Stevens Construction & Design, L.L.C. v. St. Tammany Fire Protection District No. 1 ( 2020 )


Menu:
  •                                STATE OF LOUISIANA
    COURT OF APPEAL
    FIRST CIRCUIT
    2019 CA 0431
    2018 CW 1759 and 2019 CW 0642
    STEVENS CONSTRUCTION & DESIGN, L.L.C.
    VERSUS
    ST. TAMMANY FIRE PROTECTION DISTRICT NO. 1
    Judgment Rendered:            WU 1 6 2020
    Appealed from the
    22nd Judicial District Court
    In and for the Parish of St. Tammany
    State of Louisiana
    Docket Number 2018- 14143
    Honorable Martin E. Coady, Judge Presiding
    Charles K. Chauvin                          Counsel for Plaintiff/Appellant
    Destrehan, LA                               Stevens Construction & Design,
    L.L.C.
    Troy G. Ingram                              Counsel for Defendant/Appellee
    Slidell, LA                                 St.   Tammany            Fire       Protection
    District No. 1
    Albert Dale Clary                           Counsel for Intervenor/Appellee
    Adrian G. Nadeau                            Domain Architecture, APAC,
    J. Weston Clark                             Greenleaf Lawson Architects,
    Baton Rouge, LA                            APAC, and Domain Architecture +
    Greenleaf Baton Rouge, Architects,
    A Joint Venture
    BEFORE: WHIPPLE, C. J., GUIDRY, McDONALD, McCLENDON,
    WELCH,          GINBOTHAM, CRAIN ' THERIOT, HOLDRIDGE, CHUTZ,
    PENZATO, AND LANIER, JJ.
    Justice Will Crain is serving as judge
    ad hoc by special appointment of the
    Louisiana Supreme Court.
    4#WA      A-.
    WHIPPLE, C.J.
    Plaintiff, Stevens Construction & Design, L.L.C., appeals a judgment of the
    district court denying its petition for a preliminary injunction. For the following
    reasons, we dismiss the appeal and decline to consider the related writ applications,
    2018 CW 1759 and 2019 CW 0642, which were referred to the merits panel for
    consideration, as untimely.
    FACTS AND PROCEDURAL HISTORY
    On May     11,   2017,   Stevens   Construction &   Design,   L.L.C. ( Stevens
    Construction) entered into a contract with the St. Tammany Fire Protection District
    No. 1 ( Fire District), wherein Stevens Construction would serve as the general
    contractor for the construction of a new fire station and headquarters building
    located at 522 Robert Boulevard and 530 Robert Boulevard in Slidell, Louisiana
    for a total sum of $2, 845, 678. 00. The architect for the project was a joint venture
    between two architectural firms, Domain Architecture, APAC and Greenleaf
    Lawson Architects, APAC ( the Architect). The contract provided for completion
    of the project in 365 calendar days.       Construction work on the project began on
    June 1, 2017, pursuant to a " notice to commence work" issued by the Fire District.
    An additional 47 calendar days were added to the contract' s completion date
    pursuant to approved change orders.
    On July 19,      2018, the Architect sent a letter to Stevens Construction,
    notifying it that the contractual date for substantial completion, July 18, 2018, had
    passed and requesting that Stevens Construction provide a " realistic completion
    plan by Monday, July 23."        Stevens Construction, through owner Adam Stevens,
    responded on July 23, 2018, with a " scheduled contractual completion response,"
    which proposed that the project would be substantially complete by September 14,
    2018.    On July 27, 2018, Fire Chief Chris Kaufmann issued a letter to Stevens
    2
    Construction and its surety by electronic and certified mail to the addresses listed
    in the contract, notifying them that the Fire District was considering declaring
    Stevens Construction in default under the contract and requesting a meeting with
    Stevens Construction and its surety within ten days.            Counsel   for   Stevens
    Construction responded on August 6, 2018, agreeing to a meeting. Subsequently,
    the Architect outlined various concerns with the project in a letter dated August 15,
    2018, which was sent to Stevens Construction, its surety, and the Fire District. On
    August 22, 2018, Chief Kaufmann sent a letter to Stevens Construction and its
    surety by electronic and certified mail, summarizing his concerns with Stevens
    Construction' s performance on the project and directing Stevens Construction to
    stop work on the project by 4: 00 p.m. on August 23, 2018.
