Beverly Construction, L.L.C. v. Wadsworth Estates, L.L.C. ( 2020 )


Menu:
  •                            STATE OF LOUISIANA
    COURT OF APPEAL
    FIRST CIRCUIT
    NO. 2019 CA 0911
    BEVERLY CONSTRUCTION, L.L.C.
    VERSUS
    WADSWORTH ESTATES, L.L.C.
    Judgment Rendered.-
    endered.
    FEB 2 6 2020
    Appealed from the
    22nd Judicial District Court
    In and for the Parish of St. Tammany
    State of Louisiana
    Case No. 2014- 14476
    The Honorable Martin E. Coady, Judge Presiding
    Edward J. Castaing, Jr.                    Counsel for Defendant/Appellant
    Edward J. Lilly                            Wadsworth Estates, L.L.C.
    New Orleans, Louisiana
    Lloyd N. Shields                           Counsel for Plaintiff/Appellee
    Andrew G. Vicknair                         Beverly Construction Company,
    Ashley B. Robinson                         L.L.C.
    New Orleans, Louisiana
    BEFORE: McDONALD, THERIOT, AND CHUTZ, JJ.
    THERIOT, J.
    Wadsworth Estates, L.L.C.                  appeals the Twenty -Second Judicial District
    Court' s September 28,             2018 judgment granting Beverly Construction Company,
    L.L. C.' s peremptory exception of peremption, and the Twenty -Second Judicial
    District Court' s January 22, 2019 judgment denying Wadsworth Estates, L.L.C.' s
    motion for new trial.          For the following reasons, we affirm both judgments.
    FACTS AND PROCEDURAL HISTORY
    On July 14, 2006, Beverly Construction Company, L.L.C. (" Beverly"), as
    contractor, entered into a construction contract with Wadsworth Estates, L.L.C.
    Wadsworth"),          as   owner.       Pursuant to the contract, Beverly agreed to perform
    certain     work      for the      development           of     a    subdivision known         as   Wadsworth
    Subdivision, which was located in Covington, Louisiana.                             In June 2008, Beverly
    sent a request for payment to Wadsworth via an invoice dated May 30, 2008.
    According to Beverly, Wadsworth refused to pay Beverly for the work billed in the
    May 30, 2008 invoice. Beverly asserts that, in June 2008, it stopped work due to
    non-payment and never returned to the project.
    On November 25, 2008, Beverly filed suit against Wadsworth for breach of
    contract.'     Beverly and Wadsworth ultimately reached a settlement and executed a
    settlement agreement to end the litigation. As part of this settlement, Wadsworth
    executed and provided to Beverly a promissory note in the amount of $1, 971, 000,
    as well as a related mortgage securing the note.
    On October 9, 2014, Beverly filed a petition to enforce the promissory note
    and, alternatively, for modification of the settlement agreement. Beverly alleged
    that the promissory note,                and     thus,    the       mortgage,   were in default, because
    Wadsworth had failed to fully pay the note despite amicable demand. Beverly also
    claimed that Wadsworth had breached the settlement agreement.
    According to the parties, this lawsuit was filed in the Twenty -Second Judicial District Court and captioned Beverly
    Construction, L.L. C. v. Wadsworth Estates, L. L. C., case no. 2008- 16287.
    2
    On April 25,     2016, Beverly filed a first amended and restated petition to
    enforce the promissory note and, alternatively, for modification of the settlement
    agreement.      On August 1, 2016, Wadsworth filed an answer to Beverly' s petition
    and first amended petition.      Subsequently, Beverly filed a second amended and
    restated petition to enforce the promissory note and mortgage and for breach of the
    settlement agreement and mortgage.      On December 11, 2017, Wadsworth filed an
    answer to the second amended petition and a reconventional demand.              In the
    reconventional demand, Wadsworth alleged that it had contracted with Beverly to
    conduct land work, such as clearing and paving, on the land at issue.      Wadsworth
    asserted that it had paid Beverly for the services that were performed, but that
    Beverly went beyond the terms and scope of any contract and, against the express
    authorization and consent of Wadsworth,           dug and constructed two lakes of
    approximately eleven acres that were reserved for a later phase of construction that
    was not ready for commencement.           Thus, Wadsworth     sought damages from
    Beverly for the unauthorized construction of the lakes.
