Virgil Johnson and Virgil Johnson Trucking v. Associated Milk Producers, Inc. ( 2015 )


Menu:
  •                    IN THE COURT OF APPEALS OF IOWA
    No. 15-0105
    Filed October 14, 2015
    VIRGIL JOHNSON and VIRGIL JOHNSON TRUCKING,
    Plaintiffs-Appellants,
    vs.
    ASSOCIATED MILK PRODUCERS, INC.,
    Defendant-Appellee.
    ________________________________________________________________
    Appeal from the Iowa District Court for Allamakee County, Margaret L.
    Lingreen, Judge.
    Plaintiffs appeal a district court decision granting summary judgment to
    defendant on their action for breach of contract. REVERSED AND REMANDED.
    John S. Anderson and Stephen J. Belay of Anderson, Wilmarth, Van Der
    Maaten, Belay, Fretheim, Gipp & Zahasky, Decorah, for appellants.
    Matthew C. Berger of Gislason & Hunter, L.L.P., New Ulm, Minnesota, for
    appellee.
    Heard by Doyle, P.J., Eisenhauer, S.J., and Goodhue, S.J.*
    *Senior judge assigned by order pursuant to Iowa Code section 602.9206 (2015).
    2
    GOODHUE, Senior Judge.
    Virgil Johnson and Virgil Johnson Trucking filed a petition claiming a sum
    due, alleging that Associated Milk Products, Inc. (Associated) had breached its
    contract to pay specific sums for delivering milk to Associated’s Arlington plant.
    Associated filed a motion for summary judgment alleging that the contract had
    been modified or replaced beginning September 1, 2013, and that all sums due
    had been paid in full. The motion was granted. Johnson has appealed.
    I. Background Facts
    In September 2001, Johnson and Associated entered into an oral
    agreement whereby Johnson was to pick up milk from dairy farms and deliver it
    to Associated’s plant in Arlington. Johnson was paid so many cents per gallon
    for the milk delivered and $100 a trip for each load delivered.
    In a letter dated July 31, 2013, Associated advised Johnson that it was
    reducing the trip charge by twenty-five dollars per month beginning September 1,
    and twenty-five dollars more for each succeeding month until December 1, 2013,
    when the trip charge would be totally eliminated.          There was no specific
    agreement in the original contract as to its duration or the method by which it
    could be amended or terminated.
    Neither party expressly or formally terminated the contract.      Instead,
    Johnson continued to deliver the milk and Associated continued to accept it.
    Johnson protested the amendment by continuing to bill Associated for the trip
    charge as well as the gallonage charge. Associated paid in accordance with its
    July 31 letter.   This arrangement continued until a formal written notice of
    termination was given by Associated on November 12, 2014, which terminated
    3
    the agreement effective December 2, 2014.        However, in January of 2014,
    Johnson had filed a petition claiming sums due as provided by the original
    contract. Associated filed a motion for summary judgment and it was granted.
    II. Scope of Review
    Summary judgments are reviewed for errors of law. Phillips v. Covenant
    Clinic, 
    625 N.W.2d 714
    , 717 (Iowa 2001).
    III. Error Preservation
    Issues must be raised in district court and ruled on before they will be
    considered on appeal. Meier v. Senecaut, 
    641 N.W.2d 532
    , 537 (Iowa 2002).
    Johnson filed a resistance to the motion, thereby preserving error.     See Bill
    Grunder’s Sons Constr., Inc. v. Ganzer, 
    686 N.W.2d 193
    , 197-98 (Iowa 2004).
    IV. Discussion
    When a motion for summary judgment is filed the burden is on the moving
    party to demonstrate he is entitled to judgment. Sabin v. Ackerman, 
    846 N.W.2d 835
    , 839 (Iowa 2014). On appeal the record is reviewed in the most favorable
    light to the nonmoving party.     
    Id.
       Even if facts are undisputed, summary
    judgment is not appropriate if reasonable minds could reach different conclusions
    based on inferences that can be drawn from the undisputed facts. 
    Id.
    Generally, a modification to an existing contract requires a new
    consideration, while a revision or termination of an existing contract and a
    replacement with a new contract does not require a new consideration. Recker
    v. Gustafson, 
    279 N.W.2d 744
    , 755-56 (Iowa 1979). The problem is determining
    whether there has been a revision and a new contract formed or an ineffective
    attempt to modify a contract without consideration.
    4
    If a contract does not contain an express or implied period of duration the
    court will generally construe the contract to be a contract terminable at will.
    Shelby Cnty. Cookers, L.L.C. v. Util. Consultants Int’l, Inc., 
    857 N.W.2d 186
    , 191
    (Iowa 2014).    The parties do not dispute that the initial contract could be
    terminated by either of them after providing a reasonable notice. Associated
    contends, and the district court agreed by granting the motion for summary
    judgment, that the contract between Johnson and Associated was terminated by
    the July 31 letter. Johnson, by continuing to deliver the milk, in effect consented
    to the termination and to a new contract that deleted the trip charges in
    accordance with the July 31 letter. There is no contention that any consideration
    supported the change in the payment schedule or that either party specifically
    referenced revision or termination, either orally or in writing, until the letter of
    December 12.
