Brockton Power Co. LLC v. EFSB/City of Brockton v. EFSB (No. 2) ( 2014 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    SJC-11405
    SJC-11407
    BROCKTON POWER COMPANY LLC      vs. ENERGY FACILITIES SITING BOARD
    & others.1
    CITY OF BROCKTON    vs. ENERGY FACILITIES SITING BOARD
    & another2 (No. 2).
    Suffolk.       March 4, 2014. - July 31, 2014.
    Present:     Ireland, C.J., Spina, Cordy, Botsford, Gants, Duffly,
    & Lenk, JJ.3
    Energy Facilities Siting Board. Public Utilities, Electric
    company, Energy company. Municipal Corporations, Electric
    plant, Water supply. Environment, Air pollution. Electric
    Company. Administrative Law, Decision, Judicial review,
    Substantial evidence.
    Civil action commenced in the Supreme Judicial Court for
    the county of Suffolk on October 28, 2011.
    The case was reported by Spina, J.
    1
    City of Brockton (city), and various residents of the city
    and the town of West Bridgewater, interveners.
    2
    Brockton Power Company LLC, intervener (Brockton Power or
    company).
    3
    Chief Justice Ireland participated in the deliberation on
    this case prior to his retirement.
    2
    Civil action commenced in the Supreme Judicial Court for
    the county of Suffolk on October 26, 2011.
    The case was reported by Spina, J.
    Gregor I. McGregor (Nathaniel Stevens with him) for city of
    Brockton.
    David S. Rosenzweig (Erika J. Hafner & Michael J. Koehler
    with him) for Brockton Power Company LLC.
    Sookyoung Shin, Assistant Attorney General, for Energy
    Facilities Siting Board.
    Lisa C. Goodheart (Phelps T. Turner, Joshua D. Nadreau, &
    Staci Rubin with her) for Frank J. Babbin & others.
    Wendy B. Jacobs & Aladdine D. Joroff, for Massachusetts
    Rivers Alliance & others, amici curiae, submitted a brief.
    BOTSFORD, J.      On August 7, 2009, the Energy Facilities
    Siting Board (board), acting pursuant to G. L. c. 164, § 69J¼
    (§ 69J¼), approved the petition of Brockton Power Company LLC
    (Brockton Power or company), to build and operate a 350-megawatt
    combined-cycle energy generating facility (facility or project)
    powered by natural gas and ultra-low sulfur distillate (ULSD) in
    the city of Brockton (city).     As approved by the board, the
    facility would use wastewater from the city's advanced
    wastewater reclamation facility (AWRF) for its cooling tower.
    In a consolidated appeal by three of the interveners, we
    affirmed the board's decision.     See Brockton v. Energy
    Facilities Siting Bd. (No. 1), ante        (2014) (Brockton [No.
    1]), decided today.
    On April 9, 2010, while the consolidated appeal was
    pending, Brockton Power submitted a project change filing (PCF)
    3
    to the board, seeking approval of three changes to its project.
    In the PCF, Brockton Power sought to:     (1) change the source of
    the facility's cooling tower water from the AWRF to the Brockton
    municipal water supply (BMWS); (2) eliminate the use of ULSD as
    an alternative fuel and rely solely on natural gas as the
    facility's fuel; and (3) make certain changes in the design of
    the facility.   After additional public comment, extensive
    discovery, testimony, and six days of evidentiary hearings that
    the board considered as a "continuation of the [o]riginal
    [p]roceeding," the board issued its PCF decision, denying
    Brockton Power's proposal to use BMWS but approving the two
    other project changes.4   Brockton Power appealed from the board's
    denial of the PCF with respect to the facility's water source,5
    and the city appealed from the board's approval of the design
    and fuel changes.   A single justice of this court reserved and
    reported the appeals to the full court.    We affirm the board's
    final decision with respect to both appeals.
    4
    The city, Brockton Power, various residents of the city
    and the town of West Bridgewater represented by Alternatives for
    Communities and Environment, Inc., and the Taunton River
    Watershed Alliance intervened in the project change filing (PCF)
    proceeding.
