trustees-of-the-iowa-laborers-district-council-health-and-welfare-trust ( 2014 )


Menu:
  •                     IN THE COURT OF APPEALS OF IOWA
    No. 13-1560
    Filed December 24, 2014
    TRUSTEES OF THE IOWA LABORERS DISTRICT COUNCIL HEALTH AND
    WELFARE TRUST; TRUSTEES OF THE LABORERS NATIONAL PENSION
    FUND; and TRUSTEES OF THE IOWA BUILDERS RETIREMENT FUND,
    Plaintiffs,
    vs.
    ANKENY     COMMUNITY    SCHOOL    DISTRICT,  BETTS   & BEER
    CONSTRUCTION CO., INC., WESTERN SURETY COMPANY, GROVE
    MASONRY, INC., TWIN CITY CONCRETE PRODUCTS COMPANY, SIOUX
    CITY BRICK & TILE COMPANY, and OLDCASTLE APG., INC.,
    Defendants.
    OLDCASTLE APG WEST, INC. a/k/a RHINO MATERIALS
    Defendant/Crossclaim Plaintiff-Appellant,
    v.
    GROVE MASONRY, INC.,
    Crossclaim Defendant-Appellee.
    ________________________________________________________________
    Appeal from the Iowa District Court for Polk County, Rebecca Goodgame
    Ebinger, Judge.
    Oldcastle APG West, Inc. (“Oldcastle”) appeals from the district court’s
    denial of its crossclaim for an amount owed under an open account with Grove
    Masonry, Inc. (“Grove Masonry”). It also appeals the district court’s award of
    direct and consequential damages to Grove Masonry on its counterclaim against
    Oldcastle. AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.
    Mark Weinhardt, Holly Logan, and Danielle Shelton of Weinhardt & Logan,
    P.C., Des Moines, and Christopher Low of Abendroth & Russell, P.C.,
    Urbandale, for appellant.
    Matthew G. Sease of Kemp & Sease, Des Moines, for appellee.
    Heard by Vogel, P.J., and Vaitheswaran and Potterfield, JJ.
    2
    POTTERFIELD, J.
    Oldcastle APG West, Inc. (“Oldcastle”) appeals from the district court’s
    denial of its crossclaim for an amount owed under an open account with Grove
    Masonry, Inc. (“Grove Masonry”). It also appeals the district court’s award of
    direct and consequential damages to Grove Masonry on its counterclaim against
    Oldcastle for defective product. We affirm in part, reverse in part, and remand for
    further proceedings.
    I. Factual and Procedural Background
    Oldcastle is the parent company of Rhino Materials, which manufactures
    concrete masonry units (CMUs) used by masonry contractors like Grove
    Masonry in construction projects. In 2009, Ankeny Community School District
    began two building projects, a high school and a middle school. Grove Masonry
    won the bid to be mason on the two projects. It contracted with Oldcastle to
    provide the CMUs it would need to complete the work.            The CMUs were to
    comply with the industry standard ASTM C90 guideline.1
    After work began, Grove Masonry started to notice some of the blocks
    were defective. There were two types of defects it noticed. First, some of the
    blocks were pitted and chipped on their surfaces. This was a patent defect.
    These blocks are known as “shotgun blocks.” Second, some of the blocks had a
    slight outward protrusion on their surfaces. This was a latent defect and was not
    1
    The ASTM C90 specification states, “Minor cracks, incidental to the usual method of
    manufacture or minor chipping resulting from customary methods of handling in
    shipment and delivery, are not grounds for rejection. . . . Five percent of a shipment
    containing chips . . . or cracks . . . is permitted.”
    3
    noticeable until the blocks had been installed.        These blocks are known as
    “bubble blocks.”
    Sometime between January and May of 2010, Grove Masonry first noticed
    the defects.   Shortly thereafter, it notified Oldcastle.    Oldcastle came to the
    construction site to look at the product and troubleshoot with Grove Masonry.
    Some amount of both the shotgun block and the bubble block had been installed
    prior to Oldcastle’s arrival on the scene.
    Testimony at trial was inconsistent as to when precisely Grove Masonry
    noticed the defects. It was equally unclear as to when Grove Masonry notified
    Oldcastle of the defects. One of Grove Masonry’s witnesses thought they first
    noticed the problem “probably around the first of the year, January,
    February . . . .” Another of its witnesses said that Oldcastle was on site within a
    few days of Grove Masonry noticing the defects, which “had to be in April, May,
    sometime in there.” The problems with the defective blocks required very costly
    corrective measures, a cost which Grove Masonry bore.             During this time it
    continued to receive and install multiple deliveries of additional CMUs from
    Oldcastle but stopped paying for the product.
    The Ankeny schools project had been a pivotal one for Grove Masonry.
    After the trouble with the CMUs on the Ankeny projects, Grove Masonry fell into
    serious economic hardships, became unable to obtain bonding on its projects,
    struggled to win contracts, and has been left out of calls for bids in its area.
    Oldcastle and Grove Masonry were co-defendants in an action initiated as
    a result of the expensive and troubled construction projects. Oldcastle filed a
    crossclaim for payment from Grove Masonry for the deliveries of CMUs for which
    4
    Grove Masonry still refused to pay. It filed two counts, the first of which was
    disposed of by summary judgment in Grove Masonry’s favor.              The second
    crossclaim alleged that Oldcastle held an open account in which Grove Masonry
    owed the agreed-upon amount for the CMUs it accepted, which amounted to
    $155,572.74. Before trial, Oldcastle moved to amend this second crossclaim to
    broaden its theories of recovery, but the district court denied the motion. Grove
    Masonry filed counterclaims against Oldcastle, alleging the CMUs delivered
