Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC ( 2020 )


Menu:
  •                       NOT DESIGNATED FOR PUBLICATION
    STATE OF LOUISIANA
    COURT OF APPEAL
    FIRST CIRCUIT
    2018 CA 1528 and 2018 CW 1120
    t
    BOYKIN BROTHERS, LLC
    VERSUS
    LABORDE CONSTRUCTION INDUSTRIES, LLC, JOHN LABORDE,
    CATAMOUNT CONSTRUCTORS, INC., LMK BATON ROUGE
    CONSTRUCTION, LLC, AND THE STANDARD OF BATON ROUGE, LLC
    CONSOLIDATED WITH
    2018 CA 1529
    CATAMOUNT CONSTRUCTORS, INC.
    VERSUS
    LMK BATON ROUGE CONSTRUCTION, LLC AND
    THE STANDARD AT BATON ROUGE, LLC
    Judgment rendered '   JAN 2 1 2020
    On Appeal from the
    Nineteenth Judicial District Court
    In and for the Parish of East Baton Rouge
    State of Louisiana
    No. C637569 c/ w 639816, Sec. D
    The Honorable Janice Clark, Judge Presiding
    Russel W. Wray                                Attorneys for Plaintiff/Appellee
    Jacob A. Altmyer                              Boykin Brothers, LLC
    St. Francisville, Louisiana
    Jacob B. Huddleston                           Attorneys for Defendant/ Appellee
    Scott Edward Frazier                          Catamount Constructors, Inc.
    Baton Rouge, Louisiana
    James A. Hatch                                Attorneys for Intervenor/ Appellee
    Paul E. Mayeaux                                    Osman Construction, LLC
    Metairie, Louisiana
    Jeanne C. Comeaux                                  Attorneys for Defendant/ Appellee
    Druit G. Gremillion                                Laborde Constructions Industries,
    John T. Andrishok                                  LLC, and John Laborde
    Jordan L. Faircloth
    Baton Rouge, Louisiana
    Kelsey K. Funes                                   Attorneys for Defendant/Appellant # I
    Amanda W. Messa                                   Hanover Insurance Company
    H. Alston Johnson, III
    Baton Rouge, Louisiana
    Kelsey K. Funes                                    Attorneys for Defendant/Appellant 42
    Amanda W. Messa                                    LMK Baton Rouge Construction,
    H. Alston Johnson, III                             LLC
    Baton Rouge, Louisiana
    and
    Patrick Schwedler
    Athens, Georgia
    BEFORE: McDONALD, CRAIN,' AND HOLDRIDGE, JJ.
    I Justice Will Crain is serving as judge ad hoc by special appointment of the Louisiana Supreme
    Court.
    HOLDRIDGE, J.
    LMK Baton Rouge Construction, LLC ( LMK) and The Hanover Insurance
    Company ( Hanover) appeal a partial summary judgment entered in favor of
    Boykin Brothers, LLC (Boykin) in this action to enforce a lien perfected pursuant
    to the Louisiana Private Works Act ( PWA).       LMK also seeks supervisory review
    of the trial court' s denial of its motion for summary judgment. We reverse the trial
    court' s ruling granting the partial summary judgment.       We affirm the denial of
    LMK and Hanover' s motion for summary judgment and deny LMK' s writ
    application as moot.
    FACTUAL AND PROCEDURAL BACKGROUND
    In 2014, an apartment complex known as the Standard at Baton Rouge was
    constructed pursuant to the PWA ( herein referred to as " the Project").         LMK
    served as a contractor and later as the general contractor on the Project.       LMK
    entered into a subcontract with Catamount Constructors, Inc. ( Catamount)            to
    perform foundation work for the Project.       Laborde Construction Industries, LLC
    Laborde) entered into a subcontract with Catamount to furnish all labor, materials,
    tools,   and equipment necessary to furnish and install a complete " Driven Piles
    P] ackage" for the Project. Laborde solicited a quote from Boykin to fabricate and
    deliver concrete pilings, to be furnished by Boykin and incorporated by Laborde on
    the Project.   On or about March 14, 2014, Boykin issued a " Written Proposal" to
    Laborde, which set forth the price for the fabrication of 858 pieces of 14"    pilings,
    each measuring 65 linear feet, and 281 pieces of 18" pilings, each measuring 95
    linear feet.   The proposal sets forth separate delivery charges, with the 14" pilings
    charged a delivery fee of $2. 05 per linear foot and the 18" pilings charged at $ 7. 37
    per linear foot.   The Written Proposal was not signed by Boykin or Laborde.
    3
    On March 3, 2014, LMK and the owner of the project executed a Standard
    Form Agreement, pursuant to which, LMK became the general contractor on the
    project.   On July 21, 2014, Laborde' s subcontract with Catamount was assigned to
    LMK.