    5
    We acknowledge the amicus brief filed by Massachusetts
    Rivers Alliance, Charles River Watershed Association, Jones
    River Watershed Association, North and South Rivers Watershed
    Association, and Taunton River Watershed Alliance.
    4
    The scope of our review of the board's PCF decision is the
    same as in Brockton (No. 1), supra, and is set forth in G. L.
    c. 164, § 69P.6    The board's evidentiary rulings are entitled to
    deference, and the appellants bear the burden of showing that
    the board's decision is invalid.     Alliance to Protect Nantucket
    Sound, Inc. v. Energy Facilities Siting Bd., 
    448 Mass. 45
    , 51
    (2006) (Alliance I).
    1.     Board's authority to consider PCF as part of original
    proceeding.    In its August 7, 2009, final decision, the board
    required Brockton Power to notify it of "any changes other than
    minor variations to the proposal so that the [board] may decide
    whether to inquire further into a particular issue."     In
    addition to this general requirement, noting "the uncertainty
    . . . around the availability of the Brockton AWRF water
    supply," the board directed Brockton Power to "work with the
    [city] regarding use of [the city's] AWRF water, and to provide
    a report to the [board] with respect to the outcome of such
    efforts."    In the event that Brockton Power determined not to
    6
    General Laws c. 164, § 69P, provides that the court's
    review is limited to "whether the decision of the board is in
    conformity with the constitution of the commonwealth and the
    constitution of the United States, was made in accordance with
    the procedures established under [G. L. c. 164, §§ 69H to 69O,]
    and with the rules and regulations of the board with respect to
    such provisions, was supported by substantial evidence of record
    in the board's proceedings, and was arbitrary, capricious or an
    abuse of the board's discretion under the provisions of [§§ 69H
    to 69O]."
    5
    use the AWRF water and instead "to use potable [municipal] water
    for the majority of the water requirements of its proposed
    facility," the board directed the company to "provide a project
    change filing to the [board], together with a detailed analysis
    focused on those issues that are germane to the use of potable
    water, including opportunities for water conservation."
    Consistent with this directive, on April 9, 2010, Brockton
    Power submitted its PCF to the board seeking approval of a
    change in the source of the facility's water supply for the
    cooling tower, approval of the nonuse of ULSD as an alternate
    fuel, and approval of building design changes.   Over the
    objection of interveners, who argued that the PCF should be
    treated as a new petition, the board, as previously described,
    held evidentiary hearings on the PCF and issued a decision
    rejecting the proposed change in source of water supply for the
    cooling tower, but approving the two other changes.
    Under § 69J¼, fifth and sixth pars., the board may approve,
    reject in whole or in part, or conditionally approve a petition
    for an electrical generating facility.7   The statute provides
    7
    General Laws c. 164, § 69J¼ (§ 69J¼), fifth and sixth
    pars., provide in relevant part:
    "The board shall, within one year from the date of filing,
    approve a petition to construct a generating facility if
    the board determines that the petition meets [certain
    enumerated] requirements . . . .
    6
    that "[i]n the event of rejection or conditional approval, the
    applicant may, within 180 days, submit an amended petition.
    Public and evidentiary hearings on the amended petition shall be
    held on the same terms and conditions applicable to the original
    petition."   G. L. c. 164, § 69J¼, sixth par.   See note 7, supra.
    The city contends that Brockton Power's PCF was an "amended
    petition" within the meaning of § 69J¼, sixth par., and because
    it was submitted on April 9, 2010, 245 days after the board
    issued its original decision, the board did not have the
    authority to consider it as part of the original proceeding --
    the window for filing an amended petition had already closed.
    According to the city, the board should have reviewed the PCF as
    a new petition, which would have required readjudication of the
    full range of issues the board considered in its original
    decision issued on August 7, 2009.   The city's argument fails.
