly deducted because Elbrecht included $8200 in its
    original bid to Keystone.
    9
    but not between the subcontractor and the property owner. Korellis Roofing, Inc. v.
    Stolman, 
    645 N.E.2d 29
    , 31 (Ind. Ct. App. 1995). In such a circumstance, while the
    contract price may be prima facie evidence of reasonable value, the lien is for the
    reasonable value of the work and material and not for the price as fixed by contract. 
    Id.
    Here, although the property owner, Carmel Lofts, and general contractor,
    Keystone Construction Corp., are not the same parties, the evidence shows, and the trial
    court found, that the entities are related. Their point of connection is Ersal Ozdemir.
    Ozdemir is the sole member of Keystone Group, LLC, a holding company which is the
    sole member of Carmel Lofts. Appellant’s App. p. 132. Keystone Construction Corp.
    has three shareholders: Ozdemir (president) and two other individuals. 
    Id. at 132, 137
    .
    This means that Ozdemir essentially hired his own company as the general contractor for
    the project. Thus, because Carmel Lofts and Keystone are so closely related, the trial
    court could find that Carmel Lofts was bound by the terms of the contract between
    Keystone and Elbrecht regarding notice and ultimately price. Accordingly, the trial court
    properly entered summary judgment for Elbrecht on its mechanic’s lien claim against
    Carmel Lofts for the full amount of its retainage.4
    Affirmed.
    MATHIAS, J., and BARNES, J., concur.
    4
    Elbrecht has requested appellate attorney fees pursuant to Indiana Code section 32-28-3-14(a),
    which provides that “in an action to enforce a lien under this chapter, a plaintiff or lienholder who
    recovers a judgment in any sum is entitled to recover reasonable attorney’s fees. The court shall enter the
    attorney’s fees as a part of the judgment.” As we have previously explained, where a statute authorizes
    reasonable attorney fees, such fees include appellate attorney fees. Hayes v. Chapman, 
    894 N.E.2d 1047
    ,
    1055 (Ind. Ct. App. 2008), trans. denied. However, the proper way to raise this issue is to bring this
    request directly to the trial court. 
    Id.
    10
    

Document Info

Docket Number: 29A05-1205-PL-266

Filed Date: 11/20/2012

Precedential Status: Non-Precedential

Modified Date: 10/30/2014