NIPSCO Industrial Group, and, Indiana Office of Utility Consumer Counselor v. Northern Indiana Public Service Company , 2015 Ind. App. LEXIS 292 ( 2015 )


Menu:
  •                                                                 Apr 08 2015, 10:25 am
    ATTORNEYS FOR APPELLANT,                                   ATTORNEYS FOR APPELLEE,
    NIPSCO INDUSTRIAL GROUP                                    INDIANA UTILITY REGULATORY
    Todd A. Richardson                                         COMMISSION
    Bette J. Dodd                                              David Lee Steiner
    Jennifer W. Terry                                          Deputy Attorney General
    Joseph P. Rompala                                          Office of the Indiana Attorney General
    Lewis & Kappes, P.C.                                       Indianapolis, Indiana
    Indianapolis, Indiana
    Beth Krogel Roads
    ATTORNEYS FOR APPELLANT,                                   Andrew J. Wells
    INDIANA OFFICE OF UTILITY                                  Indiana Utility Regulatory Commission
    CONSUMER COUNSELOR                                         Indianapolis, Indiana
    A. David Stippler                                          ATTORNEYS FOR NORTHERN
    Randall C. Helman                                          INDIANA PUBLIC SERVICE
    Lorraine Hitz-Bradley                                      COMPANY
    Jeffrey Reed
    Indianapolis, Indiana                                      Brian J. Paul
    Kay E. Pashos
    ATTORNEYS FOR AMICUS CURIAE,                               Kelly S. Earls
    INDIANA ENERGY ASSOCIATION                                 Ice Miller, LLP
    Indianapolis, Indiana
    Wayne C. Turner
    Patrick Z. Ziepolt                                         Claudia J. Earls
    Bingham Greenebaum Doll, LLP                               Erin Casper Borissov
    Indianapolis, Indiana                                      NiSource Corporate Services – Legal
    Indianapolis, Indiana
    ATTORNEYS FOR NLMK, INDIANA,
    A DIVISION OF NLMK USA
    Richard E. Aikman, Jr.
    Anne E. Becker
    Lewis & Kappes, P.C.
    Indianapolis, Indiana
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015                   Page 1 of 31
    IN THE
    COURT OF APPEALS OF INDIANA
    NIPSCO Industrial Group, and,                              April 8, 2015
    Court of Appeals Cause No.
    Indiana Office of Utility                                  93A02-1403-EX-158
    Consumer Counselor,                                        Appeal from the Indiana Utility
    Regulatory Commission
    Appellants-Intervenor and Statutory                        Cause No. 44370 & 44371
    Party below,                                               The Honorable James D. Atterholt,
    Chairman; The Honorable Carolene
    R. Mays; The Honorable David E.
    Ziegner, Commissioners
    v.
    Northern Indiana Public Service
    Company, et al.,
    Appellees-Petitioner and Parties below.
    Barnes, Judge.
    Case Summary
    [1]   In this consolidated appeal, the Indiana Office of Utility Consumer Counselor
    (“OUCC”) and the NIPSCO Industrial Group (“Industrial Group”) appeal the
    decision of the Indiana Utility Regulatory Commission (“Commission”)
    regarding two petitions filed by Northern Indiana Public Service Company
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015                       Page 2 of 31
    (“NIPSCO”) to establish increased rates under a new statute, Indiana Code
    Chapter 8-1-39. We affirm in part, reverse in part, and remand.1
    Issues
    [2]   The Industrial Group raises three issues, which we consolidate and restate as:
    I.       whether the Commission erred by allowing
    NIPSCO to specifically identify the proposed
    projects for only the first year of the seven-year
    plan and by establishing a presumption that the
    proposed projects for years two through seven
    of the plan were eligible for special ratemaking
    treatment; and
    II.      whether the Commission erred by approving
    costs allegedly in excess of a statutory cap on
    aggregate increases.
    [3]   The OUCC raises two issues, which we restate as:
    III.     whether the Commission erred by allowing
    NIPSCO to continue rate recovery of retired
    equipment while also recovering for
    replacement assets; and
    IV.      whether the Commission erred by approving
    NIPSCO’s     proposed    rate   allocation
    methodology.
    1
    We held oral argument on this matter on February 26, 2015. We commend counsel for their presentations.
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015                         Page 3 of 31
    Facts
    [4]   NIPSCO is a public electric and gas utility that services over 457,000 customers
    in northern Indiana. The OUCC is the statutory representative of the public
    before the Commission. See 
    Ind. Code § 8-1-1-5
    (c). The Industrial Group is a
    group of some of NIPSCO’s largest industrial customers.
    [5]   Traditionally, a utility’s rates charged to customers are adjusted through
    periodic rate cases, which are expensive, time consuming, and sometimes result
    in large, sudden rate hikes for customers. NIPSCO’s last rate case was finalized
    in December 2011. There, the Commission issued an order in Cause No. 43969
    and approved a settlement regarding NIPSCO’s proposed general rate increase.
    See In Re Petition of NIPSCO to Modify its Rates, Cause No. 43969, 
    2011 WL 6837714
     (Ind. U.R.C. Dec. 21, 2011).
    [6]   Another way to set rates is through “tracker” proceedings, which allow smaller
    increases for specific projects and costs between general rate case proceedings.
    The General Assembly has authorized several trackers, including a fuel charge
    tracker, see 
    Ind. Code § 8-1-2-42
    (d), a tracker for qualified pollution control
    projects under construction, see 
    Ind. Code § 8-1-2-6
    .8, a tracker for federally
    mandated costs, see 
    Ind. Code § 8-1-8.4
    -7, and a tracker for clean energy
    projects, see 
    Ind. Code §§ 8-1-8.8
    -11 and 8-1-8.8-12. In 2013, the General
    Assembly enacted Indiana Code Chapter 8-1-39, which allows a utility to
    petition for a tracker for certain proposed new or replacement electric or gas
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015     Page 4 of 31
    transmission, distribution, or storage projects. The new statute is referred to as
    the “TDSIC” statute.
