Stevens Construction & Design, L.L.C. v. St. Tammany Fire Protection District No. 1 ( 2020 )


Menu:
  •                                      STATE OF LOUISIANA
    COURT OF APPEAL
    FIRST CIRCUIT
    NO. 2019 CA 0955
    STEVENS CONSTRUCTION & DESIGN, L.L.C.
    VERSUS
    l
    ST. TAMMANY FIRE PROTECTION DISTRICT NO. 1
    M
    Judgment Rendered: '    JUL 0 8 2020
    On Appeal from the
    22nd Judicial District Court
    In and for the Parish of St. Tammany
    State of Louisiana
    Trial Court No. 2018- 14143
    Honorable Martin E. Coady, Judge Presiding
    Charles K. Chauvin              Attorney for Plaintiff A
    - ppellant,
    Jane Williams Chauvin           Stevens Construction & Design, L.L.C.
    Destrehan, LA
    Troy G. Ingram                  Attorney for Defendant -Appellee,
    Slidell, LA                     St. Tammany Fire Protection District No. 1
    Albert Dale Clary               Attorneys for Defendant/Intervenors- Appellees,
    Adrian G. Nadeau                Domain Architecture, APAC,
    J. Weston Clark                Greenleaf Lawson Architects, APAC, and
    Baton Rouge, LA                 Domain Architecture + Greenleaf Baton Rouge,
    Architects, A Joint Venture
    BEFORE: HIGGINBOTHAM, PENZATO, AND LANIER, JJ.
    L g          J
    HIGGINBOTHAM, J.
    In this mandamus proceeding, the contractor in a public works contract
    appeals the trial court judgment dismissing the contractor' s petition for a writ of
    mandamus and exceptions of improper joinder, no cause of action, and no right of
    action.
    FACTS AND PROCEDURAL HISTORY
    On May         11,   2017,   Stevens   Construction &    Design,   L.L.C. ( Stevens
    Construction)       entered into a public works contract with the St. Tammany Fire
    Protection District No. 1 ( Fire District), wherein Stevens Construction would serve
    as the general contractor for the construction of a new fire station and headquarters
    building located at 522 Robert Boulevard and 530 Robert Boulevard in Slidell,
    Louisiana (the construction contract). The total sum for the construction project was
    2, 845, 678. 00.     The architect for the project was a joint venture between two
    architectural firms, Domain Architecture, APAC ( Domain) and Greenleaf Lawson
    Architects, APAC ( collectively " the Architect").         The Architect entered into a
    separate contract with the Fire District to provide design services and administer the
    construction contract between the Fire District and Stevens Construction as the Fire
    District' s representative ( the architecture contract).       The Architect' s obligations
    included reviewing Stevens Construction' s pay applications, evaluating if the work
    was done in conformance with the construction contract, and certifying the
    applications to the Fire District for payment.
    The construction contract between the Fire District and Stevens Construction
    provided for completion of the project in 365 calendar days. Construction work on
    the project began on June 1, 2017, pursuant to a " Notice to Proceed" issued by the
    Fire District.      An additional 47 calendar days were added to the construction
    contract' s completion date pursuant to approved change orders, making July 18,
    W
    2018 the scheduled date of substantial completion. However, the project was not
    complete by that date.
    During construction, some of Stevens Construction' s pay applications on the
    project were not certified by the Architect, either in whole or in part, and payments
    were withheld from Stevens Construction.          Specifically, on April 9, 2018, the
    Architect issued a letter to Stevens Construction advising that " Pay Application No.