    Boykin was paid $ 1, 549, 230. 11 for its work on the Project.                 Payments to
    Boykin for its work on the Project were made by checks issued by Catamount to
    both Laborde and Boykin, which were endorsed by Laborde to Boykin.                         Boykin
    claimed that it had not been paid in full for the materials it furnished on the Project
    and   that $   589, 548. 99 remained unpaid for the amounts Boykin invoiced to
    Laborde.       On January 28, 2015, Boykin filed a " Lien Affidavit Statement of Claim
    and Privilege" with the East Baton Rouge Parish Recorder of Mortgages. Therein,
    Boykin asserted a privilege pursuant to the PWA for the amount of $589, 548. 99,
    together with interest at the legal rate, a recording fee of approximately $ 25. 00,
    and all other sums allowed by law for the materials. On February 20, 2015, LMK,
    as principal, and Hanover, LMK' s surety on the Project, filed a " Release of Lien
    Bond" with the East Baton Rouge Parish Clerk of Court in order to secure the
    cancellation of Boykin' s lien in the amount of $736, 936.24, representing 125% of
    the amount of the lien. The " Release of Lien Bond" was accepted by the Recorder
    of Mortgages, and Boykin' s lien was cancelled.2
    On March 4, 2015, Boykin filed this lawsuit against Laborde and its agent,
    John Laborde, Catamount, and LMK,3 asserting various claims for nonpayment of
    sums allegedly due to Boykin for the fabrication and delivery of concrete piles
    furnished on the Project.        As to LMK, Boykin asserted a claim under the PWA,
    Z On September 25, 2015, the owner of the Project filed a notice of termination or substantial
    completion of the Project.
    3 Boykin also sued the owner of the Project, but later dismissed it from the litigation.
    C!
    seeking the enforcement of its lien, along with other relief. Specifically, Boykin
    sought to recover $ 589, 548. 99    from LMK for the materials supplied, delivered,
    and incorporated into the Project which Laborde failed to pay Boykin, as well as
    115. 00 to record its lien.    Boykin asserted breach of contract and PWA claims
    against Laborde.
    In an amended and supplemental petition, Boykin added Hanover as a
    defendant in the litigation and also asserted breach of contract claims against LMK
    and Catamount.     Generally, as to LMK, Boykin claimed that: ( 1)        LMK promised
    to continue to pay Boykin until Boykin had been paid in full for its work on the
    Project and breached that agreement; ( 2) LMK assumed a contractual obligation in
    its contract with Catamount to make all payments on the Project by joint check to
    Boykin and Laborde and breached that agreement by issuing a check in August of
    2014 solely to Laborde; ( 3) alternatively, prevailing custom implied an obligation
    on LMK' s part to issue joint checks, or at the very least, imposed an obligation on
    LMK to give Boykin notice of the issuance of any check to Laborde alone, and
    LMK' s failure to do so constituted a breach of the obligation of good faith and fair
    dealing.
    On May 4,      2017,    Boykin filed a motion for partial summary judgment
    against LMK and Hanover ( sometimes collectively referred to as " LMK") in which
    it asked the trial court to determine those defendants'         liability under the PWA.
    Boykin claimed that it was beyond genuine dispute that the principal sum of
    589, 548. 99 remained unpaid to Boykin for amounts invoiced to Laborde for
    Boykin' s work on the Project.      It further asserted that of that principal sum, it is
    beyond genuine      dispute that $ 587, 317. 12 (   including delivery/ freight charges)
    represents   the   adjusted   principal   amount    remaining   unpaid   to   Boykin   and
    associated with the materials/ concrete piles that were delivered to the Project job
    R
    site (
    and presumably incorporated or consumed thereon),            and thus subject to
    protection under the PWA. Boykin maintained that the prices and expenses agreed
    to by Boykin and Laborde are not genuinely disputed. Boykin asked for summary
    judgment decreeing that LMK and Hanover are liable in solido for the sum of
    587, 317. 12, together with interest legally due, and the fees associated with the
    filing of its lien under the PWA.
    Boykin and LMK submitted considerable evidence in support of and in
    opposition to Boykin' s motion for partial summary judgment.              LMK urged that
    Boykin is not entitled to summary judgment on its claims because Boykin' s own
    evidence on the motion showed that there are factual disputes as to the price of and
    the number of piles delivered to the Project. Furthermore, LMK asserted, Boykin' s
    evidence of delivery of the piles to the job site, consisting of invoices and
    accounting documents produced by Boykin and not signed or certified by any
    party,    is not competent to sustain Boykin' s burden of proof on the summary
    judgment.     LMK also asserted that the arguments raised and the evidence offered
    in   opposition   to   Boykin' s   motion   defeated     Boykin' s   motion   for   summary
    judgment.
    On October 27, 2017, LMK filed a motion for summary judgment against
    Boykin.     Therein, it submitted that in November of 2014, LMK made a final
    payment on the job to Boykin and Laborde, and as a condition of that final
    payment, LMK required Boykin and Laborde to execute a final waiver and release
    Final Release)    of any claims they might have had regarding the Project.            LMK
    maintained that Laborde failed to timely remit payment to Boykin for all of the
    materials Boykin supplied to the Project.          LMK claimed it had already paid for the
    piles in question, and in this lawsuit, Boykin is attempting to force it to pay for
    some of those piles a second time.          LMK' s motion is predicated on the Final
    501
    Release,    signed by Boykin' s office manager, Linda Ball, on December 5, 2014.
