Lamar Contractors, LLC Versus Srf Group Consulting, LLC ( 2023 )


Menu:
  • LAMAR CONTRACTORS, LLC                                 NO. 22-CA-213
    VERSUS                                                 FIFTH CIRCUIT
    SRF GROUP CONSULTING, LLC                              COURT OF APPEAL
    STATE OF LOUISIANA
    ON APPEAL FROM THE TWENTY-THIRD JUDICIAL DISTRICT COURT
    PARISH OF ST. JAMES, STATE OF LOUISIANA
    NO. 36,600, DIVISION "E"
    HONORABLE ALVIN TURNER, JR., JUDGE PRESIDING
    February 01, 2023
    JOHN J. MOLAISON, JR.
    JUDGE
    Panel composed of Judges Robert A. Chaisson,
    Stephen J. Windhorst, and John J. Molaison, Jr.
    REVERSED; REMANDED
    JJM
    RAC
    SJW
    COUNSEL FOR DEFENDANT/APPELLANT,
    ST. JAMES PARISH
    Victor J. Franckiewicz, Jr.
    COUNSEL FOR DEFENDANT/APPELLEE,
    TRAVELER’S CASUALTY AND SURETY COMPANY OF AMERICA
    Elliot W. Scharfenberg
    Audrey Martin
    MOLAISON, J.
    The appellant, St. James Parish, seeks review of the trial court’s judgment
    which granted the appellee, Travelers Casualty And Surety Company Of
    America’s, exception of peremption. For the reasons that follow, we reverse.
    FACTS AND PROCEDURAL HISTORY
    The basis of the underlying lawsuit pertains to the construction of a public
    building (“the building”) known as the St. James Parish District 5 Multi-Purpose
    Recreation Building Welcome Park, which is owned by, and located within, St.
    James Parish (“the Parish”). On July 30, 2013, the Parish entered into a written
    contract with Lamar Contractors, L.L.C. (“Lamar”) to serve as the general
    contractor and to construct the building, which was designed by SRF Group
    Consulting, LLC (“SRF”). Travelers Casualty And Surety Company Of America
    (“Travelers”) furnished a performance bond on July 30, 2013, naming the Parish as
    obligee and Lamar as principal. Following a dispute over the design and
    specifications for the roof decking, Lamar stopped work on the project. On July
    15, 2015, pursuant to the general contract between the parties, Lamar filed a
    “Notice of Termination.” Lamar then filed the underlying lawsuit, which later
    named the Parish in an amended petition. The Parish filed a reconventional
    demand against Lamar on January 19, 2016, alleging that Lamar’s work was
    defective, and that Lamar had breached the general contract in unilaterally deciding
    to stop work on the building. On June 18, 2021, the Parish amended its answer and
    reconventional demand to assert a third-party demand against Travelers.
    On September 27, 2021, Travelers filed an Exception of Peremption which
    argued that the Parish’s claim against it was untimely pursuant to La. R.S. 38:2189,
    as it was brought more than five years after Lamar had allegedly been placed in
    default of the construction contract. On February 7, 2022, a hearing on Travelers’
    22-CA-213                                1
    exception was held and, in a judgment dated February 21, 2022, the trial court
    granted the exception of peremption. This appeal followed.
    ASSIGNMENT OF ERROR
    In its sole assignment of error, St. James Parish argues that the district court
    committed legal error when it misapplied La. R.S. 38:2189 and granted Travelers’
    peremptory exception.
    LAW AND ANALYSIS
    Peremptive statutes are to be strictly construed against peremption and in
    favor of maintaining the claim. Rando v. Anco Insulations Inc., 08-1163 (La.
    5/22/09), 
    16 So.3d 1065
    , 1083. Of the possible constructions of a peremptive
    statute, the one that maintains the claim rather than the one that bars prosecution of
    the claim should be adopted. 
    Id.
     A party who raises an exception of peremption
    ordinarily bears the burden of proof at trial on the exception. Schonekas, Winsberg,
    Evans & McGoey, L.L.C. v. Cashman, 11-449 (La. App. 5 Cir. 12/28/11), 
    83 So.3d 154
    , 158. However, when peremption is evident on the face of the petition, the
    burden is on the plaintiff to prove that his action is not perempted. 