    9 will show a deducted amount of $24, 600. 44 in reference to K Barber Enterprises'
    claim of non-payment."       On August 15,     2018, by letter, the Architect informed
    Stevens Construction that it was deducting from Pay Application No. 13 in the
    amount    of $   161, 228. 78 for the following reasons: incomplete work, claims of
    nonpayment by third parties, and liquidated damages for being behind schedule. On
    August 22, 2018, Fire Chief Chris Kaufmann sent a letter to Stevens Construction
    and its surety by electronic and certified mail, summarizing his concerns with
    Stevens   Construction' s    performance   on    the   project   and   directing   Stevens
    Construction to stop work on the project by 4: 00 p.m. on August 23, 2018.           After
    Stevens Construction had been terminated, it submitted Pay Application No. 14. The
    Architect responded stating that under Section 14. 2. 3,         when the Fire District
    terminated the construction contract, Stevens Construction shall not be entitled to
    further payments until the work is finished. Thereafter, Stevens Construction also
    submitted Pay Applications Nos. 15 and 16 and neither application was certified for
    payment by the Architect.
    On August 23, 2018, Stevens Construction filed a verified petition for
    temporary restraining order, preliminary injunction, permanent injunction, and writ
    of mandamus contending that the Fire District improperly withheld payment on Pay
    Application No. 9.     Stevens Construction named the Fire District as the defendant.
    On August 24, 2018, the trial court signed a temporary restraining order, enjoining
    the Fire District from taking any further action to enforce the subject stop work order
    3
    or otherwise bar Stevens Construction from continuing to complete its work on the
    project.   On September 4, 2018, the Fire District issued a Notice of Termination to
    Stevens Construction detailing the reasons the Fire District found sufficient cause
    for terminating Stevens Construction.         Attached to the Notice of Termination was
    the Architect' s certification -of c- ause letter providing reasons why sufficient cause
    existed for terminating Stevens Construction.
    The trial court held a hearing on the preliminary injunction on September 4
    and 6, 2018. Following the hearing, the trial court found that Stevens Construction' s
    request for a preliminary injunction should be denied, and that its temporary
    restraining order should likewise be dissolved. Stevens Construction appealed this
    ruling, but the appeal was untimely and was dismissed.                 Stevens Construction &
    Design, L.L.C. v. St. Tammany Fire Protection District No. 1, 2018- 1759 ( La.
    App. 1 st Cir. 1/ 16/ 20), _   So. 3d , _.    As a result, the only issue that remained from
    the original petition was Stevens Construction' s request for a writ of mandamus
    compelling payment by the Fire District under La. R.S. 38: 2191.
    On September 5, 2018, Domain filed a petition for intervention stating that it
    has an interest in the action in order to fulfill its contractual obligations, enforce its
    contractual    rights,   and    participate   in        the   proceeding that   seeks   a judicial
    determination as to the performance of its contractual obligations.                       Stevens
    Construction answered Domain' s petition for intervention asserting a dilatory
    exception of improper joinder and a peremptory exception of no cause action. In the
    exceptions,
    Stevens Construction argued that Domain was not a party to the
    construction contract between Stevens Construction and the Fire District,                     and
    therefore had no community of interest with the Fire District. Stevens Construction
    also argued that Domain failed to state a justiciable cause between the parties that is
    related or connected to the facts in the principal demand.                  Thereafter, Stevens
    Construction filed two amended petitions contending that the Fire District also
    19
    improperly withheld payment on Pay Application Nos. 13,                      14, 15, and 16, and
    seeking a writ of mandamus to compel payment under Pay Application Nos. 9, 13,
    14, 15, and 16.
    Stevens Construction' s petition for writ of mandamus seeking payment under
    Pay Application Nos. 9, 13, 14, 15, and 16, and Stevens Construction' s exceptions
    of improper joiner and no cause of action came before the court for a hearing on
    January 3, 2019. Prior to addressing the mandamus action, the trial court orally ruled
    permitting Domain to intervene in the suit.
    After the hearing, the trial court allowed all parties to submit post -hearing
    memoranda. Prior to the trial court rendering a judgment, Stevens Construction filed
    a peremptory exception raising the objection of no right of action again contending
    that Domain had no interest in the matter because Domain did not introduce evidence
    of the joint venture or a separate contract with the Fire District. In response, Domain
    requested leave to file an amended petition with the sole purpose of adding to the
    petition   for   intervention,   Greenleaf Lawson Architects,               APAC    and    Domain
    Architecture + Greenleaf Architects, A Joint Venture as petitioners/ intervenors. On
    January 17, 2019, Stevens Construction requested permission to file an omnibus
    amended and restated petition for the purpose of removing all references to the
    Architect and limiting the focus of the suit to the Fire District.
