Annan v. Woods , 158 La. 663 ( 1925 )


Menu:
  • THOMPSON, J.

    The defendant appeals from a judgment rendered in plaintiff’s favor for $2,635.66, the full amount claimed, and which judgment rejected the defendant’s re-conventional demand for $9,037.01.

    The suit grows out of a verbal contract under which the plaintiff, as supervising architect, drew the plans and specifications, and caused to be constructed a residential building for the defendant, on lots owned by the defendant in the city of Shreveport.

    It is admitted that the plaintiff was to receive for his services a commission of 12 per cent, of the total cost price of the materials used and for the services and labor performed in the construction bf the building.

    It is also admitted in defendant’s answer that the total cost of the building was $27,-037.01, practically all of which, defendant alleges, had been paid before the institution of this suit.

    It is further admitted that defendant paid $910 on plaintiff’s commission. The amount claimed by the plaintiff represents the balance due on the commission and the sum of $307.66 paid out by plaintiff on insurance.

    The answer sets up numerous complaints of faulty and defective workmanship, the use of inferior and worthless materials, and charges that the plaintiff was extravagant and wasteful in the purchase of materials *665 to be .used in tbe building, and careless, negligent, and unbusinesslike in the construction of tbe said building, all of wbicb caused tbe defendant damage in tbe amount claimed in reconvention.

    Tbe gravamen of defendant’s complaint, however, is that the plaintiff agreed that the total cost of the building, including •plaintiff’s commission, would not exceed $18,-000. This presents an issue of fact, tbe solution of wbicb depends on tbe weight to be given to tbe conflicting testimony.

    It is conceded that if, as a matter of fact, tbe plaintiff guaranteed that tbe entire cost of tbe building would not exceed tbe sum of $18,000, then beyond question tbe plaintiff is not entitled to anything, and would owe tbe defendant tbe amount wbicb be bad to I>ay in excess of tbe price agreed on.

    It appears that tbe defendant’s wife was present during several conferences between tbe plaintiff and defendant, but when tbe contract was finally consummated there was no one present except tbe plaintiff and tbe defendant.

    As already stated, tbe defendant admits that a contract was entered into with tbe plaintiff at a cost plus price, and that plaintiff’s commission was to be 12 per cent, of tbe cost. On page 42 of tbe transcript we find the defendant testifying as follows:

    “Q. What agreement did you make with Mr. Annan to build that building?
    “A. Mr. Annan was to do the architectural work and also to direct the work.
    “Q. For what?
    “A. For 12 per cent.
    “Q. Twelve per cent, of what?
    “A. Of the cost.”

    Having admitted the contract as stated, the burden was clearly on the defendant to prove that tbe cost of tbe building was to be kept within tbe limit alleged.

    This we think tbe defendant has failed to do. As tbe work progressed, tbe bills were paid by tbe defendant, and were continued to be paid long after tbe claimed limits of cost bad been exceeded.

    The plaintiff sent a complete statement of tbe cost up to tbe time of tbe statement, with a demand for bis commission thereon before tbe building was completed and when tbe amount greatly exceeded the $1S,000, and no complaint was made by tbe defendant that tbe cost was growing largely in excess of tbe limit contended for.

    On September 7, 1920, the plaintiff mailed the defendant a statement up to and including August 31, 1920, showing a total cost of $21,755.60, exclusive of the commission. In tbe letter accompanying tbe statement, tbe plaintiff said:

    “You will note the amount due me is $2,610.-67, less credits amounting to $910, which leaves a balance due ,of $1,700.67, on August 31, 1920.”

    To this letter tbe defendant replied:

    “I am in receipt of your statement relative to expenses on house up to August 31st, and would appreciate it very much if you would kindly forward me all invoices covering expenditures made, and also pay rolls, in order that I can check them. As soon as everything is cheeked up and audited, I will.try and make arrangements to settle with you.”

    It will be noted that tbe cost of tbe building up to tbe time tbe statement was sent .to defendant exceeded tbe amount which defendant' claims was tbe limit, by something over $3,000.

    Again on October 8, 1920, before tbe building was completed, the plaintiff mailed another statement to tbe defendant, showing tbe cost up to that time, on wbicb plaintiff claimed a balance as commission of $1,922.78.

    With this statement tbe plaintiff called attention to tbe fact that a previous statement had been sent with all vouchers and papers in support thereof, in order that defendant *667 might check the expenditures in connection with the building.

    Against these 'statements and expenditures the defendant made no objection, and at no time did he protest and claim that the cost price of the house was limited to $18,000, and that plaintiff was without authority to exceed that amount. It is true that, as a witness, he testified that he protested orally to the plaintiff, but the plaintiff denies that he did so.

    We deem it unnecessary to refer to the evidence in further detail. It is sufficient to say that the evidence as a whole preponderates over the contention of the defendant that a limit was placed on the cost of the building, and this conclusion applies equally to the other contentions that the increased cost of the building was due to the indifference, extravagance, and wastefulness of the plaintiff.

    There is no doubt that the building cost much more than either the defendant or the plaintiff contemplated it would at the time the contract was entered into, but, in the absence of proof establishing an agreed limit of price, there can be no sufficient reason why the cost of the building, in excess of what might have been at the time in contemplation of the parties, should be visited upon the plaintiff. It must be remembered that at the time the building was constructed the price of labor and materials was high and still advancing, and it is a fact disclosed by the evidence that “cost plus” jobs were rarely kept within the limits of the estimates. In view of such conditions, contractors were scarcely willing to agree to construct a building under a guarantee to keep the cost within a specified limit.

    The trial judge, who saw and heard the witnesses, resolved the question of fact in favor of the plaintiff, and we can find no sufficient reason for setting aside his finding.

    The judgment is affirmed.

Document Info

Docket Number: No. 25103.

Citation Numbers: 104 So. 491, 158 La. 663, 1925 La. LEXIS 2114

Judges: Thompson

Filed Date: 4/27/1925

Precedential Status: Precedential

Modified Date: 10/19/2024