Jana Stacy v. ASI Select Insurance Corporation ( 2024 )


Menu:
  •                                             IN THE
    Court of Appeals of Indiana
    FILED
    Jana Stacy,                       Aug 26 2024, 9:19 am
    CLERK
    Appellant/Cross-Appellee-Plaintiff              Indiana Supreme Court
    Court of Appeals
    and Tax Court
    v.
    ASI Select Insurance Corp., and United Dynamics, Inc.,
    Appellees/Cross-Appellants-Defendants
    August 26, 2024
    Court of Appeals Case No.
    23A-CT-2529
    Appeal from the Floyd Circuit Court
    The Honorable Justin B. Brown, Judge
    Trial Court Cause No.
    22C01-2102-CT-281
    Opinion by Judge Riley
    Judges Kenworthy and Felix concur.
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024   Page 1 of 26
    Riley, Judge.
    STATEMENT OF THE CASE
    [1]   In this consolidated appeal, Appellant/Cross-Appellee – Plaintiff, Jana Stacy
    (Stacy), appeals the trial court’s summary judgment in favor of Appellee –
    Defendant, ASI Select Insurance Corp. (ASI), on Stacy’s breach of contract
    claim. Additionally, on interlocutory appeal, Appellee/Cross-Appellant –
    Defendant, United Dynamics, Inc. (UDI), appeals the trial court’s denial of its
    motion for summary judgment, which concluded that there is a genuine issue of
    material fact that UDI’s work was negligently completed.
    [2]   We affirm in part and reverse in part.
    ISSUES
    [3]   In her appeal against ASI, Stacy presents this court with two issues, one of
    which we find dispositive and which we restate as follows:
    Whether a genuine issue of material fact exists as to whether
    Stacy failed to timely notify ASI of the damage resulting from
    UDI’s work; and
    [4]   In its interlocutory appeal, UDI presents this court with four issues, one of
    which we find dispositive and restate as:
    Whether the trial court erred, as a matter of law, by concluding
    that the relationship between UDI and Stacy should have been
    governed by the Indiana Home Improvement Contract Act
    (HICA) and not by the foreseeability doctrine as clarified by our
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024         Page 2 of 26
    Indiana Supreme Court’s holding in U.S. Automatic Sprinkler
    Corporation v. Erie Insurance Exchange, 
    204 N.E.3d 215
     (Ind. 2023).
    FACTS AND PROCEDURAL HISTORY
    [5]   In March 2019, Stacy purchased a home located at 2412 Stover Drive, New
    Albany, Indiana. Shortly after moving into the residence, Stacy noticed
    drainage issues in the bathtub, with water draining from the bathtub flowing
    back into the residence. Stacy hired Greenwell Plumbing, Inc. (Greenwell) to
    address the issue. After running a camera down the drain, Greenwell
    discovered that a collapsed sewer line was the cause of the backup. Greenwell
    informed Stacy of the collapse and Stacy retained Greenwell to repair the
    collapsed line.
    [6]   On May 15, 2019, two Greenwell employees arrived at the residence with a
    backhoe to assist in the repair of the damaged sewer line. They located the
    collapsed portion of the sewer line with a camera, dug to the top of the line with
    the backhoe, and then dug the remainder of the dirt by hand. Meanwhile Stacy
    was in the basement of the residence unpacking boxes when she heard two
    “booms,” which she attributed to Greenwell’s backhoe hitting the residence.
    (Appellant’s App. Vol. II, p. 190). However, both employees later informed
    Jason Thompson (Thompson), Greenwell’s general manager of services, that
    the backhoe never struck the residence.
    [7]   “Six weeks” after Greenwell completed its repair work at the residence, Stacy
    noticed a crack in the residence’s exterior brick work and the foundation
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024       Page 3 of 26
    moving inwards. (Appellant’s App. Vol. II, p. 190). She contacted Thompson
    and claimed the crack resulted from Greenwell’s employees hitting the
    residence with the backhoe. In September 2019, Thompson visited the
    residence to survey the alleged damage. Despite acknowledging that he did not
    notice any indication that the damage had been caused by a backhoe, as a
    gesture of goodwill, Thompson offered to retain UDI to repair the damage to
    the exterior and the foundation of the residence. In exchange for Greenwell
    retaining UDI to repair the damage for an amount of $4,800, Stacy executed a
    Standard General Release (Release) in which she released any current or future
    claim against Greenwell for its work at the residence in exchange for Greenwell
    paying UDI to repair the damage caused on May 15, 2019. Contained within
    this Release was the following provision:
    The Customer [Stacy] agrees to release, hold harmless and
    indemnify the Company [Greenwell] and its affiliates and each of
    its respective agents, attorneys, employees, directors and officers
    and the successors, assigns, heirs, executors, administrators and
    legal representative of each of the foregoing from and against any
    and all liabilities, action, causes of action, claims, rights
    obligations charges, damages, costs, attorney’s fees, suits, and
    demands of any and every kind, nature and character, whether
    known or unknown, fixed or contingent, now existing or later
    developing that arise out of or relate to the actions or inactions of
    the Company.
    (Appellant’s App. Vol. III, p. 158).
