Jacob Balash v. Steve Mader ( 2024 )


Menu:
  •                                              IN THE
    Court of Appeals of Indiana
    Jacob Balash and Jonathan Balash,                 FILED
    Oct 08 2024, 9:12 am
    Appellants-Defendants,
    CLERK
    Indiana Supreme Court
    Court of Appeals
    and Tax Court
    v.
    Steve Mader,
    Appellee-Plaintiff.
    October 8, 2024
    Court of Appeals Case No.
    24A-SC-792
    Appeal from the
    Owen Circuit Court
    The Honorable
    Darrin M. Dolehanty, Senior Judge
    Trial Court Cause No.
    60C02-2310-SC-116
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024   Page 1 of 9
    Opinion by Senior Judge Baker
    Judges Vaidik and Brown concur.
    Baker, Senior Judge.
    Statement of the Case
    [1]   In this home improvement case, Jacob and Jonathan Balash (the Balashes)
    appeal the court’s judgment entered in favor of contractor Steve Mader,
    claiming it is contrary to law. Specifically, the Balashes contend the small
    claims court’s award of damages to Mader is erroneous because Mader failed to
    provide the Balashes with a written contract in accordance with the Home
    Improvement Contracts Act. Concluding that Mader’s dealings with the
    Balashes fell within the scope of the Act and that Mader consequently cannot
    recover damages from the Balashes, we reverse with instructions.
    Facts and Procedural History
    [2]   The facts most favorable to the judgment are that in the spring of 2023, the
    Balashes hired Mader to drill a new well on their property and cap off the
    existing well for an estimated cost of $10,000 - $15,000. There was no written
    agreement memorializing the work to be done, the cost of such work, or any
    details associated with the project. Mader began work on the new well at the
    end of June. Complications ensued with the drilling of the new well, and
    Mader was unable to complete the work. He stopped work in mid-July, and the
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024        Page 2 of 9
    Balashes hired a different contractor to install a new well and cap both the old
    one and the one Mader had begun drilling.
    [3]   At the beginning of August, Mader returned to the Balash property to discuss
    payment for the work he had done, but the parties did not reach an agreement.
    The following month the Balashes received an invoice from Mader in the
    amount of $8,280. Although the Balashes made an offer to settle, Mader
    ultimately filed this action in small claims court. Following a bench trial, the
    court entered judgment for Mader in the amount of $8,280 plus court costs.
    The Balashes moved to correct error, which the court denied. This appeal
    ensued.
    Discussion and Decision
    [4]   Small claims actions involve informal trials where the sole objective is to
    dispense speedy justice between the parties according to the rules of substantive
    law. Harvey v. Keyed In Prop. Mgmt., LLC, 
    165 N.E.3d 584
    , 587 (Ind. Ct. App.
    2021), trans. denied. We will reverse the judgment of a small claims court only
    upon clear error. Wang v. Sun, 
    212 N.E.3d 1252
    , 1256 (Ind. Ct. App. 2023). In
    our review, we consider only the evidence most favorable to the judgment, and
    we neither reweigh the evidence nor assess witness credibility. Nick’s Packing
    Servs., Inc. v. Chaney, 
    181 N.E.3d 1025
    , 1028 (Ind. Ct. App. 2021). However,
    this deferential standard does not apply to substantive rules of law, which we
    review de novo. Wang, 212 N.E.3d at 1256.
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024        Page 3 of 9
    [5]   The Balashes contend the court’s judgment in favor of Mader is clearly
    erroneous because Mader’s claim is based on an oral agreement for residential
    real property improvements in violation of the Home Improvement Contracts
    Act. See 
    Ind. Code §§ 24-5-11-1
     to -14. As this Court has explained,
    [t]he purpose of the Act is to protect consumers by placing
    specific minimum requirements on the contents of home
    improvement contracts. . . . [F]ew consumers are knowledgeable
    about the home improvement industry or of the techniques that
    must be employed to produce a sound structure. The consumer’s
    reliance on the contractor coupled with the well-known abuses
    found in the home improvement industry, served as an impetus
    for the passage of the Act, and contractors are therefore held to a
    strict standard.
    Benge v. Miller, 
    855 N.E.2d 716
    , 720 (Ind. Ct. App. 2006) (internal citations
    omitted).
    [6]   Within the Act, a “consumer” is “a person that owns, leases, or rents the
    residential real property that is the subject of a real property improvement
    contract.” I.C. § 24-5-11-2 (2017). The Act defines “real property
    improvement” as “any alteration, repair, replacement, reconstruction, or other
    modification of residential real property.” I.C. § 24-5-11-3(a) (2017). In
    addition, a “real property improvement supplier” is defined as “a person who
    engages in or solicits real property improvement contracts whether or not the
    person deals directly with the consumer.” I.C. § 24-5-11-6 (2017). And the Act
    defines a “real property improvement contract” as “an agreement, oral or
    written, between a real property improvement supplier and a consumer to make
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024            Page 4 of 9
    a real property improvement and for which the real property improvement
    contract price exceeds one hundred fifty dollars ($150).” I.C. § 24-5-11-4
    (2017).
    [7]   The heart of the Act, Section 24-5-11-10(a), mandates that suppliers provide a
    completed contract to the consumer before it is signed by the consumer. The
    section further requires that the contract contain, at a minimum:
    (1) The name of the consumer and the address of the real
    property that is the subject of the real property improvement.
    (2) The name, address, and email address of the real property
    improvement supplier.
    (3) The name, telephone number, and email address for each