    After a hearing on January 29,                  2019, the trial      court denied Stevens
    Construction' s exception of no right of action, allowed Domain' s leave to file its
    amended       petition   for   intervention   to       add   petitioners,   and   denied   Stevens
    Construction' s leave to file its post -trial omnibus amended petition.              On February
    11,   2019,   the trial court signed a judgment dismissing Stevens Construction' s
    petition for writ of mandamus and no right of action, and on February 26, 2019, the
    trial court signed a judgment denying Stevens Construction' s dilatory exception of
    improper joinder and peremptory exception of no cause of action.
    5
    It is from the February 11, 2019 judgment that Stevens Construction appeals.
    While Stevens Construction raised several assignments of error, its appeal raises
    primarily two main issues: ( 1)        Whether the intervention of Domain, who was not a
    party to the construction contract and was only one party to the joint venture, was
    proper, and ( 2)    Whether the trial court erred in dismissing Stevens Construction' s
    writ of mandamus.'
    LAW AND ANALYSIS
    I.       INTERVENTION
    Stevens Construction contends that Domain' s intervention in the proceeding
    was improper, and therefore any evidence presented by Domain at the mandamus
    hearing should be stricken from the record. Stevens Construction contends that
    because the Fire District did not call any witnesses or present any evidence, without
    the evidence presented by Domain, a reversal of the judgment denying its writ of
    mandamus is warranted.
    Louisiana Code of Civil Procedure article 1091 provides:
    A third person having an interest therein may intervene in a pending
    action to enforce a right related to or connected with the object of the
    pending action against one or more of the parties thereto by:
    1) Joining with plaintiff in demanding the same or similar relief against
    the defendant;
    2) Uniting with defendant in resisting the plaintiff' s demand; or
    3) Opposing both plaintiff and defendant.
    Article 1091 and the jurisprudence construing it establish that the requirement for
    intervention is two -fold: the intervenor must have a justiciable interest in, and a
    1 On appeal, the Fire District filed a peremptory exception raising the objection of no cause of
    action. In its exception, the Fire District contends that Stevens Construction' s petition fails to state
    a cause of action for mandamus under La. R.S. 38: 2191.    We find that accepting all well -pleaded
    allegations as true in Stevens Construction' s petition, the petition sufficiently states a cause of
    action pursuant to its contract with the Fire District and La. R. S. 38: 2191.       In its petition and
    amended petition, Stevens Construction alleged that it submitted pay requests to a public entity,
    the Fire District, the Fire District withheld its payments that were due under the contract, and the
    Fire District' s refusal to pay was in violation of public bid law.
    G
    connexity to, the principal action. Clark v. State, Dept. of Revenue, 2002- 0703
    La. App. 1st Cir. 5/ 9/ 03), 
    849 So. 2d 700
    , 705, writs denied, 2003- 1600, 2003- 
    1619 La. 10
    / 3/ 03), 
    855 So. 2d 320
    , 321.       A "justiciable interest" is defined as " the right
    of a party to seek redress or a remedy against either [ the] plaintiff or defendant in
    the original action or both, and where those parties have a real interest in opposing
    it."   Mike M. Marcello, Inc. v. Louisiana Gaming Control Board, 2004- 0488 ( La.
    App. 1st Cir. 5/ 6/ 05), 
    903 So. 2d 545
    , 548 ( quoting In re Succession of Walker,
    2002- 625 ( La. App. 5th Cir. 12/ 11/ 02), 
    836 So. 2d 274
    , 277.) The right, if it exists,
    must be so related or connected to the facts or object of the principal action that a
    judgment on the principal action will have a direct impact on the intervenor' s rights.
    
    Id.