    [8]   During its repair work on Stacy’s residence, UDI installed four steel piers to
    stabilize the home. Stacy claimed UDI incorrectly performed the piering work
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024        Page 4 of 26
    and as a result damaged the drywall in the basement, the foundation of the west
    wall, the exterior bricks, and caused ceiling cracks. UDI completed its work at
    the residence on October 2, 2019. That same day, Stacy informed ASI, her
    homeowner’s insurance company, of the damage to her home. After receiving
    notification of the claim, ASI retained Tim Lee (Lee), a structural engineer with
    U.S. Forensics, to assess the damage to the residence. After inspection, Lee
    concluded that “the sewer construction work resulted in mortar joint cracks and
    separations in the concrete masonry unit foundation, additional separation in
    the west concrete foundation wall, cracks and displacements in the mortar
    joints of the brick veneer, and cracks in the interior walls and ceilings
    coverings.” (Appellant’s App. Vol. III, p. 192). He also found that “the cracks
    in the walls and ceiling of the building were recent and were the result of repairs
    to the CMU crawlspace foundation along the south side of the building.”
    (Appellant’s App. Vol. III, p. 192). Based on these conclusions, Lee further
    clarified that the “damage caused by the excavation work was not the result of
    an impact by” the backhoe. (Appellant’s App. Vol. III, p. 193).
    [9]   On March 16, 2020, ASI denied Stacy’s claim after finding that the cracks in
    the walls and ceilings were due to repair work to the foundation and that faulty,
    inadequate, or defective workmanship was not covered under the Policy. ASI
    also specifically noted that “separation in the west concrete foundation wall,
    cracks and displacements in the mortar joints of the brick veneer, and cracks in
    the interior walls and ceiling coverings and cracks in the walls and ceilings were
    caused by the repair to the CMU foundation performed by [UDI] following the
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024         Page 5 of 26
    sewer excavation.” (Appellant’s App. Vol. IV, p. 56). In its letter, ASI reserved
    the right to deny coverage on other grounds that may arise.
    [10]   On February 26, 2021, Stacy filed a Complaint, alleging claims of negligent
    workmanship against Greenwell and UDI, claims for breach of contract against
    ASI and Greenwell, and a vicarious liability claim against Greenwell. In
    August 2021, based on the terms of the Release, Stacy dismissed her claims
    against Greenwell. ASI’s Response to Stacy’s Complaint asserted in its
    Affirmative Defenses, among others, that Stacy had failed to provide timely
    notice of her claim and that her claim was excluded under the Policy to the
    extent that the claim was the result of faulty, inadequate or defective design,
    specifications, or workmanship. During discovery, Stacy answered ASI’s
    interrogatories by repeatedly asserting that “[UDI] was hired by Greenwell to
    repair the damage, and they made it worse.” (Appellant’s App. Vol. III, p. 161,
    see also in similar wording at pp. 164-65, 166).
    [11]   On April 7, 2023, ASI moved for summary judgment, filing a memorandum in
    support and designation of evidence and contending that Stacy’s late notice and
    her release of Greenwell from liability before giving notice of the claim to ASI
    were material breaches of the Policy such that ASI did not have a duty to
    provide coverage for the damages under the Policy’s provisions. Alternatively,
    ASI asserted that even if there was an issue of material fact as to Stacy’s breach
    of the Policy, Stacy’s own pleadings against Greenwell and UDI with claims of
    negligent workmanship against both contractors amounted to an admission that
    the Policy did not provide coverage. Later that same month, on April 28, 2023,
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 6 of 26
    UDI filed its motion for summary judgment, together with a memorandum in
    support and designation of evidence. In its memorandum, UDI advanced four
    grounds to grant its motion. First, UDI alleged that it did not owe a duty
    because Stacy was not in privity of contract with UDI and only property
    damage had been alleged. Second, UDI contended that the economic loss
    doctrine precluded Stacy from recovering under a tort theory. Third, in the
    event UDI owed Stacy a duty, UDI did not commit a breach of that duty
    because it performed the work correctly. Lastly, Greenwell had released UDI
    from liability for the damages now claimed by Stacy. On August 1, 2023, Stacy
    filed her responses in opposition to both ASI’s and UDI’s motions for summary
    judgment.
    [12]   On September 28, 2023, the trial court issued its Order granting summary
    judgment to ASI, while denying UDI’s motion for summary judgment. In its
    Order, the trial court concluded that there was no genuine issue of material fact
    that Stacy had released Greenwell from liability prior to reporting her claim to
    ASI thereby destroying ASI’s subrogation rights and that Stacy had failed to
    provide ASI with timely notice of her claim. In denying UDI’s motion, the trial
    court noted that a genuine issue of material fact remained as to whether UDI’s
    work was negligently performed. On October 10, 2023, the trial court entered
    final judgment in ASI’s favor pursuant to Indiana Trial Rule 54(B).