    LMK also called into question Boykin' s ability to prove its contract claims.
    On October 12, 2017, a hearing was held on the cross motions for summary
    judgment.     During the hearing, Boykin addressed its objections to evidence offered
    by LMK in support of its motion for summary judgment; the court declined to rule
    on the objections at that time.   LMK' s motion for summary judgment was heard by
    the trial court on March 1, 2018. Both motions were taken under advisement. On
    March 5, 2018, the court held a settlement conference, and on June 12, 2018, the
    court issued a ruling by minute entry on the cross motions for summary judgment,
    granting Boykin' s motion and denying LMK' s motion.                 The court noted that
    voluminous      memoranda,    depositions,       and   affidavits   had   been   extensively
    reviewed, and that based on the exhibits and affidavits submitted by Boykin, no
    genuine issue of material fact existed " as it relate[ d] to the defendant herein having
    accepted the price and terms of the written proposal and that the parties and terms
    fall under the [ PWA]."    The court further concluded that the invoiced amounts ex
    contractu could be distinguished from the invoiced amounts under the PWA, and
    therefore, LMK and Hanover were solidarily liable to Boykin on Boykin' s PWA
    claim.     In denying LMK' s motion, the trial court found LMK failed to meet its
    evidentiary burden on the motion, citing the lack of authentic evidence of a
    compromise or release agreement executed by Boykin' s office manager and LMK.
    On June 29, 2018,   the trial court signed a judgment memorializing those
    rulings.
    The written judgment granted Boykin' s motion for summary judgment as
    prayed for and denied LMK' s and Hanover' s motion for summary judgment.                The
    judgment granted all of Boykin' s claims against Hanover, and decreed that LMK
    and Hanover were liable in solido to Boykin in the amount of $ 587, 317. 12,
    7
    together with all interest due and the fees associated with the filing of Boykin' s
    lien.
    On July 17, 2018, LMK and Hanover filed a motion to designate the June
    299 2018 money judgment as a final and appealable judgment under La. C. C. P. art.
    1915B.     The next day, the trial court issued an order designating the June 29, 2018
    judgment as final.           Two days later, Hanover filed a motion and order for a
    suspensive appeal seeking review of the judgment rendered in favor of Boykin.
    Therein, Hanover asserted that the June 29, 2018 judgment is final and appealable
    pursuant to La. C. C. P. art. 1915A as to Hanover because it granted all of Boykin' s
    claims against Hanover.         The trial court granted Hanover a suspensive appeal on
    August 13, 2018, and on August 17, 2018, Hanover posted a bond in the amount of
    6759466. 98.
    LMK sought supervisory writs from this court, seeking review of the trial
    court' s grant of the partial summary judgment in favor of Boykin and the denial of
    its motion for summary judgment.          The writ application was referred to this panel.
    Boykin Brothers, L.L.C. v. Laborde Construction Industries, L.L.C., 2018 CW
    1120 ( La. App. 1st Cir. 10/ 29/ 18)( unpublished writ action).
    LMK, Hanover, and Boykin filed a joint stipulation in connection with LMK
    and Hanover' s motion to designate the judgment as final for the purposes of an
    immediate appeal under La. C. C. P. art. 1915B. In an order signed on September 6,
    2018, the trial court designated the June 29, 2018 judgment as a final judgment for
    the     purposes   of   an    immediate   appeal   pursuant    to   La.   C. C. P.   art.    1915B.
    Thereafter, LMK filed an application for a suspensive appeal in which it sought to
    appeal the judgment pursuant to La. C. C. P.            art.   1915B as well as             all prior
    interlocutory rulings or other interlocutory judgments which were adverse to its
    interests.       The trial court granted LMK a suspensive appeal of the June 29, 2018
    judgment and other interlocutory rulings or judgments adverse to LMK.
    APPELLATE JURISDICTION
    Appellate courts have a duty to examine subject matter jurisdiction sua
    sponte, even when the parties do not raise the issue.                Fils v. Allstate Insurance
    Company, 2015- 0357 ( La. App. 1St Cir. 12/ 23/ 15), 
    186 So. 3d 152
    , 155.               A partial
    summary judgment may be rendered dispositive of a particular issue, theory of
    recovery, cause of action, or defense, in favor of one or more parties, even though
    the grant of the summary judgment does not dispose of the entire case as to that
    party or parties.           La. C. C. P.   art.   966E.   A partial summary judgment rendered
    pursuant to La. C. C. P.           art. 966E may be immediately appealed during ongoing
    litigation only if it has been properly designed as a final judgment by the trial
    court.        La. C. C.P.   art.   1915B; Fils, 
    186 So. 3d at 155
    .     However, a trial court' s
    certification of a partial judgment as final does not make the judgment immediately
    appealable, as that designation is not determinative of this court' s jurisdiction. 
    Id.