    [7]   In July 2013, NIPSCO filed two petitions with the Commission under the new
    TDSIC statute. In Cause No. 44370, NIPSCO sought approval of a seven-year
    plan pursuant to Indiana Code Section 8-1-39-10. The plan included over $1
    billion in improvements and replacements to NIPSCO’s transmission and
    distribution systems. In Cause No. 44371, NIPSCO sought approval of the rate
    increases associated with the seven-year plan. The two petitions were treated as
    companion cases. The parties prefiled evidentiary submissions, and an
    evidentiary hearing was held in November 2013.
    [8]   On February 17, 2014, the Commission issued its final orders. In Cause No.
    44370, the Commission substantially approved NIPSCO’s seven-year plan.
    However, the Commission found that NIPSCO had provided sufficient detail of
    the plan for only the first of the seven years. For years two through seven, the
    Commission established a “presumption of eligibility” and required NIPSCO to
    annually update the plan through an informal process. Industrial Group’s App.
    pp. 25-26.
    [9]   In Cause No. 44371, the Commission also substantially approved NIPSCO’s
    proposed rate increases. The Commission approved NIPSCO’s adjustments to
    the customer class revenue allocation factors based on firm/non-firm load and
    distribution/transmission considerations. The Commission rejected the
    OUCC’s argument that NIPSCO should be required to reduce its return and
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015    Page 5 of 31
    depreciation so that it was not recovering on both replaced assets and the new
    replacement assets. Finally, the Commission rejected the Industrial Group’s
    interpretation of the two-percent cap found in Indiana Code Section 8-1-39-14.
    [10]   The OUCC filed a petition to reconsider in Cause No. 44371. The OUCC
    argued that “the recoverable TDSIC costs should be adjusted to reflect the
    removal of any return and depreciation expenses embedded in base rates that
    are associated with original transmission and distribution investments that will
    be retired as a result of new TDSIC investments.” 
    Id. at 34
    . The OUCC also
    argued that “NIPSCO’s request to apply adjusted customer class allocation
    factors should be denied and they should be required to apply the customer
    class revenue allocators from the Commission’s Order in Cause No. 43969.”
    
    Id.
     The Commission did “not find statutory support for the netting of
    investment in determining the appropriate investment to be afforded cost
    recovery” and declined “to require NIPSCO to adjust TDSIC costs to reflect
    the removal of any return and depreciation expenses embedded in base rates
    that are associated with original transmission and distribution investments that
    will be retired as a result of new TDSIC investments.” 
    Id. at 34-35
    . As for the
    allocation factors, the Commission found that its original order addressed the
    issue adequately. Consequently, the Commission denied OUCC’s petition to
    reconsider.
    [11]   The OUCC appealed the Commission’s order in Cause No. 44371, and the
    Industrial Group appealed the Commission’s order in Cause No. 44370. We
    granted NIPSCO’s motion to consolidate the appeals. In addition to filing an
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015   Page 6 of 31
    appellant’s brief, the Industrial Group also filed an appellee’s brief addressing
    the rate allocation issue raised by the OUCC. The Commission and NIPSCO
    also filed appellee’s briefs. Finally, we granted the Indiana Energy Association
    permission to file an amicus curiae brief.
    Analysis
    [12]   The OUCC and the Industrial Group appeal the Commission’s order regarding
    NIPSCO’s TDSIC petitions. The General Assembly created the Commission
    primarily as a fact-finding body with the technical expertise to administer the
    regulatory scheme devised by the legislature. N. Indiana Pub. Serv. Co. v. U.S.
    Steel Corp., 
    907 N.E.2d 1012
    , 1015 (Ind. 2009); I.C. § 8-1-1-5. The
    Commission’s assignment is to ensure that public utilities provide constant,
    reliable, and efficient service to the citizens of Indiana. Id. The Commission
    only can exercise power conferred upon it by statute. Id. Its authority also
    “includes implicit powers necessary to effectuate the statutory regulatory
    scheme.” United States Gypsum, Inc. v. Indiana Gas Co., 
    735 N.E.2d 790
    , 795
    (Ind. 2000). Any doubts regarding the Commission’s statutory authority must
    be resolved against the existence of such authority. U.S. Steel Corp. v. N. Indiana
    Pub. Serv. Co., 
    951 N.E.2d 542
    , 550 (Ind. Ct. App. 2011), trans. denied.
    [13]   An order of the Commission is subject to appellate review to determine whether
    it is supported by specific findings of fact and by sufficient evidence, as well as
    to determine whether the order is contrary to law. United States Gypsum, 735
    N.E.2d at 795. On matters within its jurisdiction, the Commission enjoys wide
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015     Page 7 of 31
    discretion. Id. The Commission’s findings and decision will not be lightly
    overridden just because we might reach a contrary opinion on the same
    evidence. Id. We first review the entire record to determine whether there is
    substantial evidence to support the Commission’s findings of basic fact. U.S.
    Steel Corp., 
    951 N.E.2d at 551
    . Next, we review ultimate facts, or mixed
    questions of fact and law, for their reasonableness with the amount of deference
    owed depending on whether the issue falls or does not fall within the
    Commission’s expertise. 
    Id.
     Finally, legal propositions are reviewed for their
    correctness. 
    Id.
     More precisely, “an agency action is always subject to review
    as contrary to law, but this constitutionally preserved review is limited to
    whether the Commission stayed within its jurisdiction and conformed to the
    statutory standards and legal principles involved in producing its decision,
    ruling, or order.” 
    Id.
    [14]   Many of the issues here involve the interpretation of the new TDSIC statute.
    Generally, an agency’s reasonable interpretation of a statute it is charged with
    enforcing is entitled to great weight. 
    Id.
     In statutory construction, our primary
    goal is to ascertain and give effect to the intent of the legislature. 
    Id. at 552
    .
    The language of the statute itself is the best evidence of legislative intent, and
    we must give all words their plain and ordinary meaning unless otherwise
    indicated by statute. 
    Id.
     Furthermore, we presume that the legislature intended
    statutory language to be applied in a logical manner consistent with the statute’s
    underlying policies and goals. 
    Id.
     However, we will not interpret a statute that
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015       Page 8 of 31
    is clear and unambiguous on its face; rather, we will give such a statute its
    apparent and obvious meaning. 