    [13]   On October 17, 2023, UDI filed its motion to correct error, motion for
    certification of order, and motion to enlarge expert disclosure deadline. After a
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 7 of 26
    hearing 1, the trial court denied the motion to correct error. Reaffirming its
    previous holding on UDI’s negligent workmanship, the trial court addressed
    UDI’s other three arguments in detail. The court first concluded that because
    Stacy was not a party to the contract between UDI and Greenwell, the court
    declined to find that Stacy was bound by the exculpatory clause of the UDI-
    Greenwell contract. Second, because Stacy not only characterized her claim as
    negligent workmanship, but at “oral arguments, Stacy’s counsel articulated that
    it was a claim for breach of contract,” UDI’s argument that Stacy’s claim is
    precluded by the economic loss doctrine failed. (UDI’s App. Vol. II, p. 25).
    Third, the trial court found that because UDI failed to contract with Stacy as
    mandated under the HICA which requires a real property improvement
    supplier to provide a contract to the consumer prior to commencing the work,
    UDI could not circumvent this requirement by contracting with Greenwell and
    not Stacy. Even though the trial court denied UDI’s motion to correct error, it
    granted certification of its September 28, 2023 Order for interlocutory appeal.
    [14]   On January 11, 2024, UDI filed its motion for interlocutory appeal, which this
    court granted on February 14, 2024. That same day, we consolidated Stacy’s
    already pending appeal against ASI with UDI’s interlocutory appeal.
    [15]   Additional facts will be provided if necessary.
    1
    The parties did not provide this court with a transcript of the summary judgment hearing or the hearing on
    UDI’s motion to correct error.
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024                             Page 8 of 26
    DISCUSSION AND DECISION
    I. Standard of Review
    [16]   Stacy challenges the trial court’s grant of summary judgment to ASI, while UDI
    disputes the trial court’s denial of its motion for summary judgment. “The
    purpose of summary judgment is to terminate litigation about which there can
    be no factual dispute and which can be determined as a matter of law.” Lamb v.
    Mid Ind. Serv. Co., 
    19 N.E.3d 792
    , 793 (Ind. Ct. App. 2014). “The party moving
    for summary judgment has the burden of making a prima facie showing that
    there is no genuine issue of material fact and that it is entitled to judgment as a
    matter of law.” Mint Mgmt., LLC v. City of Richmond, 
    69 N.E.3d 561
    , 564 (Ind.
    Ct. App. 2017); Ind. Trial Rule 56(C). Summary judgment is a “high bar” for
    the moving party to clear in Indiana. Hughley v. State, 
    15 N.E.3d 1000
    , 1004
    (Ind. 2014). If “the moving party satisfies this burden through evidence
    designated to the trial court, the non-moving party may not rest on its
    pleadings, but must designate specific facts demonstrating the existence of a
    genuine issue for trial.” Biedron v. Anonymous Physician 1, 
    106 N.E.3d 1079
    ,
    1089 (Ind. Ct. App. 2018) (quoting Broadbent v. Fifth Third Bank, 
    59 N.E.3d 305
    ,
    311 (Ind. Ct. App. 2016), trans. denied), trans. denied. “A fact is material if its
    resolution would affect the outcome of the case, and an issue is genuine if a trier
    of fact is required to resolve the parties’ differing accounts of the truth, or if the
    undisputed material facts support conflicting reasonable inferences.” Williams
    v. Tharp, 
    914 N.E.2d 756
    , 761 (Ind. 2009) (citation and quotation marks
    omitted).
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024          Page 9 of 26
    [17]   We review a court’s ruling on a summary judgment motion de novo, applying
    the same standard as the trial court. Hughley, 15 N.E.3d at 1003. “In
    conducting our review, we consider only those matters that were designated to
    the trial court during the summary judgment stage.” Lowrey v. SCI Funeral
    Servs., Inc., 
    163 N.E.3d 857
    , 860 (Ind. Ct. App. 2021), trans. denied. “In
    determining whether issues of material fact exist, we neither reweigh evidence
    nor judge witness credibility [but] accept as true those facts established by the
    designated evidence favoring the non-moving party.” 
    Id.
     (citations omitted).
    “Any doubts as to any facts or inferences to be drawn from those facts must be
    resolved in favor of the nonmoving party.” Denson v. Est. of Dillard, 
    116 N.E.3d 535
    , 539 (Ind. Ct. App. 2018). However, “[m]ere speculation is insufficient to
    create a genuine issue of material fact to defeat summary judgment.” Biedron,
    
    106 N.E.3d at 1089
    . In the summary judgment context, we are not bound by
    the trial court’s findings of fact and conclusions thereon, but they aid our review
    by providing the reasons for the trial court’s decision. Howard Cnty. Sheriff's
    Dep’t & Howard Cnty. 911 Commc’ns v. Duke, 
    172 N.E.3d 1265
    , 1270 (Ind. Ct.
    App. 2021), trans. denied. The party that lost in the trial court bears the burden
    of persuading us that the trial court erred. Biedron, 
    106 N.E.3d at 1089
    .
    II. ASI’s Summary Judgment
    [18]   The trial court entered summary judgment in favor of ASI based on two prongs:
    (1) Stacy’s late notice of the potentially insured claim prejudiced ASI and (2) by
    signing the Release, Stacy destroyed ASI’s subrogation rights even before she
    notified the insurance company of the damage to the residence.
