Reicher Electric, Inc. v. Atul Patel and Shri Ganapati & Bajrangbali, Inc., and Iowa Corporation, d/b/a Fairfield Inn & Suites ( 2019 )


Menu:
  •                    IN THE COURT OF APPEALS OF IOWA
    No. 18-0622
    Filed May 1, 2019
    REICHER ELECTRIC, INC.,
    Plaintiff-Appellant,
    vs.
    ATUL PATEL and SHRI GANAPATI & BAJRANGBALI, INC., an Iowa
    Corporation, d/b/a FAIRFIELD INN & SUITES,
    Defendants-Appellees.
    ________________________________________________________________
    Appeal from the Iowa District Court for Black Hawk County, John J.
    Bauercamper, Judge.
    A subcontractor appeals a district court order denying a claim for unjust
    enrichment. AFFIRMED.
    Dan McClean of McClean & Heavens Law Offices, Dyersville, for appellant.
    Max E. Kirk of Ball, Kirk & Holm PC, Waterloo, for appellees.
    Considered by Tabor, P.J., and Mullins and Bower, JJ.
    2
    BOWER, Judge.
    Reicher Electric, Inc. (Reicher) appeals the district court’s ruling in favor of
    Atul Patel and Shri Ganapati & Bajrangbali, Inc. (SGB). Reicher contends SGB
    was unjustly enriched by receiving the benefit of work when Reicher was not paid.
    We find Reicher did not establish a direct contract between Reicher and SGB and
    cannot support a claim of unjust enrichment.
    I.      Background Facts & Proceedings
    On August 19, 2013, SGB entered into a construction contract with general
    contractor Main Street Developers (MSD), a Wisconsin company, to build a
    commercial hotel property in Waterloo.1 The contract specified a firm price of
    $4,450,000 and required any changes or substitutions be approved by SGB in
    writing. Under the agreement, MSD was to “provide all labor, materials, equipment
    and services necessary to complete the Work.” The contract had as an exhibit a
    list of items to be provided by MSD, including “Interior Lighting Fixtures
    (Permanent).”
    MSD hired Reicher for the electrical work on the hotel.               The contract
    provided MSD would pay Reicher $300,000 for the electrical work. After the
    project began, MSD approached Reicher and asked for assistance in obtaining the
    lighting fixtures; Reicher agreed for a price of ten percent of the cost of the lighting.
    1
    The parties’ appendix violates the clear requirements in Iowa Rule of Appellate
    Procedure 6.905(2)(b). In particular, this appendix does not contain the initial pleadings
    between these parties, a copy of the order in question, a list of relevant docket entries, or
    relevant portions of the transcript (though a list of relevant transcript portions was
    included). The briefs refer to documents not included in the appendix. The failure to
    compile a minimally-adequate appendix forces the court to search a record of over 2000
    pages for basic information and impedes the efficiency of this court’s ability to address the
    issues in a timely manner.
    3
    Reicher approached Crescent Electric Supply Company (Crescent) to supply the
    necessary materials. Following an initial partial estimate from Crescent, MSD
    provided $70,000 to Reicher for lighting fixture orders.
    After work had already begun, Reicher and Atul Patel, president of SGB,
    met with a hotel chain representative who suggested converting to LED lighting
    and provided a “spec book” of appropriate fixtures. Reicher informed Patel while
    the conversion would save electric costs, it would cost more upfront. Reicher
    claims Patel said to change to the LED lighting. Patel testified he never received
    a quote for the lighting and did not have a formal meeting with MSD regarding the
    LED lighting. No change orders were submitted to SGB or approved for electric
    work or light fixtures.
    MSD was not present at either LED lighting meeting, but was aware Reicher
    was ordering and installing LED lights. The owner of MSD testified the change in
    lighting was a separate agreement between Reicher and Patel that MSD was not
    part of, and he denied MSD was responsible for paying for the LED lighting.
    Numerous other changes to Reicher’s work were requested, including electric car
    charging stations, floor boxes in the conference room, rewiring offices, adding
    notification lights to sump pumps, and additional outlets. Reicher also had to
    rewire for some appliances when fixtures provided by MSD did not match the
    electrical requirements on the plans Reicher was working from. Reicher included
    costs for all changes in its bill to MSD.
    From January 2014 through April 2015, Reicher ordered lighting fixtures
    from Crescent. Crescent ordered and Reicher installed the LED lights listed in the
    hotel chain’s “spec book.” As the $70,000 was paid over time by MSD, Reicher
    4
    made payments to Crescent; no other party made payments on the light fixtures
    ordered for the hotel. At the end of the project, Reicher still owed $106,209.31 to
    Crescent. Reicher provided all the invoices to MSD, and MSD indicated Reicher
    probably would not get paid for everything. One week before completion, Reicher
    raised the issue of payment with Patel and SGB.
    Around the time of opening the hotel, MSD walked off the project without
    issuing a statement of substantial completion. After discovering MSD and SGB
    would not pay for the LED lighting and extra work performed, Reicher refused to
    do additional uncontracted work on the project. Reicher did not complete rebate
    forms for the lighting installed and did not complete warranty work in the hotel.2
    Some lighting materials were returned to Crescent, but some of the items were
    special order or outside the time period for returns and Reicher could not get
    refunds for them.
