Laha Holdings v. Professional Service Industries, Inc. ( 2024 )


Menu:
  •                           NOT DESIGNATED FOR PUBLICATION
    No. 125,934
    IN THE COURT OF APPEALS OF THE STATE OF KANSAS
    LAHA HOLDINGS,
    Appellee,
    v.
    PROFESSIONAL SERVICE INDUSTRIES, INC.,
    Appellant.
    MEMORANDUM OPINION
    Appeal from Johnson District Court; RHONDA K. MASON, judge. Oral argument held March 6,
    2024. Opinion filed April 12, 2024. Affirmed.
    Mark E. McFarland, of Hinkle Law Firm, LLC, of Lenexa, for appellant.
    Daniel R. Zmijewski, of DRZ Law, LLC, of Leawood, for appellee.
    Before WARNER, P.J., ATCHESON and BRUNS, JJ.
    PER CURIAM: Professional Service Industries, Inc. (PSI) appeals from a jury
    verdict rendered in favor of Laha Holdings, LLC for breach of contract. Although PSI
    admitted liability at trial, it disputed the amount of the damages caused by its breach.
    After a three-day jury trial, the jury awarded the full amount of damages claimed by Laha
    Holdings. Subsequently, PSI filed a motion for a new trial, which was denied by the
    district court.
    On appeal, PSI contends that the district court erred in denying its motion for new
    trial. It also contends that the jury's verdict was not supported by the evidence or the jury
    1
    instructions. Based on our review of the record, we conclude that the jury's verdict is
    supported by sufficient evidence and that the district court did not err in denying PSI's
    motion for new trial. Thus, we affirm.
    FACTS
    On June 27, 2005, Laha Holdings entered into a Design-Build Agreement with
    Turner Construction Company (Turner) for the construction of an office building in
    Overland Park. Upon completion of the building in 2007, Laha Holdings leased a portion
    of the property to its principal, Dr. David Laha, for his podiatry practice. The rest of the
    building remains unfinished. In 2007, Dr. Laha had plans to use the unfinished space as a
    surgery center.
    Unfortunately, the building has experienced significant water intrusion issues
    since the completion of construction. Although Turner attempted to correct these issues
    for several years, it was unable to resolve them to the satisfaction of Laha Holdings. As a
    result, Laha Holdings filed a lawsuit against Turner for alleged construction defects. The
    lawsuit was ultimately settled, and the parties agreed to jointly retain an engineering
    consultant to evaluate the office building. They further agreed that Turner would pay a
    contractor to perform the repairs to the building that the consultant found to be necessary
    to resolve the water intrusion problems.
    In a letter agreement dated May 15, 2015, PSI agreed to serve as an independent
    expert on behalf of Laha Holdings and Turner in connection with the office building. The
    engagement letter provided that PSI would "identify the causes of water intrusion
    occurring at the [building], identify any property damaged by water intrusion on the
    [building], and detail the repairs needed to: (1) eliminate the water intrusion occurring at
    the [building]; and (2) repair or replace any property damaged by water intrusion on the
    [building] . . . ." In addition, the engagement letter provided that upon receipt of the
    2
    specified repairs recommended by PSI, Laha Holdings and Turner would jointly select a
    qualified contractor to complete the repairs that PSI determined were needed to eliminate
    the water intrusion and to repair water-damaged property.
    Over the next several months, PSI visited the site and prepared a report setting out
    the repairs it deemed to be necessary to resolve the water intrusion issues and to repair
    the property. Laha Holdings and Turner then selected Haren and Laughlin Restoration
    Company, Inc. (HLR) to perform the repairs identified by PSI. It appears from the record
    that HLR began its work at the office building in mid to late 2016. On March 1, 2017,
    Laha Holdings received a punch list from PSI that listed tasks to be performed by HLR to
    complete the project. However, on May 1, 2017, Laha Holdings advised PSI that water
    intrusion was still occurring at the office building. It appears that PSI never returned to
    the building after that date.
