Conti Enterprises, Inc. v. Providence/GSE Associates, LLC, Robert E. Williams, Jr, and Aspen Specialty Insurance Company ( 2023 )


Menu:
  •                                    STATE OF LOUISIANA
    COURT OF APPEAL
    FIRST CIRCUIT
    M
    2022 CA 12491
    CONTI ENTERPRISES, INC.
    PROVIDENCE/ GSE ASSOCIATES, LLC., ROBERT E. WILLIAMS, JR.
    AND ASPEN SPECIALTY INSURANCE COMANY
    Judgment rendered:       OCI 3 0 2023
    On Appeal from the
    32" Judicial District Court
    Terrebonne Parish
    State of Louisiana
    No. 174385
    Judge Randall L. Bethancourt, Presiding
    Stephen P. Hall                                  Attorneys for Appellee/ Defendant
    Phelps Dunbar, LLP                               XL Specialty Insurance Company
    New Orleans, Louisiana
    Adrian G. Nadeau                                 Attorneys for Appellees/ Defendants
    J. Weston Clark                                  Hartman Engineering, Inc. and
    Baton Rouge, Louisiana                           Jared Monceaux
    Brian J. Marceaux                                Attorneys for Plaintiff/Appellant
    Julius P. Hebert, Jr.                            Terrebonne Parish Consolidated
    Government
    Derick A. Bercegeay
    Brianna Wilson Orgeron
    Houma, Louisiana
    BEFORE: THERIOT, HOLDRIDGE, AND HESTER, JJ.
    Pesfe- r       I   COACkAr5
    I
    1 We note that 2022 -CA -1249, Conti Enterprises, Inc. vs. Providence/GSE Associates, LLC,
    is consolidated with 2022 -CA -1248, Conti Enterprises, Inc. vs. Providence/ GSE Associates,
    LLC, for oral argument and submission.
    HOLDRIDGE, J.
    In this appeal, Terrebonne Parish Consolidated Government ( TPCG) appeals
    a trial court' s judgment granting a motion for summary judgment dismissing all of
    TPCG' s     claims   against    Hartman   Engineering,    Inc.   and   Jared   Monceaux
    sometimes collectively referred to as " Hartman"). We affirm.
    BACKGROUND
    This lawsuit arises out of a road construction project in Terrebonne Parish
    commonly called the " Hollywood Road Widening Project" (" the Project").             On
    April 21,    2015, Conti Enterprises, Inc. ( Conti), which served as the general
    contractor on the Project, filed a lawsuit against Providence/ GSE Associates, LLC
    Providence), Robert E. Williams, Jr., and Aspen         Specialty Insurance Company,
    Providence' s insurer.      By amended petition filed on November 2, 2018, Conti
    added TPCG and the Louisiana Department of Transportation ( DOTD)                     as
    defendants in the litigation.
    In the original and amending petitions, Conti alleged that TPCG entered into
    a written contract with Providence to perform construction engineering and
    inspection services, including construction administration, in connection with the
    Project.
    Conti further alleged that it based its bid price on the ability to construct
    the Project in strict compliance with the plans,           specifications,
    and bidding
    documents.      Conti alleged that during construction, it became obvious that the
    plans,   specifications,
    and bidding documents, including the portions designed,
    issued, and let for bid by TPCG and DOTD, were inadequate and insufficient for
    proper construction of the Project. Conti sought to recover all losses it claimed
    were caused by the wrongful acts of the defendants in connection with the design
    phase and construction administration of the Project,       including all amounts for
    2
    additional time, effort, manpower, labor, equipment and money for which Conti
    had not been paid, as well as extended overhead and home office expenses.
    On May 14, 2020, TPCG filed a reconventional demand, cross- claim, and
    third -party demand in which it made Hartman and its insurer, XL Specialty
    Insurance Company ( XLSIC), third party defendants in the litigation.2 In the third -
    party demand, TPCG alleged that Hartman contracted with TPCG on October 7,
    1998,    to   prepare    an   environmental   assessment        and   to   prepare   plans   and
    specifications for the roadway, including storm drains, associated with the Project.