    Id.
    I. Plan Sufficiency
    [15]   The Industrial Group argues that the Commission erred by allowing NIPSCO
    to specifically identify the proposed projects for only the first year of the seven-
    year plan. The Industrial Group also argues that the Commission erred by
    establishing a presumption that the proposed projects for years two through
    seven of the seven-year plan were eligible for special ratemaking treatment.
    [16]   Indiana Code Section 8-1-39-10(a) requires a utility’s TDSIC petition to contain
    a “seven (7) year plan for eligible transmission, distribution, and storage
    improvements.” The Commission’s order on the petition must include the
    following:
    (1)       A finding of the best estimate of the cost of the eligible
    improvements included in the plan.
    (2)       A determination whether public convenience and necessity
    require or will require the eligible improvements included in the
    plan.
    (3)       A determination whether the estimated costs of the eligible
    improvements included in the plan are justified by incremental
    benefits attributable to the plan.
    I.C. § 8-1-39-10(b). “If the commission determines that the public utility’s
    seven (7) year plan is reasonable, the commission shall approve the plan and
    designate the eligible transmission, distribution, and storage improvements
    included in the plan as eligible for TDSIC treatment.” Id.
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015            Page 9 of 31
    [17]   The Commission found that NIPSCO’s seven-year plan included “general
    categories of spending, separated primarily by function rather than specific
    projects in Years 2 through 7, with the specific projects for Year 1 better
    defined.” Industrial Group App. pp. 20-21. Despite the lack of specificity
    regarding the projects beyond the first year of the plan, the Commission
    approved the plan as follows:
    Based upon our review of the evidence of record, and the foregoing
    considerations of each component of 
    Ind. Code § 8-1-39-10
    , we find
    that NIPSCO’s 7-Year Electric Plan is reasonable under the conditions
    as applied by this Order. . . . We find there is sufficient evidence to
    approve the Year 1 projects as eligible for TDSIC treatment.
    However, we are concerned that the project specific detail of Years 2
    through 7 does not rise to the same level of confidence. Thus, in the
    context of our 7-Year Plan approval we will presume the categories of
    spending identified in the 7-Year Electric Plan for Years 2 through 7
    are eligible for TDSIC treatment. Because we expect these eligible
    project categories will become better defined in terms of specificity as
    their respective investment year comes of age, this presumption of
    eligibility will be assigned to specific projects in the annual updating
    process as further described below.
    
    Id. at 25
    . The Commission then established an informal bi-annual update to the
    plan and anticipated that NIPSCO would provide details on specific projects,
    similar to what it provided for Year 1. The Commission found that “this
    process will reasonably balance the needs of NIPSCO for investment recovery
    confidence and customers for prudent investment assurance.” 
    Id. at 26
    . The
    Commission noted:
    Clearly, a 7-Year Plan for any public utility must necessarily include
    some level of flexibility to address changing circumstances. It would
    not be reasonable for a public utility to submit a 7-Year Plan that does
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015        Page 10 of 31
    not acknowledge that unforeseen events and changes in circumstances
    do occur and may require changes to the 7-Year Plan.
    
    Id. at 22
    .
    [18]   On appeal, the Industrial Group argues that the statutes require the
    improvements to be “designated” in the plan and that the Commission did not
    have enough information to determine whether the plan was “reasonable” or to
    determine a “best estimate of the cost” of the improvements. See I.C. § 8-1-39-
    10(b). The Commission argues that approval of the plan was a matter within its
    expertise and discretion. NIPSCO contends that the plan is reasonable because
    the Commission found NIPSCO had an “overarching goal,” included a
    “defined roadmap,” and had a “reasonably detailed overview of what types of
    projects need to be undertaken.” NIPSCO’s Appellee’s Br. pp. 29-30.
    [19]   NIPSCO’s seven-year plan included cost estimates for projected direct capital
    expenses, which included estimates for both transmission and distribution
    projects, and projected indirect capital expenditures. The plan also provided
    detailed information on the improvements for the first year of the plan.
    Specifically, for 2014 only, NIPSCO provided details on the type of
    improvement, reason for the improvement, the project title and location, and a
    project cost for each category. However, detailed information on the projects
    was not provided for years two through seven of the plan. For the remaining
    years, NIPSCO only provided “expected annual total spends for major project
    categories.” Tr. p. 624.
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015   Page 11 of 31
    [20]   NIPSCO argues that another exhibit, TAD-R1, is part of the plan. TAD-R1 is
    a list of all of NIPSCO’s major transmission and distribution assets and that
    TAD-R1 identifies the name of each asset to be replaced, the cost of each asset
    to be replaced, and the year in which the asset is to be replaced. However,
    NIPSCO’s argument conflicts with the Commission’s finding regarding the
    plan. See Industrial Group App. p. 25 (“[W]e are concerned that the project
    specific detail of Years 2 through 7 does not rise to the same level of
    confidence.”). NIPSCO also did not identify TAD-R1 as part of the “plan.” In
    fact, in the verified rebuttal testimony of Timothy Dehring, NIPSCO’s senior
    vice president of transmission and engineering, he acknowledged the OUCC’s
    concerns with the plan’s lack of detail, noted that TAD-R1 was provided during
    discovery to address the OUCC’s concerns, and stated that the OUCC “makes
    a valid recommendation that in the future this type of information should be
    provided with the 7-Year Electric Plan.” Tr. p. 589. Consequently, we
    conclude that TAD-R1 was not part of the “plan.”
    [21]   We further conclude that the plan provided to the Commission simply did not
    contain enough detail for the Commission to determine whether NIPSCO’s
    plan for years two through seven was “reasonable” or to determine a “best
    estimate of the cost” of the improvements. I.C. § 8-1-39-10(b). We
    acknowledge the arguments on appeal that a utility needs some flexibility to
    deal with changing conditions. Clearly, NIPSCO requires some flexibility in
    completing the seven-year plan because some equipment may need to be
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015    Page 12 of 31
    replaced earlier or later than initially planned. Even the OUCC acknowledged
    that some flexibility is required, and its representative testified:
    The OUCC appreciates that over the course of 7 years project priorities
    will likely change. Unforeseen events will occur and assets may fail
    sooner than anticipated. . . . The OUCC does not object to this
    shifting as long as the utility (NIPSCO) is transparent with the
    [Commission], OUCC and Intervenors regarding the reasons for the
    shift. . . . NIPSCO should not be locked into a specific set of projects
    today that in the future would not provide the greatest benefit to the
    T&D system and its users. Conversely, the OUCC does not believe
    the Statute permits NIPSCO to make wholesale substitutions of
    projects as it sees fit.