    violated an implied warranty of merchantability and an implied warranty of fitness
    for a particular purpose.
    The district court heard the case in equity in a bench trial.       It found
    Oldcastle’s relationship with Grove Masonry was not an open account and
    denied Oldcastle’s claim for payment for the accepted CMUs. It also entered
    judgment in favor of Grove Masonry on the count of violation of the implied
    warranty of merchantability.      The district court awarded Grove Masonry
    $783,096.68 in direct economic damages and $1,005,961.00 in consequential
    lost-profits damages. Oldcastle appeals.
    II. Standard and Scope of Review
    We review the district court’s rulings on contract matters for errors at law.
    Iowa R. App. P. 6.907. When we review for errors at law, “[w]e are bound by the
    trial court’s findings of fact if they are supported by substantial evidence.”
    Harrington v. Univ. of N. Iowa, 
    726 N.W.2d 363
    , 365 (Iowa 2007).
    “‘Substantial evidence’ means the quantity and quality of evidence that
    would be deemed sufficient by a neutral, detached, and reasonable person, to
    establish the fact at issue when the consequences resulting from the
    5
    establishment of that fact are understood to be serious and of great importance.”
    Iowa Code § 17A.19(10)(f)(1) (2013).
    “In assessing the evidence, we view the record in the light most favorable
    to the prevailing party, indulging in all legitimate inferences that may fairly and
    reasonably be deduced from the evidence.” Pollmann v. Belle Plaine Livestock
    Auction, Inc., 
    567 N.W.2d 405
    , 409 (Iowa 1997).
    The issues raised by Oldcastle on appeal concern Iowa’s adoption of the
    Uniform Commercial Code (UCC), effective at the time of the transactions
    between Oldcastle and Grove Masonry. Iowa Code ch. 554 (2009). “[W]hen
    interpreting any provision of the Uniform Commercial Code, we bear in mind its
    overriding purposes and objectives,” which include “the uniform application of
    commercial law among the states and the presumption in favor of predictability
    and finality of commercial transactions.” Husker News Co. v. Mahaska State
    Bank, 
    460 N.W.2d 476
    , 477 (Iowa 1990). To achieve that goal, we may “look to
    the interpretation given by other jurisdictions.” Van Ness v. First State Bank of
    Ida Grove, 
    430 N.W.2d 109
    , 110 (Iowa 1988).
    III. Notice of Breach in a Reasonable Time
    “Where a tender has been accepted[,] the buyer must within a reasonable
    time after the buyer discovers or should have discovered any breach notify the
    seller of breach or be barred from any remedy[.]” Iowa Code § 554.2607(3)(a).
    Based on the statutory language, Oldcastle asserts Grove Masonry is barred
    from any remedy related to the defective CMUs. First, it argues Grove Masonry
    failed to plead in its cross-complaint that it provided Oldcastle notice of the
    defective CMUs.     Second, it argues insofar as Grove Masonry did factually
    6
    provide notice, it was not provided within a reasonable time after it discovered or
    should have discovered the defects.
    A. Failure to Plead Notice
    Oldcastle asserts a complainant must explicitly plead its notification of
    non-conforming product to the opposing party because the notification is a
    condition precedent to its basis for recovery. Grove Masonry claims Oldcastle’s
    cited law has been outmoded by a 1976 amendment to the Iowa Rules of Civil
    Procedure.
    It is true that our supreme court has held in the past that “the giving of a
    notice must be pleaded as a condition precedent to recovery.”            Winter v.
    Honeggers & Co., Inc., 
    215 N.W.2d 316
    , 327 (Iowa 1974); see Henschel v.
    Hawkeye-Security Ins. Co., 
    178 N.W.2d 409
    , 417 (Iowa 1970) (“For pleading
    purposes, at least, a condition precedent is one whose performance or
    occurrence plaintiff must prove in order to recover.”).
    However, in 1976, the Iowa Rules of Civil Procedure were amended to
    substantially lower the burden on plaintiffs to manage arcane technical
    requirements in pleading.
    Under [the new] rule, the principal function of pleadings is to give
    the adverse party fair notice of the claim asserted in the form of a
    generalized summary sufficient to allow that party to make an
    adequate response. . . . It will no longer be necessary to determine
    whether the rigid requirements of a “cause of action” have been
    pleaded. Distinctions under the former rule between “ultimate
    facts” which were required to be pleaded and “evidence” and
    “conclusions of law” which were prohibited in pleadings are
    abolished.
    7
    Iowa R. Civ. P. 69 cmt. (1976).2 Since the amendment, our supreme court has
    noted when necessary that former pleading rules no longer apply. See Am. Nat.
    Bank v. Sivers, 
    387 N.W.2d 138
    , 139–40 n.1 (Iowa 1986) (holding relevant
    portion of 1931 Iowa Supreme Court case “has no applicability under our present
    rules of notice pleading”).      Our supreme court regularly considers factual
    satisfaction of conditions precedent, but has not revisited its requirement to plead
    conditions precedent since the amendment of the rule.
    In the absence of such a ruling from our supreme court, Oldcastle relies
    upon two cases from this court and one from the federal district court in Iowa’s
    northern district.3 We agree with the district court’s analyses of these cases. In
    Mosebach v. Blythe, 
    282 N.W.2d 755
    , 759 (Iowa Ct. App. 1979), this court
    denied relief when a plaintiff failed to address a condition precedent in his
    pleadings.      In Mosebach, we relied on Henschel, a pre-amendment case.
    
