Continental Electric Co., Inc. v. Gary Community School Corporation ( 2012 )


Menu:
  •  Pursuant to Ind.Appellate Rule 65(D), this
    Memorandum Decision shall not be
    regarded as precedent or cited before any
    court except for the purpose of establishing
    the defense of res judicata, collateral
    estoppel, or the law of the case.
    ATTORNEY FOR APPELLANT:                            ATTORNEY FOR APPELLEE:
    MICHAEL J. RAPPA                                   TRACY A. COLEMAN
    Johnson, Rappa & Ivancevich, LLC                   Robert L. Lewis & Associates
    Merrillville, Indiana                              Gary, Indiana
    FILED
    Feb 06 2012, 9:11 am
    IN THE                                                CLERK
    of the supreme court,
    COURT OF APPEALS OF INDIANA                                   court of appeals and
    tax court
    CONTINENTAL ELECTRIC CO., INC.,                    )
    )
    Appellant-Plaintiff,                        )
    )
    vs.                                 )       No. 45A05-1105-PL-247
    )
    GARY COMMUNITY SCHOOL                              )
    CORPORATION,                                       )
    )
    Appellee-Defendant.                         )
    )
    INTERLOCUTORY APPEAL FROM THE LAKE SUPERIOR COURT
    The Honorable William E. Davis, Judge
    Cause No. 45D05-1103-PL-20
    February 6, 2012
    MEMORANDUM DECISION - NOT FOR PUBLICATION
    VAIDIK, Judge
    Case Summary
    Continental Electric appeals the trial court’s denial of a preliminary injunction
    after it claims Gary Community School Corporation (GCSC) improperly awarded a
    public works contract to Great Lakes Electrical Maintenance, Inc. (GLEM). Finding that
    the trial court did not abuse its discretion in holding that Continental Electric failed to
    show a prima facie case, irreparable harm, or that the public interest would be better
    served by the granting of the preliminary injunction, we affirm.
    Facts and Procedural History
    The GCSC was commencing a construction project on Locke Elementary School
    and announced on January 25, 2011, that it would accept sealed bids for, among other
    things, an electrical contract. Continental Electric and GLEM both submitted bids for the
    project.   The bidding requirements for this project were set forth in the bidding
    documents and required a statement from a surety company that it would issue a
    performance bond and a payment bond within three days of being awarded the contract.
    However, the documents also explicitly stated that GCSC encouraged incremental
    bonding and that GCSC was free to waive any bidding formalities. Appellant’s App. p.
    36, 186.
    After reviewing the bids, GCSC awarded the contract to GLEM, the lowest bidder.
    GLEM did not provide a statement from a surety company, but instead provided GCSC
    with a certified check in the amount of $85,000 and a proposal that an incremental bond
    would be used. Continental Electric filed a Verified Complaint for Injunctive Relief,
    2
    claiming that GCSC had violated Indiana statute by awarding the contract to GLEM,
    whose bid was nonresponsive to the bidding requirements.
    On March 21, 2011, a hearing was held on Continental Electric’s motion for
    preliminary injunction. On March 28, 2011, GLEM obtained and filed a performance
    bond with the court. A telephonic conference was held and Continental Electric was
    given five days in which to respond to the filing of the performance bond. No such
    response was filed as of April 15, 2011. On April 18, 2011, the trial court denied
    Continental Electric’s motion for a preliminary injunction for failure to establish a prima
    facie case, show irreparable harm, and show that the public interest would be better
    served by granting the preliminary injunction.
    Continental Electric now appeals.
    Discussion and Decision
    The grant or denial of a request for a preliminary injunction rests within the sound
    discretion of the trial court, and our review is limited to whether there was a clear abuse
    of that discretion. Gleeson v. Preferred Sourcing, LLC, 
    883 N.E.2d 164
    , 171-72 (Ind. Ct.
    App. 2008) (citing Cent. Ind. Podiatry, P.C. v. Krueger, 
    882 N.E.2d 723
    , 727 (Ind.
