Lemartec Engineering & Construction n/k/a Lemartec Corporation v. Advance Conveying Technologies, LLC ( 2020 )


Menu:
  •                IN THE SUPREME COURT OF IOWA
    No. 18–2183
    Filed March 20, 2020
    LEMARTEC ENGINEERING & CONSTRUCTION n/k/a LEMARTEC
    CORPORATION,
    Appellant,
    vs.
    ADVANCE CONVEYING TECHNOLOGIES, LLC,
    Appellee.
    Appeal from the Iowa District Court for Monroe County, John
    Telleen, Judge.
    On interlocutory appeal of a district court order granting summary
    judgment in appellee’s favor, appellant argues appellee is not entitled to
    claim preclusion or issue preclusion even though the federal court found
    in appellee’s favor in the parallel federal case.      REVERSED AND
    REMANDED WITH DIRECTIONS.
    Erik W. Scharf, Miami, Florida, Mark L. Tripp, Andrew C. Johnson,
    Thomas M. Boes, and Robert J. Thole of Bradshaw, Fowler, Proctor &
    Fairgrave, P.C., Des Moines, and Jason L. Molder, Miami Florida, for
    appellant.
    Kevin J. Caster and Dana L. Oxley of Shuttleworth & Ingersoll,
    P.L.C., Cedar Rapids, for appellee.
    2
    APPEL, Justice.
    In this construction law case, we consider the applicability of the
    doctrines of claim and issue preclusion to disputes arising out of a contract
    between two subcontractors in a construction project.
    First, a dispute arose around the fabrication and operation of a salt
    conveyor system. In federal litigation, a number of subcontracting parties
    litigated questions related to the fabrication of the salt conveyor system
    prior to litigation.   The federal controversy was eventually reduced to
    judgment.
    The   owner      of    the   facility       filed   a   second   lawsuit   against
    subcontractors involved in the federal litigation in state court. The owner
    claimed in the state court litigation that after installation, the salt conveyor
    system developed corrosion issues in breach of contract and express and
    implied warranties.         The parties filed various cross-claims, with one
    contractor seeking indemnity from the fabricator of the salt conveyor
    system.
    After the federal litigation was resolved, a successful subcontractor
    in the federal litigation brought a motion for summary judgment in the
    state court action, arguing that determinations in the federal litigation
    precluded parties from litigating issues related to the salt conveyor system
    in state court.
    The district court granted summary judgment to the successful
    federal subcontractor on claim and issue preclusion grounds.                          A
    disappointed party sought interlocutory appeal, claiming, among other
    things, that the successful party in the federal litigation waived its claim
    preclusion argument in the state court litigation because it failed to give
    notice of intent to pursue claim preclusion in the simultaneously pending
    state court litigation.        On the question of issue preclusion, the
    3
    disappointed party asserted that it had no reasonable opportunity in
    federal court to litigate its indemnity claim related to the alleged corrosion
    problems that arose after the salt conveyor equipment was installed and,
    therefore, issue preclusion did not apply.
    We granted the application for interlocutory review. For the reasons
    expressed below, we conclude that the district court erred in granting
    summary judgment based on claim and issue preclusion under the facts
    of this case.
    I. Factual and Procedural Background.
    A. Relationship of the Parties.        In 2013, HF Chlor-Alkali, LLC
    (HFCA) entered into a written agreement with Conve & AVS, Inc. (Conve)
    to construct a chlor-alkali manufacturing facility (the Project) in Eddyville,
    Iowa. Conve in turn entered into a subcontract with Lemartec Engineering
    & Construction n/k/a Lemartec Corporation (Lemartec) to design and
    build the physical plant for the Project which included a salt conveyor
    system (conveyor system).
    Lemartec subcontracted part of the work on the conveyor system to
    two other entities. Lemartec, through a purchase order, hired Advance
    Conveying Technologies, LLC (ACT) for the design and manufacture of the
    conveyor system.      Later, Lemartec entered into a subcontract with
    Southland Process Group, LLC (SPG) for the installation and erection of
    the conveyor system at the Project location.
    The conveyor system aspect of the Project did not proceed smoothly.
    SPG claimed that there were problems with the component parts supplied
    by ACT. Lemartec contacted ACT, claiming deficiencies in ACT’s work.
    SPG eventually finished the work but claimed that it incurred significant
    additional costs and that Lemartec and ACT were responsible for them.
    4
    B. Filing of Federal Court and State Court Litigation.
    1. Overview of federal court litigation. The first litigation arrow in
    this case was fired by SPG on October 16, 2015, in the United States
    District Court for the Southern District of Iowa. SPG sought to recover its
    additional expenses related to the assembly of the conveyor system from
    Lemartec and ACT.      Lemartec and SPG settled outstanding disputes
    between them, leaving ACT’s claim that Lemartec improperly withheld
    from ATC the balance owed under the purchase order to be litigated.
    2. Overview of state court litigation.   The completed Project was
    turned over to Conve in June 2015 and later to owner HFCA. HFCA was
    dissatisfied with many aspects of the Project. As a result, HFCA launched
    the second litigation arrow in this case in state court, naming a number of
    defendants including Conve. HFCA alleged, among other things, that the
    conveyor system was installed, turned over and put to use, and failed to
    perform to specifications.   Conve, in turn brought a third-party claim
    against Lemartec for indemnification and contribution.        Lemartec on
    June 5, 2017, brought a third-party claim against ACT.
    ACT filed an answer to Lemartec’s third-party claim. In its answer,
    ACT did not make reference to the pending federal litigation and did not
    raise a res judicata affirmative defense.
    Discovery proceeded in the state court litigation. On June 14, 2018,
    HFCA served interrogatory responses on the parties. According to the
    responses, HFCA claimed that the conveyor system failed to perform in
    that the conveyor components and electrical system corroded; the
    conveyor belt did not pass approval testing; the bucket system leaked,
    corroded, and fell apart; and the equipment ruptured due to the failure to
    prevent vibrations.
    5
    3. Federal court judgment. The federal court held a bench trial in
    the federal litigation in April 2018. The federal court characterized the
    issue to be tried as “whether either of the two remaining parties [Lemartec
    and/or ACT] owes money to the other for money earned, but unpaid;
    project delays; and for additional work that was required to make the
    conveyor system functional.”
    On May 21, 2018, the federal district court entered its ruling in favor
    of ACT. The federal district court awarded ACT $317,467.07 plus interest.
    Lemartec has appealed the case to the United States Court of Appeals for
    the Eighth Circuit.
    4. Summary judgment in state court proceedings based on preclusive
    effect of federal judgment. On August 15, 2018, ACT filed a motion for
    summary judgment in the state court proceedings. In its moving papers,
    ACT claimed that the judgment in the federal litigation compelled
    judgment in its favor in the state court litigation. Lemartec responded, in
    part, that res judicata is an affirmative defense that must be raised in an
    answer and that ACT had failed to do so. In response, on October 31,
    2018, ACT filed a motion to amend its answer to include a res judicata
    affirmative defense. Lemartec opposed the motion.
    The district court granted ACT’s motion for summary judgment. The
    district court rejected Lemartec’s argument that ACT waived its right to
    assert preclusion where litigation is simultaneous by failing to provide
    Lemartec with notice. On the question of claim preclusion, the district
    court found that the claims in the federal and state actions were similar
    because they are “premised on the contractual relationship between
    Lemartec and ACT.”       Turning to issue preclusion, the district court
    reasoned that “the issue of indemnity rights arising under the Purchase
    Order has been raised and litigated in the prior federal action.” As a result,
    6
    the district court granted summary judgment on both claim preclusion
    and issue preclusion. Lemartec appealed. We retained the case for our
    consideration.
    III. Claim Preclusion.
    A. Introduction. This case involves the related concepts of claim
    preclusion and issue preclusion.
    1. Claim preclusion. Claim preclusion is “based on the principle
    that a party may not split or try his claim piecemeal . . . . A party must
    litigate all matters growing out of his claim at one time and not in separate
    actions.” Iowa Coal Mining Co. v. Monroe County, 
    555 N.W.2d 418
    , 441
    (Iowa 1996) (quoting B & B Asphalt Co. v. T.S. McShane Co., 
    242 N.W.2d 279
    , 286 (Iowa 1976)). “Once an issue has been resolved, there is no
    further fact-finding function to be performed.” Colvin v. Story Cty. Bd. of
    Review, 
    653 N.W.2d 345
    , 349 (Iowa 2002).
    2. Issue preclusion.     Issue preclusion prevents a party “from
    relitigating in a subsequent action issues raised and resolved in [a]
    previous action.” Soults Farms, Inc. v. Shafer, 
    797 N.W.2d 92
    , 103 (Iowa
    1981). “[W]here a particular issue or fact is litigated and decided, the
    judgment estops both parties from later litigating the same issue.” Grant
    v. Iowa Dep’t of Human Servs., 
    722 N.W.2d 169
    , 174 (Iowa 2006). Issue
    preclusion applies to both factual and legal issues raised and resolved in
    a previous action. See Barker v. Iowa Dep’t of Pub. Safety, 
    922 N.W.2d 581
    , 587 (Iowa 2019).
    The doctrine “serves a dual purpose: to protect litigants from ‘the
    vexation of relitigating identical issues with identical parties’ ” and to
    further “the interest of judicial economy and efficiency by preventing
    unnecessary litigation.” Winnebago Indus. v. Haverly, 
    727 N.W.2d 567
    ,
    571–72 (Iowa 2006) (quoting Am. Family Mut. Ins. v. Allied Mut. Ins., 562
    
