Wagner Interior Supply of Wichita, Inc. v. Dynamic Drywall, Inc. ( 2017 )


Menu:
  •               IN THE SUPREME COURT OF THE STATE OF KANSAS
    No. 113,037
    WAGNER INTERIOR SUPPLY OF WICHITA, INC.,
    Appellant,
    v.
    DYNAMIC DRYWALL, INC., et al.,
    Defendants,
    (PUETZ CORPORATION and UNITED FIRE & CASUALTY COMPANY),
    Appellees.
    SYLLABUS BY THE COURT
    1.
    A mechanic's lien is purely a statutory creation and, to create an enforceable lien,
    the statutory requirements must be followed strictly.
    2.
    The Kansas mechanic's lien law is remedial, providing effective security to anyone
    furnishing labor, equipment, material, or supplies used or consumed for the improvement
    of real property under a contract with the owner. The theory behind granting a lien
    against the property is that the owner of property benefitting from the improvement
    should be charged with payment for the labor, equipment, material, or supplies used in
    the improvement.
    3.
    In actions on liens, the claim, not the statutory lien, is the fundamental interest to
    be considered. Without a claim, a mechanic's lien fails at the outset. Failure to employ a
    mechanic's lien, or failure to use one effectively by not following the statutory directions
    1
    for procedure and form, does not extinguish the claim. The lien is no more than a means
    available to try to collect on the claim.
    4.
    After a bond is filed, the focus is on the claim, not the statutory lien, and the only
    requirement to recover from the bond money is to prove the material or labor was
    supplied by the claimant and was used in the improvement of the real property that was
    the subject of the lien.
    5.
    The 2005 amendments to K.S.A. 60-1110, which added procedures for smaller,
    more narrowly-directed bonds to release liens, did not change the relationship between
    claims and liens, and a perfection defense continues to be relevant only against an
    asserted statutory lien.
    6.
    Payment of a claim against a bond depends not on satisfaction of the perfection
    requirements under the lien statute but on the ability to prove the elements of the
    underlying claim.
    Review of the judgment of the Court of Appeals in an unpublished opinion filed October 2, 2015.
    Appeal from Sedgwick District Court; MARK A. VINING, judge. Opinion filed February 24, 2017.
    Judgment of the Court of Appeals reversing the district court is affirmed. Judgment of the district court is
    reversed and remanded with directions.
    Vincent F. O'Flaherty, of Law Offices of Vincent F. O'Flaherty, Attorney, LLC, of Kansas City,
    Missouri, argued the cause and was on the briefs for appellant.
    2
    Ryan M. Peck, of Morris, Laing, Evans, Brock & Kennedy, Chartered, of Wichita, argued the
    cause, and Nanette Turner Kalcik and Richard A. Kear, of the same firm, were with him on the briefs for
    appellees.
    The opinion of the court was delivered by
    STUTZMAN, J.: Puetz Corporation (Puetz) was the general contractor to build a
    hotel in Wichita, Kansas. One of its subcontractors, Dynamic Drywall, Inc. (Dynamic),
    obtained materials for its part of the project from Wagner Interior Supply of Wichita, Inc.
    (Wagner), but failed to pay for them. Wagner filed a lien statement with the district court
    in Sedgwick County, claiming a lien against the hotel property. The owner of the hotel,
    Wichita Hospitality Group, LLC, was in the process of refinancing the project and
    Wagner's lien stood as a cloud on the title, so Puetz filed a bond with the district court to
    secure payment of Wagner's claim. With approval of the bond by the district court came
    the discharge of the lien under the terms of K.S.A. 60-1110.