    WWOW1122 "
    A joint stipulation was filed by LMK, Hanover, and Boykin in connection
    with LMK and Hanover' s motion to designate the judgment as final for the
    purposes of an immediate appeal under La. C. C. P.                    art.   1915B.   The parties
    stipulated that:
    1.     The June 29, 2018 judgment granting Boykin' s motion for partial
    summary judgment against LMK and Hanover and denying LMK
    and Hanover' s motion for summary judgment holds LMK and
    Hanover liable in solido to Boykin in the amount of $587, 317. 12,
    together with all interest legally due and the fees associated with
    the filing of Boykin' s lien;
    2.     The June 29,        2018 judgment resolves all of Boykin' s claims
    against Hanover and the majority ( but not all) of Boykin' s claims,
    demands, issues, or theories against LMK;
    9
    3.   Hanover is a surety for LMK, the principal obligor, for the entire
    amount awarded to Boykin in the judgment;
    4. Hanover filed a motion for a suspensive appeal which was granted
    by the trial court and posted a suspensive appeal bond with the
    clerk of court in the amount set forth in the trial court' s order;
    5.   Because of their solidary liability and the suretyship relationship
    between them, LMK and Hanover share the same defenses to the
    claims set forth in Boykin' s motion for partial summary judgment
    making it judicially efficient for the court of appeal to consider the
    ruling against LMK in conjunction with its consideration of the
    ruling against Hanover in connection with Hanover' s appeal;
    6.   Because LMK and Hanover are solidarily liable for the amount
    awarded by the judgment to Boykin on its PWA claim, no further
    proceedings against LMK, in connection with that claim,                    are
    needed at the trial court level until the appellate court considers the
    suspensive appeal taken by Hanover;
    7.   There are no issues pending at the trial court level which will
    alleviate the need for appellate review of the judgment;
    8.   If the judgment' s effects against Hanover and LMK are considered
    simultaneously,   the   appellate    court   will   not   be   obligated    to
    consider these issues a second time once a final judgment is
    entered against LMK; and
    9.   There is no just reason to delay appellate consideration _of the
    judgment as it relates to LMK.
    In certifying the judgment as a final one as to LMK pursuant to La. C. C. P.
    art.   1915B, the trial court adopted the statements of fact, recited in the joint
    stipulations, as its reasons for the designation. The court noted that the judgment
    awarding $ 587, 317. 12, to Boykin against LMK is a partial judgment as to one or
    more but less than all of Boykin' s claims, demands, or theories against LMK and
    thus falls within the purview of La. C. C. P.         art.   1915B.    The trial court further
    found that there was no just reason to delay the review of the grant of summary
    judgment against LMK and the denial of LMK' s cross- motion for summary
    judgment.
    When, as here, an order designating a judgment as final for appeal purposes
    is accompanied by explicit reasons, this court must determine whether the trial
    court abused its discretion in certifying the judgment.            R. J. Messinger, Inc. v.
    Rosenblum, 2004- 1664 ( La. 3/ 2/ 05), 
    894 So. 2d 1113
    , 1122. We find no abuse of
    10
    the trial court' s designation of the judgment granting Boykin' s motion for partial
    summary judgment against LMK as an immediately appealable final judgment.
    That judgment had the effect of disposing of Boykin' s PWA claims in their
    entirety.    Boykin' s only remaining claims against LMK are based on contract
    theories and are separate and distinct from Boykin' s PWA claims.              Therefore, this
    court has appellate jurisdiction to review the trial court' s grant of Boykin' s motion
    for partial summary judgment on its PWA claims.
    DISCUSSION
    A motion for summary judgment is a procedural device used to avoid a full-
    scale trial when there is no genuine issue of material fact.            Jones v. Anderson,
    2016- 1361 ( La. App. 1st Cir. 6/ 29/ 17), 
    224 So. 3d 413
    , 417.         After an opportunity
    for adequate discovery, a motion for summary judgment shall be granted if the
    motion, memorandum, and supporting documents show that there is no genuine
    issue as to material fact and that the mover is entitled to judgment as a matter of
    law. La. C. C. P. art. 966A( 3).
    The burden of proof rests with the mover.            La. C. C. P. art. 9661)( 1).   On a
    motion for summary judgment, it must first be determined that the supporting
    documents presented by the moving party are sufficient to resolve all material
    issues of fact.     Neighbors Federal Credit Union v. Anderson, 2015- 1020 ( La.
    App. 1St Cir. 6/ 3/ 16),     
    196 So. 3d 727
    , 734.     In ruling on a motion for summary
    judgment, the trial court' s role is not to evaluate the evidence or determine the
    truth of the matter, but instead to determine whether there is a genuine issue of
    triable fact. 
    Id. at 735
    .
    Appellate courts review evidence de novo under the same criteria that
    govern      the   trial   court' s   determination   of   whether   summary judgment         is
    appropriate.      Jones, 
    224 So. 3d at 417
    .     This court must ask the same questions a
    11
    trial court does in determining whether summary judgment is appropriate: whether
    there is any genuine issue of material fact, and whether the mover is entitled to
    judgment     as   a   matter   of law.   The    applicable    substantive   law determines
    materiality; thus, whether a particular dispute is material can only be seen in light
    of the substantive law applicable to the case.          
    Id.