    7 N.W.2d 159
    , 163 (Iowa 1997)). Issue preclusion “prevent[s] the anomalous
    situation, so damaging to public faith in the judicial system, of two
    authoritative but conflicting answers being given to the very same
    question.” Emp’rs Mut. Cas. v. Van Haaften, 
    815 N.W.2d 17
    , 22 (Iowa
    2012) (quoting Grant, 
    722 N.W.2d at 178
    ).
    In order to successfully invoke issue preclusion,
    (1) the issue in the present case must be identical, (2) the issue
    must have been raised and litigated in the prior action, (3) the
    issue must have been material and relevant to the disposition
    of the prior case, and (4) the determination of the issue in the
    prior action must have been essential to the resulting
    judgment.
    Fischer v. City of Sioux City, 
    654 N.W.2d 544
    , 547 (Iowa 2002).
    B. Position of Lemartec.
    1. Waiver of claim preclusion. Lemartec claims that ACT waived its
    right to assert claim preclusion in the state litigation.       According to
    Lemartec, when two cases are pending simultaneously, a litigant must
    invoke claim-splitting remedies in the litigation or waive any claim-
    splitting relief. In support of its waiver theory, Lemartec cites section 26,
    comment a of the Restatement (Second) of Judgments, which provides,
    Where the plaintiff is simultaneously maintaining
    separate actions based upon parts of the same claim, and in
    neither action does the defendant make the objection that
    another action is pending based on the same claim, judgment
    in one of the actions does not preclude the plaintiff from
    proceeding and obtaining judgment in the other action. The
    failure of the defendant to object to the splitting of the
    plaintiff’s claim is effective as an acquiescence in the splitting
    of the claim.
    Restatement (Second) of Judgments § 26 cmt. a, at 235 (Am. Law Inst.
    1982) [hereinafter Restatement (Second)]. Lemartec asserts that this court
    adopted the approach of the comment in Pagel v. Notbohm, 
    186 N.W.2d 638
     (Iowa 1971), and Noel v. Noel, 
    334 N.W.2d 146
     (Iowa 1983). In Pagel,
    8
    the defendant filed answers in two simultaneous actions without taking
    any steps to consolidate or object to claim splitting. 
    186 N.W.2d at 639
    .
    In Noel, a son brought a district court action against his father seeking to
    recoup improvements to a leasehold, and, after his father’s death, brought
    a claim in probate related to the same subject matter. 
    334 N.W.2d at 147
    .
    The executor answered in both actions but did not note the pendency of
    the other action or ask for consolidation of the cases. 
    Id.
     After judgment
    was entered in the district court action, the executor sought to preclude
    the probate litigation. 
    Id.
     The Noel court rejected claim preclusion, noting
    that “decisions dealing with this situation hold that a party waives claim
    preclusion by failing to interpose it prior to judgment in the first case.” 
    Id. at 149
    .
    Lemartec recognized that the district court allowed ACT to amend
    its pleading to assert res judicata arising from the federal judgment after
    ACT filed its motion for summary judgment in this case. Lemartec asserts
    that res judicata is an affirmative defense “to be asserted by answer and
    cannot be raised by a motion to dismiss.” Bertran v. Glens Falls Ins., 
    232 N.W.2d 527
    , 532 (Iowa 1975) (quoting Bickford v. Am. Interinsurance Exch.,
    