    Id.
    A judgment granting an exception of peremption is generally reviewed de
    novo, because the exception raises a legal question and involves the interpretation
    of a statute. Scott v. Zaheri, 14-0726 (La. App. 4 Cir. 12/3/14), 
    157 So.3d 779
    , 785.
    If evidence is introduced at the hearing on an exception of peremption, the trial
    court’s findings of fact are evaluated under the manifest error standard of review.
    Schonekas, Winsberg, Evans & McGoey, L.L.C. v. Cashman, 
    supra.
     If the trial
    court’s findings are reasonable in light of the record viewed in its entirety, an
    appellate court may not reverse, even if it is convinced that it would have weighed
    the evidence differently. 
    Id.
    22-CA-213                                  2
    Evidence introduced at the hearing
    The minute entry of October 7, 2021, indicates that the Parish
    offered, filed and introduced the following exhibits that were in its memorandum: a
    copy of Title 38, Chapter 10 of the “Louisiana Revised Statutes of 1950,” and; a
    “Notice of Default of Building Contract” dated December 6, 1994, between the
    State of Louisiana and a contractor, unrelated to this case. Travelers offered, filed
    and introduced Exhibits “A-E” attached to its brief; the Parish’s answer to the
    amended and supplemental petition for damages; the Parish’s amended answer and
    third party demand against Travelers; a copy of the performance bond between
    Lamar, the Parish, and Travelers; an email dated January 19, 2015 from the
    Parish’s counsel indicating that the Parish’s answer to Lamar’s petition would be
    filed that day, and; the General conditions of the Contract for Construction
    between the Parish and Lamar.
    Traveler’s performance bond
    In public works contracts exceeding $25,000, the Louisiana Public Works
    Act generally requires contractors to furnish two bonds: a performance bond and a
    payment bond. See, La. R.S. 38:2216; La. R.S. 38:2241.3. The performance bond
    must be furnished in all public works contracts “for the faithful performance of
    [the contractor’s] duties.” La. R.S. 38:2216(A)(1). This bond “exists for the benefit
    of the public authority and in essence creates a ‘privilege’ or a source of funds
    available to the State should it be successful in a suit against the general contractor
    and the surety under La. R.S. 38:2189.” Apex Bldg. Techs. Grp., Inc. v. Catco Gen.
    Contractors, L.L.C., 15-729 (La. App. 5 Cir. 3/30/16), 
    189 So.3d 1209
    , 1212-13.
    In the instant case, section one of the performance bond states that Travelers
    and Lamar share joint and several liability for performance of the construction
    contract. Section three of the bond specifies a procedure for notification of Lamar’s
    22-CA-213                                  3
    default to Travelers, after which Traveler’s obligation under the bond “shall arise.”
    Following the notification procedure of Lamar’s default, Travelers’ obligation then
    becomes one of several options under Section five of the performance bond, which
    include: arranging for Lamar to complete the construction contract (Section 5.1),
    completion of construction through an independent contractor (Section 5.2) or, to
    determine the amount of Traveler’s liability and pay that amount to the Parish
    (Section 5.4).
    La. R.S. 38:2189, the Public Works Act
    La. R.S. 38:2189 provides:
    Any action against the contractor on the contract or on the
    bond, or against the contractor or the surety or both on the bond
    furnished by the contractor, all in connection with the construction,
    alteration, or repair of any public works let by the state or any of its
    agencies, boards or subdivisions shall prescribe 5 years from the
    substantial completion, as defined in R.S. 38:2241.1, or acceptance of
    such work, whichever occurs first, or of notice of default of the
    contractor unless otherwise limited in this Chapter.
    As argued by Travelers, the resolution of whether the Parish’s claim against it is
    perempted is based on the third condition listed as a prerequisite to action against
    the surety, the “notice of default of the contractor.” Travelers asserts that the Parish
    gave notice of Lamar’s default when it filed its reconventional demand on January
    9, 2016. Travelers concludes that, contrary to the five-year limitation set forth in
    La. R.S. 38:2189, the Parish’s claim against it was not brought until June 18, 2021.