    On November 14, 2017, HLR contacted Carl Martin, a professional engineer, to
    inspect the office building for water intrusion and to prepare a remediation report. The
    following month, Martin delivered a report to HLR listing his recommendations. Based
    on these recommendations, HLR then provided a proposal to Laha Holdings. However,
    the proposal from HLR was not accepted by Laha Holdings at that time. Instead, Laha
    Holdings continued to seek assistance from PSI based on its guarantee in the letter
    agreement to detail the repairs needed to eliminate the water intrusion.
    Because the water intrusion had not been resolved, Laha Holdings filed a lawsuit
    against PSI and HLR on February 13, 2019. In its petition, Laha Holdings asserted a
    breach of contract claim and a negligence claim against PSI. Additionally, it asserted a
    breach of contract claim and negligence claim against HLR. During the course of the
    litigation, Laha Holdings resolved its claims against HLR and HLR was voluntarily
    dismissed as a defendant. HLR then returned to perform repairs on the office building
    that were previously recommended by Martin.
    3
    Likewise, Martin returned to the office building in October 2020 to perform
    additional evaluations in an attempt to determine the various sources of the water
    intrusion. No additional repairs were recommended at that time because Martin advised
    that more testing was needed. Nevertheless, on March 16, 2021, Martin again returned to
    the building after HLR discovered moisture coming through the exterior façade of the
    building. HLR explained that in addition to the leakage at the base of the building, there
    was also evidence of water intrusion from above.
    Martin advised HLR to suspend the repair work it was performing so that he could
    evaluate the entire building. Based on his additional evaluation, Martin determined that
    there was also water coming through the roof and that moisture was collecting inside the
    building's siding. On October 29, 2021, Martin produced a report that summarized his
    evaluations and recommended additional repairs required to make the office building
    waterproof. The report also suggested that some of the repairs to the foundation of the
    building that had previously been recommended were not necessary.
    In the agreed pretrial order entered by the district court prior to trial, Laha
    Holdings alleged that it suffered damages in the amount of $277,500 to repair the office
    building. In addition, Laha Holdings alleged $9,817.50 in lost income per month because
    of its inability to rent the building. Furthermore, Laha Holdings alleged that it suffered
    these losses for 57 months, resulting in a loss of rental income of $559,597.50.
    Consequently, Laha Holdings claimed that it sustained a total amount of $837,097.50 in
    damages.
    On March 28, 2022, the district court commenced a three-day jury trial. At trial,
    Laha Holdings presented the testimony of five witnesses. In addition, Laha Holdings
    offered 25 exhibits that were admitted into evidence. Although its counsel cross-
    examined the witnesses called by Laha Holdings and presented closing arguments to the
    4
    jury, PSI did not call any witnesses to testify or offer any exhibits for admission into
    evidence.
    At trial, Laha Holdings called Lennox Cary, a project manager for HLR, who
    testified regarding the work performed on the office building by his company in an
    attempt to resolve the water intrusion based on the repairs identified by PSI. According to
    Cary, the conditions at the building did not match the details reported by PSI and, as a
    result, HLR came up with an alternative remediation plan. He explained that after PSI
    approved the alternative plan, HLR went forward with the repairs and had completed
    most of the work by March 2017.
    Cary testified that because there was still water intrusion at the office building,
    HLR did another walk through of the building with PSI on March 29, 2017. He added
    that HLR continued to document water leaks in the building until May 1, 2017. On that
    date, Cary sent an email to PSI informing them of the documented water intrusions. He
    testified that he received no response from PSI until August 2017, when he was asked to
    provide an estimate for a "not for construction detail." Cary explained that HLR could not
    use this detail to fix the water intrusion because it was the same detail from PSI's original
    plans that HLR deemed unworkable based on the conditions it encountered at the office
    building.
    Rather, Cary testified that HLR contacted Martin in November 2017, in an attempt
    to solve the continued water intrusion problems. In turn, Martin provided a report to
    HLR, which was used to create a proposal for Laha Holdings to consider. According to
    Cary, the new proposal was provided to Laha Holdings in January 2018. However, Laha
    Holdings did not authorize additional work to be performed by HLR at that time.
