Ryan Lynch v. Patrick Johnson (mem. dec.) ( 2020 )


Menu:
  • MEMORANDUM DECISION
    Pursuant to Ind. Appellate Rule 65(D),
    this Memorandum Decision shall not be                                     FILED
    regarded as precedent or cited before any                             Nov 02 2020, 8:43 am
    court except for the purpose of establishing
    CLERK
    the defense of res judicata, collateral                               Indiana Supreme Court
    Court of Appeals
    estoppel, or the law of the case.                                          and Tax Court
    ATTORNEYS FOR APPELLANT
    Christopher P. Jeter
    Erica Guernsey
    Fishers, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Ryan Lynch,                                              November 2, 2020
    Appellant-Defendant/Counterclaimant,                     Court of Appeals Case No.
    20A-SC-355
    v.                                               Appeal from the Hamilton
    Superior Court
    Patrick Johnson,                                         The Honorable Gail Z. Bardach,
    Appellee-Plaintiff/Counter-Defendant.                    Judge
    The Honorable Darren J. Murphy,
    Magistrate
    Trial Court Cause No.
    29D06-1902-SC-1379
    Altice, Judge.
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020               Page 1 of 10
    Case Summary
    [1]   Patrick Johnson brought a small claims action against Ryan Lynch, asserting
    that Lynch did not pay him for his work in designing a website for Lynch’s
    company. Lynch counterclaimed, asserting that Johnson’s work on a prior
    project involving a mobile application was incomplete. The small claims court
    found in favor of Johnson on his claim and denied relief to Lynch on his
    counterclaim.
    [2]   We affirm.
    Facts & Procedural History
    [3]   Lynch is the founder and director of a non-profit organization called
    Indianapolis Ace Academy (Ace), 1 which informs and educates youth about
    aviation. Johnson is a software designer. In 2017, Lynch hired Johnson to
    design a mobile phone application for Ace (the mobile app project), and
    thereafter he hired Johnson to design a website for a frozen yogurt shop in
    which Lynch is an owner. Lynch paid Johnson in full for both of those
    projects.
    [4]   Thereafter, in or around May 2018, Lynch hired Johnson to design an updated
    website for Ace (the Ace website project). The parties did not have a written
    contract for the Ace website project, but they did exchange emails about it. On
    1
    The organization is now known as NARY Foundation.
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 2 of 10
    June 5, 2018, Johnson’s project manager, Colleen Zana, emailed Lynch on
    behalf of Johnson stating that the Ace website project was estimated to require
    thirty hours of work over the course of four weeks. On June 7, Lynch emailed
    Zana advising that he wanted to proceed and asking her to schedule the project.
    On June 30, 2018, Johnson emailed Lynch to let him know that “[t]he new site
    design is done,” and Johnson attached a link to the website. Exhibits Vol. at 8.
    Johnson added, “There are still a few things I might want to tweak” but asked
    Lynch to let him know “if this looks good for now and I can make it live.” Id.
    Lynch replied to Johnson by email about half an hour later, stating “I love the
    new layout” and calling it “[o]utstanding,” and Lynch directed Johnson to “go
    live” with it. Id.
    [5]   On July 3, 2018, Johnson sent an invoice to Lynch for the Ace website project
    reflecting 30 hours of work at $90 per hour, for a total of $2700. The invoice
    indicated payment was due August 3, 2018, and “overdue payments are subject
    to interest charge.” Id. at 13. On September 10, 2018, Lynch texted Johnson,
    apologizing for not getting back with him and stating, “I owe you some money
    from the websites and [am] not ignoring you.” Id. at 11. Lynch explained that
    he had not yet received expected grant money that he had planned to use to pay
    for the Ace website project and offered, “Can I make payments (out of pocket)
    personally to you until I can pay it off?” Id. Lynch did not pay Johnson.
    [6]   On the afternoon of December 10, 2018, Zana emailed Lynch stating that the
    Ace website project bill had not been paid and that “we must insist on a full
    payment” of the $2700 invoice by December 31. Id. at 22. Lynch responded
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 3 of 10
    that he had been waiting “on sponsorship funding to come in,” to which Zana
    responded that Johnson had already extended “a very gracious time frame
    without interest” and that there “was never an agreement that [Johnson] . . .
    would wait . . . for you to receive [] funds from another source in order to pay
    [Johnson] for his services.” Id. at 20-21. Zana offered that Johnson was willing
    to accept payment of half of the invoice by the end of December and the other
    half by the end of January 2019. Lynch replied that he was in contact with his
    legal team.
    [7]   Later that same day, Johnson advised Lynch that his legal team should contact
    Johnson directly and that he “went ahead and removed [his] work from
    [Lynch’s] website” but would “be happy to implement it back when the
    payment is made in full.” Id. at 19. The two exchanged further emails. Lynch
    told Johnson that he had already informed Johnson that Ace expected to
    receive end-of-year funding and that Johnson had taken “illegal” and
    “unauthorized” actions in changing the Ace website. Appellant’s Appendix at 29.
    Johnson replied that the only work removed was “the work that has not been
    paid for” and offered to “reinstate the design I have done for your website on
    the basis of good faith if you agree to have the invoice paid in full by the end of