    222 N.W.2d 450
    , 454 (Iowa 1974)). Lemartec asserts that by waiting until
    a judgment was entered in the federal litigation, ACT foreclosed Lemartec’s
    ability to weigh its options in the federal litigation to ensure its indemnity
    claims were not preempted. Clements v. Airport Auth., 
    69 F.3d 321
    , 329
    (9th Cir. 1995). Lemartec urges that the burden is on the defendant to
    give timely notice of an objection to claim splitting where simultaneous
    litigation is pending. Brown v. Lockwood, 
    432 N.Y.S.2d 186
    , 199 (App.
    Div. 1980).
    2. Claims arising after filing of first complaint. Lemartec asserts that
    claims in the state court litigation arose after the filing of the complaint in
    9
    the federal law suit. Based on this factual premise, Lemartec claims Iowa
    should adopt a bright-line rule that when claims arise after the filing of
    the first complaint, the doctrine of claim preclusion should not apply.
    Lemartec contends that the approach that claim preclusion does not apply
    to foreclose litigation in another forum when the claims arise after the filing
    of the first action has been adopted by courts in California, Minnesota,
    and at least seven federal circuits. 1 Lemartec recognizes that Iowa has not
    yet adopted the rule but argues that it is consistent with Iowa law and
    should be adopted now.
    In seeking to apply the after-filing, bright-line rule, Lemartec
    emphasizes that it seeks to enforce indemnity claims in the state and
    federal litigation. Lemartec observes that indemnity claims do not accrue
    until the indemnitee’s liability is fixed.           Lemartec points out that the
    federal litigation claim dealt with SPG’s claim that the performance of
    Lemartec and ACT delayed SPG’s work and increased its expenses in
    installing the conveyor system. In contrast, in the state court litigation,
    HFCA asserted that, as installed, postcompletion, the conveyor system was
    defective. The federal court claims and the state court claims, according
    to Lemartec, did not arise at the same time. See Minch Family LLLP v.
    Buffalo-Red River Watershed Dist., 
    628 F.3d 960
    , 966–67 (8th Cir. 2010).
    3. Claims materially distinguishable. Lemartec contends that ACT
    cannot assert claim preclusion because the claims in the federal and state
    litigation are materially distinguishable. Lemartec reprises its refrain: the
    1See Howard v. City of Coos Bay, 
    871 F.3d 1032
    , 1040 (9th Cir. 2017) (stating
    California rule); Bank of N.Y. v. First Millennium, Inc., 
    607 F.3d 905
    , 919 (2d Cir. 2010);
    Smith v. Potter, 
    513 F.3d 781
    , 783 (7th Cir. 2008); Rawe v. Liberty Mut. Fire Ins., 
    462 F.3d 521
    , 529–30 (6th Cir. 2006); Mitchell v. City of Moore, 
    218 F.3d 1190
    , 1202 (10th Cir.
    2000); Manning v. City of Auburn, 
    953 F.2d 1355
    , 1360 (11th Cir. 1992); Mach v. Wells
    Concrete Prods. Co., 
    866 N.W.2d 921
    , 925 (Minn. 2015); cf. Young-Henderson v.
    Spartanburg Area Mental Health Ctr., 
    945 F.2d 770
    , 774 (4th Cir. 1991) (allowing for the
    possibility of claims that could not be raised at the time of initial filing).
    10
    federal suit involved a claim for indemnity based on SPG’s precompletion
    allegations, while the state court litigation involves a claim for indemnity
    based upon HFCA’s and Conve’s postcompletion allegations.
    Lemartec argues that a comparison of the federal district court’s
    ruling and the pleadings in the state court litigation proves the point. In
    its ruling, the federal district court noted that “[o]ther parties, and in large
    part Lemartec itself, caused the delays that Lemartec failed to prove were
    caused by ACT.” Further, the federal district court observed that “the
    evidence is that ACT delivered product within a reasonable amount of time
    from Lemartec’s implementation of the fast-track delivery system.”           In
    contrast, Lemartec argues the state court litigation focuses on HFCA’s
    allegations that the conveyor system, as installed, failed to meet
    expectations.
    Lemartec cites Iowa Coal Mining Co. for the general proposition that
    “if . . . the two actions rest upon different states of facts, or if different
    proofs would be required to sustain the two actions, a judgment in one is
    no bar to the maintenance of the other.” 
    555 N.W.2d at 441
     (quoting
    Phoenix Fin. Corp. v. Iowa-Wis. Bridge Co., 
    237 Iowa 165
    , 176, 
    20 N.W.2d 457
    , 462 (1945)). Lemartec notes, but does not address, potential contrary
    authority in Villarreal v. United Fire & Casualty Co., 
    873 N.W.2d 714
    , 729
    (2016).
    Finally, Lemartec challenges the assertion of the state district court
    that “Lemartec cannot maintain an action on its contractual rights under
    the Purchase Order after previously bringing suit on an alleged breach of
    the same agreement.”       Lemartec argues that the state district court
    overlooked the distinction between a “total breach” of contract, where the
    plaintiff sues for the entire value of the contract based on total breach, and
    a partial breach, where there can be multiple breaches of contract. In
    11
    support of its argument, Lemartec cites section 26, comment g of the
    Restatement (Second) of Judgments, which states,
    A judgment in an action for breach of contract does not
    normally preclude the plaintiff from thereafter maintaining an
    action for breaches of the same contract that consist of failure
    to render performance due after commencement of the first
    action.
    Restatement (Second) §26 cmt. g, at 240. Thus, according to Lemartec,
    the fact that the claims in the federal court and the state court litigations
    both relate to the same purchase order is not dispositive if separate issues
    are raised.
    C. Position of ACT.
    1. Transactional approach.      Whether to apply claim preclusion
    turns, in part, on the definition of a “claim.” ACT asserts that we have
    applied “the transactional approach of the Restatement.”         Under the
    Restatement (Second) of Judgments, “the claim extinguished includes all
    rights of the plaintiff to remedies against the defendant with respect to all
    or any part of the transaction, or series of connected transactions, out of
    which the action arose.” Restatement (Second) § 24, at 196. As seen from
    the above passage, the question of claim turns upon the scope of the
    “transaction.” ACT notes that Lemartec in its pleading in both cases, pled,
    nearly verbatim, breach of contract, breach of implied warranty of
    workmanlike construction, breach of implied warranty of fitness for a
    particular purpose, and breach of express warranty. ACT further claims
    that the only transaction in both cases that gives rise to the claims is the
    purchase order wherein ACT agreed to “perform and complete all Work
    required for the proper execution and completion of all Salt Conveyor
    Systems Supply work for the Project.”
    12
    In its analysis of the scope of a transaction, ACT recognizes that the
    claims of Lemartec are indemnity claims. But, according to ACT, once a
    first action seeking indemnification is launched, the party seeking
    indemnify must pursue all theories of recovery at that time where there is
    no claim that the new theories arose subsequent to resolution of the first
    indemnity claim. Arnevik v. Univ. of Minn. Bd. of Regents, 
    642 N.W.2d 315
    ,
    320 (Iowa 2002) (“[O]nce [the employee] started down the path in the first
    action seeking indemnification from [her employer], she was required to
    bring all theories of recovery at that time.”) Further, because Lemartec
    amended its complaint in the federal litigation to include the underlying
    claims of breach of contract, breach of warranty, etc., Lemartec was
    required to bring all claims arising out of the transaction.
    2. Not “materially different.” ACT next addresses the question of
    whether the indemnity claim in the state litigation is “materially different”
    from the claims raised and litigated in the federal court litigation. ACT
    notes that perfect identity of evidence is not required to assert claim
    preclusion. See Villarreal, 873 N.W.2d at 729; Restatement (Second) § 25,
    at 209–10. While ACT recognizes that Lemartec relies on a “later events”