    TPCG alleged that the TPCG-Hartman contract required Hartman to defend and
    indemnify TPCG and to maintain insurance for the Project, listing TPCG as an
    additional insured.         TPCG asserted that in the event it was found liable to Conti,
    Hartman and its insurers were obligated to indemnify TPCG for any and all
    damages cast against TPCG in the Conti lawsuit for all costs and expenses,
    including attorney' s fees. More specifically, TPCG alleged that if Conti was able
    to prove its allegations regarding the site conditions or defective roadway plans,
    Hartman, through its contract with TPCG, was liable to TPCG for its negligence or
    fault based upon Hartman' s numerous alleged breaches of the TPCG-Hartman
    contract, including: preparing plans and specifications which contained errors and
    omissions; deficient preparation of topological surveys, roadway plans, including
    drainage specifications, environmental                assessments    and Project     designs;    and
    Hartman' s deficient implementation of its scope of work associated with the
    Project.
    On January 6, 2022, Hartman filed a motion for summary judgment in which
    it asserted that TPCG' s claims were barred by the five-year peremptive period set
    forth in La. R.S.           9: 5607 for actions seeking damages against a professional
    2
    By letter dated January 2, 2019, TPCG tendered the defense and indemnity of the claims made
    against it by Conti in the amended petition to XLSIC.
    3
    engineer.     Hartman relied on La. R.S. 9: 5607( A)(3),                         which provides that the
    peremptive     period          in   a   claim    against       an    engineer    that   furnished    services
    preparatory       to    construction,      but    did        not    perform     inspection    of   the   work,
    commences to run from the date the engineer has completed its services.
    According to Hartman, the services it was contracted by TPCG to perform in
    connection with the Project were completed when Hartman signed and sealed the
    last revision to its final set of roadway plans on September 16, 2013.                              Hartman
    urged that pursuant to La. R.S. 9: 5607( A)(3), all claims against Hartman related to
    its services on the Project had to be brought no later than September 16, 2018.
    Since TPCG' s third -party demand against Hartman was filed in May of 2020,
    nearly two years after the five-year peremption period had expired.                                 Hartman
    argued that TPCG' s claims were perempted as a matter of law and should be
    dismissed.
    In opposition to the motion, TPCG insisted that the statutes pertaining to
    public works projects undertaken by DOTD provide the exclusive time limitation
    for all work arising out projects related to a DOTD contract. The provision relied
    on by TPCG, La. R.S. 48: 251. 3, provides that any action arising out or related to a
    DOTD contract or on a bond furnished by a contractor prescribes five years from
    recordation of the acceptance of such contract.                        According to TPCG, the DOTD
    prescription statutes applied to this case because the Project was let out by DOTD
    on TPCG' s behalf, TPCG was required to follow the protocol set forth in the
    DOTD statutes, Hartman' s work done on the Project undoubtedly arises out of and
    is related to the DOTD Project, and Hartman provided design services, inspection
    services,   and
    other   preparatory       services          outside   of design       engineering   in
    connection with the Project.             TPCG asserted that the five-year prescriptive period
    on such actions commenced on the date of acceptance of the work by DOTD was
    19
    recorded.   TPCG relied on evidence showing that on June 15, 2017, DOTD' s chief
    engineer, Janice Williams, signed and approved the final acceptance of the Project
    and recorded that acceptance with the clerk of court in Terrebonne Parish. On June
    23, 2017, TPCG filed its final accepted completion of the Project.       TPCG urged
    that pursuant to the DOM statutes, the five-year prescriptive period began to run
    on June 23, 2017, making its 2020 claims against Hartman timely.
    Alternatively, TPCG maintained that if La. R.S. 9: 5607' s peremptive period
    in actions against engineers provides the applicable time limitation in this case,
    subsection ( A)( 1)   governs its claims against Hartman, which provides the same
    time period for claims against engineers as La. R.S. 48: 251. 3— five years from the
    recordation date.     Thus, TPCG posited that as a matter of law, it had five years
    from the recordation of the acceptance of the Project by DOM to file its lawsuit
    against Hartman, La. R.S. 9: 5607( A)(3)       did not apply in this case, and Hartman
    was not entitled to summary judgment dismissing TPCG' s claim.