    Henschel, 178 N.W.2d at 420
    . Additionally, we did not address the effect or lack
    of effect of the amendment and held alternatively the plaintiff could not recover
    due to factual non-satisfaction of the condition. 
    Mosebach, 282 N.W.2d at 759
    .
    This case alone is not sufficient to establish the pleading requirement remains in
    effect.
    In Randa v. U.S. Homes, Inc., 
    325 N.W.2d 905
    , 909–10 (Iowa Ct. App.
    1982), this court suggested in dicta—but did not hold—that Winter’s pre-
    2
    The rule is now found at Iowa R. Civ. P. 1.402.
    3
    Oldcastle additionally cites one Iowa Supreme Court case. See Hartford-Carlyle Sav.
    Bank v. Shivers, 
    566 N.W.2d 877
    , 881 (Iowa 1987). However, Hartford does not support
    Oldcastle’s position. It acknowledges in dicta the requirement existed pre-amendment
    but does not endorse, rely upon, or renew it. 
    Id. 8 amendment
    pleading requirement may still be in effect. We went on, however, to
    decide the case on other grounds, and our language addressing the pleading
    requirement4 was not conclusive and is not now controlling.
    In Wright v. Brooke Group Ltd., 
    114 F. Supp. 2d 797
    , 829–30 (N.D. Iowa
    2000), the federal district court noted in dicta that the pre-amendment pleading
    requirement is still effective, relying on Randa. The court failed to address or
    consider the effect of the amended rule of civil procedure on the pleading
    requirement. Further, under the court’s interpretation of the pre-amendment law,
    the plaintiff’s filing of a suit itself satisfies the condition by providing notice.
    