    Puetz contends Wagner's lien was defective because it had not been properly
    perfected, so the lien could have been challenged and removed, preventing foreclosure,
    had there been time for litigation. Although it chose to file the bond rather than litigate
    the lien, Puetz claims the opportunity was not lost, as its argument about the defects in
    Wagner's lien filing survived the release of the lien and still can be asserted as a defense
    to Wagner's claim against the bond. Wagner takes the position that any defenses Puetz
    may have had against the lien filing have no relevance now, since the filing of the
    approved bond discharged the lien. The district court reviewed summary judgment
    motions from both Puetz and Wagner and granted judgment to Puetz. On Wagner's
    appeal, the Court of Appeals reversed the district court. We affirm that decision.
    3
    FACTS AND PROCEDURAL BACKGROUND
    In September 2012, Wichita Hospitality Group engaged Puetz to act as general
    contractor for the construction of a new Holiday Inn Express & Suites hotel in Wichita.
    Puetz subcontracted the drywall work on the project to Dynamic and paid Dynamic for its
    part of the work. Dynamic ordered materials for the project from Wagner, but it did not
    pay for those materials that Wagner provided and that were used in the construction.
    Dynamic later filed a petition for bankruptcy relief.
    Near the end of November 2013, Wagner, as an unpaid supplier, filed a lien
    statement with the clerk of the district court of Sedgwick County, claiming a lien against
    the hotel property in the amount of its unpaid claim, $108,162.97. At the time Wagner
    filed its lien statement, Wichita Hospitality Group was refinancing the hotel and
    Wagner's filing placed a cloud on the title, affecting the refinancing. To clear that
    problem, Puetz presented a bond to the district court pursuant to K.S.A. 60-1110, titled
    "Release of Lien Bond" with Puetz as principal and United Fire & Casualty Company
    (United) as surety, specifically securing the payment of Wagner's claim. Under the
    provisions of that statute, once the bond was approved by a judge of the district court and
    filed with the court clerk, Wagner's lien was discharged. The approved bond was filed on
    January 13, 2014.
    In February 2014, Wagner filed suit against Dynamic, Puetz, and United for
    payment for the materials it had supplied to Dynamic for the hotel. Wagner made a claim
    against the bond for the money it was owed and sought damages from Dynamic and
    Puetz for unjust enrichment. Both sides filed motions for summary judgment and, in
    November 2014, the district court entered an order granting summary judgment to Puetz
    and United. Wagner's claim against Dynamic was stayed because of Dynamic's
    bankruptcy.
    4
    On Wagner's timely appeal, the Court of Appeals reversed the order of the district
    court and directed that judgment be granted to Wagner. See Wagner Interior Supply of
    Wichita, Inc. v. Dynamic Drywall, Inc., No. 113,037, 
    2015 WL 5750465
     (Kan. App.
    2015) (unpublished opinion).
    ANALYSIS
    Standard of review
    The case is before us to review the district court's order for summary judgment
    that was reversed by the Court of Appeals. Our standard of review is de novo.
    "On appeal from summary judgment, an appellate court applies the same rules as
    the district court, and where the appellate court finds reasonable minds could differ as to
    the conclusions drawn from the evidence, summary judgment must be denied. Miller [v.
    Westport Ins. Corp.], 288 Kan. [27] at 32 [, 
    200 P.3d 419
     (2009)]. When material facts
    are uncontroverted, as they are in this case, an appellate court reviews summary judgment
    de novo. Troutman v. Curtis, 
    286 Kan. 452
    , Syl. ¶ 1, 
    185 P.3d 930
     (2008); Klein v.
    Oppenheimer & Co., 
    281 Kan. 330
    , Syl. ¶ 7, 
    130 P.3d 569
     (2006)." Adams v. Board of
    Sedgwick County Comm'rs, 
    289 Kan. 577
    , 584, 
    214 P.3d 1173
     (2009).
    We also are required to interpret and apply K.S.A. 60-1110 to undisputed facts.
    When engaging in statutory interpretation we exercise unlimited review. Redd v. Kansas
    Truck Center, 
    291 Kan. 176
    , 187, 
    239 P.3d 66
     (2010).
    5
    Discussion
    A mechanic's lien is purely a statutory creation and, to create an enforceable lien,
    the requirements of the statute must be followed strictly. Haz-Mat Response, Inc. v.
