Michael A. Mullett and Patricia N. March v. Duke Energy Indiana, LLC, Nucor Steel-Indiana, Indiana Office of Utility Consumer Counselor ( 2018 )


Menu:
  •                                                                               FILED
    May 21 2018, 5:33 am
    CLERK
    Indiana Supreme Court
    Court of Appeals
    and Tax Court
    ATTORNEY FOR APPELLANTS                                   ATTORNEYS FOR APPELLEES
    Russell Ellis                                             Robert L. Hartley
    Indianapolis, Indiana                                     Maggie L. Smith
    Frost Brown Todd LLC
    Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Michael A. Mullett and Patricia                           May 21, 2018
    N. March,                                                 Court of Appeals Case No.
    Appellants-Intervenors,                                   93A02- 1710-EX-2468
    Appeal from the Indiana Utility
    v.                                                Regulatory Commission
    The Honorable James Atterholt,
    Duke Energy Indiana, LLC,                                 Commission Chair
    Nucor Steel-Indiana, Indiana                              Honorable Sarah Freeman
    Office of Utility Consumer                                Honorable James Huston
    Counselor,                                                Honorable Angela Weber
    Honorable David Ziegner
    Appellees (Applicant/Petitioner,
    Commissioners
    Intervenor, Statutory Party).
    Honorable David Veleta
    Senior Administrative Law Judge
    IURC Case No. 38707 FAC-113
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018                            Page 1 of 11
    Bradford, Judge.
    Case Summary
    [1]   Appellee Duke Energy Indiana, LLC (“Duke”) and Benton County Wind Farm
    (the “Wind Farm”) entered into a contract under which Duke agreed to buy
    power from the Wind Farm. In 2013, a dispute arose after Duke failed to buy
    energy from the Wind Farm. The Wind Farm filed suit claiming that Duke
    owed it money for lost production under the parties’ contract. The parties
    eventually settled and Duke went to the Indiana Utility Regulatory
    Commission (the “Commission”) seeking to recover its costs from ratepayers.
    Appellants Michael A. Mullett and Patricia N. March (the “Appellants”)
    intervened in the proceeding and objected to Duke’s request. After a hearing on
    the matter, the Commission approved Duke’s request to recover the costs from
    its ratepayers over a twelve-month period.
    [2]   Appellants now appeal arguing that the Commission’s order is contrary to law
    because the damages are “liquidated” and “hypothetical” and it amounts to
    impermissible retroactive ratemaking. Finding that substantial evidence
    supports the Commission’s order and no other error, we affirm.
    Facts and Procedural History
    [3]   In 2006, Duke and the Wind Farm entered into a Renewable Wind Energy
    Power Purchase Agreement (“PPA”) in which Duke agreed to purchase a
    portion of the energy generated by the Wind Farm. After purchasing the
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018   Page 2 of 11
    energy from the Wind Farm, Duke would immediately sell it into the
    Midcontinent Independent System Operator (“MISO”) wholesale energy
    market. The Indiana Utility Regulatory Commission (“the Commission”)
    approved the PPA in its entirety in 2006, concluding that “the terms of the
    Wind [PPA were] reasonable.” Duke App. Vol. II, p. 17.
    [4]   The Commission also recognized that Duke would be incurring significant costs
    in connection with the PPA. Consequently, in order to further the
    Commission’s policy of encouraging the development of renewable resources,
    the Commission authorized Duke to recover all of its PPA costs from
    ratepayers for the entire twenty-year term:
    [T]he Commission finds that Duke Energy Indiana should be
    authorized to recover the Wind [PPA] costs provided for in the
    contract for the full 20 year term of that contract[.]
    Duke App. Vol. II, p. 19.
    [5]   Following changes to certain rules and regulations in 2013, a dispute arose
    regarding the extent of Duke’s contractual obligations to the Wind Farm. Duke
    believed that based upon the parties’ contract, it was only required to accept
    and pay for energy that the Wind Farm generated and delivered to Duke. The
    Wind Farm, however, interpreted the contract to mean that Duke had to pay