    owner, officer, employee, or agent of the real property
    improvement supplier to whom consumer problems and inquiries
    can be directed.
    (4) The date the real property improvement contract was
    submitted to the consumer and any time limitation on the
    consumer’s acceptance of the real property improvement
    contract.
    (5) A reasonably detailed description of the proposed real
    property improvements.
    (6) If the description does not include the specifications for the
    real property improvement, a statement that the specifications
    will be provided to the consumer before any work is commenced
    under the real property improvement contract and that the real
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024           Page 5 of 9
    property improvement contract is subject to the consumer’s
    separate written and dated approval of the specifications.
    (7) The approximate starting and completion dates of the real
    property improvements.
    (8) A statement of any contingencies that would materially
    change the approximate completion date.
    (9) The real property improvement contract price.
    (10) A statement as to whether any third party, including any
    subcontractor, vendor, or other person that is not a party to the
    contract, will lease or furnish any labor, services, material,
    equipment, or machinery to, or on behalf of, the real property
    improvement supplier in connection with the real property
    improvement.
    (11) Signature lines for the real property improvement supplier or
    the supplier’s agent and for each consumer who is to be a party to
    the real property improvement contract with a legible printed or a
    typed version of that person’s name placed directly after or below
    the signature.
    See id.
    [8]   We pause here to note the internal discrepancy between Section 24-5-11-4,
    providing that a real property improvement contract may be oral or written, and
    Section 24-5-11-10(a), mandating that the supplier provide the consumer with a
    completed contract before it is signed and listing the specific minimum
    requirements to be contained in the contract, including signature lines for the
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024            Page 6 of 9
    supplier and the consumer with printed or typed versions of their names.
    Further, Section 24-5-11-10(b) requires the contract to “be in a form that each
    consumer who is a party to it can reasonably read and understand.”
    [9]    A panel of this Court recently recognized this discrepancy and determined that,
    with its “unmistakable specificity,” Section 24-5-11-10(a) controls. See Logan v.
    Evans, 
    230 N.E.3d 371
    , 381 n.4 (Ind. Ct. App. 2024) (noting discrepancy,
    recognizing tenet that specific statutory provision takes priority over general
    one, and concluding that I.C. § 24-5-11-10(a)(10) “specifically and
    unambiguously requires that a real property improvement contract be in writing
    and signed by both the supplier and the customer”). Accordingly, a real
    property improvement contract must be in writing and signed by both parties.
    Id. (citing I.C. § 24-5-11-10(a)(10)); see also I.C. § 24-5-11-10.6 (2017) (referring
    to contract being signed by consumer and supplier); I.C. § 24-5-11-11 (2017)
    (requiring supplier to agree to terms of contract by “written signature” before
    consumer signs contract); I.C. § 24-5-11-12 (2017) (requiring supplier to give
    “fully executed copy” of contract to consumer “immediately after the consumer
    signs it”), and see McGraw Prop. Sols., LLC v. Jenkins, 
    159 N.E.3d 991
    , 996 (Ind.
    Ct. App. 2020) (stating that Act requires suppliers to provide consumer with
    written contract).
    [10]   In the present case, Mader is undeniably a real property improvement supplier
    who was hired by the Balashes to perform real property improvements, the cost
    of which exceeded $150. It is also undisputed that Mader never provided a
    written contract to the Balashes and that they never signed a contract with
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024            Page 7 of 9
    Mader or executed any documents that would have satisfied the minimum
    statutory contract requirements.
    [11]   Under the Act, it was Mader’s burden to supply the Balashes with a written
    contract. See I.C. § 24-5-11-10(a) (“A real property improvement supplier shall
    provide a completed real property improvement contract to the consumer before
    it is signed by the consumer.”) (emphasis added). Mader failed to do so, and,
    as such, he violated the Act. Therefore, Mader cannot enforce the oral
    agreement against the Balashes. See Ambrose v. Dalton Const., Inc., 
    51 N.E.3d 320
    , 322 (Ind. Ct. App. 2016) (stating that violation of Act makes contract
    unenforceable against consumer) (opinion on reh’g), trans. denied.
    Consequently, the trial court’s award of damages to Mader is clearly erroneous
    and must be set aside. See Cyr v. J. Yoder, Inc., 
    762 N.E.2d 148
    , 152 (Ind. Ct.
    App. 2002) (setting aside damage award in favor of contractors because they
    violated Act by failing to have consumer sign contract). Our holding reflects
    our continued mindfulness that the Act was passed to protect consumers from
    abuse and that contractors are therefore held to a strict standard. See Benge, 
    855 N.E.2d at 720
    .
    Conclusion
    [12]   Thus, in light of the foregoing, we conclude that Mader’s dealings with the
    Balashes were governed by the Act and that the damage award entered for
    Mader must be set aside.
    [13]   Reversed with instructions to vacate the judgment for Mader.
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024        Page 8 of 9
    Vaidik, J., and Brown, J., concur.
    ATTORNEY FOR APPELLANTS
    Hannah L. England
    England Law Office, P.C.
    Spencer, Indiana
    APPELLEE PRO SE
    Steve Mader
    Spencer, Indiana
    Court of Appeals of Indiana | Opinion 24A-SC-792 | October 8, 2024   Page 9 of 9
    

Document Info

Docket Number: 24A-SC-00792

Filed Date: 10/8/2024

Precedential Status: Precedential

Modified Date: 10/8/2024