        An intervenor takes the proceedings as he finds them and cannot change the
    issues between the parties or raise new ones.             IberiaBank v. Live Oak Circle
    Development, L.L.C., 2012- 1636 ( La. App. 1st Cir. 5/ 13/ 13), 
    118 So. 3d 27
    , 32.
    Stevens Construction' s petition for a writ of mandamus repeatedly alleged
    that the Architect failed to perform its obligations under the construction contract
    and architecture contract. The petition stated: "[ t]he Architect failed to comply with
    Section 9. 4. 1 of the [ construction] contract," " the Architect would not take action
    until six more days after the deadline," " the Architect failed to comply with the seven
    day deadline," and "[ Stevens Construction] has never received a notice of rejection
    of work from the Architect."
    Based on our review of this record, we find Domain clearly satisfied the two-
    part test for intervening in the pending litigation. Domain has a justiciable interest
    in the action as Stevens Construction was asking the trial court to make several
    factual findings regarding Domain' s performance under its contract with the Fire
    District,   as   well   as   under   sections   of the   construction   contract.   Domain' s
    intervention has sufficient connexity to the principal action as the defense of the
    Architect and the Fire District arise out of identical facts, and any judgment rendered
    7
    on the principal action would have a direct impact on Domain' s rights under its
    contract with the Fire District.      We find no error in the trial court' s decision to deny
    Stevens Construction' s exceptions of improper joinder and no cause of action.
    Additionally, we find no error in the trial court judgment denying Stevens
    Construction' s exception of no right of action,               or allowing Greenleaf Lawson
    Architects, APAC and Domain Architecture + Greenleaf Architects, A Joint Venture
    to be added as petitioners/ intervenors after the mandamus hearing.' The architecture
    contract lists the Architect as Domain Architecture + Greenleaf Architects, A Joint
    Venture, the joint venture' s letterhead is used throughout the record, and Stevens
    Construction in its original petition acknowledged that "[ a] t all times the Architect
    for the Project has been a joint venture between two architectural firms, Domain
    Architecture ...    and Greenleaf Lawson Architects."             Stevens Construction was not
    prejudiced by adding the additional intervenors after completion of the mandamus
    hearing.'
    II.     MANDAMUS
    We turn now to Stevens Construction' s contention that the trial court erred in
    denying its mandamus action under La. R.S. 38: 2191.               An appellate court reviews a
    2 A joint venture results from the undertaking by two or more persons to combine their efforts,
    knowledge, property or labor to engage in and carry out a single business venture for joint profit.
    Riddle v. Simmons, 
    589 So. 2d 89
    , 92 ( La. App. 2d Cir. 1991), writ denied, 
    592 So. 2d 1316
     ( La.
    1992). A joint venture is analogous to a partnership and controlled largely by the rules applicable
    to partnerships. There must be a sharing of the profits and losses with each party having some
    right of control over the business. The existence or non- existence of a joint venture is a question
    of fact and each case must be considered according to its circumstances. 
    Id.
     No formal or specific
    agreement is required.  Generally, the relationship may be formed by an oral agreement and the
    existence of a joint venture may be inferred from the conduct of the parties and other
    circumstances. 
    Id.
     We find no error in the trial court' s factual finding that Domain and Greenleaf
    entered into a valid joint venture.
    3 While Stevens Construction makes several creative arguments about the validity of Domain' s
    intervention, we addressed the arguments only briefly because, regardless of whether Domain or
    the Joint Venture had a right to intervene, the salient issue in this appeal is whether the trial court
    correctly determined that the Fire District should not be subject to mandamus under La. R.S.
    38: 2191. The evidence relied on by the trial court to conclude mandamus was not appropriate,
    including the contracts, the pay applications, and the letters sent by the Architect regarding pay
    application withholdings were introduced into the record by joint stipulation and not solely by
    Domain. Without the evidence presented by joint stipulation, Stevens Construction certainly
    would not have sufficient evidence to prove mandamus was appropriate in this case.
