Lamar Contractors, LLC Versus Srf Group Consulting, LLC ( 2023 )


Menu:
  • LAMAR CONTRACTORS, LLC                                 NO. 22-CA-212
    VERSUS                                                 FIFTH CIRCUIT
    SRF GROUP CONSULTING, LLC                              COURT OF APPEAL
    STATE OF LOUISIANA
    ON APPEAL FROM THE TWENTY-THIRD JUDICIAL DISTRICT COURT
    PARISH OF ST. JAMES, STATE OF LOUISIANA
    NO. 36,600, DIVISION "E"
    HONORABLE ALVIN TURNER, JR., JUDGE PRESIDING
    February 01, 2023
    JOHN J. MOLAISON, JR.
    JUDGE
    Panel composed of Judges Robert A. Chaisson,
    Stephen J. Windhorst, and John J. Molaison, Jr.
    REVERSED; REMANDED
    JJM
    RAC
    SJW
    COUNSEL FOR PLAINTIFF/APPELLEE,
    LAMAR CONTRACTORS, LLC
    Steven B. Loeb
    Jacob E. Roussel
    COUNSEL FOR DEFENDANT/APPELLANT,
    ST. JAMES PARISH
    Victor J. Franckiewicz, Jr.
    MOLAISON, J.
    The appellant, St. James Parish, seeks review of the trial court’s granting of
    a partial summary judgment which struck several of its reconventional demands
    brought against the appellee, Lamar Contractors, L.L.C. For the reasons that
    follow, the trial court’s ruling that granted Lamar’s motion for summary judgment
    on the issue of the Parish’s reconventional demands is reversed.
    FACTS AND PROCEDURAL HISTORY
    The basis of the underlying lawsuit pertains to the construction of a public
    recreation building (“the building”)1 owned by, and located within, St. James
    Parish (“the Parish”). On July 30, 2013, the Parish entered into a written contract2
    with Lamar Contractors, L.L.C. (“Lamar”) to serve as the general contractor for
    the project and to construct the building, which was designed by SRF Group
    Consulting, L.L.C. (“SRF”). Following a dispute over the design and
    specifications for the roof decking, Lamar stopped work on the project. On July
    15, 2015, pursuant to the general contract between the parties, Lamar filed a
    required “Notice of Termination.” Lamar then filed the underlying lawsuit, which
    later named the Parish in an amended petition.3 The Parish filed a reconventional
    demand against Lamar on January 19, 2016, alleging that Lamar had performed
    defective work and had breached the general contract in unilaterally deciding to
    stop work on the building.
    Lamar’s motion for a partial summary judgment on the Parish’s
    reconventional demands was held on December 6, 2021. In its judgment dated
    December 22, 2021, the trial court granted Lamar’s motion for partial summary
    1
    The record shows that the official name of the project was “St. James Parish District 5 Multi-
    Purpose Recreation Building Welcome Park.”
    2
    The contract used a pre-drafted form with the designation of “Document A101-2007.”
    3
    Lamar’s original petition and its amended petition have not been made part of the designated
    record on appeal.
    22-CA-212                                                 1
    judgment as to the Parish’s claims for “defective work” as “asserted in Paragraph
    36, Subparts (a) through (aa) of the Reconventional Demand,” and “reasserted in
    Paragraph 36, Subparts (a) through (z) and (bb) of the Amended Reconventional
    Demand.” The judgment also dismissed the Parish’s claim against Lamar for
    “stopping work and walking off the job.” This appeal followed.
    ASSIGNMENTS OF ERROR
    On appeal, the Parish assigns two errors:
    1. The trial court committed legal error in misconstruing the
    construction contract and applying the Article 15 claims procedure to the
    Parish’s reconventional demand without considering that article in context,
    and without applying the provisions of the contract as a whole.
    2. The trial court committed legal error by granting summary
    judgment when material facts remain in dispute.
    LAW AND ANALYSIS
    Standard of review
    Appellate courts review summary judgments de novo, using the same criteria
    that govern the trial court’s consideration of whether summary judgment is
    appropriate. Vill. Shopping Ctr. P'ship v. Kimble Dev., L.L.C., 18-740 (La. App. 5
    Cir. 4/24/19), 
    271 So.3d 376
    , 381; Lincoln v. Acadian Plumbing & Drain, LLC,
    17-684 (La. App. 5 Cir. 5/16/18), 
    247 So.3d 205
    , 209, writ denied, 18-1074 (La.
    10/15/18), 
    253 So.3d 1302