    A very similar situation was addressed by our Supreme Court in
    Davenport Osteopathic Hospital Ass’n v. Hospital Service, Inc., 
    154 N.W.2d 153
    (Iowa 1967). Hospital had agreed to provide services to Blue Cross subscribers.
    Davenport Osteopathic Hosp. Ass’n, 
    154 N.W.2d at 156
    . The contract between
    the parties had a ninety-day termination clause. See 
    id.
     A few years later Blue
    Cross advised Hospital it was changing its payment formula which reduced the
    charges payable to Hospital. See 
    id.
     Hospital protested the new rate schedule
    but Blue Cross only reimbursed by the new schedule even though Hospital
    continued to charge in accordance with the original agreement. See 
    id.
     Blue
    Cross contended that by failing to officially terminate or rescind the contract and
    instead accepting the reduced payment the hospital agreed to the modification.
    5
    See 
    id. at 158
    . The court noted that neither party elected to rescind and awarded
    Hospital recovery under the terms of the initial contract.     See 
    id.
     The court
    stated, “The law does not sanction breach of contract as a means of escape from
    its burdensome terms nor will it reward an offending party.” 
    Id.
    Tindell v. Apple Lines, Inc., 
    478 N.W.2d 428
     (Iowa Ct. App. 1991), is
    another similar case. Tindell had an operating lease with Apple in which he was
    paid so many cents per mile for hauling Apple’s freight. Tindell, 
    478 N.W.2d at 429
    . The agreement was subject to a thirty-day notice of termination. See 
    id. at 429-30
    . Apple prepared an addendum decreasing the rate but Tindell did not
    sign it and advised Apple he would not accept the rate change. See 
    id. at 430
    .
    Tindell continued to haul and accept payments at the reduced rate. See 
    id.
     The
    court found Apple owed Tindell for the period in which it unilaterally reduced the
    rate of pay. See 
    id. at 431-32
    .
    Associated contends that Davenport Osteopathic and Tindell can be
    differentiated on the grounds that both contracts had termination clauses that
    required a notice and a lapse of time before the actual termination. Associated
    further contends in a case where an agreement requires a time lapse between
    the notice and the termination it is not a contract at will. Associated reasons that
    in a contract at will a request to change by either party is an automatic
    termination of the original contract. If the other party continues to perform, a new
    contract has been formed in accordance with the requested modification.
    It is true that both Davenport Osteopathic and Tindell have specific
    termination clauses, but all contracts at will can be terminated only after
    reasonable notice of termination. See Hess v. Iowa Light, Heat & Power Co.,
    6
    
    221 N.W. 194
    , 196-97 (Iowa 1928). There is no logical or rational reason that a
    contract that in effect allows either party to terminate at will, but contains an
    agreed upon reasonable termination notice should be treated as a contract for a
    specific term rather than a contract at will. Associated has not directed the court
    to any Iowa case that has been based on that distinction. It is distinction without
    meaning as it relates to the factual situation under consideration. Associated
    provided a reasonable notice when it finally terminated the contract.
    Associated and the district court liken the case under consideration to an
    employment at will contract. An employment contract is terminable at will and
    subject to modification at any time, leaving the other party with only the
    alternatives of accepting the modification or terminating the relationship. See
    Willits v. City of Creston, 
    433 N.W.2d 58
    , 62 (Iowa Ct. App. 1988); Moody v.
    Bogue, 
    310 N.W.2d 655
    , 661 (Iowa Ct. App. 1981). There has been a long
    standing legal distinction between employees and independent contractors.
    Harvey v. Care Initiatives, Inc., 
    634 N.W.2d 681
    , 683-84 (Iowa 2001).          The
    concept of employment contracts as contracts at will is firmly rooted in Iowa law.
    Fogel v. Trustees of Iowa Coll., 
    446 N.W.2d 451
    , 455 (Iowa 1989). Employment
    contracts have been considered unilateral contracts where one party makes an
    express agreement and the other party makes no promise but accepts by
    rendering some performance. See Anderson v. Douglas & Lomason Co., 
    540 N.W.2d 277
    , 282-83 (Iowa 1995); Drake v. Block 
    74 N.W.2d 577
    , 80 (Iowa 1956).
    Johnson entered into his relationship with Associated as an independent
    subcontractor and not as an employee and that relationship continued.          The
    contract between the two parties was a bilateral contract subject to modification
    7
    by agreement. The fact that employment contracts and service contracts with an
    independent contractor are treated differently is exemplified by the cited cases.
    Assent to a modification may be implied from the acts of the other party
    when a bilateral contract exists but whether such a contract has been modified is
    ordinarily a question of fact.   See Davenport Osteopathic Hosp. Ass’n, 
    154 N.W.2d at 157
    .     The district court applied the rules applicable to contracts
    between an employer and employee and concluded as a matter of law that
    Johnson accepted the terms of the proposed modified contract when he
    continued to haul milk after the proposal was made. The rule utilized is not
    appropriate when a service contractor as opposed to an employee is involved.
    Although the facts are primarily undisputed, those facts do not support
    Johnson’s acceptance of Associated’s proposed modification as the only, or
    probable, conclusion that can be drawn from those facts.
    We therefore reverse and remand for further proceedings consistent with
    this opinion.
    REVERSED AND REMANDED.