    January 2019[.]” Exhibits Vol. at 18.
    [8]   On Tuesday, February 6, 2019, Johnson emailed Lynch to advise that, if he did
    not hear back from Lynch with arrangements to pay, he would be filing a legal
    action later that week. On February 8, 2019, Johnson filed a small claims
    complaint for “non payment for website design and build for Ace Academy,”
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 4 of 10
    seeking judgment against Lynch for $4050, comprised of the $2700 invoice and
    $1350 in expenses incurred for the collection of the amount owed. Appellant’s
    Appendix at 21.
    [9]    On February 27, Lynch sent an email to Johnson stating that the Ace website
    project “is NOT done” and that Johnson had inappropriately removed it, which
    affected sales and interrupted operations. Exhibits Vol. at 16 (emphasis in
    original). On March 4, 2019, Johnson emailed Lynch, advising that he had
    filed a small claims action but offering to dismiss the action if Lynch would
    “like to go ahead and submit payment for the money you owe by the end of this
    week[,]” which Johnson stated was $2700 per the invoice and $1350 for time,
    interest, and the money he was “having to spend to get the money that you
    owe[.]” Id. at 15.
    [10]   On June 21, 2019, Lynch filed a small claims counterclaim. The counterclaim
    asserted that in June 2017, Lynch paid Johnson $5400 for the mobile app
    project, but the app was “never [] created.” Appellant’s Appendix at 46. Lynch
    requested return of the $5400 plus legal fees from Johnson.
    [11]   After a series of reset hearings for a variety of reasons, the court held a hearing
    on January 9, 2020. Both parties were present in person; Lynch was
    represented by counsel, and Johnson was not.
    [12]   Johnson testified that he and Lynch agreed “via email and phone” that Johnson
    would design the Ace website. Transcript at 7. Johnson further testified that
    “[Lynch] specifically requested over the phone to not have a contract on this
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 5 of 10
    one” and Johnson agreed because he “trusted him[.]” Id. at 13. Johnson
    testified that the agreed rate was $90 per hour, which Johnson stated was a
    discount from his normal rate of $120 per hour, and that he had estimated 30
    hours, noting “it actually took more . . . but I decided to keep true to the
    estimate.” Id. at 6.
    [13]   Johnson also described his unsuccessful attempts to collect the money from
    Lynch and presented the court with the emails described above. Johnson
    maintained that all the projects he did for Lynch were completed and worked
    properly. Johnson explained that he did not “deactivate” the Ace website but,
    rather, “simply removed [his] work from the website.” Id. at 8. He stated that
    the additional $1350 requested in his claim was for interest and his time and
    effort expended to collect the fee for the Ace website project, but told the court,
    “I’d be happy with the $2700 at this point.” Id. at 6.
    [14]   Lynch testified that, at some point after September 2018, he had asked Johnson
    to fix “some glitches” in the website, and Johnson said he would do so but
    never did, instead removing his work from the Ace website. Id. at 17. Lynch
    stated that this removal caused him to not have access to the Ace website and
    required him to expend money to start a new website and lose sales. Johnson
    responded that there were no glitches as claimed, but recalled that Lynch had at
    some point after completion asked Johnson to add an “additional feature,”
    namely a photo gallery, which Johnson testified he “was going to provide at no
    additional cost” if Lynch had paid him. Id. at 28.
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 6 of 10
    [15]   With regard to the counterclaim, Lynch testified that Johnson never completed
    the mobile app project, maintaining, “I have no app[,]” and asking for return of
    the $5400 he paid Johnson in 2017. Id. at 17. Johnson’s position was twofold.
    First, Johnson stated that the $5400 that Lynch was seeking in his counterclaim
    was for “a separate project that was for an application design” and was “totally
    separate from this [Ace] website project.” Id. at 3. Second, Johnson asserted
    that he was hired by Lynch to design the mobile app, along with a working
    prototype, and that he did so (and was paid in full), and that he was not hired to
    develop a working mobile app, which is considerably more expensive and
    beyond his skills. He testified, “I don’t know how to develop mobile apps so
    that was never an agreement, I would never agree to develop a mobile app.” Id.
    at 24.
    [16]   The small claims court took the matter under advisement and issued an order
    on January 14, 2020, finding in favor of Johnson on his complaint and denying
    relief to Lynch on his counterclaim. The court awarded Johnson damages of
    $2700, the amount of the original invoice. Lynch now appeals.
    Discussion & Decision
    [17]   Initially, we observe that Johnson did not file an appellee’s brief. Under such a
    circumstance, we do not undertake to develop an argument on his behalf, and
    we may reverse upon a prima facie showing of reversible error. Heartland
    Crossing Found., Inc. v. Dotlich, 
    976 N.E.2d 760
    , 762 (Ind. Ct. App. 2012). Prima
    facie error, in this context, means “at first sight, on first appearance, or on the
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 7 of 10
    face [of] it.” 
    Id.
     (quoting Carter v. Grace Whitney Props., 
    939 N.E.2d 630
    , 633-34
    (Ind. Ct. App. 2010)). “This standard, however, ‘does not relieve us of our
    obligation to correctly apply the law to the facts in the record in order to
    determine whether reversal is required.’” WindGate Properties, LLC v. Sanders,
    
