Reilly Construction, Co., Inc. v. Bachelder, Inc. ( 2016 )


Menu:
  •                     IN THE COURT OF APPEALS OF IOWA
    No. 15-1192
    Filed April 27, 2016
    REILLY CONSTRUCTION, CO., INC.,
    Plaintiff-Appellant,
    vs.
    BACHELDER, INC.,
    Defendant-Appellee.
    ________________________________________________________________
    Appeal from the Iowa District Court for Winneshiek County, John J.
    Bauercamper, Judge.
    Reilly Construction Company, Inc. appeals the district court’s award of
    damages in favor of Bachelder, Inc.. AFFIRMED.
    Douglas A. Boese and John C. Beatty of Dunlap & Seeger, P.A.,
    Rochester, Minnesota, and Richard D. Zahasky of Anderson, Wilmarth, Van Der
    Maaten, Belay, Fretheim, Gipp & Zahasky, Decorah, for appellant.
    Dale L. Putnam and Erik W. Fern of Putnam, Fern & Thompson Law
    Office, P.L.L.C., Decorah, for appellee.
    Considered by Vaitheswaran, P.J., and Doyle and Mullins, JJ.
    2
    DOYLE, Judge.
    Reilly Construction Company, Inc. (Reilly) appeals the district court’s
    award of damages in favor of Bachelder, Inc. (Bachelder).            Reilly argues
    Bachelder failed to prove it was damaged by Reilly’s actions. Because the trial
    court properly determined the amount of damages incurred by Bachelder, we
    affirm.
    The facts leading up to the first appeal are fully set out in Reilly
    Construction v. Bachelder, Inc., No. 14-0817, 
    2015 WL 1331634
    , at *1-3 (Iowa
    Ct. App. Mar. 25, 2015). To summarize briefly: Bachelder contracted with Reilly
    to construct a pond on property it owns in Winneshiek County, and, to that end, it
    paid Reilly $116,962.13 for the work it performed. However, the pond did not
    hold water. Reilly billed Bachelder an additional $93,600 for the parts and labor it
    expended in an effort to remedy the defect, but problems persisted.            After
    Bachelder refused to pay the additional expenses, Reilly filed a mechanic’s lien
    and petitioned to foreclose on it. Bachelder counterclaimed for damages based
    on Reilly’s alleged negligence, breach of contract, and failure to perform work in
    a workman-like fashion. The trial court denied both claims. This court reversed
    the denial of Bachelder’s claim and remanded the case for a determination of
    Bachelder’s damages. See Reilly Constr., 
    2015 WL 1331634
    , at *9.
    On remand, the district court found, in part:
    Since this suit was filed, the water level in the pond has
    varied greatly, depending upon the amount of rainfall. Following
    rainy periods, the pond reaches levels that are aesthetically
    pleasing. When dry periods occur, the pond nearly dries up. The
    pond has been useless for recreational purposes for extended time
    periods. The springs do not significantly assist the pond in
    3
    maintaining a useable water level. No outside water source has
    been added.
    Expert testimony presented at trial by both sides established
    that the site selected for the pond was not appropriate, based upon
    the geology and soil types in the area, [as well as] the natural water
    sources available from groundwater drainage in the area and the
    existing natural springs. Furthermore, the use of agricultural water
    runoff results in poor water quality for swimming and fish habitat.
    Testimony by the expert witness retained by [Reilly] also
    disclosed that the water level of the pond could be increased and
    water quality improved if a supplemental water source were made
    available . . . .
    [Bachelder] agrees with the expert testimony presented,
    which concludes that the pond is not repairable to perform in the
    manner required by the contract. [Bachelder] is unwilling to take
    any further action to attempt improvement, including the addition of
    a supplemental water source. Instead, it seeks monetary damages
    for breach of contract in an amount that would restore its land to the
    condition it was in prior to the construction of the pond. In order to
    accomplish the proposed restoration work, it obtained an estimate
    from an earth-moving contractor for the cost of removing the
    dam/berm across the valley. The estimate, which is in the total
    amount of $98,000.00, also includes grading of the area,
    reconstruction of the waterway, and installation of a silt fence.
    [Bachelder] also seeks recovery of incidental damages of
    $4028.33 for the purchase of sand, equipment, and grass seed for
    use at the pond. It further asks for reimbursement of the prior
    payments to [Reilly] in the amount of $116,962.13.
    No evidence was presented regarding the feasibility or cost
    of adding a supplemental water source, such as a well, to
    supplement the water level and water quality of the existing pond,
    to allow it to perform in the manner required by the original contract.
    No evidence was presented to show that the work done on
    this property by [Reilly] has affected the value of the property as a
    whole, either positively or negatively, or impaired the use and
    enjoyment of the property. Without a doubt, it is highly probable
    that the proper construction of a recreational pond would have
    enhanced the value of the property, both aesthetically and
    financially. Certainly, the expenditure of the money paid already
    without any significant benefit in return constitutes a loss.
    [Reilly] claims that Bachelder has failed to prove the cost of
    repair of the pond, which it maintains is the proper measure of
    damages for breach of contract. It also alleges that an award of the
    damages requested for removal of the pond structure would
    constitute economic waste. It further argues that a refund of the
    money already paid would result in a windfall to [Bachelder].
    Finally, [Reilly] points out that there is no assurance or requirement
    4
    that [Bachelder] would actually use any awarded damages to
    remove the pond structure and “restore” the area to its former
    condition.