    On August 23,     2018,   Stevens Construction filed a verified petition for
    temporary restraining order, preliminary injunction, permanent injunction, and writ
    of mandamus.    Pertinent to this appeal, Stevens Construction alleged that the Fire
    District had invalidly issued a stop work order with the purported intent to
    terminate Stevens Construction from the project; therefore, Stevens Construction
    was seeking a temporary restraining order and injunctive relief to prohibit the Fire
    District' s purportedly invalid actions.    On August 24, 2018, the district court
    signed a temporary restraining order, enjoining the Fire District from taking any
    further action to enforce the subject stop work order or otherwise bar Stevens
    Construction from continuing to complete its work on the project. That same day,
    the Architect issued a certification in its role as the initial decision maker under the
    General Conditions of the contract, providing reasons why sufficient cause existed
    for terminating Stevens Construction under the terms of the contract.             After
    receiving the certification -of c-ause letter from the Architect, the Fire District
    issued a letter to Stevens Construction and its surety, dated August 24, 2018, via
    3
    electronic and certified mail, providing seven days written notice prior to the Fire
    District' s termination for cause of Stevens Construction.          On September 4, 2018,
    the Fire District issued a Notice of Termination to Stevens Construction and its
    surety by both electronic and certified mail, citing Articles 14.2. 1. and 14. 2. 2 of the
    General Conditions and Article 3. 10.3 of the Supplementary Conditions of the
    contract,   detailing the reasons the Fire District found              sufficient   cause   for
    terminating Stevens Construction and attaching the Architect' s certification.
    The district court held a hearing on the preliminary injunction on September
    4 and 6, 2018.'      Following the hearing, wherein the court heard testimony and
    received    evidence,    the district court took the matter under advisement.               On
    September 13, 2018, the district court issued its reasons for judgment, finding that
    in the time between the issuance of the temporary restraining order and the hearing
    on the preliminary injunction, the Fire District had complied with the terms of the
    contract between it and Stevens Construction in order to terminate Stevens
    Construction.     Accordingly, the district court found that Stevens Construction' s
    request for a preliminary injunction should be denied, and that its temporary
    restraining order should likewise be dissolved.              The district court instructed
    counsel for the Fire District to submit a judgment reflecting the court' s ruling.
    A judgment submitted by the Fire District was signed by the district court,
    2
    with a date of September 20, 2018.            On October 4, 2018, Stevens Construction
    filed a motion for new trial from the district court' s September 20, 2018 judgment
    denying its request for preliminary injunction and dissolving its temporary
    restraining order.      The following day, the district court signed a rule ordering the
    Fire District and Architect to show cause as to why Stevens Construction' s motion
    The hearing began on September 4, 2018, but was continued to September 6, 2018, due
    to approaching Tropical Storm Gordon.
    2The district court apparently dated this judgment in error, as it was actually signed on
    September 21, 2018.
    4
    should not be granted.      The district court specifically wrote on the order that the
    hearing is limited in scope only to reconsideration of plaintiff's objection raised
    regarding the language of the September 20, 2018 judgment and will be limited to
    oral arguments only."      On October 10, 2018, Stevens Construction filed a motion
    and order for suspensive appeal from the September 20, 2018 judgment, which was
    denied by the district court.
    On November 2, 2018, the district court signed a judgment purporting to
    correct    and   amend"   the September 20, 2018 judgment.       However, the district
    court' s ruling on the preliminary injunction and temporary restraining order
    remained     unchanged.     On November 14, 2018, Stevens Construction filed an
    amended and supplemental motion for suspensive appeal as well as a notice of
    intent to file a writ for supervisory review.