    Certified Waste Services Ltd., 
    259 Kan. 166
    , 170, 
    910 P.2d 839
     (1996). K.S.A. 60-
    1102(a) and 60-1103(a) prescribe the requirements for an unpaid supplier to perfect a lien
    against the real estate where the materials were used.
    The Kansas mechanic's lien law is remedial, providing effective security to anyone
    furnishing labor, equipment, material, or supplies used or consumed for the improvement
    of real property under a contract with the owner. The theory behind granting a lien
    against the property is that the property benefitting from the improvement should be
    charged with payment for the labor, equipment, material, or supplies used in the
    improvement. Haz-Mat Response, Inc., 
    259 Kan. at 170
    .
    Since the facts are undisputed, the arguments raised by Puetz and Wagner center
    on K.S.A. 60-1110, which provides:
    "The contractor or owner may execute a bond to the state of Kansas for the use of
    all persons in whose favor liens might accrue by virtue of this act, conditioned for the
    payment of all claims which might be the basis of liens in a sum not less than the contract
    price, or to any person claiming a lien which is disputed by the owner or contractor,
    conditioned for the payment of such claim in the amount thereof. Any such bond shall
    have good and sufficient sureties, be approved by a judge of the district court and filed
    with the clerk of the district court. When bond is approved and filed, no lien for the labor,
    equipment, material or supplies under contract, or claim described or referred to in the
    bond shall attach under this act, and if when such bond is filed liens have already been
    filed, such liens are discharged. Suit may be brought on such bond by any person
    interested but no such suit shall name as defendant any person who is neither a principal
    or surety on such bond, nor contractually liable for the payment of the claim."
    6
    Puetz maintains that when it filed the approved bond, its defense against the
    defectively filed lien merely migrated over to become a defense against the claim by
    Wagner against the bond. As Puetz sees it, any other interpretation would act to cure the
    errors Wagner made in filing its lien, and K.S.A. 60-1110 was not intended to improve
    the position of a party who had attempted, but failed, to file an effective lien. Wagner,
    however, contends the statute specifically discharged the lien when the approved bond
    was filed, and with the lien went any arguments about its validity. Both Puetz and
    Wagner insist the statute is absolutely clear in support of their opposite interpretations.
    We considered the requirements for claims against a statutory lien bond in
    Murphree v. Trinity Universal Ins. Co., 
    176 Kan. 290
    , 
    269 P.2d 1025
     (1954). The issue
    was whether claims could be made against the contractor's statutory bond for materials
    and labor that were not provided to the contractor or a subcontractor, but were directly
    requested by and furnished to the owner. We held those who carried out their transactions
    directly with the owner had no claim against the contractor's bond. 
    176 Kan. at 294
    . We
    also discussed the nature of the statutory bond and observed:
    "[W]hen the bond is filed a claimant is not required to file a lien statement in order to
    preserve his rights—he may then look to the bond for recovery—but other than this the
    bond effects no change in the rights and relations of the parties. A claimant can recover
    on the bond only if in its absence he could have perfected and enforced a lien." 
    176 Kan. at 294
    .
    We again took up a question on the right to claim against a statutory lien bond in
    Bob Eldridge Constr. Co., Inc. v. Pioneer Materials, Inc., 
    235 Kan. 599
    , 
    684 P.2d 355
    (1984). The facts in Eldridge bear many similarities to those in the present case and both
    parties have given it substantial attention.
    7
    The Bob Eldridge Construction case
    Bob Eldridge Construction Company, Inc. (Eldridge), was a general contractor
    building two apartment buildings for the elderly in Haysville and Wichita. Eldridge
    subcontracted its drywall work on the project to R & S Construction Company (R & S).
    Pioneer Materials, Inc. (Pioneer), supplied all drywall for the two buildings, under an
    arrangement by which Eldridge and R & S would call to place orders as they were
    needed. R & S left the projects with the work under its subcontract unfinished. After that,
    Pioneer supplied materials directly to Eldridge, and R & S later sought bankruptcy relief.