    Laha Holdings' attorney, Christopher John Mohart, testified about his numerous
    attempts to get PSI to fix the water intrusion problems at the office building. Mohart
    5
    testified that he sent several emails to PSI in April and May 2017. In the emails, he
    reminded PSI of its responsibility under the agreement with Laha Holdings to eliminate
    the water intrusion and asking that they fulfill this obligation. Mohart testified that he met
    with HLR at the office building in May 2017 to discuss potential fixes. Mohart also
    testified that PSI failed to provide any information on how it would remedy the water
    intrusion after that time. Mohart explained that he continued to attempt to get PSI to
    repair the water intrusion problems up until the time he left private practice in early 2019.
    Dr. David Laha testified that he authorized the filing of this lawsuit against PSI on
    behalf of Laha Holdings in February 2019, because "PSI wasn't doing anything to try to
    help out anymore. They weren't trying to design a fix and I think they were trying to lay
    blame elsewhere." Dr. Laha testified that he did not recall anyone from PSI ever
    returning to the office building after May 1, 2017. He explained that the January 2018
    proposal from HLR based on Martin's updated report did not provide a guarantee that all
    the problems would be fixed.
    According to Dr. Laha, he did not move forward with the new proposal because
    PSI had guaranteed that the water intrusion would be eliminated. He also testified that
    after he filed this lawsuit, he retained Martin to analyze the problems at the office
    building and to advise regarding the repairs that would be necessary. Dr. Laha explained
    that Martin had provided another report in October 2021, which included a new plan to
    remedy the water intrusion. Dr. Laha further testified that this work had not yet begun
    prior to trial because it could not be completed during the winter.
    Regarding Laha Holdings' claim for lost rental income, Dr. Laha testified that the
    expenses for the office building were covered by the rent received from his podiatry
    practice. Consequently, he testified that the potential rental income from the unfinished
    side of the building would all be profit to Laha Holdings. Dr. Laha explained that
    although he originally planned for the unfinished side of the building to be used as a
    6
    surgical center, he now planned to rent it out to another doctor or entity for use as a
    medical office.
    Martin testified that he prepared three reports regarding the repairs for the office
    building: (1) a report to HLR dated December 13, 2017; (2) a report to HLR dated
    January 30, 2020; and (3) a report to Laha Holdings dated October 29, 2021.
    Additionally, Martin testified that he visited the building in November 2017, in October
    2020, in March 2021, and in October 2021. Martin explained that Laha Holdings
    requested that he inspect the building again in March 2021 because HLR had begun the
    new repair work. According to Martin, this repair work had to stop because HLR
    encountered additional water intrusion issues.
    Martin testified that his third report not only included the recommendations made
    in his previous reports but also addressed the newly discovered issues relating to water
    intrusion in the roof that seeped into the building's siding. He also testified that in his
    opinion all the water intrusion problems he found existed when PSI initially inspected the
    office building and that it could have found the same problems. Martin further opined
    that if PSI had done an appropriate job, then the work needed to complete all the repairs
    to remedy the water intrusion could have been completed by HLR in six months.
    Brandon LaSala, a mortgage real estate broker who specializes in negotiating
    leases and sale transactions for medical office buildings, provided an expert opinion
    about the loss of rental income from the unfinished side of the office building. He based
    his estimates on this space being leased for use as a medical office. According to LaSala,
    Laha Holdings was losing rental income in the amount of $9,817.50 per month.
    After Laha Holdings rested its case, PSI chose to rest its case without presenting
    any additional evidence. Likewise, PSI did not move for a judgment as a matter of law.
    Ultimately, the case was submitted to the jury under a breach of contract theory.
    7
    Although PSI admitted that it had indeed breached its obligations under the contract, it
    denied the amount of damages claimed by Laha Holdings.
    The district court instructed the jury regarding the amount of damages it could
    award to Laha Holdings as a result of PSI's breach of contract:
    "If you find that the plaintiff is entitled to recover damages for breach of contract, in
    determining the amount of damages, the measure of damages is the reasonable cost to
    repair the property, not to exceed the sum of $277,500.00, the amount of Laha Holdings,
    LLC's claim for repairs, plus a reasonable amount to compensate for the loss of rental
    value of the property while the repairs are being made with reasonable diligence, but not
    to exceed the sum of $559,597.50, the amount of Laha Holding, LLC's claim for loss
    rental value.
    "The total amount of your verdict may not exceed the sum of $837,097.50, the total
    amount of Laha Holding, LLC's claim for breach of contract." (Jury Instruction No. 13.)