    theory to avoid preclusion, ACT characterized the “later events” theory as
    inapposite because the claims in both cases arise out of the same
    obligations owed by ACT.
    Further, ACT asserts that Lemartec in the federal litigation alleged
    a significant number of defects. Lemartec claimed in the federal litigation
    that the ACT’s deficiencies “included, but were not limited to”
    [d]efective handrail on transfer tower, defective stairs on
    transfer tower, defective hopper rail car unload pit, defective
    rail car uploading pit, defective skirt boards, defective tripper
    car, defective festoon, defective gear box and head pully,
    defective pan feeder rail car pit, defective stops for tripper car,
    13
    defective collector chute to bucket elevator, and defective
    catwalk between transfer tower and salt building.
    Further, ACT notes that Lemartec asserted, “ACT’s numerous deficiencies
    in designing and manufacturing the Salt Conveyer in accordance with the
    Project specification drawings shows that ACT failed to follow specific
    plans, which supports Lemartec’s implied contractual indemnity claim.”
    But, ACT asserts that in the federal litigation it proved that the conveyor
    system was 100% operational after it was installed.
    In response to Lemartec’s argument that the case involves multiple
    partial breaches under section 26, comment g of the Restatement (Second)
    Judgments, ACT asserts that the notion of a partial breach applies only to
    a contract involving ongoing obligations such as an employment contract.
    ACT argues that in this case, ACT’s performance under the purchase order
    was completed by June 2015.
    3. Timing of Lemartec’s claims. ACT addresses Lemartec’s assertion
    that the state court litigation claims arose after the claims litigated in
    federal court. According to ACT, Lemartec did not limit its defect claims
    in the federal litigation to the installation or precompletion period.    In
    particular, ACT notes that Lemartec argued, in order to avoid summary
    judgment, that “ACT shall Guarantee the work for 18 months after delivery
    of Equipment or 12 months after Start-up, whichever is sooner.”           In
    response, ACT argues that it put on evidence at the federal trial that the
    equipment was fully operational after it was installed. So ACT claims that
    in the federal litigation, Lemartec did raise claims related to the operation
    of the conveyor system.
    In the alternative, ACT challenges Lemartec’s assertion that the
    Lemartec’s state court indemnity claims arose after the indemnity claims
    asserted in federal court. ACT notes that while the litigation between ACT
    14
    and Lemartec began as indemnity and contribution claims, Lemartec
    amended its pleadings in both forums in October 2017 to include nearly
    identical claims for breach of contract, breach of implied warranties, and
    breach of express warranties.      ACT presses its point by noting that
    Lemartec’s amended pleading in state court was filed one day prior to its
    similar amended pleading in federal court. ACT notes that the conveyor
    system was completed in May 2015 and turned over to Conve in June
    2015, well before the October 2017 date.
    ACT recognizes that serial breaches of contract may occur. Such
    successive contract claims arise, according to ACT, only where the
    contracting party fails to render performance due after the beginning of
    the first action. Here, according to ACT, it had no performance due after
    the delivery of the conveyor system to Conve in June 2015.
    ACT further challenges Lemartec’s effort to rely on the June 2018
    date of the discovery responses served by HFCA to support its claim that
    the state court claims arose after the filing of the federal litigation.
    According to ACT, it is not the date of discovery that matters but instead
    the date when the act or event giving rise to the claim occurred.
    4. Rejection of bright-line rule. ACT argues that Iowa courts should
    reject Lemartec’s invitation to adopt a bright-line rule that claims arising
    after the filing of the first action are not subject to preclusion in later
    litigation, at least where application of the rule would be inconsistent with
    the transactional approach. In support of its argument, ACT cites Pavone
    v. Kirk, 
    807 N.W.2d 828
    , 830–31 (Iowa 2011).           In Pavone, a party
    successful in a first contract action sought to bring a second contract
    action alleging a breach similar to the first that occurred after the first
    litigation was commenced. 
    Id.
     ACT argues Pavone is determinative here.
    15
    5. No waiver. ACT argues that it did not waive or acquiesce in claim
    splitting. ACT asserts that in Pagel, the father brought part of his claim
    for his son’s wrongful death in one action and the other part for his
    personal injuries and property in another. Similarly, according to ACT, in
    Noel, the son brought part of his claim for a declaration of rights in one
    action and the other part for damages in another.
    Here, according to ACT, Lemartec has brought the exact same claim
    in both cases. As a result, ACT claims there was no claim splitting under
    section 26, comment a of the Restatement (Second) of Judgments, to
    which ACT needed to object.
    Further, ACT claims it did, in fact, object to the expansion of claims
    by Lemartec through its amendment in the federal litigation. Further, in
    the state court action, ACT sought to amend its answer to assert a
    res judicata defense early in the litigation. And, according to ACT, the fact
    that Lemartec in its settlement with SPG in the federal case included a
    release of all claims between SPG and Lemartec in the state court shows
    that Lemartec was aware of the relationship between the two cases.
    Finally, ACT notes that the waiver exception to claim preclusion does not
    apply to issue preclusion. See Noel, 
    334 N.W.2d at
    149–50.
    D. Discussion. On the issue of claim preclusion, we have several
    potential arguments to consider.          We conclude, however, that our
    approach to simultaneous litigation embraced by section 26, comment a
    of the Restatement (Second) of Judgments, and adopted in Noel and Pagel,
    is dispositive on the claim preclusion issue.
    Noel and Pagel deal with the narrow question of how to treat
    simultaneous claims in different forums that arguably deal with
    overlapping disputes. The approach in these cases is a pragmatic one,
    based on the notion that in the unusual context of simultaneous litigation
    16
    involving the same subject matter, the courts and the parties are entitled
    to notice and an opportunity to develop a framework for the resolution of
    the overlapping issues.
    Here, the federal litigation proceeded to judgment without any
    suggestion from ACT that claim preclusion might be involved. The burden
    is on ACT to give a timely notice under Noel and Pagel that claim preclusion
    might be implicated in light of the simultaneously ending state court
    litigation. Clements, 
    69 F.3d at 329
    .
    A notice under Noel and Pagel is hardly timely when made after a
    judgment has been entered in the first litigation. Indeed, as stated in Noel,
    the executor did not raise potential preclusion until a judgment was
    obtained in the first action and then tried to interpose the judgment to
    preclude the second action.     
    334 N.W.2d at
    148–49.       The Noel court
    rejected this approach, noting that “decisions dealing with this situation
    hold that a party waives claim preclusion by failing to interpose it prior to
    judgment in the first case.” 
    Id. at 149
    . Further, the Noel court stated that
    the executor in that case “waived claim preclusion by failing to interpose
    it appropriately before judgment in the declaratory action.” 
    Id.
    Pagel is consistent with the approach in Noel. In Pagel, the court
    considered a scenario in which a plaintiff instituted two separate actions
    that gave rise to potential claim splitting. The question before the court in
    Pagel was whether
    a defendant can lie back without pleading splitting, let his
    opponent proceed to judgment in the first action, and then
    amend his answer in the second action to aver that the
    plaintiff is foreclosed by splitting from prosecuting the second
    action.
    