    Pioneer remained unpaid, in part because of a dispute over manufacturing defects
    in the drywall. Pioneer moved to protect its interest by filing lien statements against both
    apartment buildings for the amounts due on its unpaid invoices. Eldridge, as principal,
    and Fireman's Fund, as surety, filed bonds to discharge Pioneer's liens. Over a year later,
    Eldridge sued Pioneer and United States Gypsum Company for damages it claimed arose
    from the defective drywall used in the projects. In response, Pioneer asserted its claim
    against the bonds for the sum it was owed. At trial, Eldridge argued that Pioneer had
    failed to perfect its liens. The trial court found, however, that since the bond discharged
    the liens, Pioneer was not required to prove perfection, and it entered judgment in favor
    of Pioneer for recovery from the bonds for the amount it claimed. Eldridge and Fireman's
    Fund appealed.
    On appeal, Eldridge argued the trial court should not have relieved Pioneer of the
    obligation to show it had perfected its liens. Eldridge contended Pioneer had failed to
    comply with all the statutory lien requirements, including falling short on the obligations
    to provide a reasonably itemized statement, an authorized verification, and proof the
    materials were used in the projects. Overall, Eldridge claimed Pioneer's liens suffered
    from ten errors, which Pioneer claimed was irrelevant, since it had not acted to foreclose
    8
    its liens against the real estate, but had made a claim against the bonds. We framed the
    issue and our holding in this way:
    "[T]he appellee still has the burden to show it could have perfected its liens. The issue
    before the court is to what extent the appellee must show it could have perfected its liens.
    We hold the rule is as stated in Murphree that 'when the bond is filed a claimant is not
    required to file a lien statement in order to preserve his rights—he may then look to the
    bond for recovery . . . .' [Murphree,] 
    176 Kan. at 294
    . This means when the bond is filed
    the statutory requirements of the lien, such as the filing of a lien statement, need not be
    complied with and are waived. The only requirement to recover the bond money is to
    prove the material or labor was supplied by the claimant and was used in the
    improvement of the real property which was the subject of the lien. The case then shifts
    from a showing that each statutory lien element was fulfilled to a showing that the
    claimant has a right to the bond. See 57 C.J.S., Mechanics' Liens § 233, p. 806. The
    posting of a bond also eliminates the need for the strict construction rule we adhered to in
    mechanics' lien cases since the lien is thereby eliminated." 
    235 Kan. at 604
    .
    The 2005 Amendments to K.S.A. 60-1110
    At the core of the present case is the impact of the 2005 amendments to K.S.A. 60-
    1110. Puetz asserts the amendments dictate a different result than the one reached in
    Eldridge, pre-amendment, while Wagner argues there is nothing in the amendments that
    would cause Eldridge to be reconsidered. The 2005 amendments to K.S.A. 60-1110 are
    shown, in context, in italics:
    "The contractor or owner may execute a bond to the state of Kansas for the use of
    all persons in whose favor liens might accrue by virtue of this act, conditioned for the
    payment of all claims which might be the basis of liens in a sum not less than the contract
    price, or to any person claiming a lien which is disputed by the owner or contractor,
    conditioned for the payment of such claim in the amount thereof. Any such bond shall
    have good and sufficient sureties, be approved by a judge of the district court and filed
    9
    with the clerk of the district court. When bond is approved and filed, no lien for the labor,
    equipment, material or supplies under contract, or claim described or referred to in the
    bond shall attach under this act, and if when such bond is filed liens have already been
    filed, such liens are discharged. Suit may be brought on such bond by any person
    interested but no such suit shall name as defendant any person who is neither a principal
    or surety on such bond, nor contractually liable for the payment of the claim."