       A genuine issue is one as to
    which reasonable persons could disagree.            If reasonable persons could reach only
    one conclusion, there is no need for trial on that issue and summary judgment is
    appropriate.      Thompson v. Center for Pediatric and Adolescent Medicine,
    L.L.C., 2017- 1088 ( La. App. 1st Cir. 3/ 15/ 18), 
    244 So. 3d 441
    , 445, writ denied,
    2018- 0583 ( La. 6/ 1/ 18), 
    243 So. 3d 1062
    .
    The Louisiana Private Works Act
    The PWA was enacted to provide protections for contractors, laborers,
    materialmen,      and subcontractors engaged in construction and repair projects.
    Burdette v. Drushell, 2001- 2494 ( La. App. 1st Cir. 12/ 20/ 02), 
    837 So. 2d 54
    , 68,
    writ denied, 2003- 0682 ( La. 5/ 16/ 03),      
    843 So. 2d 1132
    . To that end, La. R. S.
    9: 4802 provides as follows:
    A.    The following persons have a claim against the owner and a claim
    against the contractor to secure payment of the following
    obligations arising out of the performance of work under the
    contract:
    3) Sellers, for the price of movables          sold to the contractor or a
    subcontractor that become component parts of the immovable, or
    are consumed at the site of the immovable, or are consumed in
    machinery or equipment used at the site of the immovable.
    The PWA, which is          in derogation of general contract law,           must be strictly
    construed.     Because Louisiana' s lien statutes are stricti juris, the plaintiff in a lien
    enforcement action must prove its claim by a " substantial preponderance" of the
    evidence.    R.L. Drywall, Inc. v. B& C Electric, Inc., 2013- 1592 ( La. App. 1 st Cir.
    12
    5/ 2/ 14)( unpublished) 
    2014 WL 3559390
     * 2;              Parish   Concrete, Inc.    v.   Fritz
    Culver, Inc., 
    399 So. 2d 694
    , 696 ( La. App. 1St Cir. 1981).
    In this case, the parties do not dispute that Boykin took the appropriate
    procedural steps to perfect its lien pursuant to the PWA.           The primary issue in this
    appeal is whether Boykin proved, as a matter of law, that it is entitled to recover
    the sum of $587, 317. 12, together with interest and fees associated with filing of its
    lien.
    In support of its motion, Boykin claimed it was undisputed that a " Written
    Proposal"   provided by Boykin to Laborde, which set forth the price                  for the
    fabrication and delivery of the concrete piles to the Project, along with other terms
    and conditions,      was accepted by Laborde.          According to Boykin, it fabricated,
    delivered, and invoiced all concrete pilings as agreed to by Laborde in accordance
    with its ordinary course of business and under the terms of the Written Proposal,
    which serves as the basis for its PWA claim. In support of its motion, Boykin filed
    the following documents: (          1)   LMK,        Catamount,    and Laborde' s discovery
    responses; (    2)   the
    deposition testimony of Christopher Yancy,           Catamount' s
    corporate      representative,   who     testified    regarding    Catamount   and    LMK' s
    relationship and who identified the LMK and Catamount subcontract; ( 3)                    the
    affidavits of. Michael David Boykin, Boykin' s Chief Operating Officer; Dustin
    Gaspard, a Boykin sales representative; Linda Ball, Boykin' s office manager
    responsible for generating invoices; Amy Kellogg, Boykin' s                 office employee
    responsible for generating production logs; Christopher Boykin, Boykin' s Chief
    Technology Officer; and Laurie Pinson, a paralegal at the law firm engaged by
    Boykin; ( 4)    an excerpt of the deposition testimony of David Boykin; and ( 5)
    documents generated by Boykin in connection with the Project.
    13
    Michael       David Boykin, Christopher Boykin, and Mr. Gaspard made
    various attestations regarding the agreement between Boykin and Laborde as to the
    price of the concrete pilings and other terms of the parties'      agreement.   Michael
    David Boykin and Mr. Gaspard stated that they issued a verbal quote on behalf of
    Boykin to Laborde for the fabrication and delivery of 14" and 18" concrete pilings
    for use on the Project.    They also made the following attestations:      On or before
    March 13, 2014,       Boykin was notified by Mr. Laborde that Laborde accepted
    Boykin' s verbal quote.       The verbal quote given to Laborde did not include
    mandatory police escorts for the delivery of the 18" piles.       However, the Written
    Proposal, provided to Laborde on March 14, 2014 by Boykin, did include a price
    for the delivery of the 18" piles that included the mandatory police escorts.       Mr.
    Boykin attested that shortly after the Written Proposal was transmitted to Laborde,
    he and Mr. Laborde had a discussion regarding the delivery price of the 18" piles,
    during which Mr. Boykin explained to Mr. Laborde that the delivery price included
    the price for police escorts, differing from the verbal quote, and that would be the
    rate Laborde would be charged for those piles if Laborde wanted to proceed. Both
    Mr. Boykin and Mr. Gaspard attested that Mr. Laborde accepted the price set forth
    in the Written Proposal for the freight, Laborde did not subsequently complain
    about the   price,   and Laborde did not express any further objection to them
    regarding the terms of the Written Proposal, including the provision for demurrage
    charges and interest.
