Allen D. DeArmond v. E. Jacob Construction, Inc. ( 2022 )


Menu:
  •                          STATE OF LOUISIANA
    COURT OF APPEAL
    FIRST CIRCUIT
    DOCKET NUMBER
    2021 CA 0981
    ALLEN D. DEARMOND
    VERSUS
    E. JACOB CONSTRUCTION, INC.
    Decision Rendered:   APR 0 8 2022
    APPEALED FROM THE
    19th JUDICIAL DISTRICT COURT, SECTION 24
    EAST BATON ROUGE PARISH, LOUISIANA
    DOCKET NUMBER 689, 599
    HONORABLE DONALD R. JOHNSON, JUDGE
    John Dale Powers                   Attorneys for Plaintiff/ Appellant
    Andrew P. Sellers, Jr.             Allen D. DeArmond
    Baton Rouge, Louisiana
    Nancy A. Richeaux                  Attorneys for Defendant/ Appellee
    Sharon B. Kyle                      E. Jacob Construction, Inc.
    Steven K. Schilling
    Baton Rouge, Louisiana
    BEFORE:        McDONALD, LANIER, and WOLFE, JJ.
    McDONALD, J.
    Allen D. DeArmond appeals a judgment confirming an arbitration award in favor of
    E. Jacob Construction, Inc. ( EJC).          After review, we reverse the trial court judgment, modify
    the May 25, 2020 arbitration award, and render judgment.
    FACTUAL AND PROCEDURAL BACKGROUND
    In April 2018, Mr. DeArmond and EJC entered a contract whereby EJC agreed to
    repair flood -related damages to a house Mr. DeArmond owned in Baton Rouge, Louisiana.
    The original contract price was $ 56, 758. 20, to be paid in five installments based on
    completion progress.          Mr. DeArmond paid EJC two installments of at least $ 27, 210. 00. After
    EJC allegedly refused to complete punch list items, Mr. DeArmond did not pay the remaining
    three installments, leaving an unpaid balance of $ 29, 548. 20.               EJC then filed a lien against
    the project.
    After EJC refused to remove the lien, Mr. DeArmond filed this breach of contract suit
    against EJC.      EJC answered the petition and filed a reconventional demand against Mr.
    DeArmond for the remaining $ 29, 548. 20.               In May 2020, the parties signed a Settlement
    Agreement agreeing to retain Jerry Householder, an engineer ( the Arbitrator),                    to arbitrate
    their dispute.    The Settlement Agreement pertinently provided:
    1)        In order to avoid the inherent risks and uncertainties of litigation the Parties hereby
    settle all of their respective claims and irrevocably bind themselves to the following ... :
    Jerry L. Householder, P. E.[,] shall be retained at the parties' mutual and equal cost to inspect
    the Property, the contract between the parties, contract accounting, and the inspection report
    prepared by William H. Cress, Jr., A. I. A. (" Cress Report"). After said inspection( s), Dr.
    Householder shall determine:
    A.         Whether the alleged defects or deficiencies identified in the Cress Report
    Items") comply with industry standards and/ or whether same were included in [ EJC' s]
    scope of work;
    B.         For any item not in compliance with industry standards, whether same is
    included in EJC' s scope of work and should therefore result in a credit to [ DeArmond]
    and if so, the value of that credit;
    C.         Whether [DeArmond] is due any credit for work not performed and the value of
    same; and
    D.         Given all of the above, the amount of the payment, if any, [ DeArmond] shall
    pay to [ EJC] for the value of work performed. Or, if applicable, the amount of any
    payment [EJC] shall make to [ DeArmond] to correct or complete items in [ EJC' s] scope
    of work.
    Said independent determination by Dr. Householder shall be binding on both parties.
    2
    According to the parties, the Arbitrator conducted an on- site arbitration hearing at
    the house that was the subject of the dispute.             On May 25, 2020, the Arbitrator wrote a
    letter to counsel for both parties setting forth his decision. He noted that the undisputed
    unpaid balance was $ 29, 548. 20, before adjustments for deficiencies or incomplete work.
    He addressed eight punch list items identified by Mr. DeArmond. He found in EJC' s favor
    on all but two of the items.         The Arbitrator reduced the $ 29, 548. 20 unpaid balance by
    860. 00 for those two items, awarded EJC $ 10, 000. 00 in attorney fees, and $ 1, 830. 00 in
    interest on unpaid invoices,        resulting in a final award in EJC' s favor, and against Mr.