    Puetz' specific argument focuses on the phrase added to the first sentence—"a lien
    which is disputed by the owner or contractor"—which it sees as a new tool to remove the
    encumbrance of a disputed lien from the real estate while preserving any defenses to the
    lien that had been available to the owner or contractor. Puetz contends the entire lien
    dispute, with all claims and defenses, remains as it was, but the arguments are worked out
    with the bond, rather than the real estate, as security for the claim. Puetz forwards its
    interpretation as the only one that leaves the parties in the same relative posture as before
    the bond filing.
    Wagner contends the principal feature of the amendments was an additional option
    for owners and contractors. Instead of having to take the expensive step of posting a bond
    in the amount of the entire contract price just to remove the lien of a single contractor, the
    discharge of that disputed lien can be gained through a bond equal to that claim alone.
    Wagner argues there is significance in the fact that the amended statute prevents unfiled
    liens from attaching to the real estate and discharges any liens that already had been filed,
    but does so without any language limiting the discharge of liens only to those that had
    been statutorily perfected.
    Our procedure for interpreting statutes is familiar:
    "'"An appellate court must first attempt to ascertain legislative intent through the statutory
    language enacted, giving common words their ordinary meanings. When a statute is plain
    10
    and unambiguous, an appellate court does not speculate as to the legislative intent behind
    it and will not read into the statute something not readily found in it. Where there is no
    ambiguity, the court need not resort to statutory construction. Only if the statute's
    language or text is unclear or ambiguous does the court use canons of construction or
    legislative history or other background considerations to construe the legislature's intent.
    [Citations omitted.]"'" Ullery v. Othick, 
    304 Kan. 405
    , 409, 
    372 P.3d 1135
     (2016).
    There is no reason in this case to engage in statutory construction, since the
    language of K.S.A. 60-1110, as amended, created no confusion or ambiguity. As Wagner
    suggests, the 2005 amendment provided an alternative, less costly way for an owner to
    free the project property from a lien, whether to facilitate a sale or financial restructuring,
    or to allow some other action that would be hindered by the presence of a lien filed
    against the property. With the filing of an approved bond, the lien is discharged and the
    focus shifts from the satisfaction of each statutory element required for the lien, to the
    ability of the claimant to prove the basis for its claim against the bond.
    Puetz chooses to isolate the "lien which is disputed" phrase to construct its
    argument, declaring that "[w]hen this Court decided Eldridge, the legislature had not
    provided for the situation of a disputed lien." If that were true, K.S.A. 60-1110 would
    have been inapplicable to the facts presented in Eldridge, since the contractor actively
    disputed the liens that had been filed, claiming numerous statutory defects it argued
    would have prevented perfection. Puetz attributes the outcome in Eldridge to treatment of
    the bonds as if they were general obligation or performance bonds, which necessarily led
    to the finding that perfection was not required. That interpretation of Eldridge is
    unsupported.
    Before 2005, the structure of K.S.A. 60-1110 clearly contemplated disputed liens,
    and the extensive exercise in statutory construction offered up by Puetz is contrary to our
    established principle that we should not read into a statute something that is not readily
    11
    found in it. We next need to decide whether that affects our holding in Eldridge, given
    the facts before us.
    As a preliminary matter, we note that the claim, not the statutory lien, is the
    fundamental interest to be considered. The claim—someone provided labor, equipment,
    materials, or supplies pursuant to an agreement and the value was not paid—with the
    ability to prove those elements, is indispensable. Without a claim, a mechanic's lien fails
    at the outset. The mechanic's lien is a remedial device, existing only by virtue of statute,
    by which a contractor, subcontractor, or supplier can obtain some security to improve the
    chances its claim will be paid. See Haz-Mat Response, Inc., 
    259 Kan. at 170
    . Failure to
    use that device, or failure to use it effectively by not following the statute's directions for
    procedure and form, does not extinguish the claim. The lien is no more than a means
    available to try to collect on the claim.