    On January 6, 2022, XLSIC filed a separate motion for summary judgment,
    seeking dismissal of all claims against it as Hartman' s insurer.    XLSIC argued in
    its motion that there was nothing in either the TPCG-Hartman Contract or the
    XLSIC insurance policy at issue which rendered TPCG an insured under that
    policy.   XLSIC further argued that TPCG' s claims on its alleged status as an
    additional insured of XLSIC were perempted. Therefore, XLSIC urged the trial
    court to grant its motion for summary judgment.
    By judgment dated June 28, 2022, the trial court granted Hartman' s motion
    for summary judgment, and in a second judgment signed on that same date, the
    trial court granted XLSIC' s motion for summary judgment.         TPCG filed separate
    5
    motions appealing both judgments.' TPCG' s appeal from the summary judgment
    rendered in favor of XLSIC was docketed as 2022 -CA -1248, while the judgment
    granting Hartman' s motion for summary judgment was docketed as 2022 -CA -
    1249.    In connection with both appeals, this court initially issued rules to show
    cause orders as to whether the appeals should be dismissed. Thereafter, this court
    maintained the appeals.         Conti Enterprises, Inc. v. Providence/ GSE Associates,
    LLC,     2022- 1248 ( La.        App.         1    Cir.       4/ 17/ 23);    Conti    Enterprises,        Inc.   v.
    Providence/ GSE Associates, LLC, 2022- 1249 ( La. App. 1 Cir. 4/ 17/ 23).                                    The
    appeals were later consolidated for oral argument and submission by this court.
    SUMMARY JUDGMENT
    After an opportunity for adequate discovery, summary judgment shall be
    granted if the motion, memorandum, and supporting documents show that there is
    no genuine issue of material fact and that the mover is entitled to judgment as a
    matter of law.          La. C. C. P.   art.       966( A)(3).        Appellate courts review summary
    judgments         de   novo,   using the           same       criteria      that   govern   the   trial   court' s
    consideration of whether summary judgment is appropriate, i.e., whether there is
    any genuine issue of material fact and whether the mover is entitled to judgment as
    a matter of law.        See La. C. C. P. art. 966( A)(3); Turner v. Rabalais, 2017- 
    0741 La. App. 1
        Cir. 12/ 21/ 17),   
    240 So. 3d 251
    , 255, writ denied, 2018- 0123 ( La.
    3/ 9/ 18), 
    237 So. 3d 1193
    .
    A genuine issue is one as to which reasonable persons could disagree; if
    reasonable persons could reach only one conclusion,                                  summary judgment is
    appropriate. Collins v. Franciscan Missionaries of Our Lady Health System,
    Inc., 2019- 0577 ( La. App. 1 Cir. 2/ 21/ 20), 
    298 So.3d 191
    ,                          194- 95, writ denied,
    3 We note that this court remanded this matter to the trial court, on a joint motion of parties, to
    fix the decretal language in the judgment pursuant to La. C. C. P. art. 1918( A).                 The trial court
    signed an amended judgment on March 16, 2023.
    6
    2020- 00480 { La. 6/ 22/ 20), 
    297 So. 2d 773
    . A fact is " material" when its existence
    or non- existence may be essential to plaintiff' s cause of action under the applicable
    theory of recovery.      A material fact is one that would matter at a trial on the
    merits.   Any doubt as to a dispute regarding a material issue of fact must be
    resolved against granting the motion and in favor of trial on the merits.          Collins,
    298 So. 2d at 195.
    The Code of Civil Procedure places the burden of proof on the party filing
    the motion for summary judgment. La. C. C. P. art. 966( D)( 1).       The mover can meet
    this burden by filing supporting documentary evidence, and the mover' s supporting
    documents must prove the essential facts to carry the mover' s burden.            Thus, in
    deciding a motion for summary judgment, it must first be determined whether the
    supporting documents presented by the mover are sufficient to resolve all material
    factual issues.    Jenkins v. Hernandez, 2019- 0874 ( La. App. I Cir. 6/ 3/ 20), 
    305 So. 3d 365
    , 370- 71, writ denied, 2020- 00835 ( La. 10/ 20/ 20), 
    303 So. 3d 315
    .
    Once the mover demonstrates the absence of factual support for one or more
    elements essential to the adverse party' s claim, the burden shifts to the non-moving
    party to produce factual support, through the use of proper documentary evidence
    attached to its opposition, which establishes the existence of a genuine issue of
    material fact or that the mover is not entitled to judgment as a matter of law.
