Wyman v. Ayer Properties, LLC , 469 Mass. 64 ( 2014 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    SJC-11474
    BRYAN WYMAN & others, 1 trustees, 2   vs.   AYER PROPERTIES, LLC.
    Middlesex.    March 4, 2014. - July 10, 2014.
    Present:    Ireland, C.J., Spina, Cordy, Botsford, Gants, Duffly,
    & Lenk, JJ.
    Real Property, Condominium. Condominiums, Common area.
    Negligence, Construction work, Economic loss. Damages,
    Replacement or reconstruction of building, Repairs.
    Civil action commenced in the Superior Court Department on
    December 8, 2005.
    The case was heard by Paul A. Chernoff, J.
    After review by the Appeals Court, the Supreme Judicial
    Court granted leave to obtain further appellate review.
    Thomas O. Moriarty (David M. Rogers with him) for the
    plaintiffs.
    Thomas H. Hayman (Patrick T. Uiterwyk with him) for the
    defendant.
    Henry A. Goodman, for Community Associations Institute,
    amicus curiae, submitted a brief.
    1
    Frank Thoms and Vincent Cascio.
    2
    Of the Market Gallery Condominium Trust.
    2
    CORDY, J.     On December 8, 2005, Brian Wyman, Frank Thoms,
    and Vincent Cascio, as trustees of the Market Gallery
    Condominium Trust (trustees), filed a civil action against Ayer
    Properties, LLC (Ayer), seeking damages stemming from the
    negligent construction of elements of a condominium building by
    Ayer.      The trustees alleged that Ayer -- which had purchased and
    converted the building in question into condominiums -- had
    negligently constructed the window frames, the exterior brick
    masonry, and the roof of the building, resulting in damage to
    both the common areas of the building and individual residential
    units. 3
    After a jury-waived trial, a Superior Court judge found
    that Ayer was negligent in its construction of the window
    frames, masonry, and roof.     He awarded damages for Ayer's
    negligence as to the window frames and the roof, because their
    improper installation had resulted in damage to both the common
    areas and several individual units.     However, because he found
    that the damage resulting from the defective masonry work was
    limited to the masonry itself and did not cause or include
    damage to any individual units, the judge concluded that the
    3
    The trustees of the Market Gallery Condominium Trust
    (trustee) sought damages only for the damage to the common areas
    and facilities of the building.
    3
    economic loss rule precluded the trustees from recovering for
    Ayer's negligence as to that portion of the building. 4
    In determining the appropriate measure of damages, the
    judge first calculated the cost to repair and replace the
    damaged portions of the building, 5 and then reduced that amount
    by twenty per cent to reflect what the costs would have been at
    the time of the negligent construction rather than at the time
    of the actual expenditures for repair and replacement.     As a
    result, the judge awarded compensatory damages of $140,000 to
    the trustees.    To this amount, the judge noted, would be added
    simple annual interest of twelve per cent, in accordance with
    G. L. c. 231, § 6B. 6   The parties filed cross appeals.   In its
    appeal, Ayer claimed, among other things, that the condominium
    structure constituted an integrated product, and that where no
    4
    The "economic loss rule" is also referred to as the
    "economic loss doctrine."
    5
    These costs included costs actually incurred to replace
    the roof, and those estimated to be necessary for the removal
    and replacement of the windows and frames.
    6
    General Laws c. 231, § 6B, provides:
    "In any action in which a verdict is rendered or a
    finding made or an order for judgment made for pecuniary
    damages for personal injuries to the plaintiff or for
    consequential damages, or for damage to property, there
    shall be added by the clerk of court to the amount of
    damages interest thereon at the rate of twelve per cent per
    annum from the date of commencement of the action even
    though such interest brings the amount of the verdict or
    finding beyond the maximum liability imposed by law."
    4
    damage extended beyond that product, the economic loss rule
    precluded any damages.
