Citizens Action Coalition of Indiana, Inc. v. Southern Indiana Gas and Electricity Company , 70 N.E.3d 429 ( 2017 )


Menu:
  •                                                                                    FILED
    Feb 14 2017, 9:50 am
    CLERK
    Indiana Supreme Court
    Court of Appeals
    and Tax Court
    ATTORNEYS FOR APPELLANTS                                   ATTORNEYS FOR APPELLEES
    Thomas Cmar                                                Curtis T. Hill, Jr.
    Oak Park, Illinois                                         Attorney General of Indiana
    Matthew Gerhart                                            David Lee Steiner
    Denver, Colorado                                           Deputy Attorney General
    Indianapolis, Indiana
    Jennifer A. Washburn
    Indianapolis, Indiana                                      Beth Krogel Roads
    Jeremy R. Comeau
    Indiana Utility Regulatory
    Commission
    Indianapolis, Indiana
    Robert E. Heidorn
    P. Jason Stephenson
    Evansville, Indiana
    Wayne C. Turner
    Patrick A. Ziepolt
    Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017              Page 1 of 22
    Citizens Action Coalition of                               February 14, 2017
    Indiana, Inc., Sierra Club, Inc.,                          Court of Appeals Case No.
    Valley Watch, Inc.,                                        93A02-1607-EX-1637
    Appellants-Intervenors,                                    Appeal from the Indiana Utility
    Regulatory Commission
    v.                                                 The Honorable Jeffery A. Earl,
    Administrative Law Judge
    Southern Indiana Gas and                                   The Honorable Carol A. Stephan,
    Electricity Company d/b/a                                  Commissioner Chair
    Vectren Energy Delivery of                                 The Honorable Angela Weber,
    Indiana, Inc., Indiana Office of                           Commissioner
    Utility Consumer Counselor,
    The Honorable David Ziegner,
    Appellees-Petitioners                                      Commissioner
    The Honorable James Huston,
    Commissioner
    Trial Court Cause No.
    44446
    Altice, Judge.
    Case Summary
    [1]   Over three years ago, Southern Indiana Gas and Electric Company d/b/a
    Vectren Energy Delivery of Indiana, Inc. (Vectren) petitioned the Indiana
    Utility Regulatory Commission (IURC) for approval of projects to modify four
    of Vectren’s coal-powered generating stations to bring them into compliance
    with EPA emissions standards. Citizens Action Coalition of Indiana, Inc.,
    Sierra Club, Inc., and Valley Watch, Inc. (collectively, Intervenors) intervened
    in the action and opposed the petition.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017           Page 2 of 22
    [2]   The IURC ultimately approved the petition, determining that Vectren’s
    proposed projects were reasonable and necessary under Ind. Code § 8-1-8.8-11.
    Upon Intervenors’ appeal in Citizens Action Coal. of Ind., Inc. v. S. Ind. Gas & Elec.
    Co. (Vectren I), 
    45 N.E.3d 483
    (Ind. Ct. App. 2015), another panel of this court
    remanded with respect to two of the proposed projects, finding that I.C. § 8-1-
    8.7-3 rather than I.C. § 8-1-8.8-11 applied. This court instructed the IURC to
    make findings regarding the statutory factors listed in I.C. § 8-1-8.7-3 and then
    issue or deny a certificate of public convenience and necessity (CPCN) for the
    two projects.
    [3]   On remand, the IURC refused a request by Intervenors to reopen the record to
    consider new evidence. It also issued an order analyzing the nine statutory
    factors, concluding that public convenience and necessity will be served by the
    proposed clean coal technology projects, and issuing a CPCN to Vectren for the
    remaining projects. Intervenors appeal once again. They argue that the
    IURC’s findings are not adequately explained, are arbitrary and capricious, and
    are not supported by substantial evidence. Additionally, Intervenors argue that
    the IURC unlawfully denied the petition to reopen the record.
    [4]   We affirm.1
    1
    By separate order issued today, we grant Intervenors’ motion to dismiss the IURC as a party to this appeal.
    We agree that because the IURC acted as a fact-finding administrative tribunal and no statute or
    administrative provision expressly makes the IURC a party on appeal, it is not a proper party on appeal from
    its own decision. See City of Terre Haute v. Terre Haute Water Works Corp., 
    180 N.E.2d 110
    , 111 (Ind. Ct. App.