    Stevens Construction then filed both a writ application and an appeal from
    the judgments denying it injunctive relief. Stevens Construction requested that this
    court review the writ application filed on December 14, 2018,          as   an   expedited
    matter,    contending it feared that the Fire District would contract with a new
    company in the meantime to finish the project and thereby render moot the
    ultimate relief it sought, i.e., to finish the project itself and collect the monies
    allegedly owed to it. On January 10, 2019, the writ application was referred to this
    panel.     Stevens Construction and Design, LLC v.       St. Tammany Fire Protection
    District No. 1,    2018 CW 1759 ( La. App. 1St Cir. 1/ 10/ 19).   Subsequently, Stevens
    Construction sought review from the Louisiana Supreme Court, which on May 9,
    2019,     granted the plaintiff' s writ for the " sole purpose of transferring [ the]
    application to the court of appeal for consolidation with other pending matters and
    consideration in an expedited manner."          See Stevens Construction and Design,
    L.L.C. v. St. Tammany Fire Protection District No. 1, 2019- 0712 ( La. 5/ 9/ 19), 270
    
    5 So. 3d 569
    .      On May 13, 2019, Stevens Construction then fled a second writ
    application with this court, again seeking identical relief, and on May 23, 2019,
    that writ application was also referred to the panel to which this appeal was
    assigned.     Stevens Construction and Design, LLC v. St. Tammany Fire Protection
    District No. 1, 2019 CW 0642 ( La. App. 1St Cir. 5/ 23/ 19).
    The matter was initially submitted to a three-judge panel.        However, upon
    review, the matter was re -docketed for en Banc consideration to definitively set
    forth the applicable law regarding the running of the time delays for an appeal of a
    judgment or order relating to a preliminary injunction, in light of an ostensible
    conflict in the jurisprudence of this circuit which would affect the timeliness of the
    instant appeal and our jurisdiction to decide the matter.
    DISCUSSION
    A preliminary injunction is an interlocutory judgment designed to preserve
    the status quo between the parties pending a trial on the merits.          Stevens v. St.
    Tammany Parish Government, 2016- 0197 ( La. App. 1St Cir. 1/ 18/ 17), 
    212 So. 3d 5621
     565. Nevertheless, LSA- C. C. P. art. 3612($) provides that an appeal may be
    taken as a matter of right from an order or judgment relating to a preliminary
    injunction.    However, the party aggrieved by the order or judgment must take an
    appeal within fifteen days of the order or judgment, not the mailing of notice of
    judgment. LSA- C. C. P. art. 3612( 0); JODI Properties, LLC v. Cochran, 2015- 1327
    La.   App.    1st   Cir. 613116),   
    2016 WL 3134507
    , * 2 (   unpublished),   writ   not
    considered, 2016- 1277 ( La. 10/ 28/ 16),        
    208 So. 3d 3773
    ; First Guaranty Bank v.
    Perilloux, 
    498 So. 2d 239
    , 240 ( La. App. 1St Cir. 1986) 4; Zulu v. Washington, 
    487 So. 2d 1248
    , 1249 ( La. App. 1St Cir. 1986) 5, ("[       t]he fifteen day delay begins to run
    from the date of the judgment, not the mailing of notice of judgment, because it is
    article 3612 rather than article 1914 of the Code of Civil Procedure which controls
    this situation").       To the extent this court suggested otherwise in Raba, Inc.               v.
    Courtney, 2009- 0509 ( La. App. 1St Cir. 8/ 10/ 10), 
    47 So. 3d 509
    , 514 n. 12, that
    portion of the opinion is hereby overruled.