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 10 of 26
    Late Notice
    [19]   The duty to notify an insurance company of potential liability is a condition
    precedent to the insurer’s liability to its insured. Shelter Mut. Ins. Co. v. Barron,
    
    615 N.E.2d 503
    , 507 (Ind. Ct. App. 1993), trans. denied. As such, “[n]otice is a
    threshold requirement which must be met before an insurer is even aware that a
    controversy or matter exists which requires the cooperation of the insured.”
    Motorist Mutual Insurance Co. v. Johnson, 
    218 N.E.2d 712
    , 717 (Ind. Ct. App.
    1966). The notice requirement is “material, and of the essence of the contract.”
    London Guarantee & Accident Co. v. Siwy, 
    66 N.E. 481
    , 482 (Ind. Ct. App. 1903).
    The Indiana Supreme Court stated in Miller v. Dilts, 
    463 N.E.2d 257
    , 265 (Ind.
    1984):
    The requirement of prompt notice gives the insurer an
    opportunity to make a timely and adequate investigation of all
    the circumstances surrounding the accident or loss. This
    adequate investigation is often frustrated by a delayed notice.
    Prejudice to the insurance company’s ability to prepare an
    adequate defense can therefore be presumed by an unreasonable
    delay in notifying the company about the accident or about the
    filing of the lawsuit.
    “The presumption of prejudice means that if the delay in giving the required
    notice is unreasonable, the burden falls on the insured to produce evidence that
    prejudice did not actually occur in the particular situation.” Ind. Farmers Mut.
    Ins. Co. v. North Vernon Drop Forge, Inc., 
    917 N.E.2d 1258
    , 1274 (Ind. Ct. App.
    2009) (citing Erie Ins. Exch. v. Stephenson, 
    674 N.E.2d 607
    , 612 (Ind. Ct. App.
    1996)). Thus, in a summary judgment action, it is incumbent upon the alleged-
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024         Page 11 of 26
    insured to set forth “some evidence” to rebut the presumption that the insurer
    has “suffered prejudice of its right to conduct a timely and adequate
    investigation.” Erie Ins. Exch., 674 N.E.2d at 612. Once the alleged insured
    does so, “the burden shifts back to the insurer to establish prejudice.” Ind.
    Farmers, 
    917 N.E.2d at 1274
    .
    [20]   ASI’s Policy contained a specific provision regarding Stacy’s duty to promptly
    notify the insurance company after a loss:
    SECTION I – CONDITIONS
    What Must Be Done After A Loss
    In the event of a loss to which coverage may apply, the following
    duties must be performed either by you, an “insured” seeking
    coverage, or a representative of either:
    1. Give immediate notice to us;
    (Appellant’s App. Vol. III, p. 50). As the notice provision contained in the
    Policy is clear and unambiguous, Stacy’s duty to ‘immediately notify’ ASI of
    the loss is a condition precedent to ASI providing coverage under the Policy for
    the damages arising from the purported negligent work performed by Greenwell
    and UDI. Because the notice provision is a condition precedent to obtaining
    coverage under the Policy, we must determine whether Stacy satisfied its duty
    to “give immediate notice” to ASI. (Appellant’s App. Vol. III, p. 50).
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 12 of 26
    [21]   To determine whether Stacy gave immediate notice of the loss to ASI, we
    evaluate whether the notice was given within a reasonable time by considering
    the purposes for which the notice was given and the circumstances of the
    particular case. Sutton v. Littlepage, 
    669 N.E.2d 1019
    , 1023 (Ind. Ct. App.
    1996); Employers Liab. Corp. v. Light, Heat, & Power Co., 
    63 N.E. 54
    , 56 (Ind. Ct.
    App. 1902) (holding that “immediate” notice means “reasonable” notice). The
    designated evidence reflects that on May 15, 2019, Greenwell’s backhoe
    allegedly struck Stacy’s residence, resulting in damage to the foundation and a
    crack in the residence’s exterior brick work. However, Stacy did not notice the
    damage until six weeks later, around the end of June or the beginning of July.
    At that point, she contacted Thompson, who surveyed the damage in
    September 2019. After Stacy executed a Release, Greenwell contracted with
    UDI to repair the damage to the exterior and foundation of the residence. It
    was not until the day UDI finalized its repair work, on October 2, 2023,
    approximately three months after the damage of the backhoe incident was
    discovered and the damage had allegedly been rectified by UDI, that Stacy first
    contacted ASI and notified the insurance company of the loss. Although the
    temporal element of our analysis does not elevate this notice as being
    unreasonable per se, combined with the surrounding circumstances of this
    three-month time frame, we conclude that the notice was not given within a
    reasonable time. Within these three months, the damage had been assessed by
    Greenwell and a purported correction of these damages had been attempted by
    UDI. Stacy only contacted ASI of the loss after UDI had completed its
    rectification work and she became convinced that UDI had made the damage
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 13 of 26
    worse. Under these circumstances, we conclude that Stacy failed to give
    reasonable notice to ASI. See Miller, 463 N.E.2d at 266 (court ordered summary
    judgment to be entered in favor of the three insurance companies which
    received notice of the accidents giving rise to liability one month, six months,
    and seven months after their occurrence and which received notice of the
    resulting lawsuits as early as five days after the suits were filed); See Askren Hub
    States Pest Control Servs, Inc. v. Zurich Ins. Co., 
    721 N.E.2d 270
    , 278 (Ind. Ct. App.
