Tsi Construction, Inc. v. Louisville and Jefferson County Metropolitan Sewer District ( 2020 )


Menu:
  •                  RENDERED: NOVEMBER 6, 2020; 10:00 A.M.
    NOT TO BE PUBLISHED
    Commonwealth of Kentucky
    Court of Appeals
    NO. 2019-CA-1635-MR
    TSI CONSTRUCTION, INC.                                             APPELLANT
    APPEAL FROM JEFFERSON CIRCUIT COURT
    v.                HONORABLE AUDRA J. ECKERLE, JUDGE
    ACTION NO. 19-CI-004341
    LOUISVILLE AND JEFFERSON
    COUNTY METROPOLITAN SEWER
    DISTRICT                                                             APPELLEE
    OPINION
    AFFIRMING
    ** ** ** ** **
    BEFORE: CLAYTON, CHIEF JUDGE; DIXON AND JONES, JUDGES.
    DIXON, JUDGE: TSI Construction, Inc. (“TSI”) appeals from the order
    dismissing its claims against Louisville and Jefferson County Metropolitan Sewer
    District (“MSD”) entered October 1, 2019, by the Jefferson Circuit Court. After
    careful review of the briefs, record, and the law, we affirm.
    FACTS AND PROCEDURAL BACKGROUND
    On January 27, 2016, TSI, a contractor, and MSD executed a contract
    for the construction of a project identified as the Camp Taylor Sanitary Sewer
    Replacement 1A (“the Project”). The work performed under this contract required
    the excavation and removal of a large amount of rock. Article 2(B) of the contract,
    concerning the representations of the contractor, provides:
    The CONTRACTOR has visited and become familiar
    with the Project site and the local conditions under which
    the Project is to be constructed and operated, and the
    CONTRACTOR has performed such tests, if any, as are
    necessary to determine the conditions under which the
    Work will be performed[.]
    (ROA1 73.) Regarding the time for contractor’s performance, Article 6(A) states
    (in part):
    The CONTRACTOR shall commence the performance
    of this Contract on February 8, 2016 and shall diligently
    continue its performance to and until final completion of
    the Project. The CONTRACTOR shall accomplish
    Substantial Completion of the Project on or before June
    10, 2017.
    (ROA 76) (emphasis in original).
    The contract provided that certain information and materials would be
    supplied to TSI by MSD. The relevant portion of Article 8(A) states:
    MSD shall furnish to the CONTRACTOR, prior to the
    execution of this Contract, any and all written and
    1
    Record on Appeal.
    -2-
    tangible material knowingly in its possession concerning
    conditions below ground at the site of the Project. Such
    written and tangible material is furnished to the
    CONTRACTOR only in order to make complete
    disclosure of such material as being in possession of
    MSD and for no other purpose. By furnishing such
    material, MSD does not represent, warrant, or guarantee
    its accuracy either in whole or in part, implicitly or
    explicitly, or at all, and shall have no liability therefor.
    (ROA 80.) Prior to the execution of this contract, MSD hired Stantec Consulting
    Services, Inc. (“Stantec”) to perform a geotechnical investigation to identify
    potential construction problems. On January 8, 2013, Stantec issued a report
    concerning the area of the Project. This report was identified as a bid document,
    but MSD failed to provide a copy to TSI. Notably, the report “did not warn of any
    unusual conditions that could cause problems with construction in the underlying
    bedrock.” (ROA 3.)
    The contract also specifically addressed the procedures for claims by
    the contractor and alternative dispute resolution in Article 13. The pertinent
    portions of Article 13 provide:
    The procedures set forth in this Article are designed to
    resolve contractual disputes prior to resorting to litigation
    as per KRS[2] 371.405. In the event that a court of law
    finds any provision void and unenforceable, the
    remaining provisions shall remain in force and in full
    effect. Claims by the CONTRACTOR against MSD are
    subject to the following terms and conditions:
    2
    Kentucky Revised Statutes.