    Tr. pp. 842-43. The OUCC proposed that NIPSCO submit an updated plan
    annually “concurrent with its Fall TDSIC tracker filing” and that the parties
    would have the opportunity to contest the revised plans. Id. at 843. We believe
    that the legislature anticipated the necessity of flexibility when it enacted the
    updating process of Indiana Code Section 8-1-39-9. The updating process does
    not, however, relieve the utility of providing an initial seven-year plan that
    meets the statutory requirements. Allowing for flexibility in a plan is not the
    same thing as not having a plan at all. We conclude that the Commission erred
    by approving NIPSCO’s seven-year plan given its lack of detail regarding the
    projects for years two through seven.
    [22]   The Industrial Group also takes issue with the Commission establishing a
    presumption of eligibility for years two through seven. The Commission found
    that, even though NIPSCO provided insufficient detail of the plan for years two
    through seven, a presumption of eligibility would be established that the
    projects would be eligible for TDSIC treatment. See Industrial Group’s App. p.
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015       Page 13 of 31
    25 (“[W]e will presume the categories of spending identified in the 7-Year
    Electric Plan for Years 2 through 7 are eligible for TDSIC treatment. . . . [T]his
    presumption of eligibility will be assigned to specific projects in the annual
    updating process . . . .”). The Industrial Group points out that we have held
    that the Commission may not create legal presumptions. See S. Indiana Gas &
    Elec. Co. v. Indiana Farm Gas Prod. Co., 
    540 N.E.2d 621
    , 625 (Ind. Ct. App.
    1989), vacated on reh’g on other grounds, 
    549 N.E.2d 1063
     (Ind. Ct. App. 1990),
    trans. denied. The Industrial Group also asserts that, by creating a presumption
    of eligibility, the Commission has shifted the burden from NIPSCO to
    intervening parties to demonstrate that the proposed projects are eligible for
    TDSIC treatment. NIPSCO counters that the presumption is permissible
    because the Commission was exercising its expertise and inherent authority and
    the presumption “balanced the relationship between NIPSCO and its
    customers.” NIPSCO’s Appellee’s Br. p. 41. The Commission argues that it
    did not shift the burden of proof and did not establish a rebuttable presumption.
    [23]   We conclude that the Commission’s order did establish a presumption of
    eligibility regarding the undefined projects for years two through seven. There
    does not appear to be any statutory support for establishing such a presumption.
    We agree with the Industrial Group that such a presumption inappropriately
    shifts the burden of showing a project’s eligibility for TDSIC treatment from
    NIPSCO to other intervening parties. On remand, the Commission may not
    establish such a presumption.
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015   Page 14 of 31
    II. Statutory Cap
    [24]   The Industrial Group also argues that the Commission erred by approving costs
    in excess of a statutory cap on aggregate increases. Because this issue and the
    issues raised by the OUCC are likely to be relevant on remand, we will address
    them.
    [25]   Indiana Code Section 8-1-39-14 provides:
    (a)      The commission may not approve a TDSIC that would result
    in an average aggregate increase in a public utility’s total retail
    revenues of more than two percent (2%) in a twelve (12) month
    period. For purposes of this subsection, a public utility’s total
    retail revenues do not include TDSIC revenues associated with
    a targeted economic development project.
    (b)      If a public utility incurs TDSIC costs under the public utility’s
    seven (7) year capital expenditure plan that exceed the
    percentage increase in a TDSIC approved by the commission,
    the public utility shall defer recovery of the TDSIC costs as set
    forth in section 9(b) of this chapter.
    [26]   Before the Commission, the Industrial Group argued that, under the statute,
    NIPSCO was limited to a two-percent increase over the course of the seven-
    year plan. The Commission disagreed and found:
    NIPSCO and the Industrial Group have presented two different
    interpretations of 
    Ind. Code § 8-1-39-14
    . NIPSCO’s calculation
    compares the increase in TDSIC revenue in a given year with the total
    retail revenues for the past 12 months whereas the Industrial Group
    compares the total TDSIC revenue in a given year with the total retail
    revenues for the base 12 months. Since this is a case of first
    impression, we must interpret and apply this statutory language for the
    first time based on the express language of the statute and the general
    rules of statutory interpretation.
    Section 14(a) states as follows:
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015            Page 15 of 31
    The commission may not approve a TDSIC that would
    result in an average aggregate increase in a public utility’s
    total retail revenues of more than two percent (2%) in a
    twelve (12) month period. For purposes of this
    subsection, a public utility’s total retail revenues do not
    include TDSIC revenues associated with a target
    economic development project.
    Based on the unambiguous language of Section 14, we find that
    NIPSCO’s proposed calculation that compares the increase in TDSIC
    revenue in a given year with the total retail revenues for the past 12
    months is consistent with the TDSIC statute. Under the Industrial
    Group’s interpretation, a utility would be capped at an amount of
    TDSIC revenue that would have the effect of being a cumulative 2%
    increase. However, the average aggregate increase language of the
    statute allows a utility to increase its TDSIC revenues by 2% a year, on
    a year over year basis. Thus, we find that NIPSCO’s proposed
    calculation is consistent with Section 14 and should be approved.
    OUCC App. p. 29.
    [27]   On appeal, the Industrial Group argues that the statute is ambiguous regarding
    the two-percent cap. According to the Industrial Group, the “aggregate”
    increase over the entire seven-year plan cannot exceed two percent. NIPSCO
    asserts that the statute is unambiguous. According to NIPSCO, the Industrial
    Group is ignoring the “twelve (12) month period” language in the statute.