    Wright, 114 F. Supp. 2d at 830
    . Wright does not support Oldcastle’s position on
    the pleading issue.
    Oldcastle has identified a gap in our notice pleading jurisprudence, but it
    has not persuaded us that a pre-amendment formalistic pleading requirement
    survived Iowa’s adoption of its current notice pleading system, in which “[o]nly a
    general statement of the claim is required.” Christensen v. Shelby Cnty., 
    287 N.W.2d 560
    , 563 (Iowa 1980). Grove Masonry’s pleadings do not preclude it
    from recovering even though the record shows “it is undisputed that [it] failed to
    plead notice.”
    B. Failure to Give Timely Notice
    Oldcastle’s second argument regarding the requirement to provide timely
    notice of the defect is that Grove Masonry’s notice was categorically not timely
    relative to the shotgun blocks because Grove Masonry installed the blocks before
    4
    “It has been held that []the giving of a notice must be pleaded as a condition precedent
    to recovery.” 
    Randa, 325 N.W.2d at 909
    .
    9
    giving notice.5 Oldcastle argues the installation renders notice untimely as a
    matter of law. Grove Masonry argues the timeliness determination is one of fact
    and this court must defer to the district court’s finding of timeliness unless it is not
    supported by substantial evidence.
    This court has previously held “sufficiency and reasonableness are fact
    questions” in the context of the notice provision in Iowa Code section
    554.2607(3)(a). Tyrrell Cos., L.C. v. Tegeler Design Ctr., Inc., No. 03-0258, 
    2003 WL 23219948
    , at *1 (Iowa Ct. App. Nov. 26, 2003). However, Oldcastle notes
    that Tyrrell does not indicate whether timeliness is to be determined as a matter
    of law and cites to cases in other jurisdictions either explicitly or implicitly holding
    notice untimely as a matter of law when construction materials are installed.6
    Regardless, we find the district court’s determination that the notice was
    provided within a reasonable time is not supported by substantial evidence. The
    district court’s findings of fact and the record as a whole lack necessary
    specificity.
    The district court wrote that Grove Masonry discovered the defects and
    notified Oldcastle of them “in the same time frame: in the springtime, March into
    April.”    In reviewing the record, we note the testimony that the district court
    deemed credible actually reflects a fluctuating time frame in which the defects
    were discovered and Oldcastle was notified. Though the district court described
    5
    Oldcastle does not contest that notice was timely provided relative to the bubble block.
    6
    See Wilke Metal Products, Inc. v. David Architectural Metals, Inc., 
    236 N.E.2d 303
    ,
    305–06 (Ill. App. Ct. 1968); P & F Constr. Corp. v. Friend Lumber Corp. of Medford, 
    575 N.E.2d 61
    , 63–64 (Mass. App. Ct. 1991); Archstone v. Tocci Bldg. Corp. of New Jersey,
    Inc., 
    101 A.D.3d 1057
    , 1058–59 (App. Div. N.Y. 2012).
    10
    the time frame as March and April of 2010, the testimony reflects the discovery
    and notification periods were in fact anywhere between January and May.
    The findings of the district court also fail to account for the testimony
    indicating that defective CMUs were continually installed even after the defects
    were initially discovered or reasonably should have been discovered.7 These
    facts extend the reasonable-time calculus beyond simply the number of days
    between discovery and notification.
    Between the imprecise evidence concerning the dates of discovery and
    notification and the continued installation of CMUs in spite of defects, we cannot
    say the evidence is sufficient for a neutral, detached person to conclude
    notification was reasonably timely, especially because the consequences are of
    considerable importance due to the amount of damages sought.
    We reverse the district court’s finding of timely notice of defective shotgun
    block and remand to the district court for determination of what portion, if any, of
    the damages arose from Grove Masonry’s installation of shotgun block it knew or
    should have known was defective and remove that portion of liability from
    judgment entered against Oldcastle.
    IV. Consequential Damages
    Oldcastle next appeals the district court’s award of approximately
    $1 million in consequential damages to Grove Masonry for profits lost as a result
    7
    Because Iowa Code section 554.2607(3)(a) requires notice when a buyer should have
    discovered the defect and the defective “shotgun block” was patently defective, Grove
    Masonry was under a duty to notify Oldcastle of the defect when it should have
    inspected the block without regard to whether it in fact discovered the defect before or
    after installing the CMUs.
    11
    of Oldcastle’s breach of the implied warranty of merchantability. A buyer may
    recover consequential damages from a breaching seller pursuant to Iowa Code
    section 554.2715.8 Recoverable consequential economic losses “include[] loss
    of profits resulting from failure of the goods to function as warranted, loss of
    goodwill, . . . loss of business reputation, and other loss proximately resulting
    from a defective product beyond direct economic loss.”        Beyond the Garden
    Gate, Inc. v. Northstar Freeze-Dry Mfg., Inc., 
    526 N.W.2d 305
    , 309 (Iowa 1995)
    (citation omitted).
    “[T]he buyer who has accepted goods and then discovers their defects
    must show that the seller had reason to know at the time of contracting of the
    buyer’s possible losses caused by a breach to recover consequential damages.”
    Nachazel v. Miraco Mfg., 
    432 N.W.2d 158
    , 160 (Iowa 1988). The losses must be
    foreseeable, and losses are foreseeable “if they follow in the ordinary course of
    events, but also as a result of special circumstances.” 
    Id. Iowa courts
    focus on
    whether the type of damages was foreseeable rather than whether the specific
    injury itself was foreseeable. Kuehl v. Freeman Bros. Agency, Inc., 
    521 N.W.2d 714
    , 718–19 (Iowa 1994).9
    8
    Iowa Code section 554.2715 provides:
    Consequential damages resulting from the seller’s breach include
    a. any loss resulting from general or particular requirements and
    needs of which the seller at the time of contracting had reason to know
    and which could not reasonably be prevented by cover or otherwise; and
    b. injury to person or property proximately resulting from any
    breach of warranty.
    9
    Oldcastle notes the cases espousing this principle do not apply Iowa Code chapter
    554. The cases are nevertheless still applicable to demonstrate how Iowa courts
    interpret the chapter’s reasonable foreseeability requirement.
    12
    At trial, Grove Masonry requested three categories of consequential
    damages: damages arising from a loss of goodwill, damages arising from a loss
    of business reputation, and damages arising from loss of profits. The district
    court held Grove Masonry could not recover on the first two categories because
    any calculation to determine the economic value of such a loss would be purely
    speculative. However, the court found that Grove Masonry’s loss of profits was
    measurable, foreseeable, and proximately caused by Oldcastle’s breach.
    Oldcastle argues the district court’s award is improper because the
    damages are speculative in their entirety or were largely unforeseeable. We first
    address Oldcastle’s claim that the damages were speculative. Oldcastle claims
    the district court contradicted itself when it refused to award Grove Masonry
    consequential damages as a result of loss of goodwill or business reputation
    because the measure of those injuries would be speculative. At the same time, it
    awarded damages to account for profits lost as a result of a loss of goodwill and
    business reputation.
    The district court’s holding was not contradictory. The district court did not
    hold that the injury to Grove Masonry’s goodwill or business reputation itself was
    speculative.   It held any dollar amount assigned to those injuries would be