    Conversely, the Parish argues that the five-year time limitation never began to run
    because it had never provided formal notice of Lamar’s default.1
    The three triggers of peremption under La. R.S. 38:2189
    1
    In the alternative, the Parish contends that its January 2016 reconventional demand
    against Lamar preserved the Parish’s claims against Travelers, and that its June 2021 amended
    pleading, which brought the third-party demand against Travelers, relates back to its January
    2016 reconventional demand against Lamar. Because we resolve this appeal based upon the
    Parish’s primary argument, we pretermit any discussion of its alternative arguments.
    22-CA-213                                          4
    As seen above, La. R.S. 38:2189 identifies three events that begin the
    peremption period: substantial completion, acceptance of such work, or notice of
    default of the contractor. Both “substantial completion” and “acceptance” are
    terms defined in 38:2241.1, as follows:
    A. When any public entity enters into a written contract for the
    construction, alteration, or repair of any public works, in
    accordance with the provisions of R.S. 38:2241, the official
    representative of the public entity shall have recorded in the
    office of the recorder of mortgages, in the parish where the
    work has been done, an acceptance of such work or of any
    specified area of such work, not later than thirty calendar
    days after the date of completion or substantial completion
    of such work.
    B. “Substantial completion” is defined for the purpose of this
    Chapter, as the finishing of construction, in accordance with
    the contract documents as modified by any change orders
    agreed to by the parties, to the extent that the public entity
    can use or occupy the public works or use or occupy the
    specified area of the public works for the use for which it
    was intended. The recordation of an acceptance in
    accordance with the provisions of this Section upon
    substantial completion shall be effective as an acceptance
    for all purposes under this Chapter.
    C. Any public entity that does not file for recordation an
    acceptance of public work shall require the contractor to
    have recorded in the office of the recorder of mortgages, in
    the parish where the work has been done, an acceptance of
    such work or of any specified area of such work, not later
    than forty-five calendar days after the date of completion or
    substantial completion of the work.
    Thus, no requirements for the form of the contactor’s notice of default, nor
    specification on how the notice should be served and recorded, is provided for
    under the statute. The Parish asserts, however, that prior reported cases on similar
    issues demonstrate that the notice of default must be placed into the public record.
    See, Bd. of Sup'rs of Louisiana State Univ. v. Louisiana Agr. Fin. Auth., 07-0107
    (La. App. 1 Cir. 2/8/08), 
    984 So.2d 72
    , 76.
    22-CA-213                                 5
    In the instant case, Lamar filed a notice of termination of the contract and
    brought suit against the Parish. The limited record before us suggests that, after
    Lamar had filed suit, the parties were working toward a resolution of claims which
    included resuming work on the project. On this basis, it appears that trial on the
    matter was continued at least once. There is no evidence which demonstrates that
    the Parish considered Lamar to be in default of the contract prior to the
    reconventional demand, or that it formally declared Lamar’s default in any manner.
    Even the Parish’s reconventional demand against Lamar itself does not allege
    “default,” but instead pleads causes of action pursuant to a breach of contract. As
    stated in the reconventional demand:
    36. Lamar breached its contract for the Project by performing
    defective work . . .
    37. Lamar further breached its contract with the Parish by unilaterally
    stopping work and walking off the job. . .
    (Emphasis added.)
    In O & M Const., Inc. v. State, Div. of Admin., 
    576 So.2d 1030
    , 1037 (La.
    Ct. App.), writ denied, 
    581 So.2d 691
     (La. 1991), in which a public contractor
    brought suit against state seeking damages and the balance withheld on public
    building contract, the court acknowledged a distinction between a contractor’s
    passive breach of contract and placing a contractor “in default”:
    A contractor’s failure to complete a building contract within the time
    specified in the contract constitutes a passive breach, and a putting in
    default is a condition precedent to the recovery of liquidated damages
    for the contractor's delay in completion unless (1) by the terms of the
    contract a putting in default is waived, (2) by stipulation in the
    contract or by the nature and circumstances of the agreement time is
    of the essence thereof, or (3) a putting in default is excused by some
    act of the obligor which would render it a vain and useless thing.
