Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande ( 2012 )


Menu:
  •                IN THE SUPREME COURT OF IOWA
    No. 10–1278
    Filed June 1, 2012
    FLYNN BUILDERS, L.C.,
    Appellee,
    vs.
    MATTHEW P. LANDE
    and CHRIS LANDE,
    Appellants.
    On review from the Iowa Court of Appeals.
    Appeal from the Iowa District Court for Boone County, William C.
    Ostlund, Judge.
    On further review, appellants allege the district court and court of
    appeals erred in holding the appellee was entitled to enforce its
    mechanic’s lien.    DECISION OF COURT OF APPEALS AFFIRMED IN
    PART AND VACATED IN PART; DISTRICT COURT JUDGMENT
    REVERSED, AND CASE REMANDED FOR FURTHER PROCEEDINGS.
    Duane M. Huffer and Robert L. Huffer of Huffer Law P.L.C., Story
    City, for appellants.
    Meredith C. Mahoney Nerem and John D. Jordan of Jordan &
    Mahoney Law Firm, P.C., Boone, for appellee.
    2
    APPEL, Justice.
    In this action to foreclose a mechanic’s lien, we address the
    consequences of a contractor’s failure to render full and complete
    performance.1 An owner and contractor entered into an agreement for
    the construction of a new home. During construction, the owner refused
    to pay the contractor after discovering markups on the cost of materials.
    In response, the contractor halted construction and filed an action to
    enforce a mechanic’s lien. The contractor subsequently filed a petition to
    foreclose the mechanic’s lien. Although the contractor did not complete
    construction, the district court found the contractor rendered substantial
    performance under the contract and entered a judgment against the
    owner.    The court of appeals affirmed, and we granted further review.
    For the reasons expressed below, we affirm in part and vacate in part the
    decision of the court of appeals, reverse the judgment of the district
    court, and remand the case for further proceedings.
    I. Factual and Procedural Background.
    This case involves a dispute between Gregg Flynn (Flynn) and
    Matthew and Chris Lande.            In early 2009, the Landes were seeking a
    builder to construct a new home. Flynn, the owner of Flynn Builders,
    L.C., submitted to the Landes a bid to construct the home for $259,576.
    The bid included a line item for a “materials package” in the amount of
    $61,223.77. The Landes accepted the bid, and Flynn began construction
    in May 2009.
    1The  defendants raise six separate issues in their application for further review.
    In the exercise of our discretion, we choose to only address the issue related to
    substantial performance of the construction contract. As to the other issues raised on
    appeal, the court of appeals’ opinion will stand as the final decision in this appeal. See
    State v. Rodriguez, 
    807 N.W.2d 35
    , 37 (Iowa 2011).
    3
    Construction     continued      until   early   July   when     the   Landes
    discovered the materials package included a $20,000 markup that Flynn
    did not disclose.2 Though the markup did not increase the agreed upon
    price, the Landes’ lender and the Landes refused to pay the markup.
    Because the Landes and their lender refused to continue making
    payments, Flynn stopped construction on the project and filed a
    mechanic’s lien for $28,307.50 in the district court.
    In August 2009, Flynn filed a petition to enforce the mechanic’s
    lien. In their answer, the Landes denied the existence of a contract and
    made no counterclaim. The matter proceeded to trial in May 2010.
    During trial, Flynn testified that his duties as a general contractor
    were nearly completed when he left the project. He explained that, while
    the plumbing, drywall, paint, carpet, floor coverings, and trim remained
    unfinished, arrangements had been made with various subcontractors to
    complete the work. According to Flynn, “Everything was ready to go. . . .
    [A]ll Matt [Landes] had to do is contact the individual sub[contractors],
    even after I walked off, to have them come complete their jobs.” Brian
    Stolte, an employee of Flynn, testified Flynn completed between eighty
    and eighty-five percent of the project, possibly more, before leaving.
    Stolte stated the insulation, drywall, trim, and flooring remained
    unfinished when Flynn left.         The unfinished trim, which would have
    taken two weeks to complete, included the installation of cabinets, doors,
    and windows. Stolte further stated that a day of work remained with the
    heating and air conditioning and the concrete was not poured in the
    front of the garage. Stolte estimated that it would have taken a total of
    five to seven weeks to complete the four-to-five month project.
    2A   markup is defined as “[a]n amount added to an item’s cost to determine its
    selling price.” Black’s Law Dictionary 1059 (9th ed. 2009).