    DeArmond, of $40, 598. 20. 1
    On June 9, 2020, pursuant to the Louisiana Arbitration Law, La. R. S. 9: 4210, etseq.,
    Mr. DeArmond filed a Motion to Vacate, Modify, or Correct Arbitration Award, claiming the
    Arbitrator was evidently partial or had so imperfectly executed his powers that a mutual,
    final, and definite award was not made. EJC responded with a Motion to Confirm Arbitration
    Award,     contending none of the exclusive statutory grounds for vacating,          modifying,   or
    correcting the award existed.         The trial court held a hearing on the motions, and at the
    hearing' s conclusion, directed the parties to submit proposed findings of fact and conclusions
    of law. After those submissions, the trial court signed a judgment on June 7, 2021, denying
    Mr. DeArmond' s motion, granting EJC' s motion, and confirming the Arbitrator' s May 25, 2020
    arbitration award.
    Mr. DeArmond appealed from the adverse judgment. After the appeal was lodged,
    this court issued an interim order instructing the trial court to sign an amended judgment
    and to attach the arbitration award. The trial court complied; thus, this court supplemented
    the appellate record with the amended judgment, and maintained the appeal.
    On appeal, Mr. DeArmond contends the trial court erred in confirming the arbitration
    award.     He claims the Arbitrator's award should be vacated because: ( 1) the award shows
    evident partiality; ( 2)   the Arbitrator exceeded his powers in awarding EJC attorney fees
    under the Louisiana Open Account Statute and in awarding ECJ interest on unpaid invoices;
    and, (   3) the award shows a material mathematical miscalculation.
    1 We address a mathematical error in the award later in this opinion.
    3
    LOUSIANA ARBITRATION LAW
    As a matter of public policy, Louisiana strongly favors arbitration; thus, arbitration
    awards are presumed valid.          Crescent Prop. Ptrs, LLC v. American Mfrs Mut. Ins Co.,                  14-
    0969 ( La.    1/ 28/ 15),   
    158 So. 3d 798
    , 803.        A court may vacate, modify, or correct an
    arbitration award based only on the exclusive grounds specified in La. R. S. 9: 4210 and 4211,
    which do not include errors of law or fact. Id, at 803- 04. Of relevance here, under La. R. S.
    9: 4210B and D, the trial court shall vacate an arbitration award where the arbitrator was
    evidently partial or corrupt, or where the arbitrator exceeded his powers or so imperfectly
    executed them that he did not make a mutual, final, and definite award upon the subject
    matter.2 And, under La. R. S. 9: 4211A, a trial court shall modify or correct an arbitration
    award where the award contains an evident material miscalculation of figures.                         A court,
    however, is not entitled to substitute its judgment for that of the arbitrator chosen by the
    parties.     Crescent Prop. Ptrs, LLC, 158 So. 3d at 803.             Rather, a court's determination is
    limited to whether the party challenging the award has proven one or more of the specific
    statutory grounds for invalidation. Id, at 804; St. George Fire Prot. Dist. No. 2 v. J. Reed
    Constr., Inc.,   17- 1006 ( La. App. 1 Cir. 2/ 20/ 18), 
    243 So. 3d 145
    , 148. An appellate court
    conducts a de novo review of a trial court judgment confirming or vacating an arbitration
    award.     Goodrich Petroleum Co., LLC v. MRC Energy Co., 13- 1435 ( La. App. 4 Cir. 4/ 16/ 14),
    
    137 So. 3d 200
    , 207.
    Evident Partiality
    Mr. DeArmond first contends we should vacate and/ or modify the arbitration award
    because the Arbitrator's adverse decision regarding several items on the punch list shows
    he was evidently partial. Specifically, Mr. DeArmond challenges the Arbitrator's decision in
    favor of ECJ regarding the installation of cabinet doors, alleged uninstalled hardware and
    switch plates, and a missing microwave hood/ vent.
    To constitute evident partiality, it must clearly appear that the arbitrator was biased,
    prejudiced, or personally interested in the dispute. Firmin v. Garber, 
    353 So. 2d 975
    , 978
    2 While other circuit courts have adopted a " manifest disregard for the law" as an additional basis for vacating
    an arbitration award, this court has adhered to the statutory standard established by La. R. S. 9: 4210. Bergeron
    v. Patel, 16- 0600 ( La. App. 1 Cir. 5/ 17/ 17), 
    2017 WL 2170142
    , * 4, n. 3, and cases cited therein.
    
    4 La. 1977
    ).      Proof of evident partiality requires more than an appearance of bias.        A
    challenging party must show that a reasonable person would have to conclude that an
    arbitrator was partial to the other party to the arbitration. In re Arbitration Between U.5.