    1962) (“When there are two opposing parties before [the Public Service Commission of Indiana], as here, its
    action in making findings and issuing an order deemed detrimental by one of the parties is similar to that of a
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                       Page 3 of 22
    Facts2 & Procedural History
    [5]   Vectren is a public utility company that provides electricity to southern Indiana
    residents. Eighty-five percent of Vectren’s baseload electricity is generated at
    Brown unit 1, Brown unit 2, Culley unit 2, Culley unit 3, and Warrick, all of
    which are coal-powered generators. In 2012, the EPA issued a Notice of
    Violation (NOV) alleging that Vectren’s emissions control technology at its
    Brown units was noncompliant with EPA rules governing sulfuric acid
    emissions. The EPA also served Vectren with a Clean Air Act Information
    Request that highlighted concerns with the sulfur emissions at Culley unit 3.
    Vectren and the EPA eventually reached a settlement in principle to resolve the
    outstanding allegations raised in the NOV and the information request.
    Vectren also became subject to new federal mandates regarding mercury
    emissions standards.
    [6]   On January 17, 2014, as a result of the compliance issues, Vectren filed a
    petition with the IURC for approval of modifications to four of its coal-powered
    electricity generating facilities – Brown units 1 and 2, Culley unit 3, and
    Warrick. The petition sought approval of several clean energy projects and
    court which makes a decision determining a controversy between adverse parties. A court is never a party to
    an appeal from its decision.”); Cf. Ind. Code § 22-4-17-12(b) (expressly making the Review Board of the
    Indiana Department of Workforce Development a party appellee in every appeal of the review board’s
    decision).
    2
    We rely on many of the facts set out in Vectren I.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                    Page 4 of 22
    issuance of a CPCN to construct, install, and use clean coal technology (CCT). 3
    Among other projects,4 Vectren requested approval for a soda ash injection
    system for sulfur trioxide (SO3) mitigation at Brown units 1 and 2 and a
    hydrated lime injection system for SO3 mitigation at Culley unit 3.
    [7]   In April 2014, Intervenors intervened in the IURC proceedings and opposed
    Vectren’s petition.5 Intervenors contended that Vectren should replace all or
    some of the units with new electricity-generating sources (such as, natural gas,
    wind, or solar) instead of retrofitting the existing coal units. According to
    Intervenors, this would be more cost-effective for Vectren’s customers over the
    long run.
    [8]   The dispute between Vectren and Intervenors became a battle of experts.
    Vectren hired the engineering firm Black & Veatch (B & V) to compare the total
    ratepayer cost and relative risk of the proposed modifications versus the cost
    and risks associated with retiring and replacing the noncompliant units.
    B & V’s report found that the only feasible plans to meet
    environmental regulations were (1) replacing one or more of
    3
    Vectren also requested approval of certain financial incentives and approval to defer project costs, including
    depreciation and operations and maintenance expenses, for a period up to December 31, 2020. Approval of
    these financial requests is not at issue in this appeal.
    4
    The other projects addressed mercury emissions. Although the IURC’s approval of these projects was at
    issue in Vectren I, it is not here.
    5
    The Indiana Office of Utility Consumer Counselor (OUCC) initially opposed Vectren’s petition also. After
    reviewing additional information provided by Vectren, the OUCC eventually withdrew its opposition. The
    OUCC indicated to the IURC that it believed the proposed projects were appropriate and that it would
    support approval of all projects if the IURC determined that the modeling assumptions and analyses showed
    that the plan was reasonable.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                        Page 5 of 22
    Vectren’s current units with new natural gas-powered facilities
    and retiring the remaining facilities, or (2) upgrading the current
    coal-powered facilities. B & V evaluated twenty-one potential
    scenarios involving various gas-powered replacement options and
    a range of potential market and environmental scenarios. B & V
    concluded that of the twenty-one scenarios, only one offered a
    small savings over the Mandated Projects proposal. B & V found
    that the cost savings under this one scenario were “marginal” and
    conditional on a future market scenario with low natural gas
    prices and high carbon prices. Accordingly, B & V concluded
    that Vectren’s plan to modify the existing facilities was the best
    option in terms of cost to ratepayers.
    
    Id. at 487
    (record cite omitted).