    "We accord substantial discretion to an agency to interpret
    the statute it is charged with enforcing . . . ."   Alliance to
    Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd.,
    "If the board determines that the standards set forth above
    have not been met, it shall, within one year of the date of
    filing, either reject, in whole or in part, the petition,
    setting forth in writing its reasons for such rejection, or
    approve the petition subject to stated conditions. In the
    event of rejection or conditional approval, the applicant
    may, within 180 days, submit an amended petition. Public
    and evidentiary hearings on the amended petition shall be
    held on the same terms and conditions applicable to the
    original petition."
    7
    
    457 Mass. 663
    , 681 (2010).   Moreover, "administrative agencies
    have broad discretion over procedural matters before them."
    Zachs v. Department of Pub. Utils., 
    406 Mass. 217
    , 227 (1989)
    (Zachs).   We defer to an agency's procedural rulings and review
    them for "error of law or abuse of discretion."   
    Id.
       This is so
    in particular when the ruling concerns whether to reopen a
    proceeding or an administrative record.   See Alliance to Protect
    Nantucket Sound, Inc. v. Department of Pub. Utils. (No. 2), 
    461 Mass. 190
    , 193-194 & n.7 (2011); Box Pond Ass'n v. Energy
    Facilities Siting Bd., 
    435 Mass. 408
    , 420 (2001) (Box Pond).
    The board determined that Brockton Power's PCF was not an
    "amended petition" within the meaning of § 69J¼, sixth par.     As
    interpreted by the board, the "amended petition" provision is
    limited to an amended filing submitted by a project proponent
    within six months after the board has issued a final decision
    rejecting the original petition or imposing conditions from
    which the proponent seeks relief.   The board contends that its
    power under § 69J¼, fifth and sixth pars., to approve a petition
    with conditions, combined with its ability to "issue orders with
    respect to any matter over which it has jurisdiction," see G. L.
    c. 164, § 69H, provides it with more than sufficient authority
    to include in a final decision an order requiring the project
    proponent to bring back to the board for potential review any
    8
    proposed changes to the project that may affect the basis on
    which it was originally approved.
    The board's interpretation of its "statutory mandate will
    be disturbed only if the interpretation is patently wrong,
    unreasonable, arbitrary, whimsical, or capricious."     Box Pond,
    435 Mass. at 416, quoting TBI, Inc. v. Board of Health of N.
    Andover, 
    431 Mass. 9
    , 17 (2000).    Where, as here, the relevant
    statutes are silent on the means of enforcing compliance with
    its orders, the board has broad discretion to establish
    appropriate procedures.   See Zachs, 
    406 Mass. at 227-228
    .    An
    administrative agency may, as here, "adopt policies through
    adjudication as well as through rulemaking."     Alliance I, 448
    Mass. at 51, quoting Arthurs v. Board of Registration in Med.,
    
    383 Mass. 299
    , 312–313 (1981).     The board's interpretation of
    § 69J¼, fifth and sixth pars., is a reasonable one to which we
    accord deference, and the procedure the board adopted to review
    potentially material changes to Brockton Power's project does
    not constitute an abuse of its discretion.8
    2.   Water source.   The board in its original final decision
    approved Brockton Power's proposed use of water from the city's
    8
    Moreover, requiring new proceedings on the full petition
    would be futile, because "[a] final order of an administrative
    agency in an adjudicatory proceeding . . . precludes
    relitigation of the same issues between the same parties." Box
    Pond Ass'n v. Energy Facilities Siting Bd., 
    435 Mass. 408
    , 419
    (2001) (Box Pond), quoting Tuper v. North Adams Ambulance Serv.,
    Inc., 
    428 Mass. 132
    , 135 (1998).
    9
    AWRF for the facility's cooling tower.   Because the city refused
    to supply recycled wastewater from the AWRF for the facility,
    Brockton Power submitted a PCF based on the use of water from
    BMWS, which supplies potable water to the city.    The board
    concluded that the environmental impacts associated with the
    Brockton Power's use of BMWS water failed to "minimize the
    environmental impacts consistent with the minimization of costs
    associated with the mitigation, control, and reduction of the
    environmental impacts of the proposed generating facility."