    186 N.W.2d at 640
    . The Pagel court noted that “[b]y waiting to interpose
    splitting by amendment until after judgment in the first action, defendants
    17
    placed plaintiff in an inextricable position.” 
    Id. at 641
    . The Pagel court
    found the claim-splitting issue waived. 
    Id.
    As a result, we hold under Noel and Pagel that ACT has waived its
    claim-preclusion argument. Because of our resolution of the issue based
    upon waiver under Noel and Pagel, we do not reach the other issues related
    to claim preclusion raised in this case.
    IV. Issue Preclusion.
    A. Position of Lemartec. Lemartec asserts that the state district
    court ruling took too broad an approach to what the “issue” was in the
    federal lawsuit. According to Lemartec, the district court in granting ACT’s
    motion for summary judgment construed the federal judgment as
    precluding categorically any indemnity claims Lemartec might have based
    upon the purchase order with ACT.
    Lemartec argues that the federal judgment is fact bound. According
    to Lemartec, the issue in the federal litigation was whether Lemartec was
    entitled   to   receive   indemnification   for   SPG’s   claims   for   alleged
    precompletion delays and deficiencies. In support of its argument, it cites
    the federal court ruling stating that the issues remaining for trial were
    “whether either of the two remaining parties [Lemartec and/or ACT] owes
    money to the other for money earned but unpaid; project delays; and for
    additional work that was required to make the conveyor system
    functional.”    That, according to Lemartec, is a narrow issue, based on
    SPG’s claims, and not a broad categorical question regarding whether
    Lemartec is entitled to indemnity from ACT for other alleged wrongs.
    Lemartec notes that in the state court litigation the alleged defects
    did not relate to the timing, fabrication, and delivery of the conveyor’s
    component parts. Further, there was no suggestion in the federal litigation
    that latent or unknown future defects would be foreclosed by a judgment.
    18
    Lemartec additionally observes that no evidence on the issue of problems
    in the operation of the conveyor system was presented in the federal court
    litigation, and therefore the question was not “actually litigated” in that
    forum. Haverly, 
    727 N.W.2d at 572
    .
    Further, Lemartec asserts that indemnification was not raised in the
    federal litigation because the right to indemnification does not fully mature
    until the indemnitee’s liability is fixed by settlement or judgment. See
    Becker v. Cent. States Health & Life Co. of Omaha, 
    431 N.W.2d 354
    , 357
    (Iowa 1988), overruled in part on other grounds by Johnston Equip. Corp. of
    Iowa v. Indus. Indem., 
    489 N.W.2d 13
    , 17 (Iowa 1992); Evjen v. Brooks,
    