    93 N.E.3d 809
    , 813 (Ind. Ct. App. 2018) (quoting Wharton v. State, 
    42 N.E.3d 539
    , 541 (Ind. Ct. App. 2015)).
    [18]   The burden of proof in a small claims civil suit is the same as it would be had
    the case been filed in a general trial court. Harris v. Lafayette LIHTC, LP, 
    85 N.E.3d 871
    , 876 (Ind. Ct. App. 2017). We will affirm a judgment in favor of
    the party bearing the burden of proof “if the evidence was such that from it a
    reasonable trier of fact could conclude that the elements of the party’s claim
    were established by a preponderance of evidence.” 
    Id.
     Our standard of review
    in small claims cases is particularly deferential in order to preserve the speedy
    and informal process for small claims. Dotlich, 976 N.E.2d at 762. We neither
    reweigh the evidence nor assess the credibility of the witnesses. Id. We will not
    set aside the findings or judgment unless clearly erroneous. Id.
    [19]   Here, the small claims court entered judgment in favor of Johnson in the
    amount of $2700. Lynch maintains that the trial court’s decision was in error
    because there was no enforceable contract between the parties as an essential
    element was missing, namely, a meeting of the minds as to the terms of their
    agreement, including “the actual service to be received, price, scope of
    agreement, and more.” Appellant’s Brief at 6. He argues this lack of a meeting
    of the minds is evidenced by the parties’ “conflicting testimony” that he urges
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 8 of 10
    “laid bare their lack of understanding as to what each was contracting for or to
    do.” Id. at 7. We disagree and find no error with the small claims court’s
    decision.
    [20]   The evidence reveals that Lynch had worked with Johnson on two projects and
    thereafter hired Johnson in early June 2018 for the Ace website project.
    Johnson provided Lynch with an estimate of the number of hours that would be
    required to “build” the website, and Lynch directed Johnson to “go ahead”
    with it. Exhibits Vol. at 6, 9. On June 30, when Johnson sent Lynch a link to
    the design, Lynch responded that he “love[d]” it and wanted Johnson to go
    ahead and “go live” with it. Id. at 8. There was no mention by Lynch that he
    was in any way dissatisfied or that it was not complete. Lynch texted Johnson
    several months later, in September, acknowledging that he owed Johnson
    money and offering to personally pay him; he did not indicate dissatisfaction
    with the Ace website or assert that it was in some way incomplete.
    [21]   Johnson repeatedly asked for payment, and eventually removed content he had
    created from the Ace website in December 2018. More than two months later,
    on February 27, 2019, Lynch indicated he was not going to pay and claimed
    that the website was “NOT done[.]” Id. at 16. Lynch’s testimony, while stating
    that “glitches” existed in the Ace website, did not specifically identify what
    those were. Transcript at 17. Contrary to Lynch’s claim, the facts do not reflect
    a lack of agreement; they reflect that Lynch, who had failed to pay for months,
    was angry that Johnson had removed the content from the Ace website. We
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 9 of 10
    find that the evidence most favorable to the judgment supports the small claim’s
    court’s conclusion that Lynch owes Johnson $2700 for the Ace website project.
    [22]   As to Lynch’s counterclaim, the evidence was that Johnson was hired for the
    mobile app project during or before 2017 and was paid in full ($5400) in June
    2017. Lynch at no time after making payment expressed that he did not receive
    what he hired Johnson to create. In fact, Lynch chose to hire Johnson for the
    Ace website project a year later; from this, the court could reasonably infer that
    Lynch was satisfied with Johnson’s work on the mobile app project. It was not
    until June 2019, when Lynch filed his counterclaim, that he asserted the app
    was “never [] created” and that he did not receive $5400 worth of services from
    Johnson. Appellant’s Appendix at 46. At trial, Lynch suggested that all he got for
    his money was “a picture of an app,” but Johnson testified that he produced a
    design along with a working “fully clickable” prototype – not just a picture – for
    Lynch to provide to another party to use in developing an app, should Lynch
    desire to do so. Transcript at 15, 31. The trial court weighed the credibility of
    the witnesses and declined to find in favor of Lynch on his counterclaim. We
    find no error with the court’s decision.
    [23]   The court’s judgment is not clearly erroneous.
    [24]   Judgment affirmed.
    Riley, J. and May, J., concur.
    Court of Appeals of Indiana | Memorandum Decision 20A-SC-355 | November 2, 2020   Page 10 of 10
    

Document Info

Docket Number: 20A-SC-355

Filed Date: 11/2/2020

Precedential Status: Precedential

Modified Date: 11/2/2020