    G. L. c. 164, § 69J¼, fifth par.
    Brockton Power argues that the board's analysis of
    environmental impacts intruded on the authority of the
    Department of Environmental Protection (DEP) was unsupported by
    substantial evidence.   We disagree, and conclude that Brockton
    Power has not met its burden of showing that the board's
    decision is invalid.    See Alliance I, 448 Mass. at 51.
    The record reflects the following facts.   The city draws
    its water supply from the Silver Lake system, the Brockton
    Reservoir, the Hubbard Avenue well and, beginning in 2008, a
    desalination plant owned and operated by Aquaria, LLC (Aquaria),
    in Dighton.9   The city's permits issued under the Water
    Management Act (WMA), G. L. c. 21G, authorize withdrawals of
    9
    The Silver Lake system includes Silver Lake, Monponsett
    Pond, and Furnace Pond.
    10
    11.94 million gallons per day (mgd) from the Silver Lake system
    and Brockton Reservoir.10   In addition, the city is authorized to
    purchase up to 4.07 mgd from Aquaria, which draws water from the
    Taunton River.11
    In 1986, subsequent to a prolonged drought, the predecessor
    agency of the DEP issued an administrative order and emergency
    declaration that, among other requirements, directed the city to
    control water demand and withdrawals, and to develop new water
    sources.   Thereafter, in 1995, an administrative consent order
    (ACO) replaced the emergency declaration.   Pursuant to the ACO,
    the city reestablished its water commission and, among other
    measures, prepared a comprehensive water management plan
    concerning its water supply.   In 1997, a modification to the ACO
    10
    The Water Management Act (WMA), G. L. c. 21G, permits for
    the Silver Lake system authorize withdrawals of 11.11 million
    gallons per day (mgd). The WMA permit for the Hubbard Avenue
    well authorizes withdrawals of 0.04 mgd, but this well may be
    used only in emergency situations with permission of the
    Department of Environmental Protection (DEP). The WMA permit
    for the Brockton Reservoir authorizes a withdrawal of 0.83 mgd.
    Since 1994, however, the city has obtained less than ten per
    cent of its supply from the Brockton Reservoir.
    11
    By contract, the city is entitled to 3.5 mgd from
    Aquaria, LLC (Aquaria), in 2014, a withdrawal amount that will
    increase incrementally to 4.07 mgd by 2019. The city also has
    the right to purchase the first 1 mgd of excess water from
    Aquaria and to demand Aquaria produce and provide a minimum of
    0.5 mgd of excess water during June, July, and August in
    addition to the contracted amounts described above. In 2014,
    the city is expected to pay Aquaria $5.8 million for the right
    to 3.5 mgd of water from the plant, not including any payments
    for excess water purchased.
    11
    also established a "safe yield" of 10.33 mgd for the city from
    its then existing sources, which did not yet include the Aquaria
    plant.      The ACO provides that in the event the city's water
    withdrawals exceed 11.3 mgd or 110 per cent of the "safe
    yield,"12 whichever is larger, the excess withdrawal will
    "constitute a request for the imposition of a [d]eclaration of
    [w]ater [e]mergency."13     From 1996 to 2010, the city's average
    annual water use was relatively constant, at approximately 10
    mgd.    In 2014, the city is estimated to require between 10.15
    and 11.44 mgd of water from all sources.      The ACO, and the safe
    yield limits, remain in effect.14
    As proposed to be modified by the PCF, the facility's
    cooling tower will require 1.75 mgd of water at full capacity on
    12
    Pursuant to G. L. c. 21G, § 2, "[s]afe yield" is defined
    as "the maximum dependable withdrawals that can be made
    continuously from a water source including ground or surface
    water during a period of years in which the probable driest
    period or period of greatest water deficiency is likely to
    occur; provided, however, that such dependability is relative
    and is a function of storage and drought probability."