    Jenkins, 305 So. 3d at 371.     If the non-moving party fails to prove the existence of
    a genuine issue of material fact, La. C. C. P. art. 966( D)( 1)   mandates the granting of
    the motion for summary judgment. Id.
    Applicable Time Period
    asserts that the five-year peremptive period provided for in La. R.S.
    9: 5607( A)(3)    applies to   TPCG' s   claims. Louisiana Revised        Statutes 9: 5607
    provides, in pertinent part, as follows:
    7
    A.   No action for damages against any professional engineer ...
    whether based upon tort, or breach of contract, or otherwise arising
    out of an engagement to provide any manner of moveable or
    immovable planning, construction, design, or building, which may
    include but is not limited to consultation, planning, designs,
    drawings, specifications, investigation, evaluation, measuring, or
    administration related to any building, construction, demolition, or
    work,   shall be brought unless filed in a court of competent
    jurisdiction and proper venue at the latest within five years from:
    1) The date of registry in the mortgage office of acceptance of the
    work by owner; or
    2) The date the owner has occupied or taken possession of the
    improvement, in whole or in part, if no such acceptance is
    recorded; or
    3) The date the person furnishing such services has completed the
    services with regard to actions against that person, if the person
    performing or furnishing the services, as described herein, does
    not render the services preparatory to construction, or if the
    person furnishes such services preparatory to construction but the
    person furnishing such services does not perform any inspection
    of the work.
    C.   The five-year period of limitation provided for in Subsection A of
    this Section is a peremptive period within the meaning of Civil
    Code Article 3458 and in accordance with Civil Code Article
    3461, may not be renounced, interrupted, or suspended.
    Hartman contends that because it performed work only preparatory to construction
    and did not provide inspection of the work or any engineering services during the
    construction of the Project, under the plain language of La. R.S. 9: 5607( A)(3),   the
    five-year peremptive period began to run on the date it completed its services
    under its contract with TPCG.      Thus, Hartman maintains, any claims TPCG may
    have had related to its engineering services were perempted five years after
    Hartman completed its services under the TPCG contract.          This occurred when
    Hartman signed and sealed the last revision to its final set of roadway plans on
    September 16, 2013.
    In support of the motion, Hartman submitted Mr. Monceaux' s December 22,
    2021 affidavit, together with numerous exhibits attached thereto; Conti' s petition
    for damages and amended petition; correspondence between TPCG' s attorney and
    Hartman' s      attorney';    TPCG' s     cross    claim    and    amended     cross     claims;    and
    Hartman' s discovery responses.
    In his    affidavit, Mr. Monceaux,             an   engineer    and   owner      of Hartman
    Engineering, who was familiar with Hartman' s scope of work on the Project, and
    who stamped and sealed Hartman' s final plan revisions,                       made the following
    attestations:      On   October      71    1998,   Hartman        entered   into   a "   Contract   for
    Engineering       Services"    with       TPCG,    whereby        Hartman     agreed      to   provide
    Environmental Assessment ( EA) and related engineering services to TPCG for the
    Project. On June        5,   2001,   Hartman and TPCG entered into a supplemental
    agreement to the contract wherein the parties agreed to modify the payment clause
    of the contract, that Hartman had satisfactorily completed the EA services, and that
    Hartman would prepare preliminary plans for the Project. On October 4, 2004, the
    contract was again supplemented to reflect the parties' agreement that Hartman
    would prepare revisions to plans developed and perform related survey services.
    The ," public liability" provisions of the contract were replaced with "
    indemnity"
    and " errors and omissions" provisions.
    Continuing, Mr. Monceaux attested that: On October 12, 2005, Hartman
    and TCPG entered into a third supplemental agreement to the contract, in which
    the parties agreed that Hartman' s scope of work would be modified to include the
    preparation of a right-of-way map and final plans for the construction of the
    roadway for the Project and to replace the " public liability" provisions with new
    indemnity" and " errors and omissions" provisions. On May 30, 2013, Hartman
    and TPCG entered into a fourth supplemental agreement to the contract in which
    4 We note that the correspondence, which was not attached to an affidavit, is not competent
    summary judgment evidence. See La. C. C. P. art. 966( A)(4) and comment ( c). Additionally, it is
    noted that the discovery attached to the motion for summary judgment was not answered under
    oath.