    8
    trial court' s judgment denying a writ of mandamus under an abuse of discretion
    standard.     Chaisson v. State, Department of Health &                       Hospitals through
    Registrar of Vital Records, 2017- 0642 (La. App. 4th Cir. 3/ 7/ 18), 
    239 So. 3d 1074
    ,
    1078, writ denied, 2018- 00540 ( La. 5/ 25/ 18), 
    243 So. 3d 567
    . "[ F] indings of fact in
    a mandamus proceeding are subject to a manifest error standard of review."                         
    Id.
    However, in prior appeals involving the interpretation of La. R.S. 38: 2191 relative
    to a money judgment a de novo standard of review is applicable because " the proper
    interpretation of a statute is necessarily a question on law." See Quality Design and
    Construction, Inc. v. City of Gonzales, 2013- 0752 (La. App. 1st Cir. 3/ 11/ 14), 
    146 So. 3d 567
    , 569- 570. 4
    The general mandamus article of the Louisiana Code of Civil Procedure
    defines mandamus as " a writ directing a public officer, a corporation or an officer
    thereof, or a limited liability company or a member or manager thereof, to perform
    any of the duties set forth in Articles 3863 and 3864."              La. Code Civ. P. art. 3861.
    A writ of mandamus may be directed to a public officer to compel the performance
    of a ministerial duty required by law, or to a former officer or his heirs to compel the
    delivery of the papers and effects of the office to his successor. La. Code Civ. P. art.
    3863.    A ministerial duty is " a simple, definite duty, arising under conditions
    admitted or proved to exist, and imposed by law." Hoag v. State, 2004- 857 ( La.
    4 Stevens Construction suggests that the trial court made legal error in its interpretation of La. R.S.
    38. 2191 and La. R.S. 38: 2248.    We reject Stevens Construction' s argument that under La. R.S.
    38: 2191 a public entity is not permitted to exercise any discretion in withholding payment upon
    receipt of a certified pay application and any contractual provision that allows for discretion is null
    and void. The Statute provides for mandamus to compel payment of sums due under the contract
    and does prohibit contractual provisions that allow the Architect to withhold a certificate for
    payment in whole or in part for reasons set forth in the contract.
    Further, we are not persuaded by Stevens Construction' s argument that the trial court failed
    to comply with La. R.S. 38: 2248( A) by withholding more than the 5% allowed by law. Louisiana
    Revised Statute 38: 2248 prohibits public works contracts from containing a provision withholding
    more than five percent of the contract price until the expiration of forty-five days after the
    recordation of the formal acceptance of such work, or notice of default by the contractor or
    subcontractor. By the plain terms of the statute, it disallows a contract provision allowing for more
    than 5% retainage. The contract herein contained no such provision allowing for more than 5%
    retainage.
    I
    12/ 1/ 04), 
    889 So. 2d 1019
    , 1024.   The critical element necessary for the issuance of
    mandamus is that " the public official to whom the writ is directed may exercise no
    element of discretion when complying."       
    Id.
       If a public officer is vested with any
    element of discretion, mandamus will not lie. 
    Id.
     Payments for public contracts are
    governed by Louisiana Revised Statutes Title 38, Chapter 10. Specifically, La. R.S.
    38: 2191 provides:
    A. All public entities shall promptly pay all obligations arising under
    public contracts when the obligations become due and payable under
    the contract.   All progressive stage payments and final payments shall
    be paid when they respectively become due and payable under the
    contract.
    B. ( 1)Any public entity failing to make any progressive stage payment
    within forty-five days following receipt of a certified request for
    payment by the public entity without reasonable cause shall be liable
    for reasonable attorney fees and interest charged at one- half percent
    accumulated daily, not to exceed fifteen percent. Any public entity
    failing to make any final payments after formal final acceptance and
    within forty- five days following receipt of a clear lien certificate by the
    public entity shall be liable for reasonable attorney fees and interest
    charged at one- half percent accumulated daily, not to exceed fifteen
    percent.