    13
    In its November, 2009, comprehensive water management
    plan (CWMP), which has not yet been approved by the DEP, the
    city sought to increase its permissible withdrawals from the
    Silver Lake system and Brockton Reservoir to 13.1 mgd from the
    currently approved 11.3 mgd.
    14
    In its draft CWMP required as a part of the MEPA
    certification for use of water from the Aquaria plant, the city
    requested that the administrative consent order (ACO) be lifted.
    However, the DEP has not yet lifted the ACO.
    12
    a typical day, or 1.1 mgd on an average annual basis.15,16   During
    the summer electrical peak period, when the Silver Lake system
    is the most stressed, the facility is expected to use water at
    the rate of 2.1 mgd, roughly twice its estimated annual average
    rate.17
    Brockton Power contends that BMWS readily can supply the
    volume of potable water necessary for the facility's cooling
    tower, essentially because, in Brockton Power's view, "most (if
    not all) of the incremental water needed to supply [the
    facility] will come from Aquaria rather than the city's historic
    system."   The board disagreed, noting that the city had never
    had to manage the supply demand of a water customer the size of
    the Brockton Power facility, that the facility would account for
    15
    The estimate for operating at full capacity on a typical
    day is based on the facility's operation at one hundred per cent
    capacity on a day with a temperature of fifty-nine degrees
    Fahrenheit. The average annual basis estimate is based on
    operation at seventy per cent capacity, which Brockton Power
    asserts would be typical for the facility, on a day with a
    temperature of fifty-nine degrees Fahrenheit. Due to design
    changes, these estimates represent reductions from the volumes
    initially approved by the board for the use of effluent from the
    city's AWRF.
    16
    In Brockton Power's original petition as approved by the
    board, it was estimated the facility would require 0.257 mgd of
    potable water from the city for process and sanitary water
    needs. The city has issued a permit approving the facility's
    use of this quantity, and this aspect of the original project
    filing remains unchanged in Brockton Power's PCF.
    17
    This estimate is based on operation at full capacity on a
    day with a temperature of ninety degrees Fahrenheit.
    13
    more than ten per cent of the city's current water demand, and
    that despite greater flexibility in water withdrawal allocations
    due to Aquaria, "some, and possibly even a significant portion,
    of the [facility's] municipal water could come from Silver
    Lake."   Noting that the city's water supply problems have
    resulted in significant environmental impacts to the Silver Lake
    system over the years and that Brockton Power had not provided
    evidence concerning the additional environmental impacts on that
    system that might result from Brockton Power's increased
    consumption for the project, the board concluded that Brockton
    Power had not met its burden to show that the environmental
    impacts of the proposed change would be minimized consistent
    with the minimization of related costs, as required by § 69J¼,
    fifth par.
    On appeal, Brockton Power contends that the board
    impermissibly intruded into the DEP's statutory and regulatory
    authority as expressed in the ACO’s threshold for triggering a
    declaration of water emergency for the city.   Brockton Power
    argues that the DEP's "determination of safe yield as the basis
    for the 1995 ACO limit of 11.3 [mgd] specifically included
    minimization and balancing of environmental protection factors"
    to which the board was obligated to defer in conducting its
    review of the PCF.   We disagree.
    14
    In evaluating a claim that the board's determination is
    arbitrary, capricious, or unsupported by substantial evidence,
    we "give[] great deference to the board's expertise and
    experience."   Alliance I, 448 Mass. at 51. "In determining
    whether an agency decision is supported by substantial evidence,
    we must consider the record as a whole and reverse the agency's
    decision if 'the cumulative weight of the evidence tends
    substantially toward opposite inferences.'"    Boston Gas Co. v.
    Department of Telecomm. & Energy, 
    436 Mass. 233
    , 237 (2002),
    quoting Cobble v. Commissioner of the Dep't of Social Servs.,
    
    430 Mass. 385
    , 391 (1999).   Here, Brockton Power has not met its
    burden of showing that board's decision was erroneous.