    The Appeals Court affirmed the judgment in favor of the
    trustees on the claims for compensatory damages for harm to the
    common area window frames and to the roof areas, determining
    that application of the economic loss rule was not appropriate
    in this context.    Wyman v. Ayer Props., LLC, 
    83 Mass. App. Ct. 21
    , 29, 31 (2012).    It went on to note that the "closest dicta"
    of this court "lean against the unqualified application of the
    rule to defectively designed or constructed condominium common
    areas," 
    id. at 27
    , citing Aldrich v. ADD Inc., 
    437 Mass. 213
    ,
    222-223 (2002).    Based on this reasoning, the Appeals Court
    reversed the order of dismissal of the trustees' claim for
    damages for harm to the masonry, and awarded damages totaling
    $64,000 plus interest pursuant to G. L. c. 231, § 6B.    Wyman,
    supra at 31. 7   It also determined that the judge's decision to
    reduce the damages by twenty per cent to reflect the earlier
    replacement costs "fell well within the range of reasonable
    alternative calculations."    Id.
    7
    In his findings, the Superior Court judge presciently
    computed the value of the damage to the masonry to avoid the
    necessity of a retrial "in the event that an appellate authority
    subsequently ruled that the [e]conomic [l]oss [d]octrine does
    not preclude an assessment of damages to the masonry." He
    assessed the cost to repair and replace the damaged masonry as
    $80,000, which, after a twenty per cent reduction, amounts to
    $64,000.
    5
    On further appellate review in this court, the trustees
    contend that the Appeals Court was correct and that the Superior
    Court judge misapplied the economic loss rule so as to exclude
    damages resulting from the defective masonry.   They also argue
    that the judge erred in reducing the measure of the established
    damages by twenty per cent.   Ayer, on cross appeal, continues to
    contend that the economic loss rule should preclude all claimed
    damages.
    We are largely in agreement with the Appeals Court, and
    conclude that the economic loss rule is not applicable to the
    damage caused to the common areas of a condominium building as a
    result of the builder's negligence, and that recovery for
    damages resulting from the defective masonry should have been
    awarded to the trustees.   Consequently, we affirm the judge's
    decision as to the window frames and roof, and remand to the
    Superior Court for entry of an order awarding additional damages
    for the negligently constructed masonry.   We also reverse the
    judge's decision to reduce the repair and replacement damages by
    twenty per cent, and remand the case to the Superior Court for
    entry of judgment in the full amount of the damages established
    at trial.
    6
    1.   Background.   a.   The construction.   In 2002, Ayer 8
    purchased a 150 year old vacant, four-story mill building
    located on Market Street in Lowell.     Ayer intended to serve as a
    general contractor for the renovation of the building, during
    which Ayer would convert the building into five commercial units
    and twenty-two luxury condominiums.     To that end, Ayer, as
    trustee, established the Market Gallery Condominium on December
    16, 2003, and recorded the master deed on December 17, 2003,
    simultaneously with the sale of the first unit.
    The renovation began in January, 2003, and the sale and
    occupancy of the twenty-two residential units proceeded as each
    unit was completed during the three-year construction period.
    On August 2, 2004, Ayer ceded control as trustee to the newly
    appointed board of trustees. 9   The sale and occupancy of the
    residential units was completed in 2005. 10
    Shortly after the transfer of control, the trustees became
    concerned with the condition of the building, specifically the
    8
    Ayer Properties, LLC (Ayer), is a single-purpose entity
    existing solely to acquire buildings, convert them into
    condominiums, and convey finished units. It is a limited
    liability company managed by John J. DeAngelis.
    9
    At the time of the judge's decision, the board of trustees
    consisted of Philippe Jeanjean, Stephen Greene, Alyssa Faulkner,
    Clint Baptiste, and Phillip Thompson.
    10
    The residential units are located on the second, third,
    and fourth floors of the building. The first level contains
    five commercial units, all of which are owned by Ayer.
    7
    windows, exterior masonry, and roof.    Out of that concern, they
    hired a professional engineer to perform a condition survey.
    The survey revealed damage to the window frames, exterior
    masonry, and roof. 11   As a result of the damage, the trustees
    brought suit against Ayer in December, 2005, alleging, in
    relevant part, negligent design and construction of the common
    areas of the building. 12
    b.   The trial judge's findings and decision.   The judge
    first found that Ayer's negligent design and construction of the
    common-area window frames was responsible for severe weather-
    related deterioration to twenty-two frames, which in turn caused
    damage to both the common areas and several individual units.