    Turnkey Expl., Inc. & PSI, Inc., 
    577 So. 2d 1131
    , 1135 ( La. App. 1 Cir. 1991). After our de
    novo review of the record, we conclude Mr. DeArmond has failed to produce evidence
    showing that a reasonable person would have to conclude that the Arbitrator was evidently
    partial to ECJ.    The fact that the Arbitrator ruled against Mr. DeArmond on the punch list
    items is not evidence that he was partial to ECJ.      See Bell Aerospace Co, Div, of Textron,
    Inc. v. Local 516, Intern. Union, 
    500 F. 2d 921
    , 923 ( 2nd Cir. 1974) and DeVore v, IHC
    Hospitals, Inc., 
    884 P. 2d 1246
    , 1257 ( Utah 1994) ( both      cases noting that an arbitrator' s
    conclusions in the winning party's favor do not establish partiality); also see Crescent Prop.
    Ptrs, LLC, 158 So. 3d at 808 ( explaining that an arbitrator is not guilty of misconduct merely
    because he could have rendered a different award). And, even if the Arbitrator's decision
    included legal or factual errors as to the punch list items, such grounds do not merit vacating
    his award. Id., 158 So. 3d at 804; also see Mack Energy Co. v. Expert Oil and Gas, LLC, 14-
    1127 ( La. 1/ 28/ 15), 
    159 So. 3d 437
    , 442.   The parties agreed to be bound by the Arbitrator's
    decision regarding their dispute, and this court may not substitute its judgment for the
    Arbitrator' s judgment.    Crescent Prop. Ptrs, LLC, 158 So. 3d at 803.     This assignment of
    error is without merit.
    Attorney Fees and Interest
    Mr. DeArmond also contends the Arbitrator exceeded his powers by awarding ECJ
    attorney fees and interest on unpaid invoices.
    Regarding attorney fees, it is undisputed that neither the parties' contract nor their
    Settlement Agreement provided for the recovery of attorney fees by a prevailing party.
    However, attorney fees may be awarded if allowed by statute.        In his award, the Arbitrator
    awarded $   10, 000. 00 in attorney fees to ECJ under the Louisiana Open Account Statute, La.
    R. S. 9: 2781, et seq.
    Louisiana Revised Statutes 9: 2781D defines an open account as "         any account for
    which a part or all of the balance is past due, whether or not the account reflects one or
    0
    more transactions and whether or not at the time of contracting the parties expected future
    transactions."   If a debtor fails to pay an open account within 30 days after the claimant
    sends written demand therefor correctly setting forth the amount owed, the debtor " shall
    be liable to the claimant for reasonable attorney fees ...      when judgment on the claim is
    rendered in favor of the claimant."     La. R. S. 9: 2781A.    Citation and service of a petition
    shall be deemed written demand for the purpose of La. R. S. 9: 2781A.
    Under the plain reading of La. R. S. 9: 27811),   there is no requirement that there must
    be more than one transaction between the parties, nor is there any requirement that the
    parties anticipate future transactions.      Frey Plumbing Co., Inc. v. Foster, 07- 1091 ( La.
    2/ 26/ 08), 
    996 So. 2d 969
    , 972 ( per cunam).         Under Frey, which directs us to apply the
    language of La. R. S. 9: 2781D as written, an open account includes " any account"              and
    nowhere in the statute are construction accounts or contracts specifically excluded.
    Advanced Leveling & Concrete Solutions v. Lathan Co.,           Inc., 20- 0040 ( La.   App.   1 Cir.
    12/ 10/ 20), 316 So -3d 509, 513- 14; SBL Constr., LLC v. Eymard, 18- 1691 (      La. App. 1 Cir.
    11/ 12/ 19), 
    289 So. 3d 1079
    , 1083; R.L. Drywall, Inc. v. B&     CElec., Inc., 13- 1592 ( La. App.
    1 Cir. 5/ 2/ 14), 
    2014 WL 3559390
    , * 5- 6.
    In this case, ECJ filed a reconventional demand ( deemed a " written demand" under
    La. R. S. 9: 2781A)   against Mr. DeArmond alleging he owed ECJ a past due contractual
    balance of $ 29, 548. 20,   and Mr. DeArmond did not pay ECJ within 30 days of that written
    demand.    The Arbitrator reduced the amount demanded by $ 860. 00, due to defective or
    incomplete work involving painting and a cabinet door, resulting in an award to ECJ for
    28, 688. 20.    Under a plain reading of La. R. S. 9: 2781, as interpreted by Frey and its
    progeny, when the Arbitrator rendered that judgment in ECJ' s favor, Mr. DeArmond became
    liable to ECJ for reasonable attorney fees under La.          R. S. 9: 2781A.   Accordingly, the
    Arbitrator did not exceed his powers by awarding ECJ reasonable attorney fees under the
    Louisiana Open Account Statute.