    . A motion for summary judgment is a procedural device
    used to avoid a full-scale trial when there is no genuine issue of material fact, and
    is favored and designed to secure the just, speedy, and inexpensive determination
    of every action. 
    Id.
     A motion for summary judgment shall be granted if the motion,
    memorandum, and supporting documents show that there is no genuine issue as to
    material fact and that the mover is entitled to judgment as a matter of law. La.
    C.C.P. art. 966. If only one conclusion could be reached by reasonable persons,
    summary judgment is appropriate, as there is no need for a trial on that issue. 
    Id.
    22-CA-212                                 2
    First assignment of error
    In its motion for partial summary judgment, Lamar argued that the
    Parish failed to preserve its reconventional claims in the manner mandated
    by the contract under Article 15.4 The relevant provisions that Lamar relied
    upon state:
    § 15.1.1 DEFINITION
    . . .
    A Claim is a written demand or assertion by one of the parties
    seeking, as a matter of right, payment of money, or other relief with
    respect to the terms of the Contract. The term "Claim" also includes
    other disputes and matters in question between the Owner and
    Contractor arising out of or relating to the Contract. The responsibility
    to substantiate Claims shall rest with the party making the Claim.
    Claims must be initiated by written notice. Verbal communications
    shall not constitute claims.
    § 15.1.2 NOTICE OF CLAIMS
    . . .
    Claims by either the Owner or Contractor must be initiated by
    written notice to the other party and to the Initial Decision Maker with
    a copy sent to the Architect, if the Architect is not serving as the
    Initial Decision Maker. Claims by either party must be initiated within
    21 days after occurrence of the event giving rise to such Claim or
    within 21 days after the claimant first recognizes the condition giving
    rise to the Claim, whichever is later.
    In its first assignment of error, the Parish contends that the trial court erred in
    finding that a failure to follow the procedures in Article 15 of the contract served
    as a bar to its reconventional demands.
    The interpretation of a contract’s provisions is typically a matter of law that
    may properly be decided on a motion for summary judgment. Hall v. Malone, 12-
    0264 (La. App. 4 Cir. 11/7/12), 
    104 So.3d 593
    , 596. In analyzing contracts, certain
    fundamental legal principles apply. According to the rules of construction, the
    4
    The only specific examples provided in the contract which pertain to notice are: 15.1.4- Claims
    for additional cost, and; 15.1.5- Claims for additional time.
    22-CA-212                                                3
    responsibility of the judiciary in interpreting contracts is to determine the parties’
    common intent. See, La. C.C. art. 2045. Courts begin their analysis of the parties’
    common intent by examining the words of the contract itself. See, La. C.C. art.
    2046. In ascertaining the common intent, words and phrases in a contract are to be
    construed using their plain, ordinary and generally prevailing meaning, unless the
    words have acquired a technical meaning, in which case the words must be
    ascribed their technical meaning. See, La. C.C. art. 2047.
    A contract is to be construed as a whole, and each provision in the contract
    must be interpreted in light of the other provisions. One provision of the contract
    should not be construed separately at the expense of disregarding other provisions.
    See, La. C.C. art. 2050. Neither should a contract be interpreted in an unreasonable
    or a strained manner so as to enlarge or to restrict its provisions beyond what is
    reasonably contemplated by its terms or so as to achieve an absurd conclusion.
    Edwards v. Daugherty, 03-2103 (La. 10/1/04), 
    883 So.2d 932
    , 941. Courts lack the
    authority to alter the terms of contracts under the guise of contractual interpretation
    when its provisions are couched in unambiguous terms. Cadwallader v. Allstate
    Insurance Co., 02-1637 (La. 6/27/03), 
    848 So.2d 577
    , 580. The rules of contractual
    interpretation simply do not authorize a perversion of the words or the exercise of