    NIPSCO argues that the statute allows a two-percent increase every twelve
    months based on the prior twelve months’ total retail revenues. The
    Commission agreed with NIPSCO and argues that its interpretation was
    reasonable and that the statute is unambiguous. The Commission points out,
    “If the Legislature intended to apply the 2% cap to the entirety of a seven-year
    plan, why would it specifically confine the 2% increase to a twelve-month
    period?” Commission’s Appellee’s Br. p. 20. Additionally, the Indiana Energy
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015           Page 16 of 31
    Association argues that the Industrial Group’s interpretation would “cripple the
    TDSIC statute.” Indiana Energy Association’s Br. p. 3.
    [28]   The statute does not allow “an average aggregate increase in a public utility’s
    total retail revenues of more than two percent (2%) in a twelve (12) month
    period.” I.C. § 8-1-39-14(a). The plain language of the statute allows an
    average two-percent increase in a twelve month period, not during the entire
    seven-year plan. We must give the statute its apparent and obvious meaning.
    U.S. Steel Corp., 
    951 N.E.2d at 551
    . The Commission did not err in interpreting
    the two-percent cap of Indiana Code Section 8-1-39-14(a).
    III. Retired Assets
    [29]   The OUCC argues that the Commission erred by allowing NIPSCO to
    continue rate recovery of retired equipment while also recovering for
    replacement assets. According to the OUCC, under the rate increases proposed
    by NIPSCO, NIPSCO will continue recovering on assets no longer in use until
    the next general rate case, which could result “in utility rate payers paying
    millions of dollars for up to seven years for assets no longer providing them any
    service.” OUCC’s Reply Br. p. 10. The OUCC asserts that NIPSCO will
    receive a double recovery, i.e., a return on the new assets at the same time as it
    is receiving a return on the old, replaced asset.
    [30]   This argument has two facets—the calculation of NIPSCO’s “return on” the
    investments and depreciation. In general, “the end purpose of the function of
    the Commission is to establish a rate sufficient to meet the operating expenses
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015   Page 17 of 31
    of the company plus a fair return which will compensate the investors.”
    Citizens Energy Coal., Inc. v. Indiana & Michigan Elec. Co., 
    396 N.E.2d 441
    , 445
    (Ind. Ct. App. 1979). “Utility’s revenues, minus expenses, constitute the return
    on investments.” 
    Id.
     (emphasis added). On the other hand, depreciation
    accounts for a reduction in value of an asset as it ages; depreciation is
    sometimes called “return of” the investment. OUCC’s Reply Br. p. 10. The
    OUCC does not “oppose NIPSCO collecting any remaining amounts for
    undepreciated plant, but advocated for adjustments to the TDSIC to prevent
    NIPSCO from earning a ‘return on’ an investment that was no longer in
    service.” OUCC’s Appellant’s Br. p. 25 n.8.
    [31]   The OUCC challenged NIPSCO’s proposed rate increase for the TDSIC
    improvements based on this issue. The Commission allowed NIPSCO to
    recover for TDSIC projects without subtracting for returns or depreciation
    already being recovered for the assets being replaced. Specifically, the
    Commission found:
    The OUCC recommended that NIPSCO should only be permitted to
    recover the incremental capital, depreciation and operating and
    maintenance costs of replacement TDSIC projects because ratepayers
    are already paying for the replaced assets in basic rates. Similarly,
    U.S. Steel recommended NIPSCO should be required to produce
    adjustments in its updated 7-Year Electric Plan and in the calculation
    of the periodic TDSIC trackers to account for and eliminate the
    recovery of costs and depreciation associated with the early retirement
    and replacement of assets replaced and recovered in the TDSIC
    charges. U.S. Steel argued that by recovering carrying costs and
    depreciation expense for assets that are retired early and replaced
    through the 7-Year Electric Plan, NIPSCO will be recovering for assets
    that are no longer used and useful. U.S. Steel argued to allow such
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015       Page 18 of 31
    double recovery is not in the public interest or consistent with
    fundamental ratemaking principles.
    The statutory definition of eligible improvements at 
    Ind. Code § 8-1
    -
    39-2 authorizes recovery of investment for replacement projects and
    the definition of pretax return at 
    Ind. Code § 8-1-39-3
     provides that
    revenues should provide for such investments, notably without
    suggesting any deduction or netting of the replaced asset. Further,
    TDSIC costs as defined at 
    Ind. Code § 8-1-39-7
     includes this
    unadjusted pretax return. While acknowledging that 
    Ind. Code § 8-1
    -
    39-13(a) allows the Commission to consider other information in
    setting the appropriate pretax return, we read this section to be
    addressing the weighted cost of capital rate rather than the investment
    amount so as to reconcile the statutory language of Sections 13 and 3.
    Accordingly, we do not find statutory support for the netting of
    investment in determining the appropriate investment to be afforded
    cost recovery. In addition, the TDSIC statute requires a general rate
    case before the expiration of the utility’s 7-year plan which provides a
    built in mechanism to update the net investment of the utility. Thus,
    we decline to require NIPSCO to recognize the replaced asset
    investment cost already embedded in base rates because Ind. Code ch.
    8-1-39 does not support it outside of the required rate case.
    OUCC App. pp. 26-27.
    [32]   The Commission found that the TDSIC statutes do not specifically address this
    issue, and we agree. The TDSIC statute allows a utility to recover, through
    “the periodic automatic adjustment of the public utility’s basic rates and
    charges,” eighty percent of “approved capital expenditures and TDSIC costs.”
    I.C. § 8-1-39-9(a). Recovery of the remaining twenty percent of approved
    capital expenditures and TDSIC costs is deferred to the next general rate case
    filed by the utility. I.C. § 8-1-39-9(b). Although TDSIC costs are defined by the
    statutes, the statutes do not mention depreciation or return on the replaced
    equipment. See I.C. § 8-1-39-7 (defining TDSIC costs, including pretax returns,
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015        Page 19 of 31
    among other things); I.C. § 8-1-39-3 (defining pretax returns). The statute does,
    however, allow the Commission to consider “[o]ther information that the
    commission determines is necessary” in calculating pretax returns. I.C. § 8-1-
    39-13.