    [9]    Intervenors submitted testimony of their expert, Dr. Jeremy I. Fisher, who felt
    that the 10-year period used in B & V’s analysis was too short to capture
    accurate long-term costs and risks associated with the proposal and that using a
    20-year model would be more appropriate. Dr. Fisher maintained that, under a
    20-year analysis, natural gas-powered generators would be more cost efficient.
    He also noted other errors he believed B & V committed in its economic
    modeling, including the exclusion of wholesale capacity and energy sales.
    [10]   Vectren’s President and CEO, Carl L. Chapman, disagreed that Vectren should
    retire 85% of its generation facilities and opined that this was a riskier approach.
    He testified that capacity constraints, market conditions, and economic growth
    would create tremendous risk. He also noted that there would be significant
    costs left undepreciated from prior investments in the units (stranded costs). On
    the other hand, according to Chapman, Vectren’s proposed projects afforded
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 6 of 22
    flexibility to respond to changing market conditions, reliable capacity, and full
    depreciation of stranded costs.
    [11]   Wayne D. Games, Vice President of Power Supply at Vectren, testified that a
    20-year analysis skews the economic modeling. He also indicated that it would
    take 4 years to construct replacement generation and, in the meantime,
    customers would be exposed to market and reliability risks.
    [12]   Despite the criticisms of Dr. Fisher, J. Neil Copeland of B & V continued to
    maintain that a 10-year model was prudent. He also disputed Dr. Fisher’s
    contentions of analytical errors in B & V’s model and noted problems with Dr.
    Fisher’s 20-year analysis. Further, Copeland indicated that the cost differences
    between the alternatives were fairly small and opined that decisions about
    future generations should not be made solely on these small differences. He
    noted the importance of management judgment and consideration of risks of
    capacity shortages.
    [13]   On January 28, 2015, the IURC issued an order (the First Order) approving
    Vectren’s petition in total. The order is lengthy but only a portion of it is
    relevant to this appeal. After setting out in detail the evidence presented by the
    parties, the IURC issued the following relevant discussion and findings:
    C. Deferred Recovery under Ind. Code ch. 8-1-8.8. Under Ind.
    Code § 8-1-8.8-11(a)(5), the Commission can authorize other
    financial incentives that it considers appropriate for clean energy
    projects only if the projects are found to be reasonable and
    necessary.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 7 of 22
    Vectren submitted evidence showing that failure to comply with
    the federally mandated requirements would require Vectren to
    retire Brown, Culley, and Warrick, which make up
    approximately 85% of its baseload generation, in 2015. The
    Mandated Projects will enable the continued operation of the
    facilities for at least the next ten years and continued service to
    Vectren’s customers.
    Vectren evaluated several alternative compliance technologies
    that would allow the Brown, Culley, and Warrick units to
    comply with pollution limits....
    Vectren hired Black & Veatch to further evaluate the most
    promising technologies and consider alternatives for bringing its
    generation fleet in compliance with federal regulations....
    ***
    Vectren also considered whether the continued operation of
    Brown units 1 and 2, Culley unit 3, and Warrick unit 4 was the
    best option. Vectren submitted production cost modeling
    supporting its plan to continue investing in, rather than retire,
    Brown, Culley, and Warrick. Specifically, Vectren presented a
    ten-year production cost model using PROMOD IV prepared by
    Black & Veatch. Vectren also engaged Burns & McDonnell to
    conduct an analysis over a 20-year period to respond to concerns
    by the Joint Intervenors and OUCC.
    The evidence presented by Vectren shows that failure to complete
    the Mandated Projects could require the premature retirement of
    the related generation facilities, which would result in significant
    reliability, market, and regulatory risk. MISO is projecting
    capacity shortfalls as early as 2016 and constructing a new gas
    generation facility would take at least four years. Without the
    ability to obtain voltage support from distant generators to serve
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 8 of 22
    its territory, Vectren would be forced to purchase capacity in an
    already constrained market. All of these factors point to
    concerns that retirement of Brown and Culley would expose
    Vectren’s customers to significant reliability risks. Based on the
    evidence presented, we find that the Mandated Projects are
    reasonable and necessary.
    Appellants’ Appendix at 20-21.
