Woodruff Construction, LLC v. Steven P. Christensen, Individually and D/B/A Christensen Construction Company ( 2019 )


Menu:
  •                     IN THE COURT OF APPEALS OF IOWA
    No. 18-0371
    Filed May 1, 2019
    WOODRUFF CONSTRUCTION, LLC,
    Plaintiff-Appellant,
    vs.
    STEVEN P. CHRISTENSEN, Individually and D/B/A CHRISTENSEN
    CONSTRUCTION COMPANY,
    Defendant-Appellee.
    ________________________________________________________________
    Appeal from the Iowa District Court for Dickinson County, David A. Lester,
    Judge.
    Woodruff Construction, LLC appeals the judgment entered following trial on
    the parties’ breach-of-contract claims. AFFIRMED.
    Ernest Kersten, Fort Dodge, and Jerry L. Schnurr III of Schnurr Law Firm,
    P.C., Fort Dodge, for appellant.
    Richard Meyer of Fillenwarth & Fillenwarth, Estherville, for appellee.
    Considered by Vaitheswaran, P.J., and Doyle and Mullins, JJ.
    2
    DOYLE, Judge.
    Woodruff Construction, LLC (Woodruff) appeals the district court order
    entering judgment in favor of Steven P. Christensen and Christensen Construction
    Company (Christensen) on its breach-of-contract counterclaim.                      Woodruff
    challenges the district court’s finding that Woodruff breached its contract with
    Christensen. Woodruff also challenges the court’s damage award.
    Polaris Industries contracted with Christensen to construct an addition onto
    its manufacturing plant in Spirit Lake. Christensen subcontracted with Woodruff to
    complete a portion of the work. The parties signed a written agreement that states
    Woodruff was to complete a counterfort wall1 by no later than December 2, 2013,
    and a retaining wall by no later than December 19. Woodruff did not complete
    work on the counterfort wall until January 20, and it never completed the retaining
    wall.
    In August 2015, Woodruff filed a petition claiming Christensen breached the
    contract by failing to pay for the completed work. In May 2016, Christensen filed
    an amended answer and counterclaim alleging Woodruff was negligent and that it
    breached the contract in failing to complete construction properly and timely
    pursuant to the plans and specifications. A two-day bench trial was held in January
    and February 2017. The matter was deemed submitted for final ruling after briefing
    was completed in March 2017. In January 2018, the district court entered a written
    ruling finding that both parties had breached the contract. The court determined
    1
    A counterfort wall is a retaining wall with counterforts or buttresses on the back or thrust-
    receiving side. See Webster’s Third New International Dictionary 519 (unbar. ed. 2002).
    3
    the amount of Woodruff’s damages to be $84,132.86 and the amount of
    Christensen’s damages to be $78,813.
    On appeal, Woodruff contends there is insufficient evidence to support a
    finding that it breached its contract with Christensen. To succeed on a claim of
    breach of contract, a party must show:
    (1) the existence of a contract; (2) the terms and conditions of the
    contract; (3) that it has performed all the terms and conditions
    required under the contract; (4) the defendant’s breach of the
    contract in some particular way; and (5) that plaintiff has suffered
    damages as a result of the breach.
    Iowa Arboretum, Inc. v. Iowa 4-H Found., 
    886 N.W.2d 695
    , 706 (Iowa 2016)
    (citation omitted). Because this action was tried at law, our review is for correction
    of errors at law. See Iowa R. App. P. 6.907. We are bound by the district court’s
    fact findings if supported by substantial evidence. See Iowa R. App. P. 6.904(3)(a).
    The district court found each party had proved the first four elements of a
    breach-of-contract claim. With regard to Woodruff’s claim, the court found that
    Woodruff completed construction of the counterfort wall, “albeit late and not
    according to the specifications set forth in the contract.” It noted that Christensen
    and Polaris had accepted Woodruff’s work because the addition was completed,
    and therefore, it concluded that Christensen’s refusal to pay for the completed work
    constituted a breach of the contract. With regard to Christensen’s counterclaim,
    the court found that Woodruff “did not come close to meeting” the deadline for
    completing the counterfort wall specified in the contract and never constructed the
    retaining wall. It further observed that
    Woodruff did not comply with the specifications set forth in the
    contract including the type of forms used, the length of each section
    of wall that was poured, the providing of a rebar free area and a void
    4
    in the forms, and putting trash and debris from their work into a
    dumpster at the site. All of the foregoing, the court concludes,
    constitutes breaches by Woodruff of the terms of the parties’ written
    contract.
    The bulk of Woodruff’s claims concern its defense that it could not perform
    under the deadlines of the contract based on circumstances beyond its control—
    namely, the bitterly cold winter weather and Christensen’s conduct.2 In a lengthy
    ruling, the district court provided a detailed summary of the evidence presented at
    trial and concluded that neither the weather nor Christensen’s performance
    excused Woodruff from meeting the contract deadline. Specifically, the court
    found that Christensen’s performance “only temporarily delayed Woodruff’s
    performance, at most, and does not serve as a basis for excusing Woodruff’s
    wholesale failure to meet the deadlines set forth in the contract or to excuse its
    failure to perform the work it did in the manner specified in the contract.” It further
    2
    Woodruff refers to “the principle of force majeure.” “Force majeure” refers to “an event
    that can be neither anticipated nor controlled.” Pillsbury Co., Inc. v. Wells Dairy, Inc., 
    752 N.W.2d 430
    , 440 (Iowa 2008) (quoting Black’s Law Dictionary 657 (7th ed. 1999)). The
    Iowa cases on this proposition relate to contracts that contain a “force-majeure clause”—
    a clause that “allocate[es] the risk if performance becomes impossible or impracticable as
    a result of an event or effect that the parties could not have anticipated or controlled.” 