    1999) (“We believe that Askren’s delay of six months before notifying Zurich of
    the ‘occurrence’ constitutes unreasonable notice.”).
    [22]   Even though Stacy did not give ASI reasonable notice of the loss, that failure
    alone will not bar recovery under the Policy unless ASI suffered prejudice as a
    result of the delay. See Miller, 463 N.E.2d at 265-66; see also Shelter, 
    615 N.E.2d at 507
    . Although ASI must show actual prejudice from Stacy’s unreasonable
    delay in providing notice about the loss, prejudice to ASI’s ability to prepare an
    adequate defense can be presumed where, as here, there was an unreasonable
    delay in notification. See Miller, 463 N.E.2d at 265. The presumption of
    prejudice essentially means that if the delay in giving the required notice is
    unreasonable, the injured party or the insured has the burden to produce
    evidence that no actual prejudice occurred in the particular situation. See id. In
    order to rebut this presumption that ASI could conduct nothing more than a
    cursory investigation, Stacy points to her own designated statements,
    deposition, and photographs of “the work done by Greenwell and [UDI].”
    (Stacy’s Reply Br. p. 18). She also contends that other witnesses were available
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024        Page 14 of 26
    for depositions, and she alerts us to the report submitted by U.S. Forensics, the
    expert retained by ASI to assess the damage.
    [23]   We conclude that Stacy failed to rebut the presumption of prejudice resulting
    from her unreasonable delay. Stacy’s designated evidence does not address
    ASI’s inability to view the temporary aspects of the original loss and the extent
    to which each contractor contributed to the damage. At the time notice was
    given, ASI was unable to evaluate the loss as UDI had already completely
    altered the original damage, thereby preventing ASI from assessing the original
    defects. “[T]imely notice gives the insurer an opportunity to investigate while
    evidence is fresh, evaluate the claim, and participate in early settlement.” Tri-
    Etch, Inc. v. Cincinnati Ins. Co., 
    909 N.E.2d 997
    , 1005 (Ind. 2009). Because ASI
    was prevented from meaningfully investigating the claim due to the
    unreasonably late notice, Stacy failed in rebutting the presumption of prejudice
    in favor of ASI.
    [24]   In an effort to salvage part of her claim against ASI, Stacy requests this court to
    characterize her loss as two separate damage events. In a single sentence in her
    appellate brief and expounded on in her reply brief, Stacy now advances the
    theory that “[t]he separate damage by [UDI] would qualify as a new/separate
    occurrence under the Policy,” and as such, her notice of this loss would have
    been reasonable as it was provided on the same day as UDI completed its
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 15 of 26
    work. 2 (Stacy’s Br. p. 16). However, throughout these proceedings, Stacy has
    consistently maintained that Greenwell’s actions were the “efficient proximate
    cause” 3 of the damage. (Appellant’s App. Vol. III, p. 166). She also
    acknowledged numerous times that “[UDI] was hired by Greenwell to repair
    the damage, and they made it worse.” (Appellant’s App. Vol. III, p. 161, see
    also in similar wording at pp. 164-65, 166). Accordingly, without Greenwell’s
    initial damage to the foundation and the exterior wall, there was no reason for
    UDI to enter the fray and correct the loss caused by Greenwell. Without
    having to decide as to whether the loss consisted of one or two occurrences,
    Stacy only notified ASI on the day UDI completed its purported corrective
    work of Greenwell’s instigated damages. This delay prevented ASI from
    determining the exact and specific cause of the damage and the extent to which
    each contractor contributed to the loss. In other words, Stacy’s delay in
    notifying ASI resulted in ASI having to evaluate stale evidence. See Tri-Etch,
    Inc., 909 N.E.2d at 1005 (“[T]imely notice gives the insurer an opportunity to
    investigate while evidence is fresh[.]”).
    2
    While ASI claims that the argument of two occurrences was first made by Stacy on appeal, we disagree as
    Stacy raised this as an alternative argument in her Response in Opposition to ASI’s motion for summary
    judgment. See Appellant’s App. Vol. IV, p. 201.
    3
    The efficient proximate cause rule states that where a peril specifically insured against sets other causes into
    motion which, in an unbroken sequence, produce the result for which recovery is sought, the loss is covered,
    even though other events within the chain of causation are excluded from coverage. “Stated in another
    fashion, where an insured risk itself sets into operation a chain of causation in which the last step may have
    been an excepted risk, the excepted risk will not defeat recovery.” Hartford Cas. Ins. Co. v. Evansville
    Vanderburgh Public Library, 
    860 N.E.2d 636
    , 646 (Ind. Ct. App. 2007).
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024                                 Page 16 of 26
    [25]   Because there is no genuine issue of material fact that Stacy’s notice of the loss
    to ASI was unreasonably late, we affirm the trial court’s entry of summary
    judgment in favor of ASI on Stacy’s breach of contract claim. 4
    III. UDI’s Denial of Summary Judgment
    [26]   In its interlocutory appeal, UDI contends that the trial court erred as a matter of
    law in concluding that the HICA should govern the relationship between Stacy
    and UDI instead of the foreseeability doctrine, as clarified by our Indiana
    Supreme Court’s holding in U.S. Automatic Sprinkler Corporation v. Erie Insurance
    Exchange, 
    204 N.E.3d 215
     (Ind. 2023).