    [33]   Despite the lack of a specific statute addressing the OUCC’s concern here, the
    OUCC argues that Indiana Code Section 8-1-2-6(a) requires the Commission to
    “value all property of every public utility actually used and useful for the
    convenience of the public at its fair value.” (Emphasis added). The OUCC
    argues that the Commission allowed NIPSCO to continue recovering a return
    on assets that will be replaced through the TDSIC proceeding and will no
    longer be “used and useful.”
    [34]   NIPSCO argues that the “used and useful” principle applies only to
    determining whether the cost of new investments should be passed onto
    consumers. NIPSCO’s Appellee’s Br. p. 70. In support of this argument,
    NIPSCO relies on Citizens Action Coal. of Indiana, Inc. v. N. Indiana Pub. Serv. Co.,
    
    485 N.E.2d 610
     (Ind. 1985), cert. denied, where NIPSCO sought to recover costs
    for a cancelled nuclear power plant. Our supreme court did not allow NIPSCO
    to recover the costs of a project that was never used and useful. However, our
    supreme court differentiated that situation from the “long-adhered to
    administrative interpretation of allowing amortization of abandoned plants, i.e.
    plants that were ‘used and useful’ property and then retired from service.”
    Citizens Action Coal., 485 N.E.2d at 616. The court noted: “Allowance of
    amortization of cancelled plants would encourage uneconomical or
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015     Page 20 of 31
    unproductive ventures; whereas, allowance for amortization of abandoned or
    retired plants encourages utilities to remove obsolete plants and property from
    the ratebase. This treatment also benefits consumers because obsolete and
    inefficient property is removed from the ratebase.” Id.
    [35]   The OUCC argues that the language from Citizens Action Coal. of Indiana is dicta
    and that more recent Commission orders have reached contrary results. The
    OUCC notes that, in other contexts, the Commission has refused to allow a
    utility to earn such a double recovery even where the statutes do not directly
    address the issue. The OUCC cites the Commission’s determination in In Re
    Petition of NIPSCO, Cause No. 42150 ECR 21, 
    2013 WL 5740184
     (Ind. U.R.C.
    Oct. 16, 2013), where NIPSCO sought to replace pollution control equipment.
    The Commission allowed NIPSCO to recover “a return of its investment” on
    the original and replacement catalyst layers. OUCC Appellant’s Addendum p.
    13. However, the Commission noted that “should we grant full recovery of
    NIPSCO’s return on its investment in the replacement layer when it already
    receives a return on its investment in the original layer through its base rates
    and charges, then until its next base rate case, NIPSCO would receive a return
    on investment for two catalyst layers, while only one layer is in service.” 
    Id.
    The Commission concluded that NIPSCO would “be allowed to seek recovery
    of its full depreciation expense (return of investment) for the replacement
    layer,” but it would “only be allowed to seek recovery of the incremental
    amount of the return on its investment for the replacement catalyst layer that
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015    Page 21 of 31
    exceeds the return on investment currently included in its base rates and charges
    for the original catalyst layer.” 
    Id.
    [36]   The OUCC also cites In Re Indiana-American Water Co., Inc., Cause No. 42351
    DSIC-1 (Ind. U.R.C. Feb. 27, 2003). There, the Commission was considering a
    water utility’s petition under the Distribution System Improvement Charge
    (“DSIC”) statute and refused to allow a water utility to earn both a return on a
    replaced asset and a return on the replacement asset. The Commission held:
    Petitioner’s rate base is based on the fair value of its assets. When any
    asset with a positive fair value is retired that will reduce the utility’s
    fair value rate base. Thus, if retirements are ignored and a utility is
    allowed to earn a return on new plant through a DSIC and on the
    retired asset through its return on the fair value rate base determination
    from the utility’s last rate case.
    
    Id. at 32
    .
    [37]   NIPSCO responds that the Commission is not bound by its prior rulings and
    that the rulings concern different statutes. According to NIPSCO, if the
    Commission adopted the OUCC’s “netting” proposal, “NIPSCO’s common
    equity holders would not only lose their return on common equity, they would
    be required to pay NIPSCO’s long-term debt.” NIPSCO’s Appellee’s Br. p. 73.
    [38]   Under the TDSIC statutes, the Commission “may consider . . . [o]ther
    information that the commission determines is necessary” in calculating pretax
    returns. I.C. § 8-1-39-13 (emphasis added). The Commission could, under this
    statute, address the OUCC’s concern; the Commission, however, is not required
    to do so. We give “great deference” to the Commission’s rate-making
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015         Page 22 of 31
    methodology. Office of Util. Consumer Counselor v. Citizens Tel. Corp., 
    681 N.E.2d 252
    , 255 (Ind. Ct. App. 1997). This subject is “within the Commission’s special
    competence,” and “courts should give it greater deference.” Duke Energy
    Indiana, Inc. v. Office of Util. Consumer Counselor, 
    983 N.E.2d 160
    , 170 (Ind. Ct.
    App. 2012). Although we have significant concerns over the allegedly
    inconsistent treatment of this subject by the Commission, in light of the
    deference owed to the Commission, we cannot say that its methodology is
    erroneous given the lack of specificity in the statutes regarding this calculation.
    IV. Rate Allocation Factors
    [39]   The OUCC next argues that the Commission erred in calculating the rate
    allocation factors to be applied here. NIPSCO charges different rates to
    different customer classes based on the cost to serve each customer class. For
    example, Rates 610, 611, and 612 govern residential customers, while Rates
    632, 633, and 634 govern industrial customers. Some customers receive “firm
    load,” which is basically the amount of electricity that is guaranteed by the
    utility; while some customers also receive “non-firm load” (also known as
    “interruptible load”), which is electrical service that can be interrupted. See
    NIPSCO’s Appellee’s Br. p. 9.
    [40]   Another issue here is whether the customer is a distribution or transmission
    customer. Transmission is the transfer of electric energy from its sources of
    generation across high-voltage lines to either a local distributor, a substation, or
    a large-scale industrial customer. See 
    id. at 77
    . Distribution involves the
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015    Page 23 of 31
    transfer of electric energy through a retail delivery system to smaller-scale
    industrial, commercial, and residential customers. See 
    id.