    for lost production in addition to the power it delivered to Duke.
    [6]   The Wind Farm sued Duke in federal court to resolve the disputed contract
    interpretation. The federal district court agreed with Duke’s interpretation and
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018   Page 3 of 11
    granted Duke’s motion for summary judgement in 2015. The Wind Farm
    appealed to the Seventh Circuit, which agreed with the Wind Farm’s
    interpretation, reversed the district court’s ruling, and remanded with
    instructions for a determination of damages, i.e. how much Duke owed the
    Wind Farm for lost production.
    [7]       The Wind Farm and Duke entered into settlement negotiations. At the
    conclusion of the settlement negotiations, the parties agreed on $29 million,
    which Duke believed was approximately equal to what it would have cost Duke
    and its ratepayers had the parties agreed with the Wind Farm’s contact
    interpretation at the outset.
    [8]   Duke reported to the Commission in its Fuel Cost Adjustment (“FAC”) filing
    on July 27, 2017, that the dispute between Duke and the Wind Farm had
    settled.1 In its report, Duke also indicated its intention to recover the lost
    production costs from ratepayers over a six-month period.2 The Office of
    Utility Consumer Counselor (the “OUCC”) had no objection to Duke’s
    recovery of the $29 million as costs Duke incurred under the PPA, but
    requested that the recovery be spread over a twelve-month period rather than
    the six-month period Duke had proposed. Duke agreed to spreading the
    recovery out over a twelve-month period. On September 21, 2017, Duke filed
    1
    Duke kept the Commission updated on the status of the dispute throughout the litigation and settlement
    process with quarterly FAC filings.
    2
    Duke had repeatedly indicated that this was a possibility in its previous sixteen filings with the Commission.
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018                               Page 4 of 11
    its Proposed Form of Order in which it proposed to recover the $29 million
    through rates over a twelve-month period.
    [9]    Meanwhile, Appellants intervened in this proceeding as ratepayers and filed a
    Brief in Opposition to Approval of Liquidated Damages Payment as an
    Expense Recoverable through Rates as their legal objection to Duke’s Proposed
    Order. Thereafter, Duke filed its Response to Appellant’s Brief in Opposition.
    On September 27, 2017, the Commission entered its final order approving
    proposed Duke’s rate recovery over a twelve-month period.
    Discussion and Decision
    [10]   The Indiana Utility Regulatory Commission was created by the General
    Assembly “primarily as a fact-finding body with the technical expertise to
    administer the regulatory scheme devised by the legislature.” Ind. Gas Co. v.
    Ind. Fin. Auth., 
    999 N.E.2d 63
    , 65 (Ind. 2013) (internal quotation removed).
    The Commission’s “goal is to ensure that public utilities provide constant,
    reliable, and efficient service to the citizens of Indiana.” Citizens Action Coalition
    of Ind., Inc. V. S. Ind. Gas and Elec. Co., 
    70 N.E.3d 429
    , 438 (Ind. Ct. App. 2017).
    An order issued by the Commission is presumed valid unless the contrary is
    clearly apparent. 
    Id. [11] The
    standard for our review of decisions of the Commission is governed by
    Indiana Code section 8-1-3-1, which the Indiana Supreme Court has interpreted
    as providing a tiered standard of review.
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018      Page 5 of 11
    A multiple-tier standard of review is applicable to the IURC’s
    orders. A court on review must inquire whether specific findings
    exist as to all factual determinations material to the ultimate
    conclusions; whether substantial evidence within the record as a
    whole supports the findings of fact; and whether the decision,
    ruling, or order is contrary to law.
    Citizens Action Coal. of Ind., Inc. v. Pub. Serv. Co. of Ind., 
    612 N.E.2d 199
    , 201 (Ind.
    Ct. App. 1993) (citations omitted). In applying this standard, “[w]e review the
    conclusions of ultimate facts, or mixed questions of fact and law, for their
    reasonableness, with greater deference to matters within the [Commission’s]
    expertise and jurisdiction.” Citizens Action Coal. of Ind., Inc. v. Duke Energy Ind.,