    4
    According to Matt Lande, “[t]he whole house was pretty much
    studs” when Flynn stopped working on the project.             He stated the
    basement doors and garage doors were not installed and that the siding
    was only partially completed.      Lande also testified that he, not Flynn,
    was in fact the general contractor on the project. Lande explained he
    understood the agreement to be that Flynn would frame, side, and
    shingle     the   house,   and   both   Flynn   and   Lande   would   recruit
    subcontractors to build the house.
    Following trial, the district court held, inter alia, Flynn was entitled
    to enforce the mechanic’s lien because Flynn substantially performed the
    contract.    The court concluded Flynn was a general contractor of the
    project and that the general contracting markup fee of $20,000 was
    “appropriate and in accordance with standards of the industry.”           The
    court stated that Matt Lande acted in large part as a general contractor
    during construction. Addressing the substantial performance issue, the
    court found that Flynn’s completion of eighty percent of the project
    amounted to substantial performance of the contract. The court stated
    “the credibility of the parties was given substantial weight in reaching
    [the court’s] ultimate conclusion.” The court entered a judgment in the
    amount of $16,574.75, plus interest, against the Landes.         The Landes
    appealed.
    On appeal, the Landes argued the district court erred in finding
    Flynn substantially performed.      The Landes noted the home was only
    eighty to eighty-five percent complete when Flynn stopped working on
    the project.       The Landes observed a number of items remained
    unfinished on the project, including installing insulation, drywall,
    flooring, and trim. The Landes also asserted Flynn breached the contract
    5
    by walking off the job before completing the project. The court of appeals
    affirmed.
    The court of appeals reasoned that Flynn substantially performed
    the contract because the home was “framed, enclosed, roofed, sided (with
    a minor exception), and the electrical and plumbing were roughed-in.”
    The court explained evidence in the record established the home was
    seventy to ninety-five percent complete when Flynn left the project. The
    court further noted the record was devoid of any indication of bad faith
    on the part of Flynn or that the unfinished portion of the home impaired
    the structure as a whole.    The Landes filed an application for further
    review, which we granted.
    II. Standard of Review.
    Actions to enforce mechanic’s liens are in equity.       Carson v.
    Roediger, 
    513 N.W.2d 713
    , 715 (Iowa 1994).       Our review is therefore
    de novo. 
    Id. In our
    de novo review, the district court’s fact findings are
    given weight, but we are not bound by them. 
    Id. This court
    has stated
    in mechanic’s lien cases, “involving as they do numerous charges and
    counter charges which depend entirely on the credibility of the parties,
    we have frequently held the trial court is in a more advantageous
    position than we to put credence where it belongs.” McDonald v. Welch,
    
    176 N.W.2d 846
    , 849 (Iowa 1970).
    III. Discussion.
    A. Law    Related     to   Mechanic’s   Liens    and   Substantial
    Performance. Mechanic’s liens were not recognized at common law and
    are purely a creature of statute. See Clemens Graf Droste Zu Vischering
    v. Kading, 
    368 N.W.2d 702
    , 708 (Iowa 1985); Roger W. Stone, Mechanic’s
    Liens in Iowa, 30 Drake L. Rev. 39, 41 (1980) [hereinafter Stone].
    Mechanic’s lien statutes are designed to protect “persons who have
    6
    supplied labor or material for the construction, improvement, or repair of
    a building or other structure by giving the lienholders security
    independent of their contractual remedies against the owner of the
    property, if any.” Stone, 30 Drake L. Rev. at 42. Although mechanic’s
    lien statutes are in derogation of the common law, they are liberally
    construed “ ‘with a view to promote its objects and assist the parties in
    obtaining justice.’ ”   Gollehon, Schemmer & Assocs., Inc. v. Fairway-
    Bettendorf Assocs., 
    268 N.W.2d 200
    , 201 (Iowa 1978) (citation omitted).
    The Iowa territorial government enacted the first mechanic’s lien
    statute in Iowa in 1838. The Statute Laws of the Territory of Iowa 349
    (1839); Stone, 30 Drake L. Rev. at 41.         Though the statute has
    undergone a series of amendments since its adoption, Stone, 30 Drake L.