    372 N.W.2d 494
    , 496 (Iowa 1985). According to Lemartec, “[a] question
    cannot be held to have been arisen and adjudged before an issue on the
    subject could possibly have arisen.” Third Nat’l Bank of Louisville v. Stone,
    
    174 U.S. 432
    , 434, 
    19 S. Ct. 759
    , 760 (1899).
    B. Position of ACT.
    1. Scope of issue litigated in federal litigation.    ACT claims that
    determining the scope of the issue litigated in the prior action is critical to
    application of issue preclusion.       In making that assessment, ACT
    emphasizes that the fact that the opposing party raises new arguments
    and presents different evidence is not determinative. See Soults Farms,
    797 N.W.2d at 104–05.
    An important part of the issue preclusion analysis is identification
    of the elements of the claims in the prior action. In the federal litigation,
    ACT asserts that in order to prove its claim, ACT was required to show the
    terms and conditions of the contract and that it performed all the terms
    and conditions required under the contract. Royal Indem. Co. v. Factory
    Mut. Ins., 
    786 N.W.2d 839
    , 846 (Iowa 2010). The federal court, according
    to ACT, necessarily found that it had performed all the terms and
    19
    conditions of the contract and that Lemartec had no “legal excuse” to
    withhold payment.
    ACT asserts that in the federal action, the question of whether ACT
    had a duty to indemnify Lemartec was litigated and decided. In resisting
    summary judgment in the federal litigation, Lemartec identified provisions
    of its contract with ACT that gave rise to an indemnification claim. ACT
    points out that Lemartec amended its counterclaims in the federal
    litigation to include breach of contract, breach of implied warranty of
    fitness for a particular purpose, and breach of express warranty. In the
    implied warranty claim, ACT notes that Lemartec identified the litigated
    issues as whether ACT breached the independent duty “to provide the
    conveying system components in accordance with the construction
    drawings and specifications.” With respect to the indemnity claim, ACT
    observes that Lemartec characterized the issue as whether “ACT breached
    the implied warranty of merchantability and implied warranty of fitness
    for a particular purpose.” ACT argues that “Lemartec cannot prevail on
    its indemnity action because of the crucial issue of whether ACT breached
    the duties it owed under the Purchase Order has already been decided
    against Lemartec,” and contends therefore that the issue of indemnity has
    been litigated and determined and is binding on Lemartec in the state
    litigation.
    2. Precompletion vs. postcompletion defects.           ACT challenges
    Lemartec’s    characterization   of   the   federal   litigation   as   involving
    precompletion defects and the state court as involving postcompletion
    defects. It notes, for instance, that some precompletion claims were raised
    in the state litigation.
    ACT further notes that the alleged defects in both cases are based
    on the same work performed by ACT pursuant to the same purchase order.
    20
    According to ACT, the fact that HFCA filed its discovery responses in the
    state litigation identifying specific defects in June 2018 does not change
    the fact that ACT had performed all its obligations under the purchase
    order when the federal litigation was pending.
    3. Maturity of indemnity claim. On the issue of when an indemnity
    claim “fully matures,” ACT asserts that while the right to enforce a claim
    of indemnity does not “accrue” until judgment against the indemnitee, the
    claim “comes into being . . . the instant” the acts to support it occur. Evjen,
    