    Inc., 
    16 N.E.3d 449
    , 457 (Ind. Ct. App. 2014). Additionally, “[w]e neither
    reweigh the evidence nor asses the credibility of witnesses and consider only the
    evidence most favorable to the [Commission’s] findings.” Ind. Gas Co., Inc. v.
    Ind. Fin. Auth., 
    999 N.E.2d 63
    , 66 (Ind. 2013). “On matters within its
    jurisdiction, the [Commission] enjoys wide discretion and its findings and
    decision will not be lightly overridden simply because we might reach a
    different decision on the same evidence.” Citizens Action Coal. of Ind., Inc. v. S.
    Ind. Gas & Elec. Co., 
    70 N.E.3d 429
    , 439 (Ind. Ct. App. 2017).
    I. Recovery from Ratepayers
    [12]   Appellants make several arguments as to why the Commission’s order is
    contrary to law which we have consolidated and restated. First, Appellants
    argue that the Commission’s order was contrary to law because the damages
    were “liquidated” and “hypothetical.” Appellants also argue that the
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018        Page 6 of 11
    Commission acted contrary to law when it approved Duke’s recovery from
    ratepayers because it amounts to impermissible retroactive ratemaking.
    A. Liquidated “Hypothetical” Damages
    [13]   The Commission approved the PPA between Duke and the Wind Farm in its
    entirety in 2006. The PPA detailed, among other things, procedures for the sale
    and purchase of energy and a calculation of damages if Duke failed to purchase
    energy from the Wind Farm. The Commission also approved full recovery
    from ratepayers of all costs that Duke incurred from the PPA over its entire
    twenty-year term.
    [14]   In early 2013, after Duke failed to purchase energy from the Wind Farm, it
    became apparent that the two parties differed on their interpretations of the
    contract. This disagreement over whether Duke owed the Wind Farm for lost
    production led to the Wind Farm filing suit in federal court. During the course
    of the litigation, Duke kept the Commission updated in each of its quarterly
    FAC filings. Duke also was clear that when the dispute was resolved, it would
    seek to recover from ratepayers any amount that Duke eventually paid to the
    Wind Farm.
    [15]   Once the dispute settled, Duke reported in a FAC filing on July 27, 2017, that
    the dispute had been resolved and it now sought to recover the costs it incurred
    under the PPA. The Commission was presented with evidence that the
    “settlement amount is no more than customers would have paid had a different
    offer been submitted to MISO from March 2013 through June 2017, and is less
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018   Page 7 of 11
    than what potentially could have been awarded has a settlement not been
    reached.” Appellants’ App. Vol. II, p. 13. The Commission subsequently
    found that “[t]he evidence of record demonstrates that the [Wind Farm]
    settlement is in the best interest of customers and the costs are reasonable for
    what is owed to [the Wind Farm] under the Commission-approved [PPA]”.
    Appellants’ App. Vol. II, p. 13. Due to the fact that the lost production costs
    arose from the PPA, the Commission found that Duke was permitted to recover
    the $29 million from its ratepayers.
    [16]   As for the term “liquidated damages,” Appellants have not cited to any cases to
    support the proposition that the term “liquidated damages” in a contract
    precludes Duke’s recovery from ratepayers. Furthermore, there is no authority
    to support Appellants’ claim that the damages amount is purely hypothetical
    and therefore unrecoverable from ratepayers.
    [17]   The Seventh Circuit found that Duke was obligated under the PPA to “pay for
    power not taken.” Benton Cty. Wind Farm LLC v. Duke Energy Ind., Inc., 
    843 F.3d 298
    , 303 (7th Cir. 2016). The parties reached a “settlement amount [that]
    is no more than customers would have had had a different offer been submitted
    to MISO from March 2013 through June 2017, and is less than what potentially
    could have been awarded had a settlement not been reached.” Appellants’
    App. Vol. II, p. 13. The Commission subsequently found that the “7th Circuit
    decision interpreting the terms of the contract does not affect our previous
    approval of this contract.” Appellants’ App. Vol. II, p. 13.
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018    Page 8 of 11