    The district court also instructed the jury on PSI's defense that Laha Holdings had
    failed to mitigate its damages:
    "The defendant claims that plaintiff has failed to mitigate its damages. If you find that the
    plaintiff is entitled to recover damages for breach of contract, then in determining the
    amount of damages sustained by plaintiff, you should not include any loss which plaintiff
    could have prevented by reasonable care and diligence after the loss occurred. The
    defendant has the burden to prove that its claim is more probably true than not true."
    (Jury Instruction No. 14.)
    After deliberation, the jury returned a verdict in favor of Laha Holdings in the
    amount of $837,097.50. Subsequently, PSI filed a motion for new trial in which it argued
    that the jury's verdict was contrary to the jury instructions and not supported by the
    evidence. This motion was denied by the district court in a memorandum decision entered
    on December 12, 2022.
    8
    In denying the motion, the district court noted that PSI did not challenge the
    $277,500 in damages awarded to Laha Holdings for repairs to remedy the water
    intrusion. Furthermore, the district court found that PSI did not object to the damages
    instruction and by implication recognized that there was evidence presented by Laha
    Holdings—if accepted by the jury—that could support a verdict for lost rental income up
    to $559,597.50. Finally, the district court found that PSI failed to carry its burden of
    proof on the affirmative defense of failure to mitigate damages and that there was
    evidence in the record that Laha Holdings "attempted to mitigate its damages, most
    notably that it was relying on [PSI] to identify [the] problems and the parties were
    negotiating to fix the same."
    ANALYSIS
    Issues Presented
    On appeal, PSI does not deny that it breached its contract with Laha Holdings, nor
    does it challenge the amount of damages awarded to Laha Holdings by the jury for the
    cost of repairs. Rather, PSI challenges the amount of damages awarded by the jury to
    Laha Holdings for loss of rental income. Specifically, PSI argues that the award for loss
    of rental income is not supported by the evidence presented at trial or by the jury
    instructions. PSI also argues that the jury's verdict for loss of rental income is excessive
    because Laha Holdings failed to mitigate its damages.
    In response, Laha Holdings contends that the damages awarded by the jury are
    supported by the evidence. It argues that the evidence presented at trial was sufficient to
    support a verdict not only for the cost of repairs but also the loss of rental income that
    resulted from PSI's breach of contract. In addition, Laha Holdings argues that PSI failed
    to meet its burden of proof on the affirmative defense of failure to mitigate damages.
    9
    Loss of Rental Income
    When a jury's verdict is challenged for insufficiency of evidence or as being
    contrary to the evidence, we examine the record on appeal in the light most favorable to
    the prevailing party. In doing so, it is not our role to reweigh the evidence or pass on the
    credibility of the witnesses. If the evidence presented at trial supports the verdict, it
    should not be disturbed on appeal. See Wolfe Electric, Inc. v. Duckworth, 
    293 Kan. 375
    ,
    407, 
    266 P.3d 516
     (2011) (sufficiency of evidence); see also Unruh v. Purina Mills, 
    289 Kan. 1185
    , 1195, 
    221 P.3d 1130
     (2009) (contrary to evidence). Likewise, we review the
    district court's decision to deny a motion for new trial for an abuse of discretion. See City
    of Mission Hills v. Sexton, 
    284 Kan. 414
    , 421, 
    160 P.3d 812
     (2007) (denial of a motion
    for new trial "will not be disturbed on appeal unless there is a showing of an abuse of that
    discretion").
    The Kansas Supreme Court has held that a reviewing court must accept as true the
    evidence and all the inferences to be drawn from it which support or tend to support the
    jury's verdict, while disregarding any conflicting evidence or other inferences that could
    be drawn from the evidence. Unruh, 289 Kan. at 1196. The Unruh court stated,
    "When a jury's findings are attacked as being based on insufficient evidence or being
    contrary to the evidence, this court's power begins and ends with a determination of
    whether there is evidence to support those findings. If the evidence supports the jury's
    findings, this court will not disturb them on appeal. It is of no consequence that contrary
    evidence might have supported different findings if believed by the jury." 289 Kan. at
    1196.