    [14]   Intervenors appealed the First Order arguing that the IURC “failed to make
    necessary findings on (1) facts material to its determination of the issues and (2)
    statutory factors required to be addressed prior to authorizing the use of clean
    coal technology.” Vectren 
    I, 45 N.E.3d at 485
    . Intervenors appealed the
    approval of all of Vectren’s proposed projects.
    [15]   We issued our opinion in Vectren I on October 29, 2015. After a thorough
    review of relevant Indiana utility and CCT statutes, we determined that two of
    the proposed projects – those using injection systems designed to mitigate sulfur
    emissions – required issuance of a CPCN under I.C. chapter 8-1-8.7.6 In its
    First Order, however, the IURC based its decision to approve all of the projects
    on I.C. chapters 8-1-8.4 and 8.8.7 In light of this error, we remanded on a
    limited basis and instructed:
    6
    The projects concerning mercury emissions are not considered CCT projects for purposes of Chapter 8.7
    because they do not reduce airborne emissions of sulfur or nitrogen based pollutants. 
    Id. at 496.
           7
    We noted, “a finding that the projects were reasonable and necessary under Chapter 8.8 does not change
    the fact that Vectren was required to obtain a CPCN before using new CCT and that the Commission was
    required to make findings under Chapter 8.7 before granting a CPCN thereunder.” Vectren I, 45 N.E.3d at
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                   Page 9 of 22
    Vectren may not use CCT (as defined in Chapter 8.7) until the
    Commission issues them a CPCN under Indiana Code section 8-
    1-8.7-3. On remand, the Commission shall make findings on the
    factors listed in Section 8-1-8.7-3(b) regarding the soda ash and
    hydrated lime injection systems which qualify as CCT under
    Chapter 8.7 and, based on those findings, determine whether
    those systems serve public convenience and necessity.
    Vectren 
    I, 45 N.E.3d at 498
    .
    [16]   On February 12, 2016, Intervenors filed a petition to reopen the evidentiary
    record, asserting material changes of fact since the close of the evidentiary
    hearing. Vectren objected to this petition.
    [17]   The IURC issued its order on remand (the Second Order) on June 22, 2016.
    After denying Intervenors’ request to reopen the record, the IURC made
    findings with respect to I.C. § 8-1-8.7-3(b):
    Under Ind. Code § 8-1-8.7-3(b), the Commission shall issue a
    CPCN if it finds that a clean coal technology project offers
    substantial potential to reduce sulfur or nitrogen based pollutants
    in a more efficient manner than conventional technologies in
    general use as of January 1, 1989. When determining whether to
    grant a CPCN, the Commission must consider specific factors,
    which are addressed below.
    A. The costs for constructing, implementing, and using CCT
    compared to the costs for conventional emission reduction
    facilities. Vectren estimated the costs for all projects
    495. Additionally, we concluded that “a CPCN granted under Chapter 8.4 would not be sufficient to satisfy
    the CPCN requirement of Chapter 8.7.” 
    Id. at 497.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                 Page 10 of 22
    approved in [this cause] to be in the range of $75-$95 million.
    Vectren supplied a breakdown of the estimated costs by
    project as a confidential filing, which includes the estimated
    costs for the Brown and Culley Projects. No party disputed
    the estimated costs.
    Ms. Fischer[8] testified that Black and Veatch considered
    several alternative technologies, including fuel switching, coal
    washing, boiler flue gas temperature control, furnace sorbent
    injection, and others. Ms. Fischer further testified that the
    Brown and Culley Projects were selected because the
    preliminary screening showed them to be the most cost
    effective. The evidence presented sufficiently describes the
    Mandated Projects Costs and demonstrates that the
    components of the Mandated Projects offer substantial
    potential to cost-effectively reduce pollutants.
    B. Whether a CCT project will extend the useful life of an
    existing electric generating facility and the value of that
    extension. Mr. Games testified that the Brown and Culley
    Units have not reached the end of their useful lives. He said
    that the Brown and Culley Projects are necessary to resolve
    the [NOV] issued by the [EPA] and to allow the continued
    operation of the Brown and Culley Units. Mr. Chapman
    testified that the Brown and Culley Projects would extend the
    useful lives of Vectren’s plant for another ten years, allowing
    Vectren to fully depreciate its prior capital investments in
    emission controls and to avoid stranded costs.
    C. The potential reduction of sulfur and nitrogen based
    pollutants achieved by the proposed CCT system. Mr.