    3 I JODI Properties, plaintiffs sought a preliminary and permanent injunction against
    defendants, alleging defendants obstructed the natural drainage from plaintiffs' property, causing
    it to flood. JODI Properties, 
    2016 WL 3134507
     at * 1. A hearing on the preliminary injunction
    took place on October 27, 2014, at the conclusion of which the district court took the matter
    under advisement, instructing the parties to file post -hearing affidavits. On November 12, 2014,
    the district court signed an order granting the preliminary injunction, and on March 16, 2015,
    defendants filed a motion for suspensive appeal.     Defendants argued that although the motion
    was filed nearly four months after the signing of the order, the appeal delays had never begun to
    run because notice of the November 12, 2014 order had been sent to an incorrect address and,
    therefore, was never received by defendants. The district court allowed the defendants to take
    supervisory writs instead, which were denied by this court. See JODI Properties, LLC v.
    Cochran, 2015- 0625 ( La. App. 1st Cir. 4/ 23/ 15) ( unpublished). Defendants then filed a
    renewed" motion for appeal on May 18, 2015. This court noted that according to LSA-C. C. P.
    art. 3612, a motion for appeal of a preliminary injunction order must be taken within fifteen days
    from the date of the order or judgment. JODI Properties, 
    2016 WL 3134507
     at * 1.       Because the
    motions for appeal from the November 12, 2014 order were filed well after the fifteen -day delay
    set forth in LSA-C. C. P. art. 3612, they were untimely, and therefore, the appeal was dismissed.
    JODI Properties, 
    2016 WL 3134507
     at * 2.
    In First Guaranty Bank, plaintiff filed suit for executory process in connection with a
    mortgage executed by defendant. First Guaranty Bank, 
    498 So. 2d at 240
    . Defendant sought to
    stop the seizure and sale of the mortgaged property via injunctive relief. On August 28, 1985,
    the district court signed an order denying the defendant' s request for a preliminary injunction.
    Notice of the judgment was mailed to counsel of record on September 3, 1985, and defendant
    filed his motion for suspensive appeal on September 17, 1985. First Guaranty Bank, 
    498 So. 2d at 240
    .      This court held that pursuant to LSA- C. C. P. art. 3612, an appeal from an order or
    judgment relating to a preliminary injunction must be taken within fifteen days from the date of
    the order or judgment. The fifteen -day delay begins to run from the date of the judgment, not the
    mailing of the notice of judgment. Therefore, the appeal was dismissed as untimely, as the
    motion for appeal was filed twenty days after the date of the order. First Guaranty Bank 
    498 So. 2d at 240
    .
    5I Zulu, plaintiffs request for a preliminary injunction was denied by order dated April
    1,       Zulu, 
    487 So. 2d at 1249
    . Notice of the judgment was mailed to plaintiff on April 8,
    1985.
    1985, and plaintiff' s motion for appeal was filed on April 22, 1985. This court dismissed the
    appeal as untimely, finding that plaintiff had until April 16, 1985 to perfect an appeal. The court
    further noted that by the time plaintiff had filed its motion on April 22, the delay had already
    expired. Thus, because plaintiff' s appeal was not timely perfected, this court lacked jurisdiction,
    and accordingly, the appeal was dismissed. Zulu, 
    487 So. 2d at 1249
    .
    7
    The fifteen -day delay does not commence to run on a judgment granting or
    denying a preliminary injunction until the judgment is signed. Stevens, 212 So. 3d
    at 566.
    In addition, the delay for taking an appeal is not affected by the filing of a
    motion for new trial.         Stevens, 212 So. 3d at 566.           However, in cases where the
    parties stipulate that the preliminary injunction hearing will constitute a trial on the
    merits of the application for a permanent injunction, the normal appeal delays,
    rather than the fifteen -day delays under LSA- C. C. P. art. 3612, apply.                        Biu
    Hunting Club of Hunter v. DeSoto Parish Police Jury, 
    569 So. 2d 252
    , 255 ( La.