    Id.
    (citation omitted). As our supreme court has noted, “A force-majeure clause is not
    intended to shield a party from the normal risks associated with an agreement.” 
    Id.
    Even if a contract provides no such clause, “the court may still relieve the party of
    that duty ‘if performance has unexpectedly become impracticable as a result of a
    supervening event.’” Am. Soil Processing, Inc. v. Iowa Comprehensive Petroleum
    Underground Storage Tank Fund Bd., 
    586 N.W.2d 325
    , 330 (Iowa 1998) (citation omitted).
    Referred to as “the doctrine of discharge by supervening impracticability,” it applies when
    an event that the parties assumed would not occur at the time of contracting arises and
    makes performance impracticable through no fault of the nonperforming party. DuTrac
    Cmty. Credit Union v. Radiology Grp. Real Estate, L.C., 
    891 N.W.2d 210
    , 217 (Iowa 2017).
    In its answer to Christensen’s counterclaim, Woodruff alleged its timely
    performance was impossible due to Christensen’s conduct and the bitterly cold winter
    weather. Therefore, we analyze Woodruff’s claim under the doctrine of impossibility of
    performance. Under the doctrine of impossibility of performance, a party’s failure to
    perform under the contract is excused when performance is rendered impossible due to
    no fault of the nonperforming party. See 
    id.
     “In order to excuse nonperformance, the term
    must be objectively impossible to perform.” 
    Id.
    5
    found that Woodruff could have reasonably anticipated the weather conditions
    when it signed the contract and agreed to meet the deadlines provided. Most
    importantly, the court found that “Woodruff could have met the deadlines in the
    contract had it directed more manpower and time to the Polaris project but, for
    reasons not provided in the record, chose not to do so.” There is ample evidence
    to support the trial court’s findings. Because it was not objectively impossible for
    Woodruff to perform, neither the weather nor Christensen’s conduct excuse its
    failure to do so. See DuTrac Cmty. Credit Union, 891 N.W.2d at 217.
    Woodruff also challenges the finding that it failed to provide a void in the
    forms and failed to put trash and debris in a dumpster. With regard to Woodruff’s
    duty to provide a void for anchor bolts, the agreement states that Woodruff “must
    provide . . . a void in the forms.” Woodruff’s West Region President testified that
    the forms Woodruff used did not allow it to set voids for anchor bolts. Christensen’s
    construction superintendent testified that the counterfort wall constructed by
    Woodruff did not contain voids as required by the contract.           Christensen’s
    president testified that Christensen spent days cleaning excess concrete off the
    anchor bolts at a cost of $3200. The district court found sufficient corroborating
    testimony to support Christensen’s claim for compensation. We agree.
    With regard to additional cleanup costs, Woodruff claims that at the end of
    its work, it took all forms and trash to the dumpster Christensen provided, and
    when the dumpster was full, it stacked the remaining trash neatly next to the
    dumpster. Christensen’s president testified that Woodruff abandoned “big slanted
    wood forms” that were “probably 20, 24 foot tall or something” and Christensen
    had to pay $1600 to have them removed to a landfill. Christensen also charged
    6
    $450 for “picking up some more of the mess that Woodruff left behind.” Citing the
    testimony, the court found the record supported an award of $2050 for the cost of
    cleanup. Substantial evidence supports this finding.
    Woodruff objects to the district court’s award of $6270 to Christensen for
    gel patching the counterfort wall to fill holes and honeycombing caused by
    Woodruff’s defective work. The district court based this award on the testimony
    and photographs showing the extent of the patching work required. Woodruff
    alleges the damage award was “based on mere speculation and conjecture”
    because when asked how many square feet of the total wall had honeycombing,
    the construction superintendent testified, “I couldn’t even give you a guess.”
    However, Christensen’s president testified that the labor charge for the repair work
    amounted to $6270. “There is a distinction between proof of the fact that damages
    have been sustained and proof of the amount of those damages.” St. Malachy
    Roman Catholic Congregation of Geneseo v. Ingram, 
    841 N.W.2d 338
    , 352 (Iowa
    2013) (citation omitted). Because “there is proof of a reasonable basis from which
    the amount can be inferred or approximated,” the damage award was not overly
    speculative. 
    Id.
     (citation omitted).
    Woodruff alleges the court erred in awarding Christensen $9474 toward
    bond premiums it had to pay due to a mechanic’s lien filed by Woodruff. The court
    noted that Polaris required Christensen to post a bond to get the mechanic’s lien
    released from its property because the dispute was between Christensen and
    Woodruff. Because it ultimately found both parties were entitled to some amount
    of compensation for damages arising from that dispute and that each was partially
    successful in prosecuting its claim, the district court held each party responsible
    7
    for one-half of the bond premiums paid. The $9474 awarded to Christensen
    comprises Woodruff’s share of the bond premiums. The district court acted within
    its discretion in awarding Christensen damages for half the amount of the bond
    premiums. See Hawkeye Motors, Inc. v. McDowell, 
    541 N.W.2d 914
    , 917 (Iowa
    Ct. App. 1995) (“The determination of the amount of damages in a bench trial
    ordinarily lies within the sound discretion of the trial court.”).
    Woodruff also objects to the district court’s award of $55,709 to Christensen
    based on concessions Christensen made to Polaris because of additional charges
    Polaris incurred in the building’s construction.        The record shows that other
    contractors billed Polaris $55,709 in additional costs due to “incomplete and
    uncoordinated concrete structure and layout through January 25, 2014.” Because
    the damage award is within the range of the evidence, we affirm. See 
    id. at 918
    (“An award of damages within the range of the evidence will not be disturbed on
    appeal.”).
    AFFIRMED.