    inventive powers to create an ambiguity where none exists or the making of a new
    contract when the terms express with sufficient clarity the parties’ intent. Edwards,
    883 So.2d at 941.
    Lamar’s obligations created in the July 30, 2013 contract
    It is clear from the contract that Lamar’s overall obligation was to supply
    any work, labor and materials required to produce a “functionally complete
    project.”5 To further this goal, the contract outlines a process for identifying
    5
    Contract, Article 1, section 1.2.
    22-CA-212                                     4
    unsatisfactory work, through the use of a “punch list.”6 The contract states that the
    “Architect” is responsible for preparing a punch list to deliver to the owner, which
    in this case is the Parish.7 Identification of items on the punch list are not identified
    as “claims” in the contract. The final payment to Lamar, as the contractor, is
    conditioned upon its obligation to correct work under 12.2.2.8 A one year period
    for correction of work is provided to Lamar. 9 The contact provides that the Parish
    could terminate the contract if Lamar fails to timely complete the punch list.10
    Finally, section 3.20 contract states, in part, that “[t]he Contractor shall be liable to
    the Owner for all costs and/or damages that the Owner incurs as result of the
    Contractor’s failure to perform the Work…”
    The contract is clear on its face that the Parish has the right to redress in the
    event that Lamar’s work is deemed unsatisfactory, through the process described
    above. The contract also states that a failure by the Parish to use that process does
    not result in a waiver of those claims. As provided in section 13.4.2, “[N]o action
    or failure to act by the Owner, Architect or Contractor shall constitute a waiver of a
    right or duty afforded them under the Contract, nor shall such action or failure to
    act constitute approval of or acquiescence in a breach there under, except as may
    be specifically agreed in writing.” This would specifically apply to Lamar’s claim
    that the Parish waived its right to recover for a defect in Lamar’s workmanship.
    We would reach this same conclusion even if we were to find 15.1.2 applicable, as
    argued by Lamar. That section also does not specifically state that the Parish
    waives legal recourse otherwise provided under the contract11 by failing to give
    notice.
    6
    Contract, Article 3, section 3.4. The term “punch list” is not defined in the contract. In common
    usage, we understand the term to mean “[l]ists of jobs that have not been completed by a contractor before
    he is due to be paid,” as defined in the Black Law Dictionary 2nd Ed.
    7
    Contract, Article 5, section 5.1.8.
    8
    Contract, Article 5, section 5.2.1.
    9
    Contract, Article 12, section 12.2.2.
    10
    Contract, Article 14, section 14.2.1.
    11
    Contract, Section 3.20 correlates to La. C.C. art. 2769, which states:
    22-CA-212                                                 5
    The Parish’s obligation after Lamar’s termination of the contract
    The notice and remediation procedures detailed in the contract are logical in
    the context of a continuing construction project. The next question is what, if any,
    obligation the Parish had to report defects to Lamar once the contract was
    terminated.
    When Lamar terminated or ended the project, it also ended any obligations
    the Parish had except those which were provided for in the contract, which was to
    pay Lamar “for Work properly executed, including reasonable overhead and profit
    on that portion of the Work properly executed, installed, performed or completed.”
    The alleged defects are relevant, however, to show the Parish’s entitlement to a
    potential offset for the remaining payment left to Lamar after its termination of the
    contract. The Parish’s only recourse at that time was to assert these claims in
    district court, as per the Binding Dispute Resolution clause of 6.2.12
    The Parish’s reconventional demands are also permissible under La. C.C.P.
    art. 424, which states:
    A person who has a right to enforce an obligation also has a
    right to use his cause of action as a defense.
    Except as otherwise provided herein, a prescribed obligation
    arising under Louisiana law may be used as a defense if it is incidental