    speculative. However, the measure of lost profits was not guesswork—it was
    supported by trial testimony and calculations asserted by both parties.        The
    measurable injury of lost profits resulted from the immeasurable injuries to Grove
    Masonry’s goodwill and business reputation. But it does not follow that the lost
    profits are therefore speculative themselves.
    13
    We next consider whether the lost profits were foreseeable. Oldcastle
    argues they were not foreseeable because the actual cause of the $1 million in
    lost profits was Grove Masonry’s inability to obtain performance bonds after
    falling on economic hardships.10
    However, the district court found it was “reasonably foreseeable at the
    time of contracting that a breach of warranty of merchantability would result in
    lost profits.” In ruling on Oldcastle’s post-trial motion, it further noted, “[T]he
    evidence presented . . . warranted the lost profits damages, notwithstanding the
    loss of bonding capacity.”11 The foreseeability question on appeal, therefore, is
    whether there is substantial evidence to support the district court’s finding that
    lost   profits—vis   a   vis   lost   customers—was      a   reasonably foreseeable
    consequence of Oldcastle’s breach at the time of contracting.
    The record demonstrates that the Ankeny projects were of such a size and
    profile that Grove Masonry’s performance on those jobs could foreseeably have
    affected its future business prospects. It was reasonably foreseeable at the time
    of contracting that Grove Masonry’s future contracts with other customers,
    10
    A contractor’s loss of bonding ability has been held unforeseeable in transactions
    similar to the one at hand in other jurisdictions. Oldcastle cites cases considering this
    issue from several states. See Lewis Jorge Const. Mgmt., Inc. v. Pomona Unified Sch.
    Dist., 
    102 P.3d 257
    (Cal. 2004); MLK, Inc. v. Univ. of Kansas, 
    940 P.2d 1158
    (Kan.
    1997), Daniel E. Terreri & Sons, Inc. v. Mahoning Cnty. Bd. of Commrs., 
    786 N.E.2d 921
    (Ohio Ct. App. 2003); and NAJLA Assocs., Inc. v. William L. Griffith & Co., 
    480 S.E.2d 492
    (Va. 1997). These cases demonstrate that the loss of bonding capacity may not be
    reasonably foreseeable depending on the particular factual circumstances of each case,
    but they do not persuade us that the loss of bonding capacity should be unforeseeable
    as a matter of law in Iowa as Oldcastle asserts. Instead, we review the district court’s
    findings of fact for substantial evidence that supports them.
    11
    Contrary to Oldcastle’s refrain, the district court neither “ignored [n]or evaded” the
    issue of foreseeability of Grove Masonry’s loss of bonding capacity. The court simply
    found Grove Masonry had proved its claim for damages for lost profits.
    14
    retention of existing customers, and acquisition of new customers could depend
    upon the quality of its work product, i.e., the quality of the CMUs it purchased
    from Oldcastle.     There is substantial evidence to support the district court’s
    finding that the type of profits ultimately lost—future contracts with other
    customers—was reasonably foreseeable to the parties at the time of
    contracting.12
    Oldcastle raises one further question: whether, if lost profits were in fact
    reasonably foreseeable, they were foreseeable to the extent to which they have
    been awarded—i.e., whether the consequential damages awarded must be of a
    foreseeable extent in addition to a foreseeable type. Our jurisprudence does not
    directly address the issue,13 but Iowa law does not require that the lost-profits
    damages be per se proportionate to the value of the original contract. Nor is
    there any indication in the record that the damages awarded in this case are
    disproportionate under the circumstances.
    We find nothing in the record to indicate the extent of the damage shown
    in this case was not as foreseeable as its type given the value of Grove
    Masonry’s typical project. Despite Oldcastle’s assertion, the bare value of the
    12
    Our holding on this matter does not mean that there is a lack of substantial evidence
    that suggests Grove Masonry’s loss of bonding capacity is the actual cause, in whole or
    in part, of the loss of profits. Rather, that question is simply not within the scope of our
    review. Oldcastle’s preoccupation with Grove Masonry’s bonding capacity has caused it
    to misapprehend the issue. We are not searching for alternative causes of the lost
    profits; we are searching for evidence supporting the district court’s conclusion as to the
    cause.
    13
    Oldcastle’s only citation for its claim is to a case from a federal district court in
    Tennessee. Great Am. Music Mach., Inc. v. Mid-S. Record Pressing Co., 
    393 F. Supp. 877
    , 885 (M.D. Tenn. 1975). While this case expresses its reasoning for a general
    proportionality requirement, it is not a statement of controlling law in Iowa and is not
    persuasive given the current state of the law in Iowa.
    15
    CMUs in this case does not arbitrarily limit the extent of foreseeable lost-profit
    damages.
    We therefore affirm the district court’s conclusion that Grove Masonry
    suffered $1,005,961 in foreseeable consequential damages, and it may therefore
    recover from Oldcastle.
    V. Payment for Goods
    Oldcastle lastly appeals the district court’s denial of its claim it pleaded as
    an amount owed on an open account between itself and Grove Masonry. Grove
    Masonry denies the existence of an open account, and the district court found
    there was none. The questions before this court on appeal therefore are whether
    the parties maintained an open account in which there currently rests a balance
    owed to Oldcastle and whether the court properly limited Oldcastle’s claim under
    our notice pleading rules discussed earlier in the context of Grove Masonry’s
    failure to plead notice of breach in its counterclaim.14
    At trial, Oldcastle proved Grove Masonry continued to accept delivery of
    product, it did not pay for that product, and the amount owed for the product it
    accepted. The district court denied the claim for the amount owed because
    Oldcastle’s pleadings described that amount owed as an open account, and the
    14
    Oldcastle’s appeal is largely predicated on the principle of Iowa Code section
    554.2709, which provides, “When the buyer fails to pay the price as it becomes due the
    seller may recover . . . the price . . . of goods accepted . . . .” This provision allows a
    seller to recover the contract price of the goods accepted by the buyer regardless of any
    other breach of contract actions taken by the buyer against the seller. Grove Masonry
    correctly notes that Oldcastle made no claim under section 554.2709 at trial and no such
    claim is preserved for our review. Rather, Oldcastle asks this court to reverse the district
    court on its denial of the open account claim in order to effectuate the policy goal of
    section 554.2709. The actual effect of section 554.2709 on the facts of this case,
    however, is not an issue before us.
    16
    district court decided those transactions fell outside the technical definition of an
    open account. The district court’s reliance on a pleading technicality to deny its
    claim frustrated Oldcastle’s ability to recover payments to which it was entitled.
    However, even under its open account claim, Oldcastle is entitled to
    recover. The controversy arises in the parties’ competing interpretations of our
    supreme court’s decision in Roger’s Backhoe Serv., Inc. v. Nichols, 
    681 N.W.2d 647
    , 650 (Iowa 2004). In Roger’s Backhoe, the court held:
    [I]n a general sense, [an account] encompasses any claim or
    demand based on a transaction creating a debtor-creditor
    relationship. . . . [W]hen the evidence fails to establish the
    elements of an account stated, the creditor may nevertheless
    recover by proving a contractual obligation for the individual terms
    in the account and the fair and reasonable value of the amounts
    claimed.
    