    [41]   In NIPSCO’s most recent retail base rate case order in December 2011 in Cause
    No. 43969, the revenue allocation factors were based on a settlement
    agreement, not a typical cost-of-service study. When the parties reached the
    settlement in Cause No. 43969, one of the most contentious issues was the rate
    allocation. See In Re Petition of NIPSCO to Modify its Rates, Cause No. 43969,
    
    2011 WL 6837714
     (Ind. U.R.C. Dec. 21, 2011). Basically, the Order allowed
    NIPSCO to move all customers to “firm” rates. 
    Id.
     (allowing NIPSCO to
    “migrat[e] customers from special contracts to firm service”). Industrial
    customers were then allowed a credit for interruptible, or “non-firm,” usage
    through Rider 675. 
    Id.
     The Commission noted in Cause No. 43969 that
    “revenue allocation and Rider 675 were interrelated and reflected difficult and
    painstaking negotiations to reach a balanced outcome and resolution which was
    acceptable to the Settling Parties.” 
    Id.
     The Commission gave “substantial
    weight to the Settling Parties’ agreement with respect to revenue allocation.”
    
    Id.
    [42]   The allocation factors are again an issue in this litigation. The TDSIC statute
    requires the petition to “use the customer class revenue allocation factor based
    on firm load approved in the public utility’s most recent retail base rate case
    order.” I.C. § 8-1-39-9(a). Rather than use the allocation factors reached in the
    December 2011 settlement agreement, NIPSCO sought to adjust the revenue
    allocation factors from the settlement agreement because it claimed that those
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015   Page 24 of 31
    allocation factors: (1) included non-firm load; and (2) included distribution
    costs for customers that only used transmission facilities. See Petitioner’s Exh.
    DJI-1, Exh. 2, Schedule 4; Tr. pp. 923-24. NIPSCO’s proposed allocation
    factors are favorable to large industrial customers and unfavorable to residential
    customers. See Tr. p. 1308.
    [43]   The Commission agreed with NIPSCO and found the following with respect to
    the rate allocation factors:
    Petitioner is requesting approval to use modified versions of its
    customer class revenue allocation factor based on firm load that was
    approved as Joint Exhibit C to the settlement agreement approved in
    the 43969 Order. Mr. Shambo testified that for transmission costs the
    revenue allocation factor should be adjusted for Rider 675 interruptible
    credit in order to remove the non-firm portion of revenues from Rates
    632 and 634. Mr. Shambo noted that for distribution costs the revenue
    allocation factor from Joint Exhibit C should be adjusted to exclude
    revenue from Rates 632, 633, and 634, which are transmission and
    sub-transmission rates.
    OUCC witness Mr. Hand argued that NIPSCO’s request to apply
    adjusted customer class allocation factors should be denied and they
    should be required to apply the customer class revenue allocators from
    the 43969 Order.
    The 43969 Order allocated revenue to customer classes based on a
    settlement agreement rather than a cost of service study. A cost of
    service study would have included separate allocation factors for
    distribution and transmission. However, the 43969 Order includes all
    costs in one factor. Further, the approved customer class revenue
    allocation factors included non-firm load, which was effectively
    adjusted out of the revenue allocation in a subsequent ratemaking step.
    
    Ind. Code § 8-1-39-9
    (a) requires NIPSCO to use the customer class
    revenue allocation factor based on firm load developed in the most
    recent base rate case. The evidence shows that many of the same
    customers currently taking interruptible service under Rider 675 were
    interruptible prior to the date the 43969 Order was issued. However,
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015        Page 25 of 31
    the evidence shows that pursuant to the 43969 Order, NIPSCO’s old
    interruptible rates were terminated and replaced by the new firm rates
    plus an interruptible Rider 675 which established a different method to
    designate load as non-firm or interruptible. Thus, in order for the Joint
    Exhibit C allocation factors to properly reflect the customer class
    revenue allocation factors based on firm load, they must be adjusted to
    reasonably reflect non-firm load that was treated as firm under the
    construct of the settlement agreement as approved in the 43969 Order.
    Based on our review of the TDSIC statute and the evidence in this
    Cause, we find that NIPSCO’s proposal that the revenue allocation
    factor be adjusted for the Rider 675 interruptible credit in order to
    remove the non-firm portion of the revenues from Rates 632 and 634 is
    consistent with 
    Ind. Code § 8-1-39-9
    (a)(1) and should be approved.
    Further, NIPSCO’s proposal to exclude Rates 632, 633 and 634 is a
    reasonable method to accomplish the alignment of the cost causation
    with cost allocation, under the evidence specific conditions presented
    in this proceeding together with the 43969 Order, for the purpose of
    allocating distribution costs in a manner that comports with 
    Ind. Code § 8-1-39-9
    (a)(1). We find it is appropriate to adjust the 43969 Order
    approved Joint Exhibit C allocation factors by removing Rates 632,
    633 and 634 from the calculation for purposes of allocating
    distribution-related TDSIC costs so that rate classes that do not use the
    distribution system are not allocated distribution costs.
    OUCC App. pp. 24-25.
    [44]   On appeal, the OUCC argues that the Commission’s order is erroneous because
    it failed to use the allocation factors approved in the last rate case as required by
    Indiana Code Section 8-1-39-9(a). The OUCC also argues that it would be bad
    public policy to allow the parties to engage in protracted negotiations to
    establish the rate allocation factors and then allow NIPSCO to immediately
    argue that it is not bound by the settlement. NIPSCO argues that the allocation
    factors in the last rate case were established by a settlement agreement, not
    through a cost-of-service study, and that, if the allocation factors has been
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015         Page 26 of 31
    established through a cost-of-service study, the large industrial customers would
    have been allocated only transmission costs, not distribution costs. NIPSCO
    also argues that the statute required it to use allocation factors based on firm
    load and that the allocation factors established by the settlement agreement
    included non-firm load. Consequently, according to NIPSCO, the allocation
    factors had to be adjusted. NIPSCO contends that “[a]ll [it] did was to adjust
    these allocation factors to square them with traditional ratemaking principles,
    which are based on simple fairness.” NIPSCO’s Appellee’s Br. p. 78.