    On June 21,     2018, Beverly filed a peremptory exception of peremption in
    response   to     Wadsworth' s   reconventional    demand.   In   an     accompanying
    memorandum,        Beverly asserted that Wadsworth' s reconventional       demand   is
    subject to a five year peremptive period pursuant to La. R.S. 9: 2772.    According to
    Beverly, Wadsworth' s claim against Beverly for damages began when Wadsworth
    began occupying or possessing the property. Beverly provided three possible dates
    on which the five year peremptive period would have begun to run: ( 1)         in June
    2008 when Beverly left the project; ( 2) on November 25, 2008, when Beverly filed
    suit for non- payment; or ( 3) on August 17, 2011, when Wadsworth requested a
    change from residential to commercial zoning for the project.
    On September 28, 2018, the trial court signed a judgment granting Beverly' s
    exception of peremption and dismissing Wadsworth' s reconventional demand as
    3
    untimely. In oral reasons, the trial court explained that, even if Wadsworth had not
    started occupying the property once Beverly left the property, Wadsworth had
    certainly started occupying the property when Wadsworth filed for the zoning
    change in 2011.   Thus, the trial court found that the five year peremptive period
    had run.
    On October 11, 2018, Wadsworth filed a motion for new trial in response to
    the trial court' s judgment granting Beverly' s exception of peremption. On January
    22, 2019, the trial court signed a judgment denying Wadsworth' s motion for new
    trial. This appeal followed.
    ASSIGNMENTS OF ERROR
    Wadsworth assigns the following as error:
    1) The trial court erred in granting Beverly Construction, L.L.C.' s
    peremptory exception of peremption based upon a determination that
    the five year peremptive period provided for in La. R. S. 9: 2772
    commenced to run from August 17, 2011, when Wadsworth made a
    request to the St. Tammany Parish Planning Department for a Planned
    Unit Development " PUD" amendment for the Wadsworth Property.
    2) The trial court erred in denying Wadsworth' s motion for new trial,
    rejecting Wadsworth' s argument that it was not the developer of the
    Wadsworth Property authorized by the St. Tammany Parish
    Comprehensive Zoning Ordinance to make major amendments to the
    Wadsworth Property PUD.
    3) The trial court erred in denying Wadsworth' s motion for new trial,
    rejecting Wadsworth' s argument that it was enjoined by the 22nd
    Judicial District Court from proceeding with the unilateral application
    for the Wadsworth Property PUD, represented by the August 27, 2011
    letter.
    4) The trial court erred in denying Wadsworth' s motion for new trial,
    rejecting Wadsworth' s argument that it did not take the necessary
    steps to complete the submission for an amendment to the Wadsworth
    Property PUD.
    5) The trial court erred in denying Wadsworth' s motion for new trial,
    rejecting Wadsworth' s argument that Warren Treme did not have the
    authority to submit a proposed amendment to the Wadsworth Property
    PUD on behalf of Wadsworth.
    C!
    STANDARD OF REVIEW
    The objection of peremption is raised by the peremptory exception.                       La.
    Code Civ. P. art. 927( A)(2).         Ordinarily, the exceptor bears the burden of proof at
    the trial of the peremptory exception.             However, if peremption is evident on the
    face of the pleadings, the burden shifts to the plaintiff to show the action has
    not perempted.    Satterfield & Pontikes Construction, Inc. v. Breazeale Sachse &
    Wilson, LLP, 2015- 1355 ( La.          App.    1   Cir. 1/ 10/ 17);   
    212 So. 3d 554
    , 558,     writ
    denied, 2017- 0268 ( La. 3/ 31/ 17); 
    217 So. 3d 363
    .
    At a hearing on a peremptory exception of peremption pleaded prior to trial,
    evidence may be introduced to support or controvert the exception.                      Satterfield,
    
    212 So. 3d at 558
    ; see also La. Code Civ. P. art. 931.                In the absence of evidence,
    an exception of peremption must be decided upon the facts alleged in the petition
    with all of the allegations accepted as true. However, when evidence is introduced,
    the court is not bound to accept plaintiff' s allegations as true.                If evidence is
    introduced, the district court' s findings of fact are reviewed under the manifest
    error -clearly wrong standard of review. If those findings are reasonable in light of
    the record reviewed in its entirety, an appellate court cannot reverse even though
    convinced that had it been sitting as the trier of fact, it would have weighed the
    evidence differently. Lomont v. Bennett, 2014- 2483 ( La. 6/ 30/ 15);             
    172 So. 3d 620
    ,
    627.
    On review of a ruling on a motion for new trial, the applicable standard of
    review   is   whether   the   trial    court   abused     its   discretion.    Zavala    v. Dover
    Construction USA, LLC, 2017- 0001 ( La. App. 1 Cir. 4/ 11/ 18); 
    249 So. 3d 24
    , 28.