    Id. (citations omitted).
    Oldcastle asserts the multiple contracts for sale between
    itself and Grove Masonry are transactions creating a debtor-creditor relationship
    in which Oldcastle credits Grove Masonry the value of the goods upon delivery
    for future payment on that debt.
    The district court and Grove Masonry rely upon a 1931 case in which our
    supreme court held, “A series of independent express contracts for services to be
    performed for an agreed compensation does not constitute an open continuous
    current account.” Sammon v. Roach, 
    235 N.W. 78
    , 79 (Iowa 1931). We find
    Sammon, to the extent it remains good law in light of our more recent
    jurisprudence, is distinguishable.    The quoted language in context does not
    categorically foreclose Oldcastle’s claim. Sammon dealt with a quantum meruit
    17
    claim15 in which the individual contracts had been paid in full as they became
    due. The Sammon court’s statement about open accounts related only to the
    quantum meruit claim before it, as the language of the decision as a whole
    makes clear.16
    Additionally, Sammon did not outright define an open account, but relied
    on other cases, such as Tucker v. Quimby, 
    37 Iowa 17
    , 19 (1873), which stated,
    “a ‘continuous, open, current, account,’ is an account which is not interrupted or
    broken, not closed by settlement or otherwise, and is a running, connected series
    of transactions.” The Tucker language aptly describes the relationship between
    Oldcastle and Grove Masonry as the former continued to supply the latter with
    goods without receiving payment for previous deliveries.
    We agree with Oldcastle that the district court’s interpretation of our
    supreme court’s dictates in Roger’s Backhoe is improperly constrained by its
    reading of Sammon.        The transactions at issue in this case span multiple
    overlapping, unbroken contractual obligations creating an account that was never
    settled. The amount Oldcastle asserts it is owed is not derived from a single
    15
    Quantum meruit “denote[s] a particular subclass of implied-in-fact contracts.” Iowa
    Waste Sys., Inc. v. Buchanan Cnty., 
    617 N.W.2d 23
    , 29 (Iowa Ct. App. 2000).
    Sammon’s holding involved a quantum meruit assertion that a previously agreed-upon
    and paid amount was not an equitable payment for services rendered. Such a
    consideration is naturally distinguishable from the case at hand, in which Oldcastle has
    established an ongoing series of contracts in which it continued to deliver goods while
    prior contracts remained unpaid.
    16
    [Our conclusion] would seem to be clear upon reason and without the
    necessity of authority to support it. The rule is well settled in this state
    that, where a cause of action is based solely upon quantum meruit,
    recovery cannot be had if the proof offered in support thereof establishes
    an express contract. It is equally true that, if the cause of action is based
    upon contract, recovery may not be had upon the theory of quantum
    meruit.
    