    Games testified that under the NOV, Vectren has agreed to
    8
    Diane Fischer testified as the Air Quality Control Services Leader in the Energy Division at B & V.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                     Page 11 of 22
    install sodium-based sulfur trioxide (“SO3”) mitigation
    systems on both Brown Units. The systems will reduce
    sulfuric acid (“H2SO4”) emissions to 0.008 lb/mmbtu (pounds
    per million British thermal units) on Brown Unit 1 and 0.010
    lb/mmbtu on Brown Unit 2. Vectren has also agreed to
    install a SO3 mitigation system on Culley Unit 3, which will
    reduce H2SO4 emissions to 0.009 lb/mmbtu.
    D. The reduction of sulfur and nitrogen based pollutants that
    can be achieved by conventional pollution control
    equipment. Mr. Games testified that soda ash injection
    (Brown Units) and hydrated lime injection (Culley Unit) are
    required for SO3 mitigation. There is no evidence that any
    conventional pollution control equipment could achieve the
    necessary SO3 reductions. Vectren analyzed several
    alternative technologies and fuel sources to achieve the
    necessary SO3 reductions, but that analysis focused primarily
    on the economic impact of the scenarios.
    E. Federal sulfur and nitrogen based pollutant emission
    standards. Mrs. Retherford[9] testified that Vectren received
    an NOV from the EPA alleging that Vectren failed to acquire
    Prevention of Significant Deterioration (“PSD”) construction
    permits prior to construction of the SCRs to address small
    incremental increases in incidental SO3 emissions caused by
    operation of the SCRs, and a CAA §114 Information Request
    related to the 2003 Culley Consent Decree. Vectren and the
    EPA have reached a settlement in principle to resolve the
    outstanding compliance allegations brought by the EPA in the
    9
    Angela Retherford testified as Vice President of Environmental Affairs and Corporate Sustainability at
    Vectren.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                   Page 12 of 22
    NOV and the CAA §114 Information Request that requires
    the Culley and Brown Air Projects.
    F. The likelihood of success of the proposed project. Ms.
    Fischer described the Phase 1 Technology Demonstration of
    the Brown and Culley Projects. At Brown, Black & Veatch
    used a temporary soda ash injection system, which treated
    100% of the flue gas on Unit 1. The soda ash injection
    reagent flow rate, process data, and stack gas outlet
    measurements were all collected, and the data obtained
    allowed Black & Veatch to determine the optimum amount of
    soda ash that should be injected to balance sorbent
    consumption, mercury reduction, and NsSO4 mist reduction.
    Ms. Fischer testified that at Culley, highly reactive hydrated
    lime was injected at the inlet and outlet of the particulate
    matter removal device. Black & Veatch performed the test at
    different injection rates to evaluate the effect of the amount of
    hydrated lime injection on H2SO4 mist removal. As with
    Brown, the data obtained allowed Black & Veatch to
    determine the necessary sizing of the lime injection system.
    G. The cost and feasibility of retirement of an existing electric
    generating facility. Mr. Games testified that Vectren hired
    Burns & McDonald and Black & Veatch to analyze
    alternative generation options to retrofitting Brown Units 1
    and 2 and Culley Unit 3. The analysis included both the
    variable operating costs of the proposed alternatives and the
    annual fixed charge required to recover capital costs and fixed
    operating costs under various capacity scenarios. In addition,
    the analysis considered that the Brown and Culley Units are
    base load units; so any replacement technology must be able
    to supply the necessary capacity to meet the MISO-required
    Planning Reserve Margin.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 13 of 22
    The analysis considered 20 commercial generating
    technologies, including seven natural gas options, battery
    storage, compressed air, wind, solar, hydro, nuclear, wood,
    landfill gas, and coal. Of those options, Black & Veatch
    identified two, a 200 MW, Class F natural gas fired
    generation facility and a 300 MW natural gas fired combined
    cycle generation facility, as the most practical options. The
    other options were determined to be infeasible due to cost,
    size, or environmental reasons.
    Black & Veatch compared the two replacement options to the
    retrofitting option on the basis of total customer cost and
    relative risk. The analysis was run under three separate
    market scenarios and adjusted to those scenarios for variables
    including natural gas costs and carbon costs. The analysis
    compared 21 different replacement scenarios to the retrofitting
    option, and in every scenario except one, the analysis
    demonstrated that retrofitting was the lowest cost alternative.