    DISCUSSION
    Assip-nment of Error # I
    In its first assignment of error, Wadsworth argues that the trial court erred in
    granting Beverly' s exception of peremption based upon its determination that the
    E
    five year peremptive period provided in La. R.S. 9: 2772 commenced to run from
    August 17, 2011,           when Wadsworth made a request to the St. Tammany Parish
    Planning Department for a PUD amendment for the property at issue. 2
    The parties do not dispute the applicability of La. R.S. 9: 2772, which states
    in pertinent part:
    A. Except         as otherwise provided in this                   Subsection,        no    action,
    whether      ex    contractu,      ex delicto,         or   otherwise,      including but not
    limited to an action for failure to warn, to recover on a contract, or to
    recover damages, or otherwise arising out of an engagement of
    planning, construction, design, or building immovable or movable
    property       which       may      include,       without      limitation,       consultation,
    planning, designs, drawings, specification, investigation, evaluation,
    measuring, or administration related to any building, construction,
    demolition, or work, shall be brought against any person performing
    or furnishing land surveying services, as such term is defined in R.S.
    37: 682, including but not limited to those services preparatory to
    construction, or against any person performing or furnishing the
    design,      planning,         supervision,            inspection,     or     observation        of
    construction or the construction of immovables, or improvement to
    immovable property, including but not limited to a residential building
    contractor as defined in R.S. 37: 2150. 1:
    1)( a) More than five years after the date of registry in the mortgage
    office of acceptance of the work by owner.
    b) If no such acceptance is recorded within six months from the date
    the owner has occupied or taken possession of the improvement, in
    whole or in part, more than five years after the improvement has been
    thus occupied by the owner. ( Emphasis added.)
    Accordingly, if an acceptance of the construction is recorded within six months of
    occupancy, the peremptive period begins on the date the acceptance is recorded; if
    no acceptance is recorded within six months of occupancy, the peremptive period
    begins on the date of occupancy.                   Bank v. Rayford, 2017- 1244 ( La. App. 1 Cir.
    3/ 29/ 18); 247 So -3d 733, 737.
    2
    Following the trial court' s judgment granting Beverly' s exception of peremption, Wadsworth filed a motion for
    new trial and produced several documents that had not previously been presented to the court. Later in this opinion,
    we find that the trial court did not abuse its discretion in denying Wadsworth' s motion for new trial. Thus, in
    reviewing this assignment of error, we only consider the exhibits that were before the trial court when it ruled on the
    exception of peremption.
    on
    The legislature established the peremptive period in La. R.S. 9: 2772 to
    protect "
    any person performing or furnishing the design, planning, supervision,
    inspection, or observation of construction or the construction of immovables" from
    liability for past construction projects, which could extend for an indefinite period
    of time.    To achieve this purpose, La. R. S. 9: 2772 establishes a definite time period
    from which the peremptive period starts to run, which is not dependent on the
    discovery of the defect.       Burkart v.       Willamson, 2009- 0294 ( La.     App.      1   Cir.
    11/ 13/ 09); 
    29 So. 3d 635
    , 639.
    Peremptive statutes are strictly construed against peremption and in favor of
    maintaining the claim.       Of the possible constructions, the one that maintains
    enforcement of the claim or action, rather than the one that bars enforcement,
    should be adopted. Rando v. Anco Insulations Inc., 2008- 1163 ( La. 5/ 22/ 09); 
    16 So. 3d 1065
    , 1083.     Peremption may not be renounced, interrupted, or suspended.
    La. Civ. Code art. 3461.
    Louisiana      jurisprudence    has       interpreted   the    wording   of   La.       R.S.
    9: 2772( A)( 1)( b) to mean possession or occupancy.           See Ebinger v. Venus Const.
    Corp., 2010- 2516 ( La. 7/ 1/ 11);   
    65 So. 3d 1279
    , 1284 ( stating that the peremptive
    period provided by La. R.S. 9: 2772 began when homeowners took possession of
    the house or filed an acceptance of the work); Kelleher v. Custom Homes by Jim
    Fussell, Inc., 2015- 1798 ( La.      App.   1    Cir. 6/ 3/ 16);    
    2016 WL 3127395
     at * 1
    unreported) (    noting that the plaintiffs took possession of or began to occupy the
    property at issue on a particular date); Lasseigne v. Schouest & Sons, Builders, 
    563 So. 2d 371
    , 373 ( La. App. 1    Cir. 1990) ( finding that La. R.S. 9: 2772' s peremptive
    period commenced to run from the time the plaintiffs occupied or took possession
    of their house).