    2) Any interest received by the contractor pursuant to Paragraph ( 1) of
    this Subsection,   shall be disbursed on a prorated basis among the
    contractor and subcontractors, each receiving a prorated portion based
    on the principal amount due within ten business days of receipt of the
    interest.
    C. The provisions of this Section shall not be subject to waiver by
    contract.
    D. Any public entity failing to make any progressive stage payments
    arbitrarily or without reasonable cause, or any final payment when due
    as provided in this Section, shall be subject to mandamus to compel the
    payment of the sums due under the contract up to the amount of the
    appropriation made for the award and execution of the contract,
    including any authorized change orders.
    Subsection D of La. R.S.         38: 2191    sets forth two circumstances where
    mandamus relief is available against public entities: ( 1) when a public entity has
    failed to make progressive stage payments arbitrarily or without reasonable cause
    10
    under a contract; or ( 2) when a public entity had failed to tender a final payment
    when due under the contract.
    Thus, in order to be entitled to mandamus relief against the Fire District,
    Stevens Construction must establish that the Fire District " arbitrarily or without
    reasonable cause"    failed to make progressive stage payments or failed to make final
    payment "when due" under the contract. See State through Morrell v. City of New
    Orleans through Landrieu, 2017- 0110 ( La. App. 4th Cir. 12/ 21/ 17), 
    234 So. 3d 1071
    ,   1080, writ denied, 2018- 0116 ( La. 3/ 9/ 18), 
    237 So. 3d 1192
    , ( holding that
    plaintiff as the party seeking the writ of mandamus, has to establish that they were
    entitled to the relief provided by this extraordinary remedy). The public entity is not
    subject to mandamus compelling payment when the terms of the contract give the
    public entity discretion as to whether payment is due and payable. Mandamus relief
    under La. R. S. 38: 2191 is available only when there is no discretion left to the public
    entity as to whether payment is due and payable under the terms of the contract.
    Wallace C. Drennan, Inc. v. St. Charles Parish, 2016- 177 ( La. App. 5th Cir.
    9/ 22/ 16), 
    202 So. 3d 535
    , 544. "[   R] easonable cause" for nonpayment exists when
    the terms of the contract do not mandate payment under certain circumstances of the
    particular case.   
    Id.
    The following are relevant provisions from the construction contract,
    including the general conditions of the construction contract, that were relied on by
    the trial court to provide when payment is due and when a certificate for payment
    can be withheld:
    Section 5.2. 1 " Final payment constituting the entire unpaid balance of the Contract
    Sum, less retainage as set forth in Section 5. 1. 6, shall be made by the Owner to the
    Contractor when . 1 the Contractor has fully performed the Contract...; and
    2 a final Certificate for Payment has been issued by the Architect."
    Section 5. 2.2 provides in part: "[ t]he normal retainage shall not be due the contractor
    until after Substantial Completion and expiration of the forty-five day lien period
    11
    and submission to the Architect of a clear lien certificate, consent of surety and
    invoice for retainage."
    Section 9. 5. 1 " The Architect may withhold a Certificate for Payment in whole or in
    part, to the extent reasonably necessary to protect the Owner, if in the Architect' s
    opinion the representations to the Owner required by Section 9. 4.2 cannot be made."
    Also, Section 9. 5. 1 allows for the Architect to protect the owner from loss resulting
    from: ". 1 defective work not remedied; . 2 third party claims filed or reasonable
    evidence indicating probable filing of such claims unless security acceptable to the
    Owner is provided by the Contractor; . 3 failure of the Contractor to make payments
    properly to Subcontractors or for labor, materials, or equipment; . 4 reasonable
    evidence that the Work cannot be completed for the unpaid balance of the Contract
    Sum; . 5 damage to the Owner or separate contractor; . 6 reasonable evidence that the
    Work will not be completed within the Contract Time, and the unpaid balance would
    not be adequate to cover actual or liquidated damages for the anticipated delay; or
    7 repeated failure to carry out the work in accordance with the Contract
    Documents."