    He calculated the cost to "remove a storm window, remove and
    replace the frame elements, remove and replace a window, and
    11
    The initial survey was performed by Timothy Little, a
    professional engineer, who found damage to the windows and
    masonry but did not inspect the roof. Little returned to the
    site for a more detailed inspection in 2008, which is presumably
    when he discovered the damage to the roof, although the record
    is not clear on this point.
    12
    The trustees initially alleged five causes of action:
    (1) negligent design and construction of common areas; (2)
    breach of fiduciary duty by Ayer to deliver a common area free
    of defects; (3) breach of an implied warranty to deliver
    competent workmanship and material; (4) breach of fiduciary duty
    by Ayer to exercise good faith, loyalty, and due diligence; and
    (5) unfair or deceptive conduct in violation of G. L. c. 93A,
    § 2, for failing to comply with statutes and regulations
    intended to protect public health, safety, or welfare. At the
    conclusion of trial, the judge ruled for Ayer on counts two,
    three, and five, and dismissed count four on the request of the
    trustees. The trustees do not appeal those decisions.
    8
    dispose of the refuse at $1,500 per window," and the cost to
    replace the sills, a process which includes the "removal of
    storm windows and disposal of refuse," at $500 per window,
    amounting to a total cost of repair of $44,000.    He opted to
    reduce the costs by twenty per cent, "to reflect costs at the
    time the damage was incurred."   He added that the "[twenty per
    cent] reduction in replacement costs seems especially
    appropriate where the [twelve per cent] interest on the judgment
    will amount to approximately [sixty per cent]."    Thus, the
    assessable damages awarded for the windows were set at $34,000.
    The judge also found that the common-area roof was badly
    damaged as a result of the incomplete attachment of a protective
    subsurface membrane.   As a result of the damage, the roof
    allowed water to leak into common areas, as well as several
    residential units, during heavy rainstorms, causing stains on
    several walls and ceilings.   The judge noted that, in September,
    2009, the trustees contracted with L.E. Morgan Construction
    Company to completely replace the building's roof for $132,240.
    Finding that cost attributable to Ayer, the judge again reduced
    those damages by approximately twenty per cent, and awarded
    $106,000 to the trustees for damage to the roof.
    Regarding the exterior masonry, the judge found that the
    brick facade to the common area had significantly deteriorated
    due a lack of diligence that was "chargeable to Ayer."    He
    9
    assessed the cost to repair at $80,000.      However, the judge held
    that where the defects to the exterior masonry did not cause any
    harm beyond the masonry itself, the economic loss rule barred
    the trustees' recovery in negligence, and he thus awarded no
    damages for the negligently constructed masonry. 13
    2.   Discussion.    a.   Economic loss rule.   This court has
    long stood with the majority of jurisdictions in embracing the
    economic loss rule.     See, e.g., Bay-State Spray & Provincetown
    S.S., Inc. v. Caterpillar Tractor Co., 
    404 Mass. 103
    , 107 (1989)
    (Bay-State Spray).      The rule establishes limitations on damages
    a plaintiff may plead and recover in a negligence action.       It
    ensures that, "[i]n the absence of personal injury or physical
    damage to property [beyond the defective product itself], the
    negligent supplier of a defective product is not ordinarily
    liable in tort for simple economic loss."      Berish v. Bornstein,
    
    437 Mass. 252
    , 267 (2002).      See FMR Corp. v. Boston Edison Co.,
    
    415 Mass. 393
    , 395 (1993) ("purely economic losses are
    unrecoverable in tort and strict liability actions in the
    absence of personal injury or property damage").       "Economic loss
    13
    Ayer did not plead the economic loss rule as an
    affirmative defense, and instead raised the issue in a motion
    for directed verdict at the close of evidence, after which the
    judge reopened the evidence to take evidence on the
    applicability of the rule. While the trustees argued in their
    initial appeal that Ayer waived its argument that the economic
    loss rule should apply, the Appeals Court rejected its
    contention, and the trustees do not argue waiver here. See
    Wyman v. Ayer Props., LLC, 
    83 Mass. App. Ct. 21
    , 24-25 (2012).