    9
    they agreed that Hartman would update the roadway plans previously prepared to
    current DOTD specifications, add driveways, revise quantities, and revise other
    associated items.
    According to Mr. Monceaux, pursuant to the contract, as amended and
    supplemented, Hartman submitted its stamped and sealed set of final roadway
    plans for construction of the Project on July 15, 2013.    Hartman submitted its final
    invoices to TPCG for payment on August 6t' and 7t", 2013, which were paid in full
    by TPCG by check dated August 26, 2013. Thereafter, at the request of DOTD' s
    engineer for the Project, Mr. Monceaux made limited revisions to the plans to
    address changes for the final bid set of documents, stamped the revised plan sheets
    on September 16, 2013, and issued them to DOTD.           This was the last revision of
    the plans Hartman prepared under its contract with TPCG, and with this final
    revision, Hartman completed its services under its contract with TPCG as amended
    and supplemented.
    After Hartman completed its work under TPCG contract, Mr. Monceaux
    responded to emails from DOTD' s engineer and a contractor exchanged from
    September 2013 through February of 2014 relative to questions arising during the
    bidding process.      However, Mr. Monceaux advised the DOTD engineer that
    answering contractor questions was not included within the contract as amended.
    Mr. Monceaux' s request to be compensated for answering such questions was
    denied.   Hartman responded to emails from DOTD and a contractor to direct
    attention for ease of reference to a special provision Hartman had included in its
    final plans and to provide native design files for the contractor' s convenience.
    Hartman was not paid for these email communications as they were provided as a
    matter of courtesy.
    10
    Mr. Monceaux acknowledged that in 2014, he was retained by TPCG as an
    expert witness relative to an expropriation complaint by Henry Richard, who
    owned property along Hollywood Road. He stated his scope as an expert witness
    was merely to review documents and provide opinions and that neither he nor
    Hartman performed any design services in conjunction with the expert witness
    engagement.
    Finally, Mr. Monceaux made the following attestations: The TPCG contract,
    as   amended      and   supplemented,      did not include an agreement for Hartman to
    provide     any    construction      and
    engineering    inspection   services,   construction
    administrative      services,   or   any    other    construction   phase   services;   Hartman
    submitted a proposal to TPCG to be one of the engineering firms considered for
    those services for the Project; however, Hartman' s proposal was not accepted by
    TPCG; Hartman did not perform any construction phase services in connection
    with the Project and Hartman was not asked to and did not observe or inspect any
    work on the Project.
    Additional evidence submitted by Hartman in support of its motion for
    summary judgment corroborating Mr. Monceaux' s attestations included the TPCG-
    Hartman contract, executed on October 7, 1988, setting forth scope of Hartman' s
    services to include:      Preliminary Engineering, Right of Way Survey and Maps, and
    Final Plans.      On December 9, 1998, TPCG issued a notice to proceed on the
    contract.   On June 5, 2001, the contract was amended to provide to include all
    engineering services required for the completion of the preliminary plans and
    estimates for the Project and to set forth a schedule for the completion of
    Hartman' s work.        The contract was again amended on October 5, 2004, to include
    all engineering services required to revise the preliminary plans due to roadway
    changes since the original survey was acquired and to set forth deadlines for the
    11
    completion of these services.         On October 12, 2005,     another   amendment       was
    executed    to   include   all   necessary   right   of way   map   preparation    and   the
    of final plans for the Project. The contract was further amended on
    May 30, 20:13, to expand the scope of the services to include all engineering
    services to revise the construction plans,        including bringing them up to current
    DOTD specifications and adding driveways.
    The final plans were recommended and approved by Hartman and TPCG on
    July 15, 2013. DOTD approved the plans on August 9, 2013. On August 5, 2013,
    Hartman submitted an invoice to TPCG in the amount of $10, 435. 27 for services
    rendered from July 1, 2013 through July 31, 2013.          On August 7, 2013, Hartman
    submitted an invoice to TPCS in the amount of $20, 134. 93 for services rendered
    from April 23,     2009 through July 31, 2013. On August 26, 2013, TPCG issued
    Hartman a check in the amount of $30, 570. 00.