    The Louisiana Civil Code distinguishes " possession" from " ownership."
    Goal Properties, Inc. v. Prestridge, 2015- 225 ( La. App. 3 Cir. 10/ 7/ 15);        
    177 So. 3d
                        7
    126, 128.       As La. Civ. Code art. 3421 states in relevant part, "[ p] ossession is the
    detention or enjoyment of a corporeal thing, movable or immovable, that one holds
    or exercises by himself or by another who keeps or exercises it in his name."
    Further, Black' s Law Dictionary defines " possession" in relevant part as "[ t]he fact
    of having or holding property in one' s power; the exercise of dominion over
    property."      Black' s Law Dictionary ( 1 lth ed. 2019). 3
    The Louisiana Civil Code defines occupancy only as it relates to corporeal
    movables.       See La. Civ. Code art. 3412.              However, Black' s Law Dictionary defines
    occupancy"     as "[   t]he act, state, or condition of holding, possessing, or residing in
    or on     something;          actual   possession,       residence,
    or tenancy, [ especially]             of   a
    dwelling or land." Black' s Law Dictionary further states that "[ i] n this sense, the
    term denotes whatever acts are done on the land to manifest a claim of exclusive
    control and to indicate to the public that the actor has appropriated the land."
    Black' s Law Dictionary ( 1 lth ed. 2019).
    In this case, there was no recordation of acceptance pursuant to La. R.S.
    9: 2772( A)( 1)(    a);    accordingly, the five year peremptive period began to run on the
    date that Wadsworth occupied or took possession of the property.                                  The pertinent
    dates in this case are as follows.                   On July 14, 2006, Beverly and Wadsworth
    entered into their construction contract, pertaining to the Wadsworth property at
    issue.    In June 2008, Beverly apparently stopped work due to non-payment and
    never returned to the project.               The parties do not dispute that on November 25,
    2008, Beverly filed suit against Wadsworth for breach of contract.                               On August 17,
    2011, Warren Treme, one of the two members of Wadsworth, sent a letter on
    behalf of Wadsworth to the St. Tammany Parish Planning Department, formally
    requesting a zoning change for the property at issue.                             On December 11,             2017,
    3
    By contrast, ownership is the right that confers on a person direct, immediate, and exclusive authority over a thing.
    The owner of a thing may use, enjoy, and dispose of it within the limits and under the conditions established by law.
    La. Civ. Code art. 477( A).
    Wadsworth filed its reconventional demand seeking damages from Beverly for the
    unauthorized construction of the lakes.       Accordingly, if Wadsworth occupied or
    possessed the property at issue ( and thus, its improvements) prior to December 11,
    2012, which is five years before Wadsworth filed its reconventional demand, then
    Wadsworth' s reconventional demand is perempted.
    The trial court determined that, at the latest, Wadsworth' s occupancy of the
    property at issue began on August 17, 2011, when Warren Treme sent the letter
    requesting a PUD amendment for the property.        This letter was sent from Warren
    Treme to Helen Lambert, the Assistant Director of the St.            Tammany Parish
    Planning Department. The letter stated in pertinent part:
    In relation to our recent meeting, this letter is to formally request a
    PUD    Amendment     for   the   Wadsworth    Property located at the
    northwest corner of the intersection of I- 12 and LA Hwy. 1088.
    Enclosed with this letter is the following information:
    1. A copy of the Exhibit "A" showing the proposed zoning district ...
    that we are proposing to change from the present PUD will be
    submitted within a few days.
    2. A copy of the approved PUD plan of the entire property with the
    legal description.
    3.   A copy of the 92 acre site and legal description owned by
    Wadsworth LLC.
    4. A check in the amount of $75. 00 for the application fee.
    We understand that as part of the PUD Amendment, we must comply
    with the design criteria requirements for landscaping, signage, lighting
    and parking. Therefore, we will comply with these requirements.
    The letter was signed by Warren Treme and the name, address, and phone number
    for Wadsworth was handwritten underneath Warren Treme' s name.
    Wadsworth' s attorney admitted during the August 29, 2018 hearing that
    Wadsworth had applied for a zoning change.           In seeking the zoning change,
    Wadsworth was exercising dominion over the property. The zoning change would
    have changed the purpose of the entire property, including the lakes dug by
    0
    Beverly. Accordingly, we find the trial court did not manifestly err in finding that
    Wadsworth occupied or possessed the property as of August 17, 2011, when
    Treme sent the letter. See Lomont, 
    172 So. 3d at 627
    . As such, Wadsworth' s claim
    was perempted when Wadsworth filed its reconventional demand on December 11,
    2017.    The trial court properly granted Beverly' s exception of peremption.         This
    assignment of error lacks merit.