    Regarding the interest award, the Arbitrator's decision states, " I calculate that the
    interest on the unpaid invoices [ is] $ 1, 830. 00."     Mr. DeArmond contends the Arbitrator
    exceeded his powers in awarding interest, because the parties' contract did not provide for
    11
    such, the Arbitrator gave no statutory authority for the interest award, nor did he give
    authority for his reliance on " unpaid invoices" to calculate interest when the agreed upon
    price was based on a contract, not invoices.
    As earlier noted, a court may vacate, modify, or correct an arbitration award based
    only on the exclusive grounds specified in La. R. S. 9: 4210 and 4211, and those grounds do
    not include errors of law or fact.     Crescent Prop. Ptrs, LLC, 158 So. 3d at 803- 04.        In their
    Settlement Agreement, the parties agreed that the Arbitrator would evaluate their respective
    claims and determine the amount Mr. DeArmond owed EJC " for the value of the work
    performed"     or, conversely, the amount EJC owed Mr. DeArmond "' to             correct or complete
    items in [ EJC' s] scope of work."    In fulfilling his duty, the Arbitrator found Mr. DeArmond
    owed EJC and apparently determined that the " value of the work EJC performed" included
    interest on unpaid invoices.      Even in the absence of a contractual or statutory provision
    authorizing such, and even if an error of law or fact, the Arbitrator's interest award does not
    meet one of the exclusive grounds for vacating, modifying, or correcting an arbitration award
    specified in La. R. S. 4210 and 4211.      See St. Tammany Manor, Inc. v. Spartan Bldg. Corp.,
    
    509 So. 2d 424
    , 427 ( La. 1987) (   even if arbitrator incorrectly applied law as to when interest
    should accrue, such is insufficient to invalidate an award fairly and honestly made);               X
    Developments, LLC v. Amtek ofta., Inc,, 07- 1825 ( La. App. 1 Cir. 3/ 26/ 08),         
    985 So. 2d 199
    ,
    203- 04 ( affirming judgment that declined to vacate arbitrator's interest award). To hold
    otherwise would expand the remedy available by statute and defeat the purpose of
    arbitration.   X Developments, LLC, 
    985 So. 2d at 204
    . This assignment of error is without
    merit.
    Material Mathematical Miscalculation
    Mr.   DeArmond   next    argues    that   the    arbitration   award   contains   a   material
    miscalculation in the amount awarded to ECJ.            Under La. R. S. 9: 4211A, a court is required
    to modify or correct an arbitration award containing an evident material miscalculation of
    figures. As earlier stated, the Arbitrator reduced the $ 29, 548. 20 unpaid balance by $ 860. 00
    for two items, awarded EJC $     10, 000. 00 in attorney fees, and $ 1, 830. 00   in interest on unpaid
    invoices, and then awarded EJC $ 40, 598. 20.          At the hearing on this matter, EJC' s counsel
    7
    conceded that the above amounts total $ 40, 518. 20, not $ 40, 598. 20, which is a difference
    of $80. 00.
    When a court confirms,     modifies, or corrects an arbitration award,      it may enter
    judgment in conformity therewith.         See La. R. S. 9: 4212.      Accordingly, we modify the
    arbitration award to correct the evident mathematical error and to render judgment
    accordingly, under La. R. S. 9: 4212, for the correct amount of $40, 518. 20 ($ 29, 548. 20, less
    860. 00, plus $ 10, 000. 00, plus $ 1, 830. 00).     See King Co., Ltd. P'ship v. MBD Const. Co.,
    Inc.,   10- 0902 ( La. App. 1 Cir. 10/ 29/ 10), 
    2010 WL 4273003
    , *    7.
    CONCLUSION
    For the above reasons, we reverse the trial court judgment.              We modify the
    Arbitrator's May 25, 2020 award to correct a mathematical error. We render judgment in
    favor of ECJ, and against Allen D. DeArmond, for $40, 518. 20. We assess costs of the appeal
    to Allen D. DeArmond.
    TRIAL    COURT     JUDGMENT        REVERSED;         ARBITRATOR' S     MAY    25,   2020
    AWARD MODIFIED; JUDGMENT RENDERED.
    E:3