    App. 2nd Cir. 1990). In the instant matter, there is no indication in the record that
    the parties agreed to try the merits of the action for a permanent injunction at the
    preliminary injunction hearing. Instead, the                  record indicates that the parties
    intended for this hearing to solely determine the issue of the preliminary
    injunction.6
    In Morris v. Transtates Petroleum, Inc., 
    258 La. 311
    , 321, 
    246 So. 2d 183
    ,
    186 ( 1971),     the Louisiana Supreme Court explained that appeal delays run from
    the date of the judgment and are not interrupted or suspended by the filing of a
    motion for new trial because " the delays incident to applications for new trials
    6I City of Baton Rouge v. State, ex rel. Dept. of Social Services, 2007- 0005 ( La. App.
    Pt Cir. 9/ 14/ 07), 
    970 So. 2d 985
    , 995, this court stated:
    The principal demand for a permanent injunction, as opposed to the preliminary
    injunction, is determined on its merits only after a full trial under ordinary
    process, even though the hearing on the summary proceedings to obtain the
    preliminary injunction may touch upon or decide issues regarding the merits.
    Only when the parties have expressly agreed to submit the case for a final
    decision at the hearing on the rule for a preliminary injunction, may the ruling on
    the preliminary injunction definitively dispose of the merits of the case. An
    express agreement by the parties to consolidate the preliminary and permanent
    injunctions is essential; a trial court is without the authority to unilaterally convert
    a hearing for a preliminary injunction into a judgment of permanent injunction.
    Internal citations omitted].
    In the instant matter, the trial court specifically stated on the record the scope of the
    hearing as relating to the preliminary injunction only, after conferencing with the parties.
    Moreover, counsel for Stevens Construction maintained prior to and after the hearing that the
    hearing in question " dealt solely with the request for preliminary injunction."
    8
    have no reference to the fifteen[ -]day delay for perfecting an appeal from an order
    or judgment relating to a preliminary injunction under Article 3612."                              The
    Supreme Court emphasized in Morris that there are no exceptions to the mandate
    in this article, and there is no reference to applications for new trials suspending
    the time provided for appeal. Morris, 258 La. at 321, 246 So. 2d at 186- 187.                      As
    stated therein:
    The articles regulating new trials ([ LSA-C. C. P.]            arts.   1971,   et
    seq.) pertain to cases which have been tried on the merits, and the
    articles have no relation to interlocutory orders such as orders or
    judgments bearing on preliminary injunctions which are only rendered
    during the course of the proceeding and before final judgment.
    Morris, 258 La. at 321- 322, 246 So. 2d at 187.
    The Supreme Court held that the delays for appeal from a judgment denying
    a preliminary injunction are not suspended or held in abeyance when a party files
    an improper motion for new trial.             Instead, the fifteen -day delay prescribed by
    LSA-C. C. P.    art.   3612 for appeal tolls from the day the judgment is rendered
    denying the preliminary injunction. Morris, 258 La. at 322, 246 So. 2d at 187.
    In the instant case, the hearing on the preliminary injunction was held on
    September 4 and 6, 2018, and the matter was then taken under advisement.                           On
    September 13, 2018, the district court issued its reasons for judgment, denying the
    preliminary injunction and requesting that a written judgment be submitted
    reflecting the court' s ruling. The district court signed the judgment dissolving the
    temporary restraining order and denying the preliminary injunction on September
    20, 2018.      However, this was a typographical error, as the district court later
    acknowledged that it actually signed the judgment on September 21, 2018.7 Thus,
    in accordance with LSA-C. C. P. art. 3612, September 21, 2018 is the date from
    7It is well- settled that prior to final judgment a district court may, at its discretion and on
    its own motion, change the result of interlocutory rulings it finds to be erroneous. VaSalle v.
    Wal- Mart Stores, Inc., 2001- 0462 ( La. 11/ 28/ 01), 
    801 So. 2d 331
    , 334.
    9
    which appeal delays began to toll.            Counting fifteen days from September 21,
    2018, the deadline would have fallen on October 6, 2018, which was a Saturday.