    Here, the district court instructed the jury that it could award "a reasonable amount
    to compensate for the loss of rental value of the property while the repairs are being made
    with reasonable diligence, but not to exceed the sum of $559,597.50, the amount of Laha
    Holdings, LLC's claim for loss rental value." (Jury Instruction No. 13.) Moreover, PSI
    10
    did not object to this instruction, nor does it challenge its validity on appeal. Instead, it
    argues that there is no evidence in the record to support the jury's award of the full
    amount of $559,597.50 for Laha Holdings' loss of rental value.
    As the Kansas Supreme Court has held, a district court must "give an instruction
    supporting a party's theory if the instruction is requested and there is evidence supporting
    the theory which, if accepted as true and viewed in the light most favorable to the
    requesting party, is sufficient for reasonable minds to reach different conclusions based
    on the evidence." Puckett v. Mt. Carmel Regional Med. Center, 
    290 Kan. 406
    , 419, 
    228 P.3d 1048
     (2010). As a result, the giving of jury instruction No. 13 by the district court—
    without an objection from PSI—suggests that there was evidence presented at trial upon
    which a reasonable juror could conclude that $559,597.50 was a reasonable amount to
    compensate Laha Holdings for the loss of rental income resulting from PSI's breach of
    contract.
    Although damages need not be proven with absolute certainty, there must be at
    least a reasonable basis to enable a jury to arrive at an approximate sum of damages.
    Wolfe Electric, Inc., 
    293 Kan. at 395
     (quoting Puckett, 
    290 Kan. 406
    , Syl. ¶ 3). In the
    present case, there was evidence presented that Laha Holdings had lost rental income for
    up to 57 months—beginning in June 2017 and running until the trial began in March
    2022—based on testimony of Dr. Laha and Mohart that PSI failed to take steps to
    remediate the water intrusion after May 2017. Likewise, there was evidence presented
    through the testimony of LaSala that Laha Holdings was losing rental income in the
    amount of $9,817.50 per month over this period.
    Also, Martin, Dr. Laha, Mohart, and Cary each testified about the nature and
    extent of the water intrusion problems encountered at the office building and the
    difficulties in getting PSI to fulfill its contractual obligation to remediate the water
    intrusion. These witnesses informed the jury that between May 2017 and February 2019,
    11
    Laha Holdings was communicating with and requesting PSI provide the repairs necessary
    to eliminate the water intrusion issues at the office building. Dr. Laha testified that his
    attorney, Mohart, went back and forth with PSI "for a couple of years about . . . what the
    fix was going to be and who would cover the fix or pay for the fix." Mohart confirmed
    that he attempted to get PSI to fix the water intrusion problem from April 2017 until he
    left private practice in early 2019. Dr. Laha also testified that these failed attempts to
    resolve the dispute led Laha Holdings to file this lawsuit in February 2019.
    Dr. Laha also testified that after the lawsuit was filed, he continued to take steps to
    repair the water intrusion into the office building. He explained that he retained Martin to
    analyze the building and advise what kind of repairs should be performed at that point. In
    turn, Martin testified that he visited the building multiple times from 2017 through 2021.
    Although HLR began to make additional repairs in March 2021, the work had to stop
    because they encountered more water intrusion issues.
    Martin further testified that he prepared his final report in October 2021 to address
    these new issues. However, as Dr. Laha explained, the work to implement the repairs
    identified in Martin's final report had not yet begun as of the trial date because the work
    could not be completed during winter. Accordingly, we find that the testimony presented
    at trial was sufficient—when viewed in the light most favorable to Laha Holdings as the
    prevailing party—to support a finding by the jury that reasonable diligence was exercised
    to repair the office building from June 2017 until the trial began in March 2022.
    Accordingly, we conclude that there was sufficient evidence presented at trial to support
    the jury's verdict of $559,597.50 in loss of rental income caused by PSI's breach of
    contract and that the verdict was consistent with jury instruction No. 13.