    The performance bond’s requirements for the “contractor’s default”
    While La. R.S. 38:2241.1 is silent on the requirements of what constitutes a
    valid and actionable contractor’s default, this issue is squarely addressed in the
    22-CA-213                                 6
    July 30, 2013 performance bond between Travelers, Lamar, and the Parish. First,
    Section 14.3 of the performance bond defines “contractor’s default” as the
    “[f]ailure of the Contractor, which has not been remedied or waived, to perform
    or to otherwise comply with a material term of the Construction Contract.”
    [Emphasis added.] Here, Lamar unilaterally terminated the construction contract
    and stopped work on the project, obviously a condition that has not been remedied.
    Nor has the Parish specifically waived its rights against Lamar, and by extension,
    Travelers’ obligations to a remedy guaranteed by the performance bond. Thus,
    under the facts presented, the contractual definition of “contractor’s default” has
    been met.
    Under section 3 of the performance bond, three requirements were required
    to be met in order for Lamar to be put in default and for Travelers obligation under
    the bond to arise, if “there is no Owner default under the Construction Contract,”
    which applies in this case. In summary, the Parish needed to: 1) provide notice to
    both Lamar and Travelers that it “is considering declaring a Contractor Default,”
    which in turn gives Travelers the option to request a conference to discuss possible
    terms of settlement; 2) the Parish is required to “declare a Contractor Default,”
    “terminate the Construction Contract,” and notify the surety, and; 3) pay the
    balance of the “Contract Price” either to Travelers or “to a contractor selected to
    perform the Construction Contract.”
    Contracts have the effect of law upon the parties, and the courts are bound to
    give legal effect to all contracts according to the common intent of the parties. This
    intent is determined by the words of the contract when they are clear and explicit
    and lead to no absurd consequences. O & M Construction, Inc. v. State, Division of
    Administration, supra. The record before us does not show that the Parish has
    complied with any of these contractual requirements to place Lamar in default.
    22-CA-213                                 7
    Because the bond details the very specific procedure for placing Lamar in default
    and triggering Travelers obligations, and that procedure was not followed, we do
    not find that a simple allegation of a breach of contract in the Parish’s
    reconventional demand is sufficient to start the five-year peremptive period of La.
    R.S. 38:2189.2 Conversely, if as Travelers argues, the Parish had placed Lamar in
    default of the construction contract as required by the security bond, then Travelers
    would have been required to fulfill its obligations under the bond by way of one of
    the pre-determined remedies available. There is no evidence to demonstrate that
    Travelers has done so.
    We are mindful of the legislature’s intended public policy, as acknowledged
    by other courts, regarding the peremptive period of La. R.S. 38:2189. As explained
    by the supreme court in State Through Div. of Admin. v. McInnis Bros. Const., 97-
    0742 (La. 10/21/97), 
    701 So.2d 937
    , 946:
    A conclusion that La. R.S. 38:2189 is prescriptive, and thus
    susceptible of suspension, interruption and renunciation, abolishes the
    statute's clearly stated time limitation and substitutes for it an unknown date
    potentially very far in the future, thereby preventing the surety, from whom
    the general contractor must obtain a performance bond in order to contract
    with the State, from ever accurately calculating to any degree the length of
    its possible exposure under the statutory bond. It is self-evident that
    providing a certain time period for which the surety will be exposed to
    liability on the bond as well as reducing the length of exposure from up to 19
    years under La. C.C. arts. 2762 and 3500 to 5 years under La. R.S. 38:2189
    will result in reducing the cost of the bond, the contractor's bond expense,
    and thus the price paid by the State for the construction of the public work.
    An obvious purpose of public contract laws is to advance the interest of the
    taxpaying citizens of this state. Haughton Elevator Division v. State, 
    367 So.2d 1161
    , 1164 (La.1979).