    Crescent filed a mechanic’s lien on July 23, 2015, for $104,388.94, naming
    Reicher as general contractor for the building owned by SGB. On August 14, 2015,
    nearly four months after completing its work on the hotel, Reicher filed a
    mechanic’s lien against SGB for items provided between December 2014 and April
    2015, claiming a sum of $191,805. It appears Reicher’s mechanic’s lien is still
    outstanding.
    On November 11, Crescent filed a petition at law against Reicher for breach
    of contract, quantum meruit, unjust enrichment, and statement on account.
    Crescent requested relief of the principal due plus statutory interest and court
    2
    According to Reicher, the rebates would have been worth approximately fifteen to
    twenty thousand dollars.
    5
    costs. On June 2, 2016, Reicher filed a cross-petition for breach of contract,
    quantum meruit, and unjust enrichment against Patel and SGB as third-party
    defendants. Reicher did not name MSD in the petition. Reicher claimed to have
    entered into an oral contract with Patel and SGB for the installation of electrical
    fixtures and lighting at the hotel and to have conferred benefit in the form of
    material, services, labor, and time for which the company is entitled to the
    reasonable value.     Reicher’s requested relief included full contribution and
    indemnity, attorney fees, court costs, and interest.
    On June 1, 2017, the district court entered a judgment order agreed to by
    Crescent and Reicher in favor of Crescent, entering a judgment of $119,207.60
    against Reicher.3 On June 8, the cross-petition between Reicher and SGB was
    tried to the court.
    On February 10, 2018, the court filed its findings of fact, conclusions of law,
    judgment and decree. The court found no express contract—written or oral—
    existed between Reicher and SGB. The court then noted changes in a contract
    between a general contractor and subcontractor do not create a contract between
    the subcontractor and the owner. Without contractual privity, the court ruled “no
    common law remedy of restitution is available.” Reicher appeals only the issue of
    unjust enrichment.
    II.     Standard of Review
    “A claim for unjust enrichment ‘arises from the equitable principle that one
    shall not be permitted to unjustly enrich oneself by receiving property or benefits
    3
    The judgment included both Reicher’s outstanding balance with Crescent, statutory
    interest, and court costs.
    6
    without making compensation therefor.’” Legg v. W. Bank, 
    873 N.W.2d 763
    , 771
    (Iowa 2016) (quoting Ahrendsen ex rel. Ahrendsen v. Iowa Dep’t of Human Servs.,
    
    613 N.W.2d 674
    , 679 (Iowa 2000)). The district court expressly noted the case
    was being tried at law without objection from the parties. Therefore, our review is
    for correction of errors at law. See Iowa R. App. P. 6.907; Pursell Constr., Inc. v.
    Hawkeye-Sec. Ins. Co., 
    596 N.W.2d 67
    , 69 (Iowa 1999).
    III.   Analysis
    In Henning v. Security Bank, 
    564 N.W.2d 398
    , 401–03 (Iowa 1997), our
    supreme court analyzed the rights and remedies available to subcontractors in
    comparison to general contractors. While general contractors have common-law
    remedies for the value of materials and labor in addition to statutory mechanic’s
    lien rights, these remedies are based on the existence of express or implied
    contracts. Henning, 
    564 N.W.2d at 402
    . Because the subcontractor’s contractual
    relationship is with the general contractor, contractual and common-law remedies
    are against the contractor, not the owner. 
    Id.
     at 403 (citing Roger W. Stone,
    Mechanic’s Liens in Iowa, 
    30 Drake L. Rev. 39
    , 45–46 (1980)). Iowa’s mechanic’s
    lien law provides the means of recovery by a subcontractor against the property
    owner. 
    Id.
     The court found in the absence of a contractual arrangement with the
    owner, subcontractors do not have a common-law right of action based on implied
    contract or unjust enrichment for the work and materials furnished. Id. at 399.
    In order to prove a right to a common-law recovery, Reicher had to prove a
    direct contract with SGB—either express or implied. The district court found no
    express contract existed directly between Reicher and SGB. SGB’s fixed-price
    contract with MSD specifically assigned the responsibility to provide the permanent
    7
    interior lighting fixtures to the contractor. MSD then delegated that job to Reicher
    as an addition to their original contract. “The law will not imply a contract where
    there is an express contract.” Clemens Graf Droste Zu Vischering v. Kading, 
    368 N.W.2d 702
    , 712 (Iowa 1985).        An express contract supersedes an implied
    contract. Welte Ins., Inc. v. Big Red Lighting & Elec., Inc., No. 11-0254, 
    2011 WL 5391616
    , at *7 (Iowa Ct. App. Nov. 9, 2011). Because the contract between the
    owner and general contractor expressly covers permanent interior lighting fixtures,
    and MSD then contracted with Reicher on the light fixtures, we cannot find an
    implied contract between Reicher and SGB.
    Reicher’s primary remedies as a subcontractor on the project are
    contractual actions against the general contractor.     If the principal contractor
    becomes insolvent or otherwise defunct, then our mechanic’s lien law provides a
    means of recovery. Louie’s Floor Covering, Inc. v. DePhillips Interests, Ltd., 
    378 N.W.2d 923
    , 927 (Iowa 1985). It does not appear from the record before us that
    Reicher has sought recovery from MSD or attempted to foreclose its mechanic’s
    lien. We find Reicher has not established the express contract between Reicher
    and SGB necessary to support a claim of unjust enrichment and is limited to
    recovery from MSD or through its mechanic’s lien.
    AFFIRMED.