    12
    Mitigation of Damages
    PSI also argues that the jury's verdict should be set aside because Laha Holdings
    failed to mitigate its damages. Mitigation of damages is an affirmative defense, and the
    burden of proof is on the party—in this case PSI—who asserts a failure to mitigate. See
    Leavenworth Plaza Assocs., L.P. v. L.A.G. Enterprises, 
    28 Kan. App. 2d 269
    , 272, 
    16 P.3d 314
     (2000). Likewise, "[t]he duty to mitigate damages is not an unlimited one and
    an injured party is required only to exert reasonable efforts to prevent or minimize his
    damages within the bounds of common sense." Steele v. J. I. Case Co., 
    197 Kan. 554
    ,
    Syl. ¶ 5, 
    419 P.2d 902
     (1966). Hence, PSI had the burden to prove this affirmative
    defense at trial.
    At trial, the district court appropriately instructed the jury in instruction No. 14
    regarding PSI's affirmative defense that Laha Holdings had failed to mitigate its damages.
    Again, PSI did not object to the instruction, nor does it challenge the instruction on
    appeal. As indicated above, this instruction advised the jury that "in determining the
    amount of damages sustained by [Laha Holdings], you should not include any loss which
    [it] could have prevented by reasonable care and diligence after the loss occurred." The
    instruction also advised the jury that PSI had "the burden to prove that its claim is more
    probably true than not true."
    Nevertheless, the jury awarded Laha Holdings the entire amount of the damages
    which it claimed. On appeal, PSI suggests that "[s]uch an award without deduction would
    indicate that [Laha Holdings] mitigated its damages, and acted with reasonable care and
    diligence after the loss occurred, which is contrary to the evidence and the law." Of
    course, it is just as likely that the jury found that PSI failed to meet its burden to prove a
    failure to mitigate.
    13
    As discussed above, PSI did not present the testimony of any witnesses or offer
    any exhibits into evidence at trial. Instead, it simply attempted to rely on cross-
    examination of the witnesses called by Laha Holdings. In addition, PSI presented the
    arguments of counsel but "closing arguments are not evidence." Marcus v. Swanson, 
    317 Kan. 752
    , 763, 
    539 P.3d 605
     (2023). Although it is theoretically possible to do so, it is
    much more difficult for a party to meet its burden of proof under these circumstances.
    In its memorandum decision denying PSI's motion for new trial, the district court
    determined that PSI had failed to carry its burden to prove that Laha Holdings failed to
    mitigate damages. The district court explained:
    "[The] jury found that [PSI]'s affirmative defense of failure to mitigate did not bar [Laha
    Holdings'] damages. This burden was [PSI]'s to carry. And mitigation is analyzed using a
    reasonability standard, which is an inherent question of fact. A damaged party is only
    required to exert reasonable efforts to prevent or minimize [its] damages within the
    bounds of common sense. [Laha Holdings] provided evidence that it attempted to
    mitigate its damages, most notably that it was relying on [PSI] to identify problems and
    the parties were negotiating to fix the same. [Laha Holdings] also submitted testimony
    that it attempted to begin repairs, but that the cost exceeded estimates. These are pieces of
    evidence [the] jury could have relied on in reaching its verdict and not giving credence to
    [PSI]'s mitigation affirmative defense."
    We agree with the district court's analysis of this issue.
    As addressed in the previous section of our opinion, Laha Holdings presented
    sufficient evidence—when viewed in a light most favorable to it as the prevailing party—
    to establish its claim for damages. Even though PSI had the burden to prove that Laha
    Holdings failed to use reasonable efforts to mitigate damages, it was unable to convince
    the jury, and—as discussed above—it is not our role to reweigh the evidence or to
    determine the credibility of witnesses. See Leavenworth Plaza Associates, L.P., 
    28 Kan. App. 2d at 274
    . Consequently, we find no reason to disturb the jury's verdict on appeal.
    14
    CONCLUSION
    In conclusion, after examining the record on appeal in the light most favorable to
    Laha Holdings as the prevailing party, we find that there is sufficient evidence to support
    the jury's award of damages in this case. Likewise, we do not find the jury's verdict to be
    contrary to the evidence or to the jury instructions. Accordingly, we do not find that the
    district court abused its discretion in denying PSI's motion for new trial and we affirm the
    jury's verdict.
    Affirmed.
    15
    

Document Info

Docket Number: 125934

Filed Date: 4/12/2024

Precedential Status: Non-Precedential

Modified Date: 4/12/2024