Kim Garrigus v. Chad Burnett D/B/A Heartland Garage, Inc. ( 2021 )


Menu:
  •                     RENDERED: JUNE 18, 2021; 10:00 A.M.
    NOT TO BE PUBLISHED
    Commonwealth of Kentucky
    Court of Appeals
    NO. 2020-CA-0702-MR
    KIM GARRIGUS                                                         APPELLANT
    APPEAL FROM GRAVES CIRCUIT COURT
    v.                HONORABLE TIMOTHY C. STARK, JUDGE
    ACTION NO. 19-CI-00101
    CHAD BURNETT D/B/A HEARTLAND GARAGE, INC.                              APPELLEE
    OPINION
    AFFIRMING
    ** ** ** ** **
    BEFORE: CALDWELL, DIXON, AND L. THOMPSON, JUDGES.
    THOMPSON, L., JUDGE: Kim Garrigus (“Appellant”) appeals from the findings
    of fact, conclusions of law, and trial order of the Graves Circuit Court awarding
    her $5,250.20 for an unused portion of a construction retainer. Appellant argues
    that the circuit court erred in ruling that Chad Burnett d/b/a Heartland Garage, Inc.
    (“Appellee”) did not breach a construction contract and that Appellant took no
    steps to mitigate the damages. For the reasons addressed below, we find no error
    and affirm the order on appeal.
    FACTS AND PROCEDURAL HISTORY
    On December 31, 2018, the parties executed a contract providing that
    Appellee would construct a residential, detached garage on Appellant’s parcel for
    the sum of $15,912.00. Pursuant to the contract, Appellant paid Appellee
    $10,912.00 as a retainer for the project. On January 24, 2019, Appellee installed
    forms and footers for the foundation of the garage. According to the record, the
    forms and footers were in place for 19 days.
    On February 13, 2019, Appellee began pouring the concrete
    foundation. While the foundation was being poured, Appellant told Appellee that
    the foundation was being installed in the wrong location. Appellee told Appellant
    that it was impossible to stop pouring the concrete in the midst of the job.
    Appellant also claimed that the garage was one foot short of the contracted
    dimensions. After the foundation was poured, no further work was completed on
    the project.
    The following month, Appellant filed the instant action in Graves
    Circuit Court alleging that Appellee breached the contract by pouring the
    foundation in the wrong location and to the wrong dimensions. The matter
    proceeded to a bench trial, whereupon the Graves Circuit Court determined that
    -2-
    Appellant failed to demonstrate that Appellee breached the contract. The court
    further determined that Appellant made no effort to mitigate the alleged damages.1
    The court accepted Appellee’s testimony that it expended $5,661.80 to install the
    forms and the footers and to pour the foundation. It then deducted that sum from
    the $10,912.00 retainer paid by Appellant, resulting in damages payable to
    Appellant in the amount of $5,250.20. This appeal followed.
    ARGUMENT AND ANALYSIS
    Appellant argues that the trial court erred by finding that Appellant
    had not demonstrated that Appellee breached the contract and that Appellant made
    no effort to mitigate damages. Citing Kentucky Shakespeare Festival, Inc. v.
    Dunaway, 
    490 S.W.3d 691
     (Ky. 2016), Appellant contends that in the absence of
    ambiguity, a written instrument will be enforced according to its terms. As applied
    herein, Appellant argues that she provided the trial court with the contract, as well
    as pictures showing where the garage was incorrectly placed. She argues that
    common sense shows that the garage was placed in the wrong area. According to
    Appellant, the garage did not match the diagram in the contract, it did not line up
    with Appellant’s driveway, and it was placed over utility lines. Further, Appellant
    1
    Though not expressly stated in the order on appeal, it appears from the record that the trial
    court believed that Appellant had ample opportunity to request a change in the placement of the
    garage during the approximately 19 days that the forms and footers were present in her yard.
    -3-
    maintains that the size of the foundation was smaller than the 30’ x 24’ design
    specified in the diagram on the contract.