    A copy of the Written Proposal was attached to the affidavits of Mr. Boykin
    and Mr. Gaspard.       This document sets forth a freight charge of $7. 37 per linear
    foot for the delivery of the 18"        concrete   pilings.   It further states that any
    demurrage incurred by the fault of others will be charged to the general contractor
    at a rate of $ 170. 00   per hour.   Finally, the document states that ``[ t]his proposal
    14
    when signed by the Seller and Buyer constitutes a binding contract[.]"             The
    Written Proposal was not signed by Boykin or Laborde.
    In its response to requests for admissions,      Laborde flatly denied having
    entered into a purchase order with Boykin pursuant to which Laborde would
    purchase piles according to the fabrication charges and delivery charges set forth
    therein.   Laborde stated that the written document provided to it by Boykin was not
    signed because it did not reflect the terms agreed upon by Mr. Laborde and Mr.
    Gaspard and/ or Mr. Boykin.        Specifically, Laborde claimed that the price for
    delivery of each 18" pile was $ 2 per linear foot more than the parties had agreed.
    Laborde also denied that the principal amount of $589, 548. 00 remained due to
    Boykin for concrete piles supplied to Laborde for use in the Project, noting that
    this balance represented charges that were not agreed upon by the parties, and
    further that it contained amounts that could be offset by Laborde' s claims against
    Boykin for failing to deliver the concrete pilings to the site where they were to be
    installed.   Laborde also denied that it had been paid in full by the general
    contractor for the concrete piles supplied by Boykin.
    Laborde claimed that in August of 2014, Boykin stopped delivering each
    pile to the location where it was to be driven,         as it had previously done in
    accordance with the parties'    agreement throughout the entire Project, and began
    delivering piles to the entrance of the Project site.   Laborde asserted that Boykin' s
    actions required Laborde to physically move each pile from the entrance of the
    Project site to the location where each pile was to be installed at its own expense,
    causing Laborde to incur at least $ 341, 331. 85 in additional expenses.      Laborde
    claimed that it submitted extra work orders to LMK for payment, resulting from
    LMK' s failure to maintain the Project site, which resulted in Boykin' s failure to
    deliver the piles to the installation site.   According to Laborde, despite assurances
    15
    from LMK that such additional charges would be paid, no additional payments
    were made to Laborde, and a balance exceeding $ 590, 000.00 remains to be paid by
    LMK to Laborde.     Laborde insisted that Boykin' s failure to deliver the piles to the
    proper location constituted a breach of its oral agreement with Laborde, entitling
    Laborde to offset these costs against the balance Boykin claims it is owed on the
    Project.
    The Boykin affiants made numerous statements regarding how Boykin
    invoiced Laborde for the concrete pilings furnished for the project.        According to
    the affiants, Boykin created and regularly updated a production log which served
    as a contemporaneous data compilation of the pilings fabricated and delivered for
    the Project, and that from this production logs, invoices were generated for the
    fabricated piles and for freight upon delivery.       The affiants made statements
    regarding the amounts invoiced to Laborde, the invoices that were paid by
    Laborde, those that were not paid by Laborde and the amounts owed on those
    invoices, including charges for demurrage or cancelled loads, and other charges
    identified by the affiants. According to Ms. Ball, the total amount of $589, 538. 99
    invoiced to Laborde remained unpaid and of that amount, $ 587, 317. 12 ( including
    freight and delivery) represented the principal unpaid amount associated with the
    materials/ piles delivered to the Project job site, and of that amount, $ 276, 323. 62
    represented the amount unpaid for piles, without freight, but including additional
    incorporated bars in the pilings, that had been delivered to the Project.
    In his deposition, David Boykin generally discussed Boykin' s charges and
    explained the nature of demurrage charges.     In her affidavit, Ms. Pinson identified
    documents she retrieved from the Clerk of Court' s Office that had been filed in
    connection with the Project and Boykin' s lien. Boykin' s voluminous documentary
    C
    evidence included its production log for the Project and numerous invoices
    generated therefrom.
    In opposition to Boykin' s motion, LMK argued that Boykin is not entitled to
    summary judgment on its claims because Boykin' s own evidence shows the
    existence of factual disputes as to the price and the quantity of the piles it delivered
    for the Project.   LMK traversed Boykin' s statement of undisputed material facts,
    specifically contesting Boykin' s claim that Mr. Laborde accepted the terms of the
    Written Proposal provided by Boykin to Laborde.              It pointed to   Laborde' s
    discovery responses indicating that Laborde did not pay the full amount of the
    purchase order because Boykin charged more than the agreed- upon price for the
    pilings.
    LMK also focused on Laborde' s discovery responses indicating that the
    Written Proposal did not reflect Boykin and Laborde' s agreement as to the price
    for the piles, as that written agreement set forth a price for the delivery of the 18"
    piles that was more than had been verbally agreed to by Laborde.