    [27]   Under long-standing Indiana law, a defendant is liable to a plaintiff for the tort
    of negligence if (1) the defendant has a duty to conform its conduct to a
    standard of care arising from its relationship with the plaintiff, (2) the defendant
    failed to conform its conduct to that standard of care, and (3) an injury to the
    plaintiff was proximately caused by the breach. Indianapolis-Marion Cnty. Pub.
    Library v. Charlier Clark & Linard, P.C., 
    929 N.E.2d 722
    , 726 (Ind. 2010).
    Construction negligence cases can generally be divided into two categories:
    “cases where the plaintiffs seeking to recover in tort were in privity of contract
    with the defendants and cases where they were not.” Id. at 734. It is
    uncontested that Stacy and UDI were not in privity of contract; rather
    4
    Because we affirm the trial court’s entry of summary judgment in favor of ASI based on Stacy’s untimely
    notice of the loss, we do not analyze Stacy’s claim that the execution of the Release only impacted ASI’s
    subrogation rights against Greenwell and not against UDI.
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024                           Page 17 of 26
    Greenwell contracted with UDI, with Stacy’s approval, to correct the perceived
    damage caused to the residence by Greenwell. There is also no dispute that
    Stacy only alleged property damage and did not complain of having been
    personally injured.
    [28]   In U.S. Automatic Sprinkler Corporation v. Erie Insurance Exchange, 
    204 N.E.3d 215
    (Ind. 2013), our supreme court recently considered whether a duty was owed
    when, like here, there was no privity of contract between the parties. The
    supreme court observed that traditionally the acceptance rule, with its various
    exceptions, “generally shielded” contractors “from third-party liability once the
    work is completed and then accepted by the owner.” 
    Id. at 225
    . In other
    words, “‘contractors do not owe a duty of care to third parties after the owner
    has accepted the work.”’ Peters v. Forster, 
    804 N.E.2d 736
    , 738 (Ind. 2004)
    (quoting Blake v. Calumet Constr. Corp., 
    674 N.E.2d 167
    , 170 (Ind. 1996)).
    However, the Automatic Sprinkler Court noted that in Peters it had abandoned
    the acceptance rule in favor of the “foreseeability doctrine.” Automatic Sprinkler,
    204 N.E.3d at 225. Specifically, in Peters, our supreme court held that,
    A rule that provides that a builder or contractor is liable for injury
    or damage to a third person as a result of the condition of the
    work, even after completion of the work and acceptance by the
    owner, where it was reasonably foreseeable that a third party
    would be injured by such work due to the contractor’s
    negligence, is consistent with traditional principles of negligence
    upon which Indiana’s scheme of negligence law is based.
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024        Page 18 of 
    26 Peters, 804
     N.E.2d at 742. Continuing on the framework established in Peters,
    the Supreme Court, in Automatic Sprinkler, “clarif[ied] the foreseeability
    doctrine’s scope in two ways.” Automatic Sprinkler, 204 N.E.3d at 226. “First,
    the foreseeability doctrine applies when a third party seeks recovery for personal
    injury that was a foreseeable consequence of a contractor’s allegedly negligent
    work.” Id. This harmonized the Peters decision’s goal of “equaliz[ing] the
    liability field in the context of negligence claims resulting in injuries to third
    parties.” Id. “Second, the doctrine applies when a third party seeks recovery
    for property damage if personal injury—though not sustained—is a foreseeable
    consequence of a contractor’s allegedly negligent work.” Id. This harmonized
    the Citizen's Gas & Coke Util. v. Amer. Econ. Ins., 
    486 N.E.2d 998
    , 1000 (Ind.
    1985) decision’s goal of maintaining the privity requirement’s operation to
    preclude recovery for property damages in a negligence action, where the
    negligent work poses a risk only to property and not persons. Automatic
    Sprinkler, 204 N.E.3d at 226-27. However, when the contractor’s work
    “possesses a risk to only property—not persons—the privity requirement
    remains operative and precludes recovery for property damages in a negligence
    case.” Id. at 227. In other words, the Court in Automatic Sprinkler granted two
    avenues for third parties to recover against contractors: (1) seek recovery for a
    personal injury caused by the contractor’s allegedly negligent work if the injury
    was a foreseeable consequence of the allegedly negligent work, or (2) pursue a
    claim for property damages against the contractor if personal injury was a
    foreseeable consequence of the contractor’s allegedly negligent work.
    Therefore, for a third party to recover for property damage under the
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024         Page 19 of 26
    foreseeability doctrine, “it must be ‘reasonably foreseeable’ that a third party
    would be injured by such work.” Id. at 226 (quoting Peters, 804 N.E.2d at 742).