    Section 9. 4.2 provides that: "[ t]he issuance of a Certificate for Payment will
    constitute a representation by the Architect to the Owner, based on the Architect' s
    evaluation of the Work and the data comprising the Application for Payment that, to
    the best of the Architect' s knowledge, information, and belief, the Work has
    progressed to the point indicated and that the quality of the Work is in accordance
    with the Contract Documents."
    Section 14. 2. 3 provides: " when the Owner terminates the Contract for one of the
    reasons stated in Section 14. 2. 1 , the Contractor shall not be entitled to receive further
    payment until the Work is finished."
    After hearing the testimony and considering many documents related to
    Stevens Construction' s writ of mandamus, the trial court provided the following
    detailed reasons for its decision to deny Stevens Construction' s writ of mandamus
    under each pay application at issue.
    Pay Application No. 9
    In a letter, ...    Justin Greenleaf, one of the architects on the
    project,   notified [   Stevens Construction] that $ 24,600.44
    was being
    withheld from certification on pay application 9 because of a claim of
    nonpayment made by a third -party vendor... .
    Stevens Construction] submitted a " Claim" as set forth in the
    contract disputing the withholding from pay application 9.               The
    architect, in its contractual role as Initial Decision Maker (" IDM"),
    responded to and rejected [ Stevens Construction' s] claim, citing section
    9. 5. 1 of the General Conditions, which specifically authorizes the
    architect to withhold certification " to the extent reasonably necessary
    12
    to    protect   the   Owner... because            third party claims
    of ...                     filed   or
    reasonable evidence indicating probable filing of such a claim."
    Based on the evidence and contractual provisions, the Court
    finds that the $ 24, 600. 44 which was withheld from certification in pay
    application 9 was not " due and payable" under the terms of the contract,
    and the Fire District' s action in withholding payment of $24, 600.44 was
    not arbitrary or without reasonable cause under the circumstances.
    Footnote omitted.)
    Pay Application No. 135
    Stevens Construction] submitted a request for payment in the
    amount      of $ 451, 257. 48   in payment application 13...       The architect
    withheld $125, 299. 08 from the total requested due to a finding of
    incomplete work at the time of billing, claims of non-payment by a
    third -party, and liquidated damages. [ Stevens Construction] submitted
    a Claim objecting to the withholdings which was subsequently denied
    by the architect in its role as IDM. In the IDM ruling, the architect
    addressed each line item for which it withheld certification with reasons
    explaining each withholding, attaching photos of its observations at the
    project site.    A total of $ 89, 203. 45 was deducted from the pay
    application due to the architect' s finding of incomplete work at the time
    of billing. ( Footnotes omitted.)
    As to the withholding of $25, 625. 63 due to a claim of non-
    payment by ABC Supply, as noted previously, the General Conditions
    of the contract allow for withholdings due to " third party claims".
    Accordingly, the Court finds that the amounts withheld from
    certification in pay application 13 were not " due" under the terms of
    the contract, and therefore the Fire District was not arbitrary or without
    reasonable      cause    in   not   paying     those   amounts    withheld   from
    certification.
    Pay Application No. 14
    Stevens Construction] submitted pay application 14 on August
    31, 2018 which was never certified or paid. On August 24, 2018, the
    Fire District gave [ Stevens Construction]             seven days notice of its
    termination of the contract for Cause under Section 14. 2.2 of the
    General Conditions, and a Notice of Termination for cause letter was
    issued to [ Stevens Construction] on September 4, 2018. In a letter dated
    September 7, 2018 to [ Stevens Construction] the Architect asserts that
    pay application 14 could not be certified because section 14. 2. 3 of the
    5 In its reasons for finding that the amounts under Pay Application No. 13 were not due, the trial
    court thoroughly considered Stevens Construction' s argument that under the Woodrow Wilson
    decision, the Fire District cannot justify withholding payments based on a claim of liquidated
    damages for delay. We agree with the trial court' s conclusion that the Woodrow Wilson case,
    which considered liquidated damages when all express terms for final payment of a contract were
    met,   is    distinguishable from the circumstances     in this matter.   See Woodrow        Wilson
    Construction LLC v. Orleans Parish School Board, 2017- 0936 (La. App. 4th Cir. 4/ 18/ 18), 
    245 So. 3d 1
    , writ denied, 2018- 0971 ( La. 10/ 8/ 18), 
    253 So. 3d 793
    .