    to, or connected with, the obligation sought to be enforced by the
    plaintiff.
    Under this article, Louisiana courts have allowed reconventional demands to stand,
    even when they otherwise would have been prescribed, as long as they are
    incidental to, and directly connected with the obligation sought to be enforced.
    If an undertaker fails to do the work he has contracted to do, or if he does not execute it
    in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses
    that may ensue from his non-compliance with his contract.
    12
    Contract, Article 6, section 6.2 provides that an optional mediation between the parties is a
    precursor to litigation. In its brief, the Parish asserts that prior to the filing of its reconventional demand, all
    parties to Lamar’s lawsuit went through mediation and even sought the appointment of a special master to
    assist in re-starting construction.
    22-CA-212                                                     6
    Dixie Bldg. Materials Co., Inc. v. Bob L. Whittington & Associates, Inc., 
    588 So.2d 78
     (La.1991); Hennessey Const. Corp. v. Halpern, 06-1099 (La. App. 4 Cir.
    1/31/07), 
    952 So.2d 739
    , 741. In the instant case, because Lamar’s main demand
    pertains to the construction of a building, we find the Parish’s reconventional
    demands regarding defects in the work to be connected.
    In conclusion, upon de novo review, and construing the contract as a whole,
    we find that the trial court erred as a matter of law in finding that Article 15 could
    be used to preclude the Parish’s reconventional demand. We reverse the trial
    court’s granting of Lamar’s motion for summary judgment. As noted above, even
    if the Parish’s claims for damages were prescribed, La. C.C.P. art. 424 allows them
    to use these claims as a reconventional demand.
    Because we have granted relief on the Parish’s first assignment of error, we
    pretermit discussion on its second assignment as moot.
    CONCLUSION
    For the foregoing reasons, the trial court’s ruling that granted Lamar’s
    motion for summary judgment on the issue of the Parish’s reconventional demands
    is reversed. This matter is remanded for further proceedings consistent with this
    opinion.
    REVERSED; REMANDED
    22-CA-212                                  7
    SUSAN M. CHEHARDY                                                               CURTIS B. PURSELL
    CHIEF JUDGE                                                                     CLERK OF COURT
    SUSAN S. BUCHHOLZ
    FREDERICKA H. WICKER
    INTERIM CHIEF DEPUTY CLERK
    JUDE G. GRAVOIS
    MARC E. JOHNSON
    ROBERT A. CHAISSON                                                              LINDA M. WISEMAN
    STEPHEN J. WINDHORST
    FIRST DEPUTY CLERK
    HANS J. LILJEBERG
    JOHN J. MOLAISON, JR.                          FIFTH CIRCUIT
    MELISSA C. LEDET
    JUDGES                                 101 DERBIGNY STREET (70053)
    DIRECTOR OF CENTRAL STAFF
    POST OFFICE BOX 489
    GRETNA, LOUISIANA 70054                (504) 376-1400
    (504) 376-1498 FAX
    www.fifthcircuit.org
    NOTICE OF JUDGMENT AND CERTIFICATE OF DELIVERY
    I CERTIFY THAT A COPY OF THE OPINION IN THE BELOW-NUMBERED MATTER HAS BEEN DELIVERED
    IN ACCORDANCE WITH UNIFORM RULES - COURT OF APPEAL, RULE 2-16.4 AND 2-16.5 THIS DAY
    FEBRUARY 1, 2023 TO THE TRIAL JUDGE, CLERK OF COURT, COUNSEL OF RECORD AND ALL PARTIES
    NOT REPRESENTED BY COUNSEL, AS LISTED BELOW:
    22-CA-212
    E-NOTIFIED
    23RD JUDICIAL DISTRICT COURT (CLERK)
    HONORABLE ALVIN TURNER, JR. (DISTRICT JUDGE)
    STEVEN B. LOEB (APPELLEE)               VICTOR J. FRANCKIEWICZ, JR.      ELLIOT W. SCHARFENBERG (APPELLEE)
    (APPELLANT)
    MAILED
    DARREN A. PATIN (APPELLEE)              KEITH J. BERGERON (APPELLEE)     JACOB E. ROUSSEL (APPELLEE)
    ATTORNEY AT LAW                         TERRENCE L. BRENNAN (APPELLEE)   ATTORNEY AT LAW
    3445 NORTH CAUSEWAY BOULEVARD           ATTORNEYS AT LAW                 POST OFFICE BOX 3197
    SUITE 800                               755 MAGAZINE STREET              BATON ROUGE, LA 70821
    METAIRIE, LA 70002                      NEW ORLEANS, LA 70130
    

Document Info

Docket Number: 22-CA-212

Judges: Alvin Turner

Filed Date: 2/1/2023

Precedential Status: Precedential

Modified Date: 10/21/2024