    Assignments of Error #2, # 3, # 4, and # 5
    In its remaining assignments of error, Wadsworth argues that the trial court
    erred in denying its motion for new trial.        Wadsworth attached several documents
    to its memorandum in support of its motion for new trial, which it had not
    presented in its response to Beverly' s exception of peremption.      These documents
    included the affidavit of Ashton J. Ryan, Jr., the managing member of Wadsworth;
    an agreement to purchase and sell between The Azby Fund ( as                seller)   and
    Wadsworth ( as purchaser); the August        17, 2011 letter; a petition for preliminary
    injunction and permanent injunction filed by The Azby Fund, which sought to
    prevent Wadsworth from amending the property' s PUD; a September 29, 2011
    order from the trial court issuing a preliminary injunction enjoining Wadsworth
    from seeking an amendment to the property' s PUD; a judgment signed October 19,
    2011    granting The Azby Fund' s motion for preliminary injunction;           and     the
    affidavit of Warren Treme.
    Louisiana Code of Civil Procedure article 1972 provides:
    A new trial shall be granted, upon contradictory motion of any party,
    in the following cases:
    1)   When the verdict or judgment appears clearly contrary to the law
    and the evidence.
    2) When the party has discovered, since the trial, evidence important
    to the cause, which he could not, with due diligence, have obtained
    before or during the trial.
    10
    3)   When the jury was bribed or has behaved improperly so that
    impartial justice has not been done.
    Further, a new trial may be granted in any case if there is good ground therefor,
    except as otherwise provided by law.       La. Code Civ. P. art. 1973; see Horton v.
    Mayeaux, 2005- 1704 ( La. 5/ 30/ 06); 
    931 So. 2d 338
    , 345.
    Louisiana    Code    of Civil   Procedure   article   1972( 2)   pertains to newly
    discovered evidence.      When a motion for new trial is based on the grounds of
    newly discovered evidence, the motion should be granted when such evidence: ( 1)
    is not merely cumulative; ( 2) would tend to change the result of the case; and ( 3)
    was newly discovered after trial, and could not, with due diligence, have been
    obtained before or during trial. In re Succession of McLean, 2009- 1851 ( La. App.
    1 Cir. 6/ 11/ 10); 
    2010 WL 2342752
    , at * 3 ( unreported).       Due diligence does not
    require that a party do all that is possible to discover the evidence; it requires that a
    party do all that is reasonable to lead to the discovery of the evidence.      Barker v.
    Rust Engineering Co., 
    428 So. 2d 391
    , 394 ( La. 1983).
    At the hearing on Wadsworth' s motion for new trial, Wadsworth' s attorney
    asked the court to revise the judgment " based on the new documents"           provided.
    However,    Wadsworth' s attorney does not dispute that the documents were
    available prior to trial court' s consideration of the exception of peremption.     The
    only documents that were new were the affidavits of Ashton Ryan, dated October
    10, 2018, and Warren Treme, dated October 11, 2018, both of which could have
    reasonably been obtained prior to the trial court' s hearing on the exception of
    peremption.    Accordingly, the evidence provided by Wadsworth does not warrant
    any of the grounds set forth in La. Code Civ. P. art. 1972.
    Although a new trial may be granted in any case if there is good ground
    therefor, Wadsworth has failed to provide any such grounds.        We have conducted a
    thorough review of the record before us and cannot say that the trial court abused
    11
    its discretion in denying the motion for new trial. See In re Succession ofMcLean,
    
    2010 WL 2342752
    , at * 3.   These assignments of error lack merit.
    DECREE
    For the above and foregoing reasons, the Twenty -Second Judicial District
    Court' s September 28,   2018 judgment granting Beverly Construction, L.L.C.' s
    peremptory exception of peremption is affirmed.      The Twenty -Second Judicial
    District Court' s January 22, 2019 judgment denying Wadsworth Estates, L.L.C.' s
    motion for new trial is also affirmed. Costs are assessed to Appellant, Wadsworth
    Estates, L.L. C.
    AFFIRMED.
    12
    

Document Info

Docket Number: 2019CA0911

Filed Date: 2/26/2020

Precedential Status: Precedential

Modified Date: 10/22/2024