    372 N.W.2d at
    496–97 (quoting 18 Am. Jur. 2d Contributions § 46 (1965)).
    In any event, as long as the issue of indemnity was raised in the first
    litigation, ACT argues that issue preclusion applies if the issues “in the
    second case involve[] issue[s] decided in the first case.”
    4. Waiver.    ACT argues that throughout Lemartec’s brief to this
    court, Lemartec only asserts that its indemnity claims in the two actions
    involve different issues. But ACT asserts that Lemartec did not argue that
    its other state court claims––for breach of contract and breach of various
    warranties––were not the same as the claims in federal litigation. As a
    result, ACT argues that Lemartec has waived all claims in the state court
    litigation except the indemnity claim.
    ACT then asks what the waiver of underlying substantive issues has
    to do with its unwaived indemnity claim.        According to ACT, the state
    district court will be bound by the federal court determination that the
    other substantive claims are without merit. As a result, ACT suggests that
    there is no remaining substantive basis for Lemartec’s indemnity claim.
    C. Discussion. A party asserting issue preclusion must establish
    four elements:
    (1) the issue in the present case must be identical, (2) the issue
    must have been raised and litigated in the prior action, (3) the
    issue must have been material and relevant to the disposition
    21
    of the prior case, and (4) the determination of the issue in the
    prior action must have been essential to the resulting
    judgment.
    Soults Farms, Inc., 797 N.W.2d at 104 (quoting Fischer, 
    654 N.W.2d at 547
    (Iowa 2002).
    We think the issue-preclusion question centers on a determination
    of the proper level of generality to be applied in determining the scope of
    an “issue” for preclusion purposes. ACT argues that the scope of the issue
    in the federal litigation should be broadly and categorically construed to
    include all contract-type issues arising out of the purchase order between
    ACT and Lemartec in this case. Because of ACT’s categorical approach,
    its focuses on the similarity of the pleadings in the state and federal
    litigation. And, there is no doubt that Lemartec’s pleadings in both cases
    are similar.
    But there are certainly factual differences.      As pointed out by
    Lemartec, the claims for which it seeks indemnity arise as a result of
    different factual scenarios. SPG’s claims arose based on preinstallation
    problems, while HFCA’s claims arose postinstallation and were based
    upon the alleged corrosion of the installed conveyor belt system. The main
    difference between ACT and Lemartec is whether the issue in this case is
    a categorical one relating to all claims under the purchase order or a more
    granular one based on the facts that give rise the dispute.
    We agree with Lemartec. In the federal court litigation, Judge Wolle
    noted,
    Pared down to essentials, the remaining issues for trial were
    whether [Lemartec and/or ACT] owes money to the other for
    money earned but unpaid; project delays; and for additional
    work that was required to make the conveyor system
    functional.
    22
    In the state court litigation, HFCA seeks recovery for claims that arose
    from postinstallation defects.
    While it is true that the pleadings of Lemartec in both proceedings
    were quite similar, Lemartec correctly points out that Iowa is a notice
    pleading state and, as a result, the pleadings themselves may be so general
    that they do not define the scope of the issues being litigated in the action.
    Based on our examination of the record, the issue of corrosion in the
    installed conveyor belt system was not “actually litigated” in the federal
    litigation as generally required for application of issue preclusion. Haverly,
    