    The only scenario that favored replacement, was a low
    natural gas and high carbon cost scenario that showed a 2.2%
    benefit by replacing Brown Units 1 and 2 with a combined
    cycle natural gas facility.
    H. The dispatching priority for the facility utilizing CCT,
    considering direct fuel costs, revenues, and expenses of the
    utility, and environmental factors associated with
    byproducts resulting from the utilization of the CCT. Mr.
    Games testified that any changes in dispatching priority will
    depend on future regulations, fuel costs, and future load
    growth. He said that the additional variable production costs
    of using additives to reduce SO3 emissions will increase the
    cost to generate a MW of electricity, but that Black &
    Veatch’s analysis shows that replacing the Brown and Culley
    Units would be a more expensive option.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 14 of 22
    Mr. Games also testified that the Brown and Culley Projects
    will allow for the continued reuse of the fly ash from the
    Brown and Culley Units for the production of cement and
    gypsum wall board. Mr. Games said that while Vectren is not
    paid for the fly ash, the reuse is beneficial to customers
    because Vectren avoids disposal costs.
    I. Any other factors the Commission considers relevant,
    including whether the construction, implementation, and
    use of CCT is in the public’s interest. Mr. Games testified
    that Vectren cannot continue to operate the Brown and Culley
    Units without investing in additional pollution control
    equipment to comply with the NOV. Vectren has evaluated
    alternative technologies and the possibility of retiring the units
    and identified the Brown and Culley Projects as the lowest
    cost alternative. Retiring the Brown and Culley Units would
    retire 76% of Vectren’s coal-fired base load, which would
    require Vectren to construct new generation facilities to
    replace the capacity or to purchase capacity on the open
    market. Market Purchases would also place a large
    percentage of Vectren’s base load energy need outside of its
    direct control. Because the Brown and Culley Units have not
    reached the end of their useful lives, retiring them early would
    result in significant stranded costs. In addition, Vectren
    would experience stranded costs related to infrastructure in
    place to capture, store, and transport fly ash for reuse. For
    these reasons, we find that it is in the public interest for
    Vectren to install the Brown and Culley Projects.
    J. Conclusion. Based on our analysis of the factors required by
    Ind. Code § 8-1-8.7-3(b), we find that public convenience and
    necessity will be served by the use of CCT, specifically the
    Brown and Culley Projects, on Brown Units 1 and 2 and
    Culley Unit 3. In our January 28, 2015 Order in this Cause,
    we approved the estimated costs, and found that Brown Units
    1 and 2 and Culley Unit 3 will continue to utilize Indiana coal
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 15 of 22
    as their primary fuel, specifically coal [] sourced from the
    Illinois Basin. Therefore, we issue a CPCN to Vectren for the
    Brown and Culley Projects.
    
    Id. at 8-11.10
    Intervenors appeal from this order.
    Discussion & Decision
    Standard of Review
    [18]   The General Assembly created the IURC primarily as a fact-finding body with
    the technical expertise to administer the regulatory scheme devised by the
    legislature. N. Ind. Pub. Serv. Co. v. U.S. Steel Corp., 
    907 N.E.2d 1012
    , 1015 (Ind.
    2009). The IURC’s goal is to ensure that public utilities provide constant,
    reliable, and efficient service to the citizens of Indiana. 
    Id. An order
    from the
    IURC is presumed valid unless the contrary is clearly apparent. Citizens Action
    Coal. of Ind., Inc. v. N. Ind. Pub. Serv. Co., 
    485 N.E.2d 610
    , 612 (Ind. 1985).
    [19]   The standard for our review of decisions of the IURC is governed by I.C. § 8-1-
    3-1, which our courts have interpreted as providing a tiered standard of review.
    A multiple-tier standard of review is applicable to the IURC’s
    orders. A court on review must inquire whether specific findings
    exist as to all factual determinations material to the ultimate
    conclusions; whether substantial evidence within the record as a
    10
    Headings A through I directly correspond with the factors listed in I.C. § 8-1-8.7-3(b).
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                    Page 16 of 22
    whole supports the findings of fact; and whether the decision,
    ruling, or order is contrary to law.