    10
    includes 'damages for inadequate value, costs of repair and
    replacement of the defective product or consequent loss of
    profits without any claim of personal injury or damage to other
    property.'"    Berish, supra, quoting Marcil v. John Deere Indus.
    Equip. Co., 
    9 Mass. App. Ct. 625
    , 630 n.3 (1980).    Essentially,
    where the negligent design or construction of a product leads to
    damage only to the product itself, the recovery for economic
    loss is in contract, and the economic loss rule bars recovery in
    tort.
    We have said that "[t]he economic loss doctrine applies not
    only to the purchase and sale of products but also to claims of
    negligent design and installation in a newly constructed home."
    Berish, 437 Mass. at 267.    See McDonough v. Whalen, 
    365 Mass. 506
    , 514 (1974) (doctrine did not apply where negligently
    designed septic system overflowed causing damage to other
    property).    We have not, however, had occasion to consider
    whether the economic loss rule applies to damage caused by
    negligent design and construction of the common areas of a
    condominium building, whether or not such negligence caused
    damage to other property.    As the issue is now squarely before
    us, we hold that the economic loss rule does not ordinarily
    apply in such circumstances.
    An examination of the purpose of the economic loss rule
    guides our decision.    The rule was developed in part to prevent
    11
    the progression of tort concepts from undermining contract
    expectations.   See East River S.S. Corp. v. Transamerica
    Delaval, Inc., 
    476 U.S. 858
    , 866 (1986).   The rationale for
    excluding tort recovery for economic loss is that, "[w]hen a
    product injures only itself," a party should be left to its
    contractual remedies.   Bay-State Spray, 
    404 Mass. at 109
    ,
    quoting East River S.S. Corp., supra at 871.   "The commercial
    user can protect himself by seeking express contractual
    assurances concerning the product (and thereby perhaps paying
    more for the product) or by obtaining insurance against losses."
    Bay-State Spray, 
    supra at 109-110
    .   See Sebago, Inc. v. Beazer
    E., Inc., 
    18 F. Supp. 2d 70
    , 89 (D. Mass. 1998), quoting East
    River S.S. Corp., supra at 872 ("The rationale underlying the
    economic loss doctrine is that damage to a product itself 'means
    simply that the product has not met the customer's expectations,
    or, in other words, that the customer has received 'insufficient
    product value.'   The maintenance of product value and quality is
    precisely the purpose of express and implied warranties").     As a
    result, "[w]hen a product injures only itself the reasons for
    imposing a tort duty are weak and those for leaving the party to
    its contractual remedies are strong."   Bay-State Spray, supra at
    109, quoting East River S.S. Corp., supra at 871.
    The nature of condominium unit ownership supports our
    conclusion that claims such as those raised here do not fit into
    12
    the rubric of claims intended to be covered by the rule.
    "Ownership of a condominium unit is a hybrid form of interest in
    real estate, entitling the owner to both 'exclusive ownership
    and possession of his unit, G. L. c. 183A, § 4, and . . . an
    undivided interest . . . in the common areas."    Berish, 437
    Mass. at 262, quoting Noble v. Murphy, 
    34 Mass. App. Ct. 452
    ,
    455-456 (1993).   As part of the statutory structure of
    condominium ownership, "condominium unit owners cede the
    management and control of the common areas to the organization
    of unit owners, which is the only party that may bring
    litigation relating to the common areas of the condominium
    development on their behalf."    Berish, supra at 263, citing
    G. L. c. 183A, § 10 (b) (4).    See Cigal v. Leader Dev. Corp.,
    
    408 Mass. 212
    , 217 (1990) (G. L. c. 183A, § 10, "plainly
    contemplates that the association is to act as the exclusive
    representative of the unit owners in litigation for negligent
    construction").