    -3-
    (A) ARTICLE 13 COMPLIANCE: In the event
    the CONTRACTOR seeks to make a claim for an
    increase in the Contract Price, as a condition
    precedent to any liability of MSD therefore, the
    CONTRACTOR shall strictly comply with the
    requirements of this Article 13 and such claim
    shall be made by the CONTRACTOR before
    proceeding to execute any additional or changed
    Work. Failure of the condition precedent to occur
    shall constitute waiver by the CONTRACTOR of
    any claim for additional compensation;
    (B) NOTICE REQUIREMENT: All
    CONTRACTOR claims, disputes and other
    matters in question against MSD arising out of or
    related to the Contract or the breach thereof,
    specifically including without limitation claims in
    respect to changes in the Contract Price or
    Contract Time, shall be initiated by a written
    notice of claim submitted to MSD. Such written
    notice of claim shall be received by MSD no later
    than ten (10) days after the event, or the first
    appearance of the circumstances causing the claim,
    and the same shall set forth in detail all known
    facts and circumstances supporting the claim
    including the specific amount claimed. The
    CONTRACTOR agrees and acknowledges that its
    failure to provide written notice of a claim as set
    forth herein shall constitute waiver of any claim
    for additional compensation or time extension
    related thereto;
    ....
    (D) UNKNOWN CONDITIONS: A claim for an
    increase in the Contract Price shall not be allowed
    for concealed or unknown conditions that may be
    encountered in the performance of the Work.
    Whether the concealed or unknown conditions
    exists [sic] (1) below the surface of the ground, or
    -4-
    (2) the concealed or unknown conditions of an
    existing structure are at variance with the
    conditions indicated by the Contract, and are not
    reasonably discoverable by the CONTRACTOR’s
    diligent inspections as required herein, or the
    concealed or unknown conditions are of an
    unusual nature differing materially from those
    ordinarily encountered in the area and generally
    recognized as inherent in the CONTRACTOR’s
    Work of the character provided for in the Contract,
    such conditions shall not serve as the basis for a
    claim for an increase in the Contract Price. The
    CONTRACTOR has expressly represented that
    prior to execution of this Contract, the
    CONTRACTOR has visited and become familiar
    with the Project site and local conditions under
    which the Project is to be constructed and
    operated, and the CONTRACTOR has performed
    such tests, if any, as are necessary to determine the
    conditions under which the Work will be
    performed, and the CONTRACTOR accepts the
    conditions of the Work site and has taken those
    conditions into account in entering into this
    Contract. The CONTRACTOR’s failure, whether
    or not inadvertent or reasonable, to properly
    perform its duties and obligations set forth
    hereinabove, shall not serve as the basis for any
    change in the Contract Price. The
    CONTRACTOR’s sole recourse in the event of
    concealed or unknown conditions that may be
    encountered in the performance of the Work which
    were not reasonably discoverable by the
    CONTRACTOR’s diligent inspections as required
    herein, or are of an unusual nature differing
    materially from those ordinarily encountered in the
    area and generally recognized as inherent in the
    CONTRACTOR’s Work of the character provided
    for in the Contract, shall be appropriate adjustment
    of the date for achieving Substantial Completion,
    -5-
    or, as applicable, Final Completion, pursuant to
    Paragraph 13(G);
    ....
    (J) SUBMITTAL OF DOCUMENTATION: No
    later than thirty (30) days after the date of the
    written notice of claim, the CONTRACTOR shall
    submit a formal written claim which shall include
    at least the following information: (1) a concise
    statement of the occurrence(s) supporting the
    claim, dispute or other matter, and the relief
    sought; (2) identification of the facts giving rise to
    the claim, dispute or other matter; (3) the date the
    party discovered the occurrence(s); (4) a detailed
    schedule of values identifying all costs resulting
    from the claim, dispute or other matter; (5)
    documentation supporting the schedule of values;
    (6) identification of any impact the claim, dispute
    or other matter has on the critical path schedule;
    (7) all correspondence, internal memoranda,
    progress notes, and other documentation relating to
    the events which form the basis of the claim,
    dispute or other matter. Additional information or
    documents requested by MSD shall be submitted
    to MSD within ten (10) days after the written
    request. The failure to provide a claim as set forth
    herein, or failure to provide such other documents
    or information requested by MSD within ten (10)
    days after the written request shall constitute a
    waiver of any claim for additional compensation or
    time extension related thereto[.]
