Facility Maintenance USA, LLC v. Brown Sprinkler Corporation (mem. dec.) ( 2020 )


Menu:
  •       MEMORANDUM DECISION
    Pursuant to Ind. Appellate Rule 65(D),
    this Memorandum Decision shall not be                                      FILED
    regarded as precedent or cited before any                             Nov 04 2020, 8:36 am
    court except for the purpose of establishing                               CLERK
    Indiana Supreme Court
    the defense of res judicata, collateral                                   Court of Appeals
    and Tax Court
    estoppel, or the law of the case.
    ATTORNEY FOR APPELLANT                                   ATTORNEY FOR APPELLEE
    Christopher J. McElwee                                   Kevin L. Moyer
    Monday McElwee Albright                                  Moyer Law Firm
    Indianapolis, Indiana                                    Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    Facility Maintenance USA,                                November 4, 2020
    LLC,                                                     Court of Appeals Case No.
    Appellant-Defendant,                                     19A-SC-2827
    Appeal from the
    v.                                               Marion Small Claims Court
    The Honorable
    Brown Sprinkler Corporation,                             Kimberly J. Bacon, Judge
    Appellee-Plaintiff                                       Trial Court Cause No.
    49K03-1904-SC-1882
    Vaidik, Judge.
    Case Summary
    [1]   Facility Maintenance USA, LLC, contracted for Brown Sprinkler Corporation
    to install a sprinkler system in a commercial building. However, Facility
    Court of Appeals of Indiana | Memorandum Decision 19A-SC-2827 | November 4, 2020               Page 1 of 5
    Maintenance later refused to pay Brown Sprinkler the final $7,000 owed,
    arguing Brown Sprinkler breached the contract. Brown Sprinkler then sued in
    small-claims court, and the court found for Brown Sprinkler. We affirm.
    Facts and Procedural History
    [2]   In July 2018, Facility Maintenance contracted for Brown Sprinkler to design
    and install a sprinkler system at a commercial building on the northeast side of
    Indianapolis for $45,400. The contract stated Brown Sprinkler was to “comply
    with local state and city building codes[.]” Ex. p. 4. Brown Sprinkler installed
    the system in compliance with a plan approved by the City of Indianapolis and
    the State of Indiana. However, when the project was almost complete, the
    Indianapolis Fire Department asked Brown Sprinkler to relocate the fire-
    department connection (FDC), despite the original FDC location being
    “accessible by all of the things [] the fire code require[d].” Tr. p. 32. The fire
    department granted a “release based on the new location of the FDC.” Ex. p.
    42.
    [3]   Brown Sprinkler sent Facility Maintenance a change order stating Brown
    Sprinkler would relocate the FDC for an additional $2,944.15. Facility
    Maintenance did not sign the change order because it believed the relocation
    “was part of the original deal.” Tr. p. 21. Without a signed change order,
    Brown Sprinkler did not relocate the FDC. Facility Maintenance refused to pay
    Brown Sprinkler the final $7,000 of the $45,400 owed under the July 2018
    contract, arguing Brown Sprinkler was required under that contract to relocate
    Court of Appeals of Indiana | Memorandum Decision 19A-SC-2827 | November 4, 2020   Page 2 of 5
    the FDC at no additional cost. Brown Sprinkler then filed a small-claims action
    against Facility Maintenance for the $7,000 owed under the contract. At the
    hearing, Brown Sprinkler argued relocating the FDC was not required under
    the July 2018 contract, it had completed all work required under the July 2018
    contract, and Facility Maintenance was in breach for the $7,000 owed. Facility
    Maintenance argued the relocation of the FDC was required under the July
    2018 contract, and therefore Brown Sprinkler breached by not completing the
    relocation at no additional cost.
    [4]   The court took the matter under advisement and later issued a judgment for
    Brown Sprinkler and against Facility Maintenance for $7,000 plus court costs.
    [5]   Facility Maintenance now appeals.
    Discussion and Decision
    [6]   Facility Maintenance appeals the small-claims court’s judgment in favor of
    Brown Sprinkler. Small-claims actions involve informal trials with the sole
    objective of dispensing speedy justice between the parties according to the rules
    of substantive law. Lae v. Householder, 
    789 N.E.2d 481
    , 483 (Ind. 2003). We will
    reverse only upon clear error. Kalwitz v. Kalwitz, 
    934 N.E.2d 741
    , 748 (Ind. Ct.
    App. 2010), trans. denied. We will neither reweigh the evidence nor assess
    witness credibility and will consider only the evidence most favorable to the
    judgment. 
    Id.
     But this deferential standard does not apply to the substantive
    rules of law, which are reviewed de novo just as they are in appeals from a
    Court of Appeals of Indiana | Memorandum Decision 19A-SC-2827 | November 4, 2020   Page 3 of 5
    court of general jurisdiction. Lae, 789 N.E.2d at 483. The issue in this case turns
    on the meaning of the parties’ July 2018 contract, which is a pure question of
    law and is reviewed de novo. Trinity Homes, LLC v. Fang, 
    848 N.E.2d 1065
    ,
    1068 (Ind. 2006). When a contract is clear and unambiguous, the language
    must be given its plain meaning. Tippecanoe Valley Sch. Corp. v. Landis, 
    698 N.E.2d 1218
    , 1221 (Ind. Ct. App. 1998), trans. denied.
    [7]   Facility Maintenance argues Brown Sprinkler breached the contract because the
    suppression system “was to be installed pursuant to all local codes, which
    included the fire department’s release of the FDC.” Appellant’s Br. p. 7.
    However, the contract contains no mention of the fire department’s approval or
    “release,” requiring only compliance with “local state and city building
    codes[.]” Ex. p. 4. The plain meaning of the term “building code” does not
    include a fire department’s “release,” and Facility Maintenance fails to offer
    evidence or legal authority suggesting the fire department’s release is a code
    requirement. And tellingly, Facility Maintenance cites no code provision the
    current FDC location allegedly violates. In contrast, Brown Sprinkler testified
    repeatedly that the original design and location of the FDC was code
    compliant, as the original location made the FDC “accessible by all of the
    things [] the fire code requires.” Tr. p. 32. Nonetheless, the fire department
    could request a relocation because it has the authority to “throw[] out” the
    codebook and “ask for anything[.]” Id. at 31. Because the contract required only
    code compliance, and Brown Sprinkler offered evidence all their work complied
    Court of Appeals of Indiana | Memorandum Decision 19A-SC-2827 | November 4, 2020   Page 4 of 5
    with the code, it was reasonable for the small-claims court to conclude that the
    relocation of the FDC was not covered under the contract.
    [8]   Based on this evidence, the judgment for Brown Sprinkler is not clearly
    erroneous.
    [9]   Affirmed.
    Bailey, J., and Weissmann, J., concur.
    Court of Appeals of Indiana | Memorandum Decision 19A-SC-2827 | November 4, 2020   Page 5 of 5
    

Document Info

Docket Number: 19A-SC-2827

Filed Date: 11/4/2020

Precedential Status: Precedential

Modified Date: 11/4/2020