    The district court concluded:
    There is no evidence of the cost of any additional work that
    could be done that would result in a recreational pond that would
    provide the type of recreational activities that the court of appeals
    decision determined to be a requirement of the contract. The
    plaintiff has also rejected this option.
    There is no evidence of any monetary diminution in the value
    or profitability of the property. There is evidence that the work
    already done and the expenditures already made have not
    enhanced the use and value of the property as contemplated by the
    contract. These facts were confirmed by the court of appeals in its
    decision.
    Removal of the pond structure to restore the property as
    proposed by [Bachelder] involves an expenditure of nearly
    $100,000.00 with no clear economic benefit to [Bachelder]. This
    work will not make the property useful for any other purpose and
    will have no apparent effect on use, value, or profitability of the
    farm. There is no assurance that the work would be performed and
    the money spent for that purpose. Therefore, an award of
    damages based upon that concept of damages would constitute
    economic waste.
    The court determined Bachelder’s damages to be the $116,962.13 it paid
    Reilly to construct the pond plus the $4028.33 it incurred for incidental expenses
    related to the pond’s construction, for a total award of $120,990.46 in damages.
    Reilly now appeals.
    Both parties assert that our standard of review is for corrections of errors
    at law. Under this standard, the trial court’s factual findings have the effect of a
    special verdict.   See Iowa R. App. P. 6.907.      While the factual findings are
    binding upon us if supported by substantial evidence, we are not bound by the
    district court’s application of legal principles or conclusions of law. See Revere
    Transducers, Inc. v. Deere & Co., 
    595 N.W.2d 751
    , 763 (Iowa 1999).
    5
    “The purpose of a damage suit is compensation; the goal is to place the
    injured party in as favorable position as though no wrong had occurred.” R.E.T.
    Corp. v. Frank Paxton Co., 
    329 N.W.2d 416
    , 421 (Iowa 1983). “Damages in
    defective construction cases may include diminution in value, cost of construction
    or completion as required under the contract, or loss of rentals.” Serv. Unlimited,
    Inc. v. Elder, 
    542 N.W.2d 855
    , 857 (Iowa Ct. App. 1995). Typically, the cost of
    correcting the defects or completing the omissions is the proper measure of
    damages in a defective construction case. 
    Id. at 858.
    However, if the cost of
    repair is grossly disproportionate to the result or the benefit obtained, or would
    involve unreasonable destruction of the contractor’s work, damages may be
    calculated based on diminution in value.          
    Id. A combination
    of the various
    damage elements may be employed in certain circumstances in order to render
    the injured party whole.     See R.E.T. 
    Corp., 329 N.W.2d at 421
    .            Finally,
    “[d]amages are limited to the actual loss.” 
    Id. Reilly argues
    Bachelder failed to produce evidence of the cost of repairing
    the pond or loss of rentals. It further argues that because the evidence shows
    there has been no diminution in the value of the property, it would be economic
    waste to award Bachelder damages for the cost of removing the pond structure
    from the property. On this basis, Reilly argues the court’s award of $120,990.46
    in damages to Bachelder is unsupported and in error.
    Like the pond it built, Reilly’s argument does not hold water. The evidence
    presented shows the site of the pond is not suitable for a pond structure because
    the underlying soils in the pond area are permeable and ineffective in holding
    water. As a result, the pond cannot maintain a permanent pool of water without
    6
    the addition of a supplemental water source. The fact that the pond cannot be
    adequately repaired without economic waste does not relieve Reilly of its duty to
    compensate Bachelder. Nor does it mean Bachelder was not damaged. Reilly’s
    argument overlooks the $116,962.13 Bachelder expended for the pond’s
    construction, plus the $4028.33 in additional costs. Because the pond does not
    function, it is of no value. While the land’s value was not diminished by the
    pond’s construction, it was also not benefited.      In other words, Bachelder’s
    position has not improved in exchange for the $120,990.46 it spent. This cost,
    for which it received no benefit, is the amount of Bachelder’s damages. See
    Vorthman v. Keith E. Myers Enters., 
    296 N.W.2d 772
    , 777 (Iowa 1980) (“The
    measure of damages for breach of warranty is the loss directly and naturally
    resulting, in the ordinary course of events, from the breach.”); Bause v. Anthony
    Pools, Inc., 
    23 Cal. Rptr. 265
    , 267 (Cal. Dist. Ct. App. 1962) (holding damages
    for defectively constructed pool that was not capable of being repaired included
    the amount the owner paid the contractor, as well as the costs of removing the
    pool and refilling the hole); Bowling v. Jones, 
    300 S.W.3d 288
    , 295-96 (Tenn. Ct.
    App. 2008) (holding an award for monies spent by owner in constructing a house
    was the proper measure of damages where the house was defectively
    constructed and of no value).
    Bachelder contracted with Reilly to construct a recreational pond. As a
    result of Reilly’s breach, the pond is useless to Bachelder, and it is therefore of
    no value to Bachelder. Under the circumstances presented, we agree the district
    court employed the proper measure of damages. In order to place Bachelder in
    as good a position as if the breach had not occurred, it should be reimbursed the
    7
    $116,962.13 it paid Reilly, plus the $4028.33 in additional costs it incurred.
    Accordingly, we affirm the district court’s judgment.
    AFFIRMED.