    (ROA 84-85, 87) (emphasis in original) (footnote added).
    Soon after it began its work in February 2016, TSI discovered that the
    depth to the bedrock was considerably less than indicated on MSD’s plans for the
    Project. Consequently, TSI was required to remove more of the underlying
    -6-
    bedrock than had been expected. TSI claims that it gave notice to MSD at the
    Project meetings about this issue. Nonetheless, TSI achieved substantial
    completion of the Project, recognized by MSD, on October 6, 2017.
    On February 8, 2018, TSI advised MSD via letter that it would be
    filing a claim for additional and unanticipated costs incurred to excavate rock due
    to the unforeseen conditions encountered. Its letter asserted, “TSI has provided
    notice to MSD with notices of its intent to file a claim due [to] the irregularities in
    the rock excavation versus information provided at bid time, as reflected in the
    Project Progress Meetings.” (ROA 98.) TSI hired Hagerty Engineering, Inc.
    (“Hagerty”) to investigate the rock conditions it encountered. Hagerty authored a
    report dated September 21, 2018, finding, “the mechanical excavation problems
    could not have been known by the contractor in advance through methods
    reasonable in scope for preparation of a construction bid.” (ROA 6, 108). On
    November 26, 2018—more than nine months after it advised MSD it would be
    filing a claim—TSI submitted its formal claim document to MSD along with the
    Hagerty report and documentation of its additional and unanticipated costs.
    By letter dated December 20, 2018, MSD denied TSI’s claim. MSD
    asserted that TSI did not preserve its claim because it failed to timely file a formal
    claim, resulting in its waiver. TSI disputed MSD’s denial of its claim and
    requested executive negotiation under the contract. MSD refused, stating that
    -7-
    Article 13 of the contract no longer applied since TSI failed to preserve, and
    thereby waived, its claim.
    On July 18, 2019, TSI filed the instant action, alleging breach of
    contract and breach of the implied obligation of good faith and fair dealing. MSD
    moved the trial court to dismiss TSI’s complaint for failure to state a claim upon
    which relief may be granted. After the matter was fully briefed, the trial court
    entered its order dismissing TSI’s claims. This appeal followed.
    STANDARD OF REVIEW
    A trial court should only grant a motion to dismiss if “it appears the
    pleading party would not be entitled to relief under any set of facts which could be
    proved in support of his claim.” Benningfield v. Petit Envtl., Inc., 
    183 S.W.3d 567
    ,
    570 (Ky. App. 2005) (citation omitted). In considering the motion to dismiss, the
    truth of the allegations in the complaint is assumed and the pleadings are to be
    liberally construed in a light most favorable to the plaintiff.
    Id. This determination requires
    no factual findings and is purely a question of law.
    Id. ANALYSIS A fundamental
    rule of contract law is that a written agreement will be
    enforced according to its terms. Conseco Finance Servicing Corp. v. Wilder, 
    47 S.W.3d 335
    , 341 (Ky. App. 2001). On appeal, TSI begins its argument by
    attacking MSD’s failure to comply with the portion of Article 8 quoted herein, as
    -8-
    well as asserting that the issues concerning whether TSI’s notice of claims was
    timely or sufficient are jury questions. The heart of this matter, however, is
    whether the trial court erred in dismissing TSI’s claims against MSD as
    unenforceable, having been waived pursuant to the terms of the contract, and more
    specifically under Article 13. Taking TSI’s allegations in its complaint as true, it
    either provided or attempted to provide notice of its claims to MSD on or before
    February 2, 2018. Yet, it is undisputed that TSI failed to make any formal written
    claim until November 26, 2018, more than nine months later. Article 13(J)
    specifically requires that a formal written claim be submitted within thirty days of
    the written notice of claim. TSI’s failure to comply with Article 13(J) of the
    parties’ contract, therefore, constitutes waiver of its claims.