    That basic relationship of the claim to the lien is at the heart of the question before
    us. When K.S.A. 60-1110 states "if when such bond is filed liens have already been filed,
    such liens are discharged," we must give those words their ordinary meanings, without
    reading new provisions into the statute. That standard precludes recasting the phrase to
    read "liens have already been filed and perfected." Also, as the Court of Appeals panel
    observed, the ordinary meaning attached to a lien being "discharged" is incompatible with
    the idea that the lien is at the same time preserved so it can be "transferred" to a bond
    along with any lien defenses.
    The structure of the statutory lien remedy is also inconsistent with Puetz' "preserve
    and transfer" theory. Failure of perfection because of technical errors, the defense that
    Puetz wants to preserve against Wagner's claim against the bond, is a concept associated
    with a mechanic's lien, not a claim against a bond. In a real estate foreclosure of a
    mechanic's lien, that lack of perfection may defeat the attempt to collect the unpaid claim
    12
    from the property. But when the statutory lien is discharged, fulfillment of the statutory
    requirements to perfect that lien loses relevance. As we recognized in Eldridge, there are
    no corresponding technical requirements to perfect a claim against the bond.
    There are, however, substantive requirements that must be met to show a creditor
    is entitled to recover from the bond. In Eldridge, we held that, even though the unpaid
    party was relieved of the statutory requirements with the filing of the bond, the claimant
    still bore the burden of showing "it could have perfected its liens." Eldridge, 
    235 Kan. at 604
    . That phrasing did not resurrect the ten errors in Pioneer's lien filings that Eldridge
    claimed were improperly disregarded by the trial court. Instead, we adopted the rule from
    Murphree to define the extent to which a claimant must prove a lien "could" have been
    perfected, and clarified that "the statutory requirements of the lien, such as the filing of a
    lien statement, need not be complied with and are waived." 
    235 Kan. at 604
    . After the
    bond is filed, the claim, not the statutory lien, is the focus and, we held "[t]he only
    requirement to recover the bond money is to prove the material or labor was supplied by
    the claimant and was used in the improvement of the real property which was the subject
    of the lien." 
    235 Kan. at 604
    .
    The 2005 amendments that added the procedure for smaller, more narrowly-
    directed bonds to release liens did nothing to change the relationship between claims and
    liens, and a perfection defense continues to be relevant only against an asserted statutory
    lien. And, contrary to Puetz' argument, the amendments do not require a departure from
    the reasoning or holdings in Eldridge.
    Terms of the bond
    Finally, we look to the terms of the bond itself, as the approved, statutorily-based
    commitment that Puetz and United filed, and against which Wagner now asserts its claim.
    13
    As permitted by the post-2005 version of K.S.A. 60-1110, the stated purpose of the bond
    was release of the single lien filed by Wagner, and the bond amount matched the total of
    Wagner's claim. The bond bound the parties to the following:
    "[T]he condition of this obligation is such that if the lien claimant shall be finally
    adjudged to be entitled to recover upon the claim upon which lien is based, the Principals
    or its Surety shall pay to such claimant the amount of the judgment." (Emphasis added.)
    Payment of Wagner's claim against the bond, by its own terms, depends not on
    satisfaction of the perfection requirements under the lien statute, but on the ability to
    prove the elements of the underlying interest—the claim.
    Conclusion
    The parties do not dispute the elements necessary to support Wagner's claim
    against the bond: materials were supplied to a subcontractor, Dynamic, pursuant to an
    agreement; the materials were used in the project; the materials were valued at
    $108,162.97; and Wagner was not paid for the materials.
    The decision of the Court of Appeals reversing the district court is affirmed, the
    order of the district court granting summary judgment to Puetz is reversed, and the case is
    remanded to the district court for entry of summary judgment in favor of Wagner.
    ROSEN, J., not participating.
    DAVID L. STUTZMAN, Senior Judge, assigned.¹
    _______________________
    ¹REPORTER'S NOTE: Senior Judge Stutzman was appointed to hear case No. 113,037
    vice Justice Rosen under the authority vested in the Supreme Court by K.S.A. 20-2616.
    14