    Thereafter, the evidence shows that on September 25, 2013, DOTD' s project
    engineer sent Hartman an email regarding a revision to estimated quantities.             The
    engineer advised other than changing the date of the revision to September 30,
    2013, the plan sheets were " good to go."         DOTD' s engineer stated that he would
    change the date and planned to readvertise the Project on October 2" d.            Another
    email from DOTD' s project engineer to Hartman on September 19, 2013, stated
    that DOTD had received a number of questions from                    contractors   on    the
    construction plans and specifications; he advised that the Project would have to be
    withdrawn from letting, and the next possible letting would be October 23, 2013, if
    the plans and specifications were complete by the close of business on September
    30, 2013.   Hartman responded on September 19, 2013, to inquire whether DOTD
    paid for addressing contractor questions during the bidding phase. Hartman sent
    an email later that day requesting that DOTD' s engineer send him the applicable
    12
    contractor     questions;   DOTD' s engineer responded that the main question was
    temporary asphalt, which Hartman addressed, and the remainder of the questions
    were regarding the utility plans.        Email correspondence exchanged between
    Hartman and others in November of 2013 were also attached; in one of the emails,
    Hartman was asked for a contract expiration date for the Project, and the sender
    was instructed to " close it out" as they were " 100 percent complete."   In February
    of 2014, various emails were exchanged between Hartman and TPCG regarding a
    special provision drafted by Hartman, and a request for a release of the CAD
    drawing on the Project. Finally, in August of 2017, DOTD requested Hartman' s
    design files to update its inventory files at it had just received final acceptance of
    the Project.
    In further support of the motion, Hartman submitted its responses to TPCG' s
    interrogatories, in which it asserted that it only provided professional engineering
    services in preparation for construction of the Project.   Hartman denied providing
    any engineering services pursuant to any written contract with DOTD or Conti,
    denied providing any services whatsoever during the construction phase of the
    Project, and denied having ever been contracted relative to any problems during
    the construction phase of the Project.     Hartman acknowledged that at request of
    DOTD,     Hartman made limited revisions to plan sheets to address changes
    requested by DOTD' s engineer, issued the revision to DOTD on September 16,
    2013, and the September 16, 2013 revisions were the last revisions Hartman made
    to its plans under its contract with TPCG.
    In opposition to the motion for summary judgment, TPCG insists that La.
    R. S. 9: 5607( A)(3)   does not apply to its claims against the Hartman.     Instead,
    TPCG maintained that pursuant to La. R.S. 28: 251. 3 or La. R.S. 9: 5607( A)( 1), it
    13
    had five years from the date the final acceptance of the Project was filed and
    recorded on June 23, 2017. 5
    After Hartman' s motion for summary judgment was filed, the deposition of
    Mr. Monceaux was taken in which he was thoroughly questioned on the statements
    made in his affidavit.       His deposition was an exhibit to TPCG' s opposition to
    Hartman' s motion for summary judgment.                  The deposition testimony of Mr.
    Monceaux did not establish that the inspection or any other work was done by
    Hartman through January 2015.
    Louisiana Revised Statutes 48: 250 et seq., set forth the laws specially
    governing DOTD contracts for public works and all contracts for the construction
    of public works let by DOTD on behalf of political subdivisions.                 The provision
    relied    on   by   TPCG,    La.   R.S.   48: 251. 3,   entitled, "   Prescription;   claims   by
    contractors; surety," provides, in part:
    Any action arising out of or related to a department contract or on the
    bond furnished by a contractor shall prescribe five years from
    recordation of the acceptance of such contract or of notice of default
    of the contractor or other termination of the contract,              whichever
    occurs first.
    TPCG urged that this provision, which governs DOTD-related contracts, such as
    contracts for construction and engineering on public works projects, applies to its
    claims against Hartman. TPCG insisted that its evidence showed that the TPCG-
    Hartman contracts arose out of and were related to the DOTD contract, focusing on
    the following: DOTD bid and let out the contract for the Project; DOTD selected
    engineers,     prepared the bid documents, selected the contractor;               prepared     all
    contracts for the Project, including the TPCG-Hartman contract, which contains a
    DOTD number; DOTD paid 80% of the cost for the Project; DOTD selected
    Hartman and Providence to perform engineering services, which then contracted
    5 DOTD' s engineer signed the final acceptance of the Project on June 15, 2017; TPCG filed the
    final acceptance in the mortgage records on June 23, 2017.