    13
    General Conditions of the contract provides that " when the owner
    terminates    the    contract   for   one     of   the    three   reasons           stated   in
    sectionl4. 2. 1,    the contractor shall not be entitled to receive further
    payment until the work is finished."         At the time pay application 14 was
    submitted, the work on the project was not finished, so pursuant to the
    contract the architect could not certify the release of any funds to the
    contractor.
    Accordingly, the Court finds that the amounts withheld
    from certification in pay application 14 were not " due" under the terms
    of the contract, and therefore the withholding of payment by the Fire
    District    under    the   circumstances       was       not   arbitrary       or    without
    reasonable cause.
    Pay Application No. 15
    In pay application 15, [ Stevens Construction] requested final
    payment of the remainder of the contract balance, less a five percent
    retainage. The Architect asserts that to receive final payment under the
    contract, the contractor must have fully performed the contract, and a
    final Certificate for Payment must be issued by the Architect.                          Other
    requirements        include   approval      and    acceptance      of      a    substantial
    completion certificate, formal final acceptance of the work, a receipt of
    clear lien and privilege certificate from the contractor, and various other
    requirements.       There was no evidence presented to support that these
    contractual requirements were met. ( Footnote omitted.)
    The evidence clearly establishes that the requirements for final
    payment were not met, therefore no ministerial duty arose. The Court
    also notes that under the circumstances, the Fire District had reasonable
    cause to withhold final payment.
    Pay Application No. 16
    In pay application 16, [ Stevens Construction] requested the
    142, 587.46 retainage amount that had been withheld during the
    contract.    Pursuant to section 5. 2. 2 of the agreement, retainage " shall
    not be due the contractor until after 1)                 substantial    completion,          2)
    expiration of the forty- five day lien period and submission to the
    Architect of a clear lien certificate, 3)
    consent of the surety, and 4)
    invoice for retainage."       The Court finds that none of the requirements
    for payment of retainage under the contract have been met. Therefore,
    there were no amounts due to be paid in pay application 16, and the Fire
    District had reasonable cause to withhold payment for the retainage
    payment in pay application 16. ( Footnote omitted.)
    In seeking a writ of mandamus, Stevens Construction had the burden of
    proving that the Fire District was arbitrary or without reasonable cause in not making
    progressive stage payments under the contract; or failed to tender final payment
    when due under the contract.        As pointed out by the trial court, the valid provisions
    14
    of the construction contract herein do not mandate payment under the circumstances
    presented in this case and allow for discretion in payment when the provisions of the
    contract    are not met.    The evidence submitted by joint stipulation included the
    construction contract, pay applications submitted by Stevens Construction, and
    letters from the Architect explaining the reasons for withholdings payment. In each
    withholding the Architect listed what provision of the contract it was considering to
    recommend that the payment not be made in whole or in part. After thorough review
    of the record, as well as the trial court' s extensive written reasons, we find no
    manifest error in the trial court' s finding that the Fire District was not arbitrary or
    without reasonable cause in not making progressive stage payments under the
    construction contract, or that the Fire District did not fail to tender final payment
    when due under the construction contract.           Accordingly, we find no abuse of
    discretion by the trial court in denying Stevens Construction' s writ of mandamus.
    CONCLUSION
    For the foregoing reasons, the judgment of the trial court is affirmed. All costs
    of the appeal are assessed to plaintiff-appellant, Stevens Construction &          Design,
    L.L. C.
    AFFIRMED.
    15
    

Document Info

Docket Number: 2019CA0955

Filed Date: 7/8/2020

Precedential Status: Precedential

Modified Date: 10/22/2024