    Directing our attention to Barnett v. Mercy Health Partners-Lourdes,
    Inc., 
    233 S.W.3d 723
    , 726 (Ky. App. 2007), Appellant argues that she proved a
    breach of the contract by demonstrating 1) the existence of a contract; 2) breach of
    that contract; and 3) damages flowing from the breach. She notes that the parties
    have stipulated as to the existence of a contract and maintains that the evidence she
    presented proves a breach thereof. Appellant argues that she has suffered a
    pecuniary loss by virtue of the breach, including loss of performance under the
    contract, as well as the cost of removing the foundation and hiring another
    company to build the garage. She seeks an opinion and order reversing the order
    on appeal.
    We review a trial court’s factual findings for clear error and will not
    set them aside if they are supported by substantial evidence. Kentucky Rules of
    Civil Procedure (“CR”) 52.01; Owens-Corning Fiberglas Corp. v. Golightly, 
    976 S.W.2d 409
    , 414 (Ky. 1998). Substantial evidence means evidence of substance
    and relevant consequence having the fitness to induce “conviction in the minds of
    reasonable men.” Kentucky State Racing Comm’n v. Fuller, 
    481 S.W.2d 298
    , 308
    (Ky. 1972) (citation omitted). Questions of law are subject to de novo review.
    -4-
    Cantrell Supply, Inc. v. Liberty Mut. Ins. Co., 
    94 S.W.3d 381
    , 385 (Ky. App.
    2002).
    The first question for our consideration is whether the trial court’s
    findings of fact were supported by substantial evidence. We must answer this
    question in the affirmative. The evidence presented to the trial court consisted
    primarily of the parties’ testimony and the contract. Appellant maintained that the
    garage was not properly situated in conformity with the contract, whereas Appellee
    stated that it was correctly placed. The contract contains a simple, hand-drawn
    representation of a garage, and shows exterior dimensions of 30’ x 24’. Neither
    the contract language nor the drawing, however, gives any clue as to where the
    garage was to be located. While Appellant provided the trial court with pictures
    showing where she wanted the garage placed, these pictures are not part of the
    contract.
    The trial court made the following findings: that there was a contract
    in the amount of $15,912.00; that Appellant paid a retainer of $10,912.00; that the
    forms and footers were in place for 19 days; that while the foundation was being
    poured, Appellant claimed it was in the wrong place; and that Appellee’s cost in
    the project up to that point was $5,661.80. Each of these findings is supported by
    substantial evidence contained in the record.
    -5-
    The question of law presented to the trial court was whether Appellee
    breached the contract by pouring the foundation in the wrong place and to the
    wrong dimensions. The trial court determined that Appellant failed to demonstrate
    that Appellee breached the contract. It also found that Appellant made no effort to
    mitigate her alleged damages. Reviewing this question of law de novo, Cantrell
    Supply, Inc., 
    supra,
     we find no basis for concluding that Appellee breached the
    contract. The contract is silent as to the garage’s placement, and Appellant has
    offered nothing other than her own testimony to support her claim that the
    foundation was not poured to the proper dimensions. Due regard must be given to
    the opportunity of the trial judge to consider the weight and credibility of the
    witnesses. Lawson v. Loid, 
    896 S.W.2d 1
    , 3 (Ky. 1995) (citing CR 52.01). As a
    breach is an essential element of a claim of breach of contract, Barnett, 
    supra,
     and
    having found no breach, we cannot conclude that the Graves Circuit Court erred in
    finding no breach of contract.
    As to the issue of mitigation of damages, while it is true that a party
    claiming damages for breach of contract must use reasonable efforts to mitigate his
    damages, “[t]he party committing the breach bears the burden of proving that the
    plaintiff failed to mitigate his damages.” Jones v. Marquis Terminal, Inc., 
    454 S.W.3d 849
    , 852 (Ky. App. 2014). Since Appellant has not demonstrated that
    Appellee breached the contract, the issue of mitigation of damages is moot.
    -6-
    CONCLUSION
    The findings of the Graves Circuit Court are supported by substantial
    evidence, and our review leads us to conclude that circuit court properly found no
    breach of contract. For these reasons, we affirm the findings of fact, conclusions
    of law, and trial order of the Graves Circuit Court.
    ALL CONCUR.
    BRIEF FOR APPELLANT:                       BRIEF FOR APPELLEE:
    Heather L. Jones                           Andrew D. Leonard
    Paducah, Kentucky                          Mayfield, Kentucky
    -7-