    14
    with TPCG for those services.           TPCG also claims that its evidence shows that
    Hartman' s work was more than preparatory and involved inspection work through
    2015. In support, TPCG relies on the fact that Mr. Monceaux testified on behalf of
    TPCG on January 28, 2015, in a lawsuit brought by a property owner seeking
    damages against TPCG.         According to TPCG, this evidence proves that Hartman
    provided inspection services by its involvement in the design issues that arose
    during the construction of the Project through January 28, 2015, rendering La. R.S.
    9: 5607( A)(3) inapplicable.
    We disagree.     TPCG failed to show how Mr. Monceaux' s retention                   by
    TPCG to testify in a lawsuit by a property owner on Hollywood Road equates to
    Hartman' s providing inspection and other work on the Project through January of
    2015.     Mr. Monceaux was hired by TPCG to serve as an expert witness in a lawsuit
    by a property owner who resided on Hollywood Road. Mr. Monceaux attested that
    his services in connection with the lawsuit did not involve any design work. TPCG
    failed to introduce any contract for engineering services with Mr. Monceaux from
    2015 and it has not supported its claim that Mr. Monceaux' s testimony in a lawsuit
    related to the Project constitutes inspection of the work so as to bring its claims
    outside of the scope of La. R.S. 9: 5607( A)(3). 6
    Furthermore, we find no merit in TPCG' s argument that the DOTD statutes
    pertaining to public works projects override the specific peremptive period
    provided by La. R.S. 9: 5607. It is a well-settled canon of statutory construction
    that the more specific statute controls over a general statute. Sharp v. Sharp, 939
    6 In an affidavit submitted by TPCG in support of its opposition to the motion, Al Levron, who
    was TPCG' s parish manager who worked closely on, supervised, and was intimately involved
    with the Project, attested that " Hartman ... performed services outside the scope of design work
    for the Project," citing Hartman' s environmental, survey, and title work for the Project;
    Hartman' s handling of issues involving citizens disputes; and Hartman' s exchange of
    information with contractors during the bidding phase of the Project. However, TPCG failed to
    show how any of these actions were unrelated to the engineering services Hartman was hired to
    perform on behalf of TPCG or occurred within the 5 -year peremptive period set forth in La. R.S.
    9: 5706( A)( 3).
    
    15 So.2d 418
    , 421 ( La. App. I Cir. 6/ 28/ 06), writ denied, 2006- 1877 ( La. 11/ 17/ 06),
    
    842 So. 2d 533
    .       Louisiana Revised Statutes 9: 5607 applies to all actions for
    damages against a professional engineer arising out of an engagement to provide
    design services related to any manner of moveable or immovable planning,
    design,   or building, including, but not limited to,             consultation,
    planning, designs, drawings, specification, investigation, evaluation measuring, or
    administration.
    It contains three factual circumstances that trigger the running of
    the peremptive period: ( 1)     the date of registry in the mortgage office of acceptance
    of the work by the owner; ( 2) the date the owner has occupied or taken possession
    of the improvement, if no such acceptance is recorded;               and (   3)   the date the
    engineer rendering services has completed the services, if the engineer does not
    render services preparatory to construction or if the engineer furnishes services
    preparatory to construction but does not perform any inspection of the work.
    These factual triggers clearly contemplate that work performed by professional
    engineers in connection with public works projects fall within the scope of La. R.S.
    9: 5607.
    We are mindful of the difference between prescription and peremption.
    Although related, the two are not the same and should not be confused; what is true
    of   prescription   may   not    be   true   of    peremption.   Peremption       differs   from
    prescription in two respects: ( 1)      the expiration of the peremptive time period
    destroys the cause of action itself-,and ( 2) nothing may interfere with the running
    of a peremptive time period.      Naghi v. Brener, 2008- 2527 ( La. 6/ 26/ 09), 
    17 So. 3d 919
    , 926.   Statutes of limitation are exclusively a legislative prerogative. In setting
    the five-year: peremptive period under La. R.S. 9: 5607( A)(3) for claims against a
    professional engineer, the legislature determined that after five years, no cause of
    action can arise, regardless of the claim.          See Reeder v. North, 97- 0239 ( La.