    The problem arises where the party exclusively responsible
    for bringing litigation on behalf of the unit owners for the
    negligent construction of the common areas (here, the trustees)
    has no contract with the builder under which it can recover its
    costs of repair and replacement, that is, its economic losses
    caused by defective construction.    We agree with the Appeals
    Court that "the rule does not require a court to leave a wronged
    13
    claimant with no remedy," Wyman v. Ayer Props., LLC, 83 Mass.
    App. Ct. at 28, and that "[t]he fundamental purpose of the rule
    is to confine the indeterminacy of damages, not to nullify a
    right and remedy for a demonstrated wrong and its harm." 14   Id.
    The rationale for applying the rule is made even weaker
    where the trustees seek damages that are finite and foreseeable.
    The rule is intended to preclude recovery for intangible and
    unknown damages for lost contract or economic opportunity.    See
    FMR Corp., 
    415 Mass. at 394-395
     (economic loss doctrine
    precluded recovery for lost income and increased costs of doing
    14
    While the trustees do not have a contract with Ayer, the
    individual unit owners who purchased their units from Ayer do,
    and, as such, depending on the terms of each contract, they
    might each bring an action for breach of contract against Ayer
    for damage to their units and to their interest in the common
    areas stemming from negligent construction. See Cigal v. Leader
    Dev. Corp., 
    408 Mass. 212
    , 215 (1990) ("Nothing in G. L. c. 183A
    divests the purchaser of a condominium of the right to sue in
    breach of contract"). See also Gordon v. State Bldg. Code
    Appeals Bd., 
    70 Mass. App. Ct. 12
    , 20 (2007) (although
    association has exclusive right to protect owners' common
    rights, individual owners may assert claims "relating to their
    individual rights even though such claims may arise from
    something that takes place in a common area"). Were we to
    determine that the economic loss rule precluded the trustees'
    suit, we would force each individual unit owner to sue Ayer for
    breach of contract, even though the harm complained of stemmed
    from common structural problems. Such a result is precisely the
    sort of "[p]iecemeal litigation by individual unit owners [that]
    would frustrate the statutory scheme, in which the association
    acts as the representative of all owners in common." Cigal,
    supra at 218. Simply put, where contractual remedies for the
    individual unit owners are not easily enforceable, and actions
    brought by such individuals would be inconsistent with judicial
    economy and with the role delegated to the condominium
    association by statute with regard to common areas, the
    rationale for applying the economic loss rule is weak.
    14
    business due to three-day power outage resulting from
    defendant's negligence).   See also Garweth Corp. v. Boston
    Edison Co., 
    415 Mass. 303
    , 304-305 (1993) (plaintiff's claim
    "thwarted by the economic damage rule" where malfunctioning
    measuring device installed by defendant resulted in oil spill at
    plaintiff's station, and alleged damages resulted in part from
    157-day delay in plaintiff's ability to complete contracted work
    with third party); Marcil, 9 Mass. App. Ct. at 630 (plaintiff
    suffered unrecoverable economic losses where he alleged that
    defendant's negligently manufactured tractor caused him "severe
    losses in his business and good will").   Here, there is no such
    danger.   An eleven-day trial established Ayer's fault, the harm
    suffered by the trustees as representative of the unit owners'
    rights in the common areas, and the exact amount of the damages.
    There is no allegation of consequential damages, but simply a
    reliably proven amount needed to repair or replace the
    negligently constructed window frames, masonry, and roof.     Thus,
    the purposes of the economic loss rule have little applicability
    in these circumstances.
    b.   Damages calculation.   The trustees argue that the judge
    incorrectly reduced the damages by twenty per cent in an attempt
    to reflect the costs of repair and replacement at the time of
    the negligent construction.   They contend that the proper award
    of damages is the actual and projected repair and replacement
    15
    costs as found by the trial judge, without any reductions.      We
    agree.
    A basic premise of tort law is that "[t]he plaintiff is
    entitled to that sum of money which will place him in the
    position in which he was immediately before the defendant's
    negligent act or omission."    J.R. Nolan & L.J. Sartorio, Tort
    Law § 13.1 (3d ed. 2005).    The general rule for determining
    property damage is diminution in market value.    See Hopkins v.
    American Pneumatic Serv. Co., 
    194 Mass. 582
    , 583 (1907).