    [18]   The evidence of record demonstrates that the “[Wind Farm] settlement is in the
    best interest of customers and the costs are reasonable for what is owed to [the
    Wind Farm] under the Commission-approved [PPA].” Appellants’ App. Vol.
    II, p. 13. There is also evidence in the record that the OUCC—which
    represents ratepayers, consumers, and members of the general public—
    appeared and had no objection to the proposed recovery except that it be spread
    out over a twelve-month period. Specifically, the representative for the OUCC
    testified that “the Commission has approved longer recovery times for similar
    settlements as an acceptable way to recover these costs while mitigating the
    impact on ratepayers.” Appellants’ App. Vol. II, p. 121. The Commission was
    also presented with evidence from Duke’s Director of Fuels & Systems
    Optimization that the amount paid in the settlement is materially equivalent to
    what the ratepayers would have paid had Duke agreed with the Wind Farm’s
    interpretation of the PPA at the outset. The evidence in the record readily
    supports the Commission’s decision to authorize Duke’s recovery from
    ratepayers.
    B.      Retroactive Ratemaking
    [19]   Appellants also argue that the Commission’s order is contrary to law because
    allowing Duke to recover the costs amounts to impermissible retroactive
    ratemaking. The fact that the damages arose from a past dispute regarding a
    contract interpretation does not automatically make the Commission’s order
    contrary to law. This appeal arose out of an FAC proceeding, not a rate case.
    Similar to a Gas Cost Adjustment proceeding, the prohibition against
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018   Page 9 of 11
    retroactive ratemaking does not apply because, in both, the rates that are set are
    subject to subsequent reconciliation after historical costs have become known.
    See Ind. Gas Co., Inc. v. Office of Utility Consumer Counselor, 
    575 N.E.2d 1044
    (Ind.
    Ct. App. 1991).
    [20]   Moreover, the Commission’s decision is consistent with its decisions in similar
    disputes involving Indianapolis Power and Light (“IPL”) and Northern Indiana
    Public Service Company (“NIPSCO”). In both proceedings, IPL and NIPSCO
    were involved in disputes regarding their wind farm power purchase agreements
    and were seeking to recover lost production costs from ratepayers. Based on
    how these proceedings were handled by the Commission, it appears that the
    Commission prefers that utilities defer seeking recovery from their ratepayers
    until the dispute is resolved and the full amount is known.
    [21]   In accordance with the Commission’s clear preference to defer payment until a
    dispute is settled, Duke kept the Commission updated throughout the course of
    the litigation. Specifically, Duke consistently advised the Commission and the
    parties throughout the litigation and settlement process that future
    reconciliation by Duke to recover the costs may be necessary.3 When the cost
    incurred became known and the dispute was resolved, Duke provided the
    Commission with the new information in an FAC filing.
    3
    Duke repeatedly indicated in sixteen filings (FAC-97–FAC-112) that it would seek to recover costs under
    the PPA.
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018                        Page 10 of 11
    [22]   After reviewing the record, there is no indication that any of the parties or the
    Commission thought Duke would be forfeiting its right to recover the deferred
    costs in a future FAC proceeding nor is there any evidence that this deferral was
    improper. In fact, based on proceedings with other utilities, it appears that
    Duke acted in accordance with the Commission’s preferences for such matters.
    The Commission has the expertise to analyze and weigh the evidence in this
    case, and, after our review of the record, we conclude that there is substantial
    evidence support its decision to approve Duke’s recovery from ratepayers.
    [23]   The judgment of the Commission is affirmed.
    Baker, J., and Kirsch, J., concur.
    Court of Appeals of Indiana | Opinion 93A02-1710-EX-2468| May 21, 2018   Page 11 of 11
    

Document Info

Docket Number: 93A02-1710-EX-2468

Judges: Bradford

Filed Date: 5/21/2018

Precedential Status: Precedential

Modified Date: 10/19/2024