    However, the motion for appeal was not fax filed until October 10, 2018 which
    was beyond the fifteen day time period.'
    The requisite      actions that must be taken to perfect an appeal of a
    preliminary injunction are specifically governed by LSA- C. C. P. art. 3612.                The
    article provides that the appellant, if he so chooses, may take an appeal from the
    ruling on the preliminary injunction, but the appeal must be taken within fifteen
    days from the date of the order or judgment. Although the district court " amended
    and corrected" the date of the original judgment as well as some of the other relief
    granted, we are constrained to recognize that the district court did not dissolve or
    otherwise modify its ruling denying the preliminary injunction, taking the action
    9
    out of the realm of LSA-C. C. P. art. 3607.             Any changes to other portions of the
    trial court' s judgment do not affect the delay for appealing the portion of the
    judgment denying Stevens Construction' s request for a preliminary injunction. See
    Bayou Hunting Club of Hunter, 
    569 So. 2d at 254
    .                 Furthermore, the filing of a
    motion for new trial did not affect the appeal delays for this action; therefore we
    are likewise constrained to find that the motion for appeal filed on October 10,
    We note that even if Columbus Day, October 8, 2018, were considered to be a legal
    holiday, the next non -legal holiday on which Stevens Construction was obligated to file its
    motion was October 9, 2018. Stevens Construction did not file until October 10, 2018; therefore,
    even using this later date, its filing would remain untimely.
    9Louisiana Code of Civil Procedure article 3607 provides in part that "[ a] n interested
    person may move for the dissolution or modification of a temporary restraining order or
    preliminary injunction, upon two days' notice to the adverse party, or such shorter notice as the
    court may prescribe."
    10
    2018 was untimely.10 When an appellant fails to timely take and perfect an appeal,
    the   appellate      court    lacks jurisdiction    to        hear   the   appeal.   See   Board     of
    Commissioners of Hammond Area Economic and Industrial Development District
    v. All Taxpayers, Property Owners, Citizens of the City of Hammond, 2006- 
    1832 La. App. 11
     Cir. 10/ 6/ 06), 
    944 So. 2d 640
    , 642- 643, writ denied, 2006- 2426 ( La.
    11
    11/ 3/ 06), 
    940 So. 2d 675
    .          Accordingly, the instant appeal must be dismissed.
    CONCLUSION
    For the above and foregoing reasons, the appeal of the district court' s
    judgment        denying      Stevens     Construction' s       preliminary    injunction   is   hereby
    dismissed.        Costs of this appeal are assessed against plaintiff/appellant, Stevens
    Construction & Design, L.L.C.
    APPEAL DISMISSED; WRITS NOT CONSIDERED.
    10For the same reasons, the notice for supervisory writs filed by Stevens Construction on
    November 14, 2018, requesting supervisory review of the denial of its preliminary injunction
    was also untimely. Therefore, 2018 CW 1759 and 2019 CW 0642 cannot be considered.
    Louisiana Code of Civil Procedure Article 3612 uses the permissive " may" rather than " shall"
    indicating than an appeal is permitted, but not mandated, to seek review of judgments relating to
    injunctions. If a party elects to seek review by applying for supervisory writs, it must be done
    within the same time limits allowed for an appeal of the judgment complained of, which is
    fifteen days under LSA-C. C. P. art. 3612. See In re Harrier Trust, 2018- 0667 ( La. App. 3          Cir.
    10/ 17/ 18),   
    259 So. 3d 402
    , 408; First Bank and Trust v. Duwell, 2011- 0104 ( La. App. 4th Cir.
    5/ 18/ 11), 
    70 So. 3d 15
    , 17 n. 5.
    11 We note, however, that appellant is not without remedy, as it may proceed to trial on
    the merits of the request for a permanent injunction, from which an appeal may be taken.
    11
    

Document Info

Docket Number: 2019CW0642

Filed Date: 1/16/2020

Precedential Status: Precedential

Modified Date: 10/22/2024