    [29]   Accordingly, in order for Stacy to recover for the damage to her residence in the
    absence of any contractual or privity relationship with UDI, she must establish
    that it was reasonably foreseeable Stacy would be injured by UDI’s perceived
    defective work. In Automatic Sprinkler, our Supreme Court did not elaborate on
    what constituted a ‘reasonably foreseeable’ personal injury. Since Automatic
    Sprinkler was decided, Indiana courts have applied this new foreseeability
    doctrine in two cases. In BMI Properties, LLC v. Daewong, LLC, 
    224 N.E.3d 1000
    ,1005 (Ind. Ct. App. 2023), the subsequent owner of a mixed-use building
    filed a complaint against the builder of the property, alleging that a bedpost fell
    through the floor when a tenant was moving in, that bricks fell off the exterior
    of the building and damaged a nearby car, that the brick veneer of the building
    was peeling away allegedly due to design defects and improper drainage leading
    to bricks falling to the ground, and that there were visible mold spores which
    posed a health risk. Applying Automatic Sprinkler’s clarification of the
    foreseeability rule, the BMI court concluded that even though no one became
    injured when the bedpost broke through the floorboard, no one became ill due
    to exposure to the airborne spores and/or black mold, and no passersby were
    injured when the brick veneer peeled away from the building, whether personal
    injury was a foreseeable consequence of these events amounted to a genuine
    issue of material fact. 
    Id.
     In Elpers Bros. Construction & Suppel, Inc. v. Smith, 
    230 N.E.3d 920
    , 931 (Ind. Ct. App. 2024), this court evaluated whether a duty was
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024        Page 20 of 26
    owed by a development company to a homeowner, when the parties were not
    in privity of contract and where the homeowner had suffered only property
    damage. Upon analysis, we found that it was undisputed that the development
    company’s alleged negligence—its construction of other residences in the
    subdivision contributed to the erosion and sediment buildup in the nearby lake,
    which resulted in the homeowner’s malfunctioning geothermal heating and
    cooling system—did not pose a reasonably foreseeable risk of personal injury to
    the homeowner. 
    Id.
     In light of these circumstances, we concluded that the
    privity requirement set forth in Citizens Gas and Automatic Sprinkler controlled,
    and the homeowner was therefore precluded from recovering property damages
    from the development company. 
    Id.
    [30]   Turning now to the case at hand, we observe that due to the lack of privity
    between Stacy and UDI, in order to recover for the perceived property damage
    Stacy must establish that “personal injury—though not sustained—[was] a
    foreseeable consequence of” UDI’s alleged negligent work. Automatic Sprinkler,
    204 N.E.3d at 226. The evidence reflects that six weeks after Greenwell
    completed its repair work at the residence, Stacy noticed a crack in the
    residence’s exterior brick work. Unlike in BMI, the evidence does not reflect
    the presence of any dislocated or fallen bricks. See BMI Properties, LLC, 224
    N.E.3d at 1005. Although the original damage was discovered sometime early
    July, UDI’s repairs did not commence until late September and were completed
    on October 2. There is no evidence that during this time the damage to the
    residence worsened or Stacy felt unsafe to remain in the home. Through her
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 21 of 26
    designated evidence and in her appellate brief, Stacy now contends that she
    presented “substantial evidence demonstrating” that UDI’s work did not meet
    industry standards and “directly resulted in significant property damage.”
    (Appellant’s Reply Br. p. 14). She claimed that UDI’s negligence “violated the
    standard practices for foundation stabilization and directly led to the observed
    property damage.” (Appellant’s Reply Br. p. 14). Stacy contended that the
    piering system to rectify the foundation problem required pouring new concrete
    footers and driving steel piers into bedrock. However, Stacy did not designate
    any evidence, nor can we find any, establishing that personal injuries might
    have been a reasonably foreseeable result from UDI’s perceived negligent work.
    To the contrary, Howard Byrd (Byrd), UDI’s employee who inspected Stacy’s
    property before and after UDI performed the work, affirmed that UDI’s system
    did not require pouring new concrete footings, rather the piers installed by UDI
    “were pressed into the ground until they reached load bearing strata.”
    (Appellant’s App. Vol. IV, p. 161). Byrd also noted that, when he inspected the
    property on October 10, 2022, after UDI’s work had been completed, he did not
    see any new cracks in the mortar joints where UDI had made repairs.
    Similarly, neither Lee’s report nor Mark Ricketts, 5 Stacy’s expert, found
    incorrectly installed resistance piers but rather only noted cosmetic repairs to
    the residence. At no point during these corrective repairs was Stacy ever
    advised that she needed to vacate the residence because it was unsafe.
    5
    We note that Mark Ricketts’ report also depicts certain cracks in bricks and concrete that are not in the area
    of the repairs completed by UDI and therefore are not defects that UDI was employed to remedy.
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024                              Page 22 of 26
    Although Stacy points to a statement from UDI acknowledging that its work
    could physically injure Stacy or her dwelling, the statement was made as a
    caution to the homeowner “not to fall in the holes that [UDI] digs” for the
    footings, it does not amount to a recognition that personal injury was a
    reasonably foreseeable consequence of the work. (Appellant’s App. Vol. VI, p.