    Rev. at 41–42, Iowa caselaw has developed a requirement that in order to
    enforce a mechanic’s lien, the work must be substantially performed by
    the contractor, Keys v. Garben, 
    149 Iowa 394
    , 395, 
    128 N.W. 337
    , 337
    (1910); see also S. Hanson Lumber Co. v. De Moss, 
    253 Iowa 204
    , 208,
    
    111 N.W.2d 681
    , 684 (1961); Farrington v. Freeman, 
    251 Iowa 18
    , 23, 
    99 N.W.2d 388
    , 391 (1959); Peterman v. Hardenbergh, 
    250 Iowa 931
    , 933,
    
    97 N.W.2d 152
    , 154 (1959); S.D. & D.L. Cota Plastering Co. v. Moore, 
    247 Iowa 972
    , 978, 
    77 N.W.2d 475
    , 478 (1956); Huffman v. Hill, 
    245 Iowa 935
    , 938, 
    65 N.W.2d 205
    , 206 (1954). The more recent applications of
    the substantial performance doctrine in Iowa appear in published
    decisions of the Iowa Court of Appeals. See, e.g., Nepstad Custom Homes
    Co. v. Krull, 
    527 N.W.2d 402
    , 406 (Iowa Ct. App. 1994); Moore’s Builder &
    Contractor, Inc. v. Hoffman, 
    409 N.W.2d 191
    , 194 (Iowa Ct. App. 1987).
    Our caselaw in this regard is consistent with the law in a significant
    number of states. See 53 Am. Jur. 2d Mechanic’s Liens § 49, at 133–34
    (2006).
    7
    In Huffman, the court explained that “a technical, exact and
    perfect performance is not necessary” in an action to foreclose a
    mechanic’s lien. 
    Huffman, 245 Iowa at 938
    , 65 N.W.2d at 206. So long
    as the builder substantially performs the contract, the builder “is entitled
    to the contract price less reasonable damages on account of slight
    defects in performance.”   
    Id. This court
    elaborated on the substantial
    performance doctrine in Farrington, stating,
    “ ‘Substantial performance,’ as defined by the cases, permits
    only such omissions or deviations from the contract as are
    inadvertent or unintentional, are not due to bad faith, do not
    impair the structure as a whole, are remediable without
    doing material damage to other parts of the building in
    tearing down and reconstructing, and may without injustice
    be compensated for by deductions from the contract price.
    So much is allowed in building contracts because of the
    hardship to the contractor if slight, unintentional deviations
    should bar his recovery.”
    
    Farrington, 251 Iowa at 24
    , 99 N.W.2d at 391 (quoting Littell v. Webster
    Cnty., 
    152 Iowa 206
    , 215, 
    131 N.W. 691
    , 694 (1911)).
    The concept of substantial performance in the mechanic’s lien
    context is derived from contract law.     In Farrington, for example, the
    court’s definition of substantial performance was taken directly from a
    breach of contract case. See 
    Farrington, 251 Iowa at 24
    , 99 N.W.2d at
    391; 
    Littell, 152 Iowa at 215
    , 131 N.W. at 694. In the area of contracts,
    “[s]ubstantial performance is performance without a material breach,
    and a material breach results in performance that is not substantial.”
    II E. Allan Farnsworth, Farnsworth on Contracts § 8.16, at 518 (3d ed.
    2004); see also 5 Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner &
    O’Connor Construction Law § 18:12, at 892–93 (2002) (“Substantial
    performance means the contractor has completed its work to such an
    extent that it cannot be said to have materially breached the contract.”);
    Richard A. Lord, Williston on Contracts § 44:55, at 232–33 (4th ed. 2000)
    8
    (“A breach of a contract is not material if substantial performance has
    been rendered.”).
    B. Application of Law to Facts. With these principles in mind,
    we now turn to the facts in this case. In our de novo review, we conclude
    Flynn did not substantially perform the contract.      We note that more
    than simply punch-list items remained to be completed when Flynn left
    the project. See Cont’l Ill. Nat’l Bank & Trust Co. v. United States, 101 F.
    Supp. 755, 758 (Ct. Cl. 1952) (holding unfinished punch-list items did
    not amount to material breach); Pettit v. Hampton & Beech, Inc., 
    922 A.2d 300
    , 305 (Conn. App. Ct. 2007) (substantial performance even though
    punch-list items totaling $5000 unfinished). Flynn himself testified that,
    although he made arrangements with subcontractors to complete the
    house, the plumbing, drywall, paint, carpet, floor coverings, and trim
    remained unfinished.     According to Stolte, Flynn’s own witness, the
    unfinished trim included the installation of cabinets, doors, and
    windows.   Stolte also stated the heating and air conditioning was not
    complete and the concrete had not been poured in front of the garage.
    Stolte estimated it would take an additional five to seven weeks to
    complete the project.    All told, Stolte believed Flynn completed only
    eighty to eighty-five percent of the project when the contract was
    terminated. See Carefree Bldg. Prods., Inc. v. Belina, 
    564 N.Y.S.2d 852
    ,
    854 (App. Div. 1991) (holding, as a matter of law, contractor failed to
    substantially perform when deficiencies represented twenty-five percent
    of contract price); Jerry B. Wilson Roofing & Painting, Inc. v. Jobco-E.R.