    2
    In S. Const. Co. v. Hous. Auth. of City of Opelousas, 
    250 La. 569
    , 582, 
    197 So.2d 628
    ,
    633 (1967), the Louisiana Supreme Court rejected an argument that extraneous circumstances in a
    case “obviated the necessity” of formally putting a party to a public works contract in default. In
    Roy Anderson Corp. v. 225 Baronne Complex, L.L.C., 18-0962 (La. App. 4 Cir. 9/25/19), 
    280 So.3d 730
    , 744, which involved a performance bond for a private construction contract, the Court
    rejected an argument that being in default as a matter of law dispensed the requirement that
    formal notice of default be given before the surety’s obligations are triggered.
    22-CA-213                                            8
    Under the facts presented, we do not find this to be an instance where Travelers
    has been, or will be exposed to liability on the performance bond for an
    indeterminate amount of time. According to La. R.S. 38:2189 and the plain
    language contained in the bond itself, we cannot say after a de novo review of the
    record that Lamar was put into default sufficient to trigger the five-year peremptive
    period.
    CONCLUSION
    For the foregoing reasons, the trial court’s judgment granting Traveler’s
    exception of peremption is reversed. This matter is remanded for further
    proceedings consistent with this opinion.
    REVERSED; REMANDED
    22-CA-213                                   9
    SUSAN M. CHEHARDY                                                               CURTIS B. PURSELL
    CHIEF JUDGE                                                                     CLERK OF COURT
    SUSAN S. BUCHHOLZ
    FREDERICKA H. WICKER
    INTERIM CHIEF DEPUTY CLERK
    JUDE G. GRAVOIS
    MARC E. JOHNSON
    ROBERT A. CHAISSON                                                              LINDA M. WISEMAN
    STEPHEN J. WINDHORST
    FIRST DEPUTY CLERK
    HANS J. LILJEBERG
    JOHN J. MOLAISON, JR.                          FIFTH CIRCUIT
    MELISSA C. LEDET
    JUDGES                                 101 DERBIGNY STREET (70053)
    DIRECTOR OF CENTRAL STAFF
    POST OFFICE BOX 489
    GRETNA, LOUISIANA 70054                (504) 376-1400
    (504) 376-1498 FAX
    www.fifthcircuit.org
    NOTICE OF JUDGMENT AND CERTIFICATE OF DELIVERY
    I CERTIFY THAT A COPY OF THE OPINION IN THE BELOW-NUMBERED MATTER HAS BEEN DELIVERED
    IN ACCORDANCE WITH UNIFORM RULES - COURT OF APPEAL, RULE 2-16.4 AND 2-16.5 THIS DAY
    FEBRUARY 1, 2023 TO THE TRIAL JUDGE, CLERK OF COURT, COUNSEL OF RECORD AND ALL PARTIES
    NOT REPRESENTED BY COUNSEL, AS LISTED BELOW:
    22-CA-213
    E-NOTIFIED
    23RD JUDICIAL DISTRICT COURT (CLERK)
    HONORABLE ALVIN TURNER, JR. (DISTRICT JUDGE)
    STEVEN B. LOEB (APPELLEE)               VICTOR J. FRANCKIEWICZ, JR.      AUDREY MARTIN (APPELLEE)
    ELLIOT W. SCHARFENBERG (APPELLEE)       (APPELLANT)
    MAILED
    DARREN A. PATIN (APPELLEE)              KEITH J. BERGERON (APPELLEE)     JACOB E. ROUSSEL (APPELLEE)
    ATTORNEY AT LAW                         TERRENCE L. BRENNAN (APPELLEE)   ATTORNEY AT LAW
    3445 NORTH CAUSEWAY BOULEVARD           ATTORNEYS AT LAW                 POST OFFICE BOX 3197
    SUITE 800                               755 MAGAZINE STREET              BATON ROUGE, LA 70821
    METAIRIE, LA 70002                      NEW ORLEANS, LA 70130
    

Document Info

Docket Number: 22-CA-213

Judges: Alvin Turner

Filed Date: 2/1/2023

Precedential Status: Precedential

Modified Date: 10/21/2024