    However, "[r]eplacement or restoration costs have also been
    allowed as a measure of damages in other contexts where
    diminution in market value is unavailable or unsatisfactory as a
    measure of damages."    Trinity Church in the City of Boston v.
    John Hancock Mut. Life Ins. Co., 
    399 Mass. 43
    , 49 (1987).
    "Where expenditures to restore or to replace to predamage
    condition are used as the measure of damages, a test of
    reasonableness is imposed."    
    Id. at 50
    .   Both the cost of repair
    or replacement and the repair or replacement itself must be
    reasonably necessary in light of the damage inflicted by Ayer's
    negligence.   
    Id.
       "[A]n award of damages must stand unless to
    make it or permit it to stand was an abuse of discretion on the
    part of the court below, amounting to an error of law."
    Mirageas v. Massachusetts Bay Transp. Auth., 
    391 Mass. 815
    , 822
    (1984), quoting Bartley v. Phillips, 
    317 Mass. 35
    , 43 (1944).
    16
    While we have held that repair and replacement costs are an
    appropriate measure of damages, we have not explicitly addressed
    whether or when it is proper for those damages to be reduced to
    account for the lower costs of repair and replacement that would
    have been incurred had they been done closer in time to the
    negligent construction.   The cases cited by the Appeals Court in
    affirming the trial judge's reduced award stand only for the
    proposition that repair and replacement damages are appropriate.
    See, e.g., Commonwealth v. Johnson Insulation, 
    425 Mass. 650
    ,
    665-666 (1997); Belkus v. Brockton, 
    282 Mass. 285
    , 288 (1933).
    We need not now decide whether such a reduction is ever
    appropriate, where the judge's decision to reduce the damages by
    twenty per cent here was not reasonable.
    It is not clear from the record why the judge concluded
    that the actual costs of repair and replacement that he found
    had already been incurred or were likely to be incurred were an
    unreasonable remedy.   At the time the damages were awarded, the
    trustees had already contracted for the roof repair at a cost of
    $132,240.   Absent any finding that this cost was excessive, we
    discern no basis to conclude that the trustees should not be
    entitled to the costs they had already incurred.   Similarly,
    while work apparently remains to be done on the window frames
    and masonry, there is no finding that the costs of their repair
    and replacement, as determined by the judge, were unreasonable.
    17
    While the judge was in the best position to determine the
    proper amount of actual damages, and wrote a meticulously
    detailed, fifty-five page memorandum of decision in which he
    carefully explained his method of determining damages, his
    subsequent twenty per cent reduction is largely unexplained and
    unsupported by any evidence.
    The only explanation of the reduction is alluded to in the
    judge's statements that the reduction with regard to the windows
    seemed "especially appropriate" given the addition of interest,
    and that the reduction with regard to the roof was reasonable
    "based on the evidence and the fact that damages will be
    enhanced by interest on the near [sixty per cent] interest on
    the judgment."   Thus, it appears that the judge's decision to
    reduce the amount of damages was motivated, in significant part,
    by a desire to prevent the trustees from receiving the full
    benefit of the statutorily mandated interest.   We agree with the
    trustees that the awarding of interest "is not within the
    purview of the fact finder," and conclude that reducing damages
    for the purpose of preventing aggrieved plaintiffs from
    receiving interest that the Legislature intended they receive is
    unreasonable (citation omitted).   Lawrence Sav. Bank v.
    Levenson, 
    59 Mass. App. Ct. 699
    , 711 (2003) ("Prejudgment
    interest, awarded pursuant to G. L. c. 231, § 6B, is designed to
    18
    compensate a damaged party for the loss of use or the unlawful
    detention of money" [citation omitted]).
    3.   Conclusion.   We affirm the trial judge's decision
    awarding damages for negligent construction of the roof and
    window frames, and reverse his decision with regard to the
    damaged masonry.   We also vacate the award of damages and remand
    to the Superior Court for entry of an award of the full amount
    of damages found by the trial judge, amounting to $256,240, plus
    interest pursuant to G. L. c. 231, § 6B.
    So ordered.