ORDER
Saris, Chief Judge. Aleo’s motion for reconsideration of the Court’s order on summary judgment (Docket No. 78) is DENIED. Section 210(g)(2) of PURPA lays out the enforcement process by “[a]ny person” against an electric utility to “enforce any requirement” established by a state regulatory authority, 16 U.S.C. § 824a-3(g)(2). There is no federal statutory provision providing a private cause of action for damages against the utility independent of the PURPA enforcement scheme. Section 210(h)(1) applies only to Commission enforcement. Id. § 824a-3(h)(1).
Parties shall file proposed form of judgment by 2/6/2017.
Document Info
Docket Number: Civil Action No. 15-13515-PBS
Citation Numbers: 235 F. Supp. 3d 320, 2017 WL 343899, 2017 U.S. Dist. LEXIS 11868
Judges: Saris
Filed Date: 1/23/2017
Precedential Status: Precedential