    2008)). When determining whether to grant a preliminary injunction, the trial court is
    required to make special findings of fact and state its conclusions thereon. Id. at 172.
    When findings and conclusions thereon are made, we must determine if the trial court’s
    findings support the judgment. Id. We will reverse the trial court’s judgment only when
    it is clearly erroneous. Id. A judgment is clearly erroneous when a review of the record
    leaves us with a firm conviction that a mistake has been made. Id. We consider the
    3
    evidence only in the light most favorable to the judgment and construe findings together
    liberally in favor of the judgment. Id. Moreover, “[t]he power to issue a preliminary
    injunction should be used sparingly, and such relief should not be granted except in rare
    instances in which the law and facts are clearly within the moving party’s favor.” Id.
    (quotation omitted).
    To obtain a preliminary injunction, the moving party has the burden of showing by
    a preponderance of the evidence the following: (1) a reasonable likelihood of success at
    trial; (2) the remedies at law are inadequate; (3) the threatened injury to the movant
    outweighs the potential harm to the nonmoving party from the granting of an injunction;
    and (4) the public interest would not be disserved by granting the requested injunction.
    Id. (citing Krueger, 882 N.E.2d at 727). If the movant fails to prove any of these
    requirements, the trial court’s grant of an injunction is an abuse of discretion. Id. (citing
    Ind. Family & Soc. Servs. Admin. v. Walgreen Co., 
    769 N.E.2d 158
    , 161 (Ind. 2002)).
    Continental Electric contends that GLEM’s bid was nonresponsive to the bidding
    requirements and that the trial court therefore abused its discretion in denying the
    preliminary injunction by finding that Continental Electric failed to show a prima facie
    case, irreparable harm, or that the public interest would be better served by the granting
    of the preliminary injunction. Viewing the evidence in the light most favorable to the
    judgment, we disagree.
    Along with its bid, GLEM provided a certified check in the amount of $85,000.00
    and a proposal for incremental bonding rather than providing a statement from a surety
    company that it would issue a performance bond and a payment bond within three days
    4
    of being awarded the contract, as the bid book requested. Appellant’s App. p. 20, 31-32.
    Continental Electric argues that this makes the bid nonresponsive to GCSC’s bidding
    requirements. Indiana Code section 36-1-12-4 requires the awarding of public works
    projects to the lowest responsive and responsible bidder. However, in the front-end bid
    documents, it was explicitly stated that GCSC “promotes incremental bonding and other
    appropriate strategies designed to assist Gary businesses and to increase local
    employment opportunities,” id. at 36, and GCSC represented that it “reserve[d] the right
    to reject any and all bids and to waive any formalities in the bidding.” Id. at 186
    (emphasis added). Therefore, we find that it was not an abuse of the trial court’s
    discretion to find that this bid was responsive to the bid requirements.
    Additionally, at the preliminary injunction hearing, it was said that payment and
    performance bonds do not need to be acquired before work on the project begins and
    GLEM had yet to begin work. Tr. p. 35-36. Also, after the hearing, GLEM obtained and
    filed a performance bond with the court.         A telephone conference was held, and
    Continental Electric had five days in which to file a response to the filing of the
    performance bond, which they failed to do. Appellant’s App. p. 4.
    Construing these findings in favor of the judgment, we find that the trial court did
    not abuse its discretion in finding that GLEM’s bid was responsive to the bid request.
    Continental Electric failed to show that it had a prima facie case, had suffered irreparable
    harm, or that the public interest would be better served by the granting of the preliminary
    injunction. We therefore affirm.
    5
    Affirmed.
    ROBB, C.J., and NAJAM, J., concur.
    6
    

Document Info

Docket Number: 45A05-1105-PL-247

Filed Date: 2/6/2012

Precedential Status: Non-Precedential

Modified Date: 4/17/2021