    727 N.W.2d at 572
    . The issues that were actually litigated in the federal
    proceeding arose from SPG’s claim that it lost money because of additional
    expenses that arose prior to the installation of the conveyor belt.
    We do not think there is a generally applicable rule that there can
    be only one litigated dispute under a contract. A contract may impose a
    number of obligations on a contracting party, and breaches of the contract
    may occur at different times and under different circumstances.           For
    example, in Storey Construction, Inc. v. Hanks, 
    224 P.3d 468
    , 471 (Idaho
    2009), an owner sued a contractor upon completion of a home and lost in
    arbitration. Subsequently, the owner discovered water entering the house
    arising from other defects. 
    Id.
     The Hanks court noted, “There can be more
    than one construction defect in a construction project. Under the parties’
    contract, there can also be more than one claim ‘arising out of or related
    to’ the parties’ construction contract.” Id. at 475.
    We conclude similar reasoning is applicable here.        The fact that
    there has been prior litigation based on breach of contract does not mean
    that there can be no subsequent action where the underlying claims arose
    23
    at a different time based on different breaches. As a result, the district
    court erred in granting summary judgment based on issue preclusion. 2
    V. Conclusion.
    For the above reasons, we conclude that the order of the district
    court granting ACT summary judgment should be reversed and the case
    remanded to the district court for further proceedings.
    REVERSED AND REMANDED WITH DIRECTIONS.
    All justices concur except Oxley, J., who takes no part.
    2ACT   suggests that Lemartec waived dismissal of some of claims III–VI by arguing
    on appeal only that the indemnity claims involve separate issues. All of Lemartec’s
    claims, however, fall under the umbrella of indemnity claims, regardless of the underlying
    legal theory. The district court referred to indemnity counts in this case. We conclude
    that there is no waiver problem here.
    

Document Info

Docket Number: 18-2183

Filed Date: 3/20/2020

Precedential Status: Precedential

Modified Date: 3/20/2020

Authorities (25)

carrie-young-henderson-v-spartanburg-area-mental-health-center-anne-s , 945 F.2d 770 ( 1991 )

Arnevik v. University of Minnesota Board of Regents , 2002 Iowa Sup. LEXIS 46 ( 2002 )

Phoenix Finance Corp. v. Iowa-Wisconsin Bridge Co. , 237 Iowa 165 ( 1945 )

State v. Harper , 1974 Iowa Sup. LEXIS 1143 ( 1974 )

Bertran v. Glens Falls Insurance Company , 1975 Iowa Sup. LEXIS 1189 ( 1975 )

B & B Asphalt Co. v. T. S. McShane Co. , 1976 Iowa Sup. LEXIS 993 ( 1976 )

National Bank of Louisville v. Stone, Auditor , 19 S. Ct. 759 ( 1899 )

Noel v. Noel , 1983 Iowa Sup. LEXIS 1536 ( 1983 )

Winnebago Industries, Inc. v. Haverly , 2006 Iowa Sup. LEXIS 160 ( 2006 )

Colvin v. Story County Board of Review , 2002 Iowa Sup. LEXIS 224 ( 2002 )

Minch Family LLLP v. Buffalo-Red River Watershed District , 628 F.3d 960 ( 2010 )

Bank of New York v. First Millennium, Inc. , 607 F.3d 905 ( 2010 )

Pagel v. Notbohm , 1971 Iowa Sup. LEXIS 838 ( 1971 )

Fischer v. City of Sioux City , 2002 Iowa Sup. LEXIS 253 ( 2002 )

Iowa Coal Mining Co. v. Monroe County , 1996 Iowa Sup. LEXIS 429 ( 1996 )

Melissa Rawe Thomas J. Rawe Kimberly Rawe v. Liberty Mutual ... , 462 F.3d 521 ( 2006 )

Johnston Equipment Corp. of Iowa v. Industrial Indemnity , 1992 Iowa Sup. LEXIS 330 ( 1992 )

95-cal-daily-op-serv-8316-95-daily-journal-dar-14415-douglas , 69 F.3d 321 ( 1995 )

Mitchell v. City of Moore , 218 F.3d 1190 ( 2000 )

Smith v. Potter , 513 F.3d 781 ( 2008 )

View All Authorities »