    Kelly Assocs., Inc., 
    513 N.Y.S.2d 263
    , 265 (App. Div. 1987) (fifteen
    percent); Fuchs v. Saladino, 
    118 N.Y.S. 172
    , 176 (App. Div. 1909) (fifteen
    percent). While “[n]o mathematical rule relating to the percentage of the
    price, of cost of completion or of completeness can be laid down to
    9
    determine substantial performance of a building contract,” Plante v.
    Jacobs, 
    103 N.W.2d 296
    , 298 (Wis. 1960), the work left unfinished in
    this case was much more than a technical or inadvertent omission;
    rather, the omissions materially affected the habitability of the house.
    See Nelson v. Hazel, 
    406 P.2d 138
    , 144 (Idaho 1965) (“The mere fact that
    a shell was constructed containing the rooms outlined in the contract,
    does not in itself mean that the contract was substantially performed.”).
    We acknowledge the record demonstrates Matt Lande agreed to
    perform some tasks that are ordinarily the responsibility of a general
    contractor.      But    the    owner’s   willingness   to   take     on   additional
    responsibilities      does    not   absolve   the   builder’s   responsibility    to
    substantially perform the work the builder agreed to perform.                 While
    Matt Lande had the ability to contact Flynn’s subcontractors to complete
    the work, the responsibility to complete the project was Flynn’s in his
    capacity as general contractor. As observed by the Wisconsin Supreme
    Court,
    the owner has a right to contract for the completed structure
    or work and in the building of a house the contract price
    pays for the relief from trouble and personal effort on the
    part of the owner in respect to building.
    Kreyer v. Driscoll, 
    159 N.W.2d 680
    , 681–82 (Wis. 1968) (holding $50,000
    contract for building of house not substantially performed when $4650
    remained); see also Harris v. Desisto, 
    932 S.W.2d 435
    (Mo. Ct. App.
    1996) (stating the general contractor “cannot argue that he had
    substantially performed under the agreement when it is obvious that [the
    developer] had performed in his stead and that [l]ogically, under a claim
    of substantial performance, [the general contractor] cannot claim the
    benefits   of   the    [developers’]   efforts   precipitated   by    [the   general
    contractor’s] breach as a basis for avoiding the effect of the breach”);
    10
    Local Union No. 964, United Bros. of Carpenters & Joiners of Am. v.
    Lighting Servs., Inc., 
    557 N.Y.S.2d 764
    , 765 (App. Div. 1990) (holding
    that, although certificate of occupancy had been delivered, evidence in
    the record established work that should have been done by the
    contractor was performed by others).
    C. Disposition.    Having determined Flynn did not substantially
    perform the contract, we recognize that there may be additional legal and
    factual issues that were not reached by the district court that could have
    an impact on the disposition of this case.     The district court did not
    address, for instance, the factual disputes in the record for the reason
    Flynn walked off the job and whether lack of specific performance might
    be excused by the conduct of the Landes. See Horsfield Constr., Inc. v.
    Dubuque Cnty., 
    653 N.W.2d 563
    , 573 (Iowa 2002) (stating that
    anticipatory repudiation “excuses performance on the part of the non-
    breaching party”).      The district court also did not address the
    significance, if any, of the hidden nature of the markup on the ability of
    Flynn to enforce a mechanic’s lien.        We intimate no view on these
    questions, but remand the case on the current record for further
    proceedings. See, e.g., Lewis Elec. Co. v. Miller, 
    791 N.W.2d 691
    , 694–96
    (Iowa 2010) (reversing based on lack of evidence of substantial
    performance and remanding for new findings “on the basis of the current
    record”); Sauder v. Union Produce Coop., 
    592 N.W.2d 695
    , 698 (Iowa
    1999) (remanded for findings on an issue the district court did not
    consider “on the existing record”).
    IV. Conclusion.
    For the reasons discussed above, we hold that the trial court erred
    in concluding that Flynn had substantially completed work for the
    Landes. On this issue, we vacate the opinion of the court of appeals,
    11
    reverse the judgment of the district court, and remand the case for
    further proceedings. The opinion of the court of appeals is affirmed as to
    all other issues raised in this appeal.
    DECISION OF COURT OF APPEALS AFFIRMED IN PART AND
    VACATED IN PART; DISTRICT COURT JUDGMENT REVERSED, AND
    CASE REMANDED FOR FURTHER PROCEEDINGS.