    In an effort to circumvent the written notice requirement, however,
    TSI asserts that it was impossible to comply with the 10-day and 30-day limits in
    the contract, citing Louisville and Jefferson County Metropolitan Sewer District v.
    T+C Contracting, Inc., 
    570 S.W.3d 551
    (Ky. 2018), for the proposition that
    contractual time limits must be reasonable. It further maintains that the
    reasonability of such limits is a question of fact for jury determination.
    Herein, TSI acknowledged in its complaint that “[a]lmost as soon as it
    began its work, [it] discovered that the depth to the bedrock was considerably less
    than was indicated on MSD’s plans for the Project, requiring TSI to have to
    -9-
    remove more of the underlying bedrock than anticipated.” (ROA 4). Yet, TSI did
    not comply with the written requirement of notice to MSD that it intended to make
    a claim for additional work until February 2018, finally submitting its actual claim
    in November 2018, well after TSI’s work on the Project was concluded.
    Despite TSI’s reliance on T+C, the Court therein determined similar
    contractual provisions to those here were ultimately upheld. Articles 13(A) and (J)
    of the T+C contract were similar to Articles 13(B) and (J), respectively, of the
    contract herein. In T+C, a contractor sued MSD, claiming MSD’s contractual
    provision mandating the chief engineer’s determination to be conclusive of any
    dispute—and thereby wholly prohibiting further administrative/judicial review—
    violated the KFCA.3 On appeal, this Court agreed and found the provision invalid
    and the entirety of Article 13 null and void. The Supreme Court, however, while
    agreeing the procedural provision was void, severed that provision from the
    remainder of Article 13. The Court further held, “Contractual provisions . . . that
    afford the contractor the opportunity to continue asserting a dispute before a
    neutral adjudicator, so long as certain preservation requirements are complied with,
    do not run afoul of KRS 371.405(2)(a).”
    Id. at 562.
    Finally, the Court determined:
    Admittedly, there are several issues that could
    conceivably be argued as being issues of material fact
    that would preclude summary judgment—whether the
    3
    The Kentucky Fairness in Construction Act, KRS 371.400 et seq.
    -10-
    correspondence sent by T+C to MSD constitutes a
    “notice of claim” sufficient to satisfy Subsection (A) of
    Article 13; whether that correspondence complied with
    the time requirements set out by Subsection (A); etc.
    However, what cannot be argued as being an issue of
    material fact, and what resolves all other issues of
    material fact that would preclude the granting of
    summary judgment in favor of MSD, is the failure of T+C
    to file a formal written claim thirty days after filing
    anything that could be argued as being written notice of
    a claim. The trial court’s ruling was correct in this
    regard.
    Id. at 569
    (emphasis added). Thus, herein, and as in T+C, TSI’s failure to comply
    with the contractual provisions necessary for it to preserve its claim is fatal and
    was properly disposed of via summary judgment.
    CONCLUSION
    Therefore, and for the foregoing reasons, the order entered by the
    Jefferson Circuit Court is AFFIRMED.
    ALL CONCUR.
    BRIEFS FOR APPELLANT:                      BRIEF FOR APPELLEE:
    Gerald L. Stovall                          Adam T. Goebel
    Louisville, Kentucky                       Angela S. Fetcher
    Louisville, Kentucky
    -11-
    

Document Info

Docket Number: 2019 CA 001635

Filed Date: 11/5/2020

Precedential Status: Precedential

Modified Date: 11/13/2020