    LMK also insisted that any claims Boykin had for demurrage charges, or
    ancillary service charges, reflected in Boykin' s unpaid invoices, and based on
    Boykin' s purported written contract with Laborde,         are not recoverable by a
    supplier against a contractor under the PWA. LMK asserted that under the PWA,
    Boykin' s sole claim against LMK is for the price paid for the movables it delivered
    and the cost of delivering those movables, but only to the extent that the movables
    became component parts of the immovable property that is the object of the work.
    According to LMK, Boykin' s motion for summary judgment on its PWA claims
    was presented in the same manner as a suit for payment under the purported
    Boykin -Laborde contract, with Boykin seeking payments for invoices issues to
    LMK pursuant to the terms of that contract regardless of the PWA' s requirements.
    LMK urged that Boykin' s unpaid invoices do not reflect the relevant value of
    17
    Boykin' s PWA claim against LMK, as those invoices do not isolate the amounts
    recoverable under the PWA which are included in Boykin' s remaining unpaid
    invoices.   LMK further pointed out that the invoices for which Boykin is seeking
    payment clearly include charges for piles that were not delivered to the job site,
    were never incorporated into the immovable, and are not recoverable from LMK
    under the PWA.
    In opposition to the motion, the bulk of LMK' s evidence pertained to the
    issue of whether Boykin waived its claims against LMK.           LMK' s opposition
    evidence also includes the deposition testimony of Ms. Ball, who acknowledged
    that Boykin invoiced Laborde for freight charges when loads had been cancelled,
    then charged freight again when the load was delivered to the job site.     She also
    was questioned regarding an invoice charging Laborde for freight costs for the
    delivery of a broken pile back to the plant; Ms. Ball speculated it was broken at the
    job site because Boykin would not have charged Laborde for the return freight if
    Boykin was at fault for the broken pile.
    In its motion for summary judgment, LMK asserted that Boykin' s PWA
    claim is contrary to the clear and unambiguous terms of the Final Release signed
    by Boykin' s office manager.        LMK' s motion sought a judgment enforcing the
    terms of the Final Release and decreeing that Boykin waived and released all of the
    claims asserted against LMK in this matter.         In support thereof, LMK filed
    evidence of various individuals' understanding of that document along with some
    of the evidence it had offered in opposition to Boykin' s motion for summary
    judgment.    LMK also argued that Boykin could not meet its burden of proof on
    any of Boykin' s contract claims.
    To support its motion, Boykin took issue with LMK' s claim that Boykin
    failed to distinguish its contract claim against Laborde and its PWA claim against
    LMK.         Boykin insisted that it has, specifically and in great detail, distinguished its
    claim under the PWA versus its contract claim.           Evidence of such cited by Boykin
    includes the fact that the total amount Boykin invoiced to Laborde is $ 589, 548. 99,
    but Boykin is only seeking to recover $ 587, 317. 12 from LMK. Boykin asserted
    that the price differential reflects the fact that Boykin acknowledged that all but
    two of the piles associated with one of the invoices were delivered to the job site,
    and given that Boykin did not deliver these piles, payment for those two piles is
    not being sought in its PWA claim against LMK. Boykin claimed that it subtracted
    three " non- lienable amounts"       from the total amount invoiced to Laborde including:
    1) $   1, 823. 67 for the two piles on one of the invoices that were not delivered to the
    project; ( 2) $     141. 70 for two of the bars associated with an invoice that were not
    delivered to the site; and ( 3) a charge of $266. 50 reflected on Invoice NO. 17905 -
    IN.
    Boykin also urged that its demurrage charges are secured under the PWA on
    the basis that such charges were agreed to by Laborde in the Written Proposal and
    thus represent amounts owed to Boykin by Laborde for the cost of delivering the
    movables that became part of the immovable.            This rationale, Boykin posited, also
    applies to the cancel load expenses incurred by Boykin and owed by Laborde.4
    In defending the trial court' s grant of the partial summary judgment in its
    favor, Boykin insists that it is not genuinely disputed that Laborde accepted the
    price and terms of the Written Proposal.               Boykin maintains that with great
    precision, it meticulously segregated and detailed its PWA claim, distinguishing its
    contract claims against Laborde from the amounts secured under the PWA, and
    made a prima facie showing of its PWA claim. Boykin claims that it met its
    4
    Additionally, Boykin objected to numerous exhibits offered by LMK in support of LMK' s
    motion for summary judgment and argued that LMK failed to meet its burden of proving that
    Boykin entered into a compromise with LMK so as to defeat Boykin' s lien enforcement action
    against LMK.
    19
    burden of proof to establish that no genuine issue of material fact remained for trial
    and it is entitled to judgment as a matter of law.
    We disagree.    Instead, we find that there are numerous genuine issues of
    material fact in dispute which precluded the entry of summary judgment in favor of
    Boykin on its PWA claim. As a supplier to the Project, Boykin' s PWA lien rights
    are limited to the " price of movables" sold to Laborde which " become component
    parts of the immovable, or are consumed at the site of the immovable...."         La.