    121). Based on these circumstances, we do not find any genuine issues of
    material fact establishing that the alleged negligent workmanship carried with it
    a reasonable foreseeability of personal injury. See Automatic Sprinkler, 204
    N.E.3d at 226. Therefore, the privity requirement controls, and Stacy is
    precluded from recovering her property damages. See id.
    [31]   Trying to avoid the application of our Supreme Court’s holding in Automatic
    Sprinkler, Stacy contends that the lack of contract between herself and UDI
    constituted a violation of the HICA. Relying on Indiana Code section 24-5-11-
    10, which requires that “[a] real property improvement supplier shall provide a
    completed real property improvement contract to the consumer before it is
    signed by the consumer,” Stacy argues that UDI, as a real property
    improvement supplier under I.C. § 24-5-11-6, should have contracted directly
    with her, as a consumer pursuant to I.C. § 24-5-11-2, and not with Greenwell.
    She maintains that UDI’s failure to comply with these statutory requirements
    “exposes [UDI] to liability for failing to meet statutory obligations.” (Stacy’s
    Reply Br. p. 11).
    [32]   While we agree with Stacy that public policy strongly favors the enforcement of
    consumer protection statutes to ensure that homeowners are safeguarded
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 23 of 26
    against deceptive practices and poor workmanship, Stacy’s argument in essence
    amounts to the abrogation of the well-known adage that Indiana courts
    recognize the freedom of parties to enter into contracts and presume that
    contracts represent the freely bargained agreement of the parties. Fresh Cut, Inc.
    v. Fazli, 
    650 N.E.2d 1126
    , 1129 (Ind. 1996).
    [33]   The reality before us acknowledges that Greenwell and UDI contracted for the
    benefit of Stacy. The contract between Greenwell and UDI was not a “real
    property improvement contract” because it was not entered into between a
    “consumer” and a “real property improvement supplier.” I.C. § 24-5-11-4.
    Therefore, the HICA did not apply to UDI for the purpose of its transaction
    with Greenwell. Moreover, Stacy consented to Greenwell entering into an
    “agreement to allow [UDI] to fix the foundation.” (Appellant’s App. Vol. IV,
    p. 85). Stacy and Greenwell negotiated the Release, which directly contributed
    to Greenwell entering into a contract with UDI to correct Greenwell’s alleged
    damages. In the provisions of the Release, Stacy acknowledged that “[t]he
    customer accepts that by Greenwell paying [UDI] for quoted repairs due to
    damage caused during service on 05/15/2019 in the amount of $4,800.00 that
    this claim will be satisfied and closed.” (Appellant’s App. III, p. 158). Instead
    of negotiating with Greenwell to pay her a lump sum and then contracting
    directly with the provider of the repairs, Stacy voluntarily elected to permit
    Greenwell to coordinate and pay for the foundation repairs. To that end,
    Greenwell entered into a contract with UDI. It is only after the Release was
    executed and the repairs made that Stacy complained of the contractual
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024      Page 24 of 26
    structure that she freely negotiated and agreed upon. While we agree that
    HICA’s intent is to protect consumers from substandard and deceptive practices
    in home improvement transactions, Stacy has not designated any evidence
    supporting the allegation that the agreed upon contractual framework
    intentionally allowed “UDI to bypass the protections afforded by HICA” to
    Stacy. (Stacy’s Reply Br. p. 11).
    [34]   Accordingly, based on the designated evidence before us, we conclude that UDI
    did not owe a duty to Stacy because the parties were not in privity of contract
    and personal injury was not reasonably foreseeable to result from the alleged
    acts of negligence. Therefore, as there are no genuine issues of material fact,
    UDI is entitled to summary judgment as a matter of law. We reverse the trial
    court’s denial of UDI’s motion for summary judgment. 6
    CONCLUSION
    [35]   Based on the foregoing, we hold that no genuine issue of material fact exists
    that Stacy failed to timely notify ASI of the damage resulting from UDI’s
    workmanship. However, because we hold that no privity of contract exists
    between Stacy and UDI and personal injury was not reasonably foreseeable to
    6
    Because we find UDI’s privity of contract argument determinative of the cause before us, we will not
    address UDI’s alternative arguments with respect to the application of the economic loss doctrine and with
    respect to waiver of claims for property damage pursuant to the exculpatory clause in UDI’s contract with
    Greenwell.
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024                            Page 25 of 26
    result from the alleged acts of negligence, we reverse the trial court's denial of
    UDI’s motion for summary judgment and enter summary judgment for UDI.
    [36]   Affirmed in part and reversed in part.
    Kenworthy, J. and Felix, J. concur
    ATTORNEY FOR APPELLANT
    William D.Beyers
    Buchanan & Bruggenschmidt, PC
    Zionsville, Indiana
    ATTORNEYS FOR APPELLEES
    William J. Beggs
    Ryan M. Heeb
    Bunger & Robertson
    Bloomington, Indiana
    Eric C. McNamar
    Edmund L. Abel
    Lewis Wagner, LLP
    Indianapolis, Indiana
    Court of Appeals of Indiana | Opinion 23A-CT-2529 | August 26, 2024       Page 26 of 26
    

Document Info

Docket Number: 23A-CT-02529

Filed Date: 8/26/2024

Precedential Status: Precedential

Modified Date: 8/28/2024