Jahncke Service, Inc. v. Snow , 1956 La. App. LEXIS 608 ( 1956 )


Menu:
  • REGAN, Judge.

    This litigation emanates from the same building contract, the facts and pertinent issues of which are the same as those found in the-case of Moore Steel, Inc., v. Snow, La.App., 85 So.2d 648, with: the exception of the amount thereof and the judgment therefor which is $626.52, and the fact that the plaintiff instituted suit against Paul D. Snow, Jr., the owner, in addition to Charles Snow, the contractor, and Maryland Casualty Company, his surety. The suit against Paul D. Snow, Jr., was dismissed.

    In the case of Moore Steel, Inc., v. Snow, we were of the opinion, for the reasons assigned therein, that the contractor, Charles Snow, and his surety, Maryland Casualty *654Company, were liable in solido, to the plaintiff for the amount of its claim, plus costs and ten percent attorney’s fees and, by virtue of the stipulation entered into 'between counsel for the Maryland Casualty Company and counsel for ’Charles Snow and Paul D. Snow, Jr., the Maryland Casualty Company is entitled to judgment against Paul D. Snow, Jr., and Charles Snow for the judgment rendered against it in the above entitled suit.

    For the reasons assigned the judgment appealed from is affirmed.

    Affirmed,

Document Info

Docket Number: No. 20657

Citation Numbers: 85 So. 2d 653, 1956 La. App. LEXIS 608

Judges: Regan

Filed Date: 3/5/1956

Precedential Status: Precedential

Modified Date: 10/18/2024