    Sammon, 235 N.W. at 79
    .
    18
    “contract for a lump sum.” McIntire v. Muller, 
    522 N.W.2d 329
    (Iowa Ct. App.
    1994). Oldcastle proved Grove Masonry had not paid for CMUs it accepted, and
    should have prevailed on this claim.
    We reverse the district court’s judgment against Oldcastle in its count II
    styled as an open account claim. Grove Masonry must pay for the $155,572.74
    in goods it accepted. That amount may be used to offset damages awarded to
    Grove Masonry. We remand for further proceedings consistent with this opinion.
    VI. Conclusion
    As to Oldcastle’s claim that Grove Masonry was entirely precluded from
    recovery because it failed to plead the condition precedent that it gave timely
    notice of the defect, we affirm the district court. Grove Masonry’s pleadings gave
    Oldcastle fair notice of the claim sufficient to allow it to make an adequate
    response and were therefore sufficient to permit recovery.
    As to Oldcastle’s claim that Grove Masonry was partially precluded from
    recovery because it failed in fact to provide timely notice of the patently defective
    shotgun block, we reverse the judgment entered and remand for recalculation of
    damages.
    As to Oldcastle’s claim that the district court’s consequential damages
    award was improper because it was not foreseeable, we affirm the district court.
    Substantial evidence exists in the record that Grove Masonry’s loss of future
    contracting partners was reasonably foreseeable at the time of contracting.
    As to Oldcastle’s claim that the district court’s consequential damages
    award was improper because it was speculative, we affirm the district court. The
    19
    damages were the result of evidence properly before the court and thorough
    calculations based on that evidence.
    As to Oldcastle’s open account claim, we reverse the district court’s entry
    of judgment in Grove Masonry’s favor and remand for further proceedings.
    AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.
    