    [45]   The Commission also briefly addresses this issue in its Appellee’s Brief. The
    Commission only addresses the non-firm adjustment and does not mention the
    transmission/distribution adjustment. According to the Commission, the
    statute requires only allocation factors based on firm load and it was reasonable
    to allow NIPSCO to make the adjustments.
    [46]   The Industrial Group also filed an appellee’s brief responding to the allocation
    factor argument. The Industrial Group supports the allocation factors
    advocated by NIPSCO. In its reply brief, the OUCC argues that the evidence
    does not support the Commission’s finding that the settlement agreement’s
    allocation factors included non-firm load.
    [47]   At the hearing before the Commission, Frank Shambo, vice president of
    regulatory and legislative affairs for NIPSCO, testified that “NIPSCO proposes
    that the customer class revenue allocation factor be adjusted for the Rider 675
    interruptible credit in order to remove the non-firm portion of revenues from
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015   Page 27 of 31
    Rates 632 and 634.” Tr. pp. 956, 1017. Shambo also testified: “For distribution
    TDSIC costs, NIPSCO proposes that the customer class revenue allocation
    factor be adjusted to exclude revenues from Rates 632, 633 and 634 which are
    transmission and subtransmission service rates.” 
    Id. at 1017
    ; see also 
    id. at 956
    .
    OUCC witness Eric Hand testified that the proposed allocation factors did not
    match the factors approved in the settlement agreement and that allowing
    NIPSCO to make the proposed adjustments to the allocation factors would
    undercut the settlement agreement. Although the OUCC argues that non-firm
    load was not included in the settlement agreement’s allocation factors, it seems
    clear that non-firm load was included and that a credit was given to the
    customers using non-firm load.
    [48]   In support of its argument, NIPSCO relies on Citizens Action Coalition of Indiana,
    Inc. v. NIPSCO, 
    804 N.E.2d 289
     (Ind. Ct. App. 2004). In Citizens Action
    Coalition, NIPSCO sought to increase rates to implement pollution control
    equipment. A regulation required: “A utility’s jurisdictional revenue
    requirement that results from the ratemaking treatment of qualified pollution
    control property under construction under this rule shall be allocated among the
    utility’s customer classes in accordance with the allocation parameters established by the
    commission in the utility’s last general rate case.” 170 IAC 4-6-15 (emphasis added).
    Despite the regulation’s requirement that the allocations used in the utility’s last
    general rate case be utilized, NIPSCO sought to use an allocation methodology
    from a later cost study. The Commission allowed NIPSCO to do so, and on
    appeal, we affirmed.
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015          Page 28 of 31
    [49]   NIPSCO argued that “the purpose of the rule requiring that allocation among
    customer classes be governed by the utility’s last general rate case is to allow
    utilities to avoid the necessity of preparing a costly cost of service study every
    time they seek authorization for QPCP investments.” Citizens Action Coalition,
    
    804 N.E.2d at 303
    . “It argue[d] that the rule is not intended to preclude use of
    newer and more accurate studies in situations where they have already been
    prepared for other reasons.” 
    Id.
     We concluded that, given the evidence of the
    benefits of using the more recent study, the Commission’s decision was not
    erroneous. 
    Id. at 304
    . We noted that “[e]nforcing strict compliance with 170
    IAC 4-6-15 by requiring the Commission to use the 1987 study would produce
    the illogical result of having NIPSCO allocate costs based on outdated data
    when a more recent study is available.” 
    Id.
     Emphasizing “our preference to
    place substance over form,” we could not conclude that the Commission erred
    by using the later study rather than the allocations from the last general rate
    case. 
    Id.
    [50]   We reach a similar conclusion here. The TDSIC statute requires the use of “the
    customer class revenue allocation factor based on firm load approved in the
    public utility’s most recent retail base rate case order.” I.C. § 8-1-39-9(a). The
    allocation factors from the December 2011 settlement agreement were based on
    both firm and non-firm load. Consequently, the adjustment to remove the non-
    firm load portion was within the Commission’s discretion and expertise.
    [51]   The statute, however, did not require an adjustment for transmission versus
    distribution considerations. The adjustment of the allocation factors to account
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015    Page 29 of 31
    for differences between transmission and distribution customers would conflict
    with the clear language of the statute, which requires the use of the allocation
    factors approved in the December 2011 settlement agreement. We recognize
    that the Commission has “the technical expertise to administer regulatory
    schemes devised by the legislature.” Indiana Office of Util. Consumer Counselor v.
    Lincoln Utilities, Inc., 
    834 N.E.2d 137
    , 145 (Ind. Ct. App. 2005), trans. denied.
    “We also give great deference to the [Commission’s] rate-making
    methodology.” 
    Id.
     However, the Commission’s “authority is limited to that
    which is granted to it by statute.” 
    Id. at 142
    . We conclude that the
    Commission exceeded its statutory authority by allowing the adjustment of the
    allocation factors based on transmission and distribution considerations.
    Conclusion
    [52]   We conclude that the Commission improperly approved NIPSCO’s seven-year
    plan under the TDSIC statute because it lacked detail regarding the proposed
    projects for years two through seven. We also conclude that the Commission
    improperly established a presumption of eligibility for the projects in years two
    through seven. However, we conclude that the Commission properly
    interpreted the two-percent cap language in the TDSIC statute, and we give
    deference to the Commission’s decision regarding the rate recovery of retired
    assets. Finally, we conclude that the Commission was within its discretion to
    adjust the rate allocation factors to remove non-firm load; however, the
    Commission exceeded its statutory authority when it adjusted the allocation
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015     Page 30 of 31
    factors based on transmission and distribution considerations. We affirm in
    part, reverse in part, and remand.
    [53]   Affirmed in part, reversed in part, and remanded.
    May, J., and Pyle, J., concur.
    Court of Appeals of Indiana | Opinion 93A02-1403-EX-158 |April 8, 2015   Page 31 of 31