    R. S. 9: 4802A( 3).   It is evident that Boykin' s PWA claim is predicated on the
    enforceability of the terms of the Written Proposal, as Boykin is seeking to recover
    from LMK unpaid amounts it invoiced to Laborde pursuant to the price and the
    terms set forth in in the Written Proposal. However, Boykin' s own evidence calls
    into question the enforceability of the very agreement upon which Boykin' s PWA
    claim against LMK is based. This evidence showed that the Written Proposal was
    never signed by Boykin and Laborde and that Laborde refused to sign that
    document because it did not reflect the terms previously allegedly verbally agreed
    to by the parties regarding the delivery price of the 18" piles.   Further, Boykin' s
    evidence showed that Laborde did not agree with other terms of the Written
    Proposal, such as demurrage charges, which clearly form part of Boykin' s PWA
    claim against LMK.
    Because the price Laborde agreed to pay Boykin for furnishing and
    delivering the concrete piles to Laborde for use on the Project is disputed, the trial
    court erred in granting partial summary judgment to Boykin on its PWA claim
    against LMK.      Clearly, as reflected by Laborde' s discovery responses, there are
    numerous genuine issues of material fact regarding the actual amount owed to
    Boykin by Laborde, and thus, the amount owed by LMK to Boykin for Boykin' s
    20
    work on the Project.     Accordingly, the partial summary judgment entered in favor
    of Boykin on its PWA claim is hereby reversed.
    LMK and HANOVER' S APPEAL                  OF THE JUDGMENT DENYING                    THEIR
    MOTIONFOR SUMMARYJUDGMENT
    The trial court certified the judgment denying LMK and Hanover' s motion
    for summary judgment as a final appealable judgment pursuant to La. C. C.P. art.
    1915B.    The trial court clearly erred in so doing.               The denial of a motion for
    summary judgment is an interlocutory judgment that is not appealable and cannot
    be certified as such.      Ascension School Employees Credit Union v. Provost
    Salter Harper &        Alford, L.L.C., 2006- 0992 ( La. App. 1St Cir. 3/ 23/ 07), 960
    1st
    So. 2d 939, 940; Belanger v. Gabriel Chemicals, Inc., 2000- 0747 ( La. App.
    Cir. 5/ 23/ 01),   
    787 So. 2d 559
    , 563, writ denied, 2001- 2289 ( La. 11/ 16/ 01),       
    802 So. 2d 612
    .    Therefore, this court lacks appellate jurisdiction under La. C. C. P. art.
    1915B to review this ruling.
    However, when an unrestricted appeal is taken from a final judgment, the
    appellant is entitled to seek review of all                 adverse interlocutory judgments
    prejudicial to him, in addition to the review of the final judgment.               Judson v.
    Davis, 2004- 1699 ( La.      App.   1St Cir. 6/ 29/ 05),    
    916 So. 2d 1106
    , 1112- 13,   writ
    denied, 2005- 1998 ( La. 2/ 10/ 06),      
    924 So. 2d 167
    .     Pursuant to this general
    principle,   we shall consider LMK and Hanover' s argument that the trial court
    erroneously denied their motion for summary judgment. See Fonseca v. City Air
    of Louisiana, LLC, 2015- 1848 ( La. App. 1St Cir. 6/ 3/ 16), 
    196 So. 3d 82
    , 85 fn.3.
    In their cross motion for summary judgment, LMK and Hanover argued that
    Boykin waived and released all of its liens and claims against LMK pursuant to the
    terms of a " Final Release"   signed by Boykin' s office manager. According to LMK
    and Hanover, the terms of the release must be enforced as written because the
    21
    language is unambiguous and because Boykin' s office manager had authority to
    bind Boykin to that agreement.        However, after a thorough review of the relied -
    upon document and all of the evidence submitted in connection with LMK and
    Hanover' s motion for summary judgment, we find that there are numerous
    disputed factual issues which must be resolved before it can be determined that
    Boykin in fact waived all of the claims asserted in this litigation. The presence of
    these disputed factual issues preclude the entry of summary judgment in favor of
    LMK and Hanover, and the trial court correctly denied their motion for summary
    judgment.'
    CONCLUSION
    The June 29, 2018 judgment is reversed insofar as it granted the motion for
    partial    summary judgment in favor of Boykin Brothers,                 LLC     on   its   lien
    enforcement claim pursuant to the Private Works Act.              In all other respects, the
    judgment is affirmed.       LMK Baton Rouge Construction, LLC' s application for
    supervisory writs is denied as moot.           The case is remanded for proceedings
    consistent with this opinion.
    All costs of this appeal are assessed equally to
    Boykin Brothers, LLC, LMK Baton Rouge Construction LLC, and The Hanover
    Insurance Company.
    REVERSED IN PART AND AFFIRMED IN PART; WRIT DENIED.
    S LMK filed an application for supervisory writs with this court, seeking supervisory review of
    the trial court' s denial of its motion for summary judgment. Boykin Brothers, L.L. C. v.
    Laborde Construction Industries, L.L.C., 2018CW1120. We deny the writ application as
    moot.
    22
    

Document Info

Docket Number: 2018CA1528, 2018CA1529

Filed Date: 1/21/2020

Precedential Status: Precedential

Modified Date: 10/22/2024