Document Info

Docket Number: 13-1560

Filed Date: 12/24/2014

Precedential Status: Precedential

Modified Date: 2/1/2016

Authorities (23)

American National Bank v. Sivers , 1986 Iowa Sup. LEXIS 1162 ( 1986 )

Husker News Co. v. Mahaska State Bank , 1990 Iowa Sup. LEXIS 192 ( 1990 )

Pollmann v. Belle Plaine Livestock Auction, Inc. , 1997 Iowa Sup. LEXIS 211 ( 1997 )

Kuehl v. Freeman Bros. Agency, Inc. , 1994 Iowa Sup. LEXIS 185 ( 1994 )

Roger's Backhoe Service, Inc. v. Nichols , 2004 Iowa Sup. LEXIS 198 ( 2004 )

P & F Construction Corp. v. Friend Lumber Corp. of Medford , 31 Mass. App. Ct. 57 ( 1991 )

Randa v. U.S. Homes, Inc. , 1982 Iowa App. LEXIS 1447 ( 1982 )

Beyond the Garden Gate, Inc. v. Northstar Freeze-Dry ... , 1995 Iowa Sup. LEXIS 19 ( 1995 )

McIntire v. Muller , 1994 Iowa App. LEXIS 81 ( 1994 )

Mosebach v. Blythe , 1979 Iowa App. LEXIS 47 ( 1979 )

Harrington v. University of Northern Iowa , 2007 Iowa Sup. LEXIS 2 ( 2007 )

Iowa Waste Systems, Inc. v. Buchanan County , 2000 Iowa App. LEXIS 9 ( 2000 )

Van Ness v. First State Bank of Ida Grove , 1988 Iowa Sup. LEXIS 274 ( 1988 )

Great American Music MacHine, Inc. v. Mid-South Record ... , 393 F. Supp. 877 ( 1975 )

Lewis Jorge Construction Management, Inc. v. Pomona Unified ... , 22 Cal. Rptr. 3d 340 ( 2004 )

Christensen v. Shelby County , 1980 Iowa Sup. LEXIS 772 ( 1980 )

NAJLA Associates, Inc. v. William L. Griffith & Co. , 253 Va. 83 ( 1997 )

Nachazel v. Miraco Mfg. , 1988 Iowa Sup. LEXIS 318 ( 1988 )

Winter v. Honeggers'& Co., Inc. , 1974 Iowa Sup. LEXIS 1258 ( 1974 )

Henschel v. Hawkeye-Security Insurance Company , 1970 Iowa Sup. LEXIS 852 ( 1970 )

View All Authorities »