    Vectren 
    I, 45 N.E.3d at 491
    . In applying this standard, “[w]e review the
    conclusions of ultimate facts, or mixed questions of fact and law, for their
    reasonableness, with greater deference to matters within the IURC’s expertise
    and jurisdiction.” Citizens Action Coal. of Ind., Inc. v. Duke Energy Ind., Inc., 
    16 N.E.3d 449
    , 457 (Ind. Ct. App. 2014). Additionally, “[w]e neither reweigh the
    evidence nor assess the credibility of witnesses and consider only the evidence
    most favorable to the IURC’s findings.” Ind. Gas Co., Inc. v. Ind. Fin. Auth., 
    999 N.E.2d 63
    , 66 (Ind. 2013). On matters within its jurisdiction, the IURC enjoys
    wide discretion and its findings and decision will not be lightly overridden
    simply because we might reach a different decision on the same evidence.
    Vectren 
    I, 45 N.E.3d at 491
    .
    Adequacy of Findings on Remand
    [20]   Intervenors challenge the adequacy of the IURC’s findings on remand, arguing
    that they are not adequately explained, are arbitrary and capricious, and are not
    supported by substantial evidence. Their grievance stems from the notion that
    the IURC failed to consider any evidence other than Vectren’s pre-filed direct
    testimony. Had the IURC considered the other evidence, according to
    Intervenors, it would have concluded that the long-term cost of installing
    pollution controls on the existing units would be more than the cost of building
    new natural gas plants and retiring existing coal-fired units.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 17 of 22
    [21]   Initially, we observe that the First Order remained intact after Vectren I. This
    order contained a detailed summary of the evidence presented by the parties,
    which included over 2000 pages of written testimony and exhibits and two days
    of live testimony. Although the IURC considered the voluminous evidence on
    both sides, it based its ultimate decision and findings in the First Order
    primarily on Vectren’s evidence. For example, in finding the proposed projects
    to be reasonable and necessary, the IURC expressly relied upon the evidence
    presented by Vectren, including Games’s testimony and the B & V 10-year
    model. The IURC’s reliance on the B & V model indicates that Vectren won
    the battle of the experts in the First Order.
    [22]   In Vectren I, we did not reverse the First Order. Rather, we did nothing more
    than remand for additional findings with regard to two of the proposed projects.
    We directed the IURC to make findings on the nine statutory factors listed in
    I.C. § 8-1-8.7-3(b) and balance these factors to determine whether to grant a
    CPCN. The IURC did just that.
    [23]   We cannot agree with Intervenors that, on remand, the IURC was required to
    consider the expert testimony regarding the cost models anew. Further,
    Intervenors’ assertion that Copeland abandoned his original B & V 10-year
    analysis for a “corrected analysis” at the hearing is a mischaracterization of the
    evidence. Appellants’ Brief at 21. At the hearing, Copeland steadfastly stood by
    his opinion that a 10-year analysis was more appropriate than a 20-year
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 18 of 22
    analysis.11 Further, to the extent he adjusted the assumptions used in his 10-
    year model to reflect Dr. Fisher’s assumptions, Copeland testified that he was
    “not totally in agreement” with the assumptions.12 
    Id. at 374.
    Additionally,
    Copeland testified that the revised results should “absolutely not” change
    Vectren’s conclusions on the proposed compliance plan. 
    Id. at 373.
    He noted
    that “changes in the variable costs can change the outcome very easily” and
    given the “uncertainty in the future, [he] would not think it would be prudent to
    make an $800 million fixed cost investment”. 
    Id. at 374.
    [24]   Intervenors’ arguments amount, essentially, to a claim that the IURC credited
    the wrong expert testimony. This is an improper contention on appeal, as it
    requires a reweighing of the evidence. There is substantial evidence in the
    record to support the IURC’s findings regarding the cost effectiveness of the
    proposed projects as compared to retirement of the existing units. Moreover,
    the cost analysis was not the sole basis of the IURC’s decision to issue the
    CPCN to Vectren. The IURC issued specific findings on all nine statutory
    factors as set out above, many of which had nothing to do with the cost
    11
    Copeland testified in this regard:
    [T]he original analysis was done on ten years, and I feel very confident with that given the
    uncertainty we could see in the future, and because we don’t know exactly what the future looks
    like, we felt like it was prudent to look at a ten-year analysis, and we still stand by that.