    16
    10/ 21/ 97), 
    701 So. 2d 1291
    , 1296.       Stated differently, after the five-year peremptive
    period expires as mandated by La. R.S. 9: 5607, the cause of action no longer
    exists;    it is ' lost.   See Regions Bank v. Eymard, 2021- 0926 ( La. App. 1 Cir.
    5/ 23/ 22), 
    342 So.3d 908
    , 919, writ denied, 2022- 00977 ( La. 10/ 18/ 22), 
    348 So. 3d 731
    .   Thus, we find that although the DOTD statute, La. R.S. 48: 251. 3, applies to
    this case, the more specific statute, La. R.S. 9: 5607, is applicable and creates a
    peremptive period that TPCG had five years from September 16, 2013 to file an
    action for damages against Hartman.             After September 16, 2018, the peremptive
    period had lapsed and any cause of action against Hartman for engineering services
    no longer existed.         Therefore, La. R.S. 48: 251. 3 only applies if a cause of action
    against an engineering service exists.          In this case, after September 16, 2018, no
    cause of action existed against Hartman or Mr. Monceaux.
    Hartman offered evidence on the motion demonstrating that the services it
    performed on behalf of TPCG were preparatory to construction of the Project.
    Hartman was not contracted by TPCG to provide construction engineering and
    inspection services, construction administration services, or any other construction
    phase engineering services.          Instead,   another engineering firm was engaged by
    TPCG to perform the construction phase engineering and inspection services.
    Hartman' s evidence showed that it did not inspect the work on the Project. The
    evidence offered by TPCG in opposition to the motion failed to create a genuine
    issue of fact as to whether Hartman provided services falling outside the purview
    of La. R. S. 95067(A)(3).
    Accordingly, we hold that in this case, the five-year peremptive period
    began to run on the date Hartman completed the services it was contracted to
    provide to TPCG.           Hartman showed that its services under the TPCG contract, as
    amended and revised, were completed when Hartman signed and sealed the last
    17
    revision of the final set of roadway plans on September 16, 2013.                 TPCG had until
    September 16, 2018 to file an action for damages against Hartman.                        Because
    TPCG' s claim against Hartman was not filed until May of 2020, any action it may
    have had against Hartman arising out of the design services provided by Hartman
    was extinguished.
    The trial court correctly granted summary judgment dismissing
    TPCG' s claims as those claims were perempted under La. R.S. 9: 5607( A)(3).'
    CONCLUSION
    For the foregoing reasons, the trial court' s judgment granting summary
    judgment in favor of Hartman Engineering, Inc. and Jared Monceaux is affirmed.
    Costs of this appeal, docketed as 2022 CA 1249, in the amount of $23, 728. 50, are
    assessed to Terrebonne Parish Consolidated Government.
    AFFIRMED.
    7 We reject TPCG' s argument that its claims against Hartman should " relate back" to the date the
    original lawsuit was filed by Conti in April of 2015. There is nothing to relate back since the
    cause of action does not exist.
    See Stewart v. Continental Cas. Co., Inc., 2011- 0505 ( La. App.
    1 Cir. 11/ 9! 11),   
    79 So. 3d 1047
    , 1049, writ denied, 2011- 2721 ( La. 2/ 17/ 12), 
    82 So. 3d 285
    .
    Under La. R.S. 9: 5607( C), the five-year peremptive period may not be interrupted or suspended.
    Furthermore, La. C.C.P. art. 1041, which provides for a 90 -day grace period for filing incidental
    demands, only applies if the incidental demand was filed within 90 days of the date of service of
    the main demand.
    TPCG did not file its claims against Hartman until 2020, long after the
    lawsuit was filed by Conti. TPCG was added to the suit by Conti on October 22, 2018, and
    TPCG was served with Conti' s suit on November 8, 2018. Unfortunately, when TPCG was
    sued, its claim against Hartman and Mr. Monceaux was perempted and no longer existed.
    18
    

Document Info

Docket Number: 2022CA1249

Filed Date: 10/30/2023

Precedential Status: Precedential

Modified Date: 10/30/2023