    Transcript at 377.
    12
    Regarding the addition of capacity sales to his model, Copeland testified that he did not believe it is
    appropriate to include revenue from excess capacity sales. He was then asked why he included this
    assumption in his revised model. Copeland responded, “I was responding to Dr. Fisher’s comments about
    capacity sales not being included and wanted to analyze the impact if those were added in there.” 
    Id. at 214.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                     Page 19 of 22
    analysis. Based on its consideration of all of these factors, the IURC
    determined that public convenience and necessity will be served by the use of
    CCT at Brown Units 1 and 2 and Culley Unit 3. Intervenors have failed to
    establish that the IURC abused the broad discretion granted it.
    Petition to Reopen Record
    [25]   Intervenors argue that the IURC erred by declining to reopen the record on
    remand to hear additional evidence. With their petition, Intervenors attached
    evidence purporting to show that the existing units would face higher costs than
    originally assumed and the cost to run new plants would be lower. Other
    evidence submitted indicated that the projections of a capacity deficit in the
    region were no longer accurate.
    [26]   The IURC denied the petition as follows:
    170 IAC 1-1.1-22 allows a party to move to reopen the record[13]
    “At any time after the record is closed, but before a final order is
    issued.” The Commission has already issued a final order based
    13
    In petitioning to reopen the record, the petitioner
    must set forth clearly the facts claimed to constitute grounds requiring reopening of the
    proceedings, including the following:
    (1) Material changes of fact or law alleged to have occurred since the conclusion of the hearing.
    (2) The reason or reasons such changes of fact or law could not have been reasonably foreseen
    by the moving party prior to the closing of the record.
    (3) A statement of how such changes of fact or law purportedly would affect the outcome of
    the proceeding if received into evidence.
    (4) A showing that such evidence will not be merely cumulative.
    170 Ind. Admin. Code 1-1.1-22(b). While it sets out the requirements of such a petition, 170 I.A.C. 1-
    1.1-22 does not establish a standard of review. Accordingly, we conclude that the determination of
    whether to grant or deny a petition to reopen the record is within the IURC’s sound discretion.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017                         Page 20 of 22
    on the evidentiary hearing in this Cause. Although the Court of
    Appeals remanded the final order for the Commission to
    consider the limited issue of whether a CPCN should be issued
    for the proposed soda ash and hydrated lime injection systems,
    the court did not instruct the Commission to receive additional
    evidence; nor did it bar the Commission from receiving
    additional evidence if necessary. Therefore, it is within the
    Commission’s discretion to determine whether the record should
    be reopened to receive additional evidence.
    In this case, we find that there is sufficient evidence in the
    evidentiary record to make the required findings under Ind. Code
    § 8-1-8.7-3. [Intervenors], in asserting that new evidence might
    change the original analysis, amounts to a request that the
    Commission engage in hindsight review, which we decline to do.
    Therefore, the Motion is denied.
    Appellants’ Appendix at 8.
    [27]   In its First Order, the IURC granted Vectren’s petition for approval of all the
    proposed projects. In Vectren I, this court did not reverse the First Order but
    simply remanded the case for additional findings with respect to two of the
    projects. Given the volatile utility market, the cost analyses and facts on which
    the First Order was based were sure to change over time (i.e., while the First
    Order was being appealed) but this is no reason to require the IURC to reopen
    the evidence and re-litigate the case with respect to the two remaining projects.
    [28]   Under the circumstances presented here, we conclude that the IURC did not
    abuse its discretion by denying the petition to reopen the record. There was
    ample evidence in the record from which the IURC could evaluate the statutory
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 21 of 22
    factors on remand, and thus there was no need for additional evidence. See
    Citizens Action Coal. of Ind., Inc. v. Duke Energy Ind., Inc., 
    44 N.E.3d 98
    , 110 (Ind.
    Ct. App. 2015).
    [29]   Affirmed.
    Riley, J. and Crone, J., concur.
    Court of Appeals of Indiana | Opinion 93A02-1607-EX-1637 | February 14, 2017   Page 22 of 22
    

Document Info

Docket Number: 93A02-1607-EX-1637

Citation Numbers: 70 N.E.3d 429

Filed Date: 2/14/2017

Precedential Status: Precedential

Modified Date: 1/12/2023