    Pursuant to § 69J¼, fifth par., the board is the agency
    charged with determining whether a project proponent's petition
    is an accurate and complete description of the environmental
    impacts of the proposed facility, and also minimizes
    environmental impacts consistent with the minimization of costs
    associated with mitigation, control, and reduction of
    environmental impacts.   "A permit issued by the board is only
    the first of many permits and licenses that will be required of
    a developer of a generating facility, and no other State agency
    may issue a construction permit for a generating facility until
    it has first been approved by the board."     Andover v. Energy
    Facilities Siting Bd., 
    435 Mass. 377
    , 380 (2001) (Andover).       The
    15
    Legislature has provided for complementary but independent roles
    for the board and the DEP.   Just as the board does not delegate
    or abdicate its statutory responsibility by recognizing the
    authority and expertise of the DEP over water management issues,
    see id. at 381, the board's independent exercise of its
    statutory authority does not intrude upon DEP's authority over
    issues relating to municipal water supplies under the WMA, G. L.
    c. 21G, §§ 3, 7.
    In short, the board's and the DEP's mandates are not
    identical although they touch on many of the same environmental
    concerns; "sensible administrative coordination" between the two
    agencies is necessary.18   See Andover, 435 Mass. at 382.   The
    board's approval of a petition to construct an energy facility
    will not necessarily satisfy the DEP's requirements for a permit
    for that facility under the WMA.   Cf. id. at 380-381 (discussing
    different roles of board and DEP in relation to review of air
    emissions).   Likewise, a DEP permit issued to a municipality
    18
    General Laws c. 164, § 69H, fourth par., provides in
    part: "In carrying out its functions, the board shall cooperate
    with, and may obtain information and recommendations from every
    agency of the state government and of local government which may
    be concerned with any matter under the purview of the board.
    Each state or local government agency is directed to provide
    such information and recommendations as may be requested by the
    board." In addition, § 69H, second par., provides that the
    board membership include "the secretary of energy and
    environmental affairs, who shall serve as chairman, . . . the
    commissioner of the department of environmental protection,
    . . . or the designees of any of the foregoing . . . ."
    16
    under the WMA is not equivalent to a determination that a
    proposed facility would minimize environmental impacts as
    required by § 69J¼, nor does the existence of such a permit
    compel the board to grant a petition under that statute.    Far
    from intruding on the DEP's authority, the board would have
    abdicated its statutory duties if it had based its decision on
    the proposed water source change wholly on the DEP's municipal
    water withdrawal determinations under the WMA.19
    Moreover, the board's determination was supported by
    substantial evidence.   In its PCF, Brockton Power contended that
    because the city was already withdrawing close to the limit of
    its ACO threshold from its traditional sources, the incremental
    water volume required by the facility would primarily come from
    the Aquaria plant, which provided a significant new source of
    19
    Although Brockton Power correctly notes that
    environmental protection principles, including water
    conservation, are an integral component of DEP's water
    management authority, it does not follow that the ACO threshold
    limit of 11.3 mgd (or 110 per cent of the system's safe yield at
    the time of the ACO) is "fully protective" of the environmental
    concerns that the board must consider under § 69J¼, fifth par.
    Indeed, other than the DEP's general mandate to consider
    environmental effects of water withdrawals under G. L. c. 21G,
    § 7, there is no evidence that the ACO specifically considers
    the environmental effects of the safe yield threshold. Rather,
    the focus of the ACO is to "ensure an ample supply of potable
    water is available to [the city]." The safe yield established
    by the ACO merely sets a threshold at which a declaration of
    water emergency will be imposed on the city if the twelve month
    average exceeds the designated amount; it does not purport to
    establish a level of water withdrawals that is protective of the
    city's traditional water sources, such as the Silver Lake
    system.
    17
    potable water for the city.   Consequently, Brockton Power urged,
    despite the city's historical water supply challenges, the
    facility would not have a negative effect on the environment of
    the Silver Lake system.   As the board recognized, however, the
    city's water conservation efforts and stable population forecast
    made it likely that the city's withdrawals would remain under
    the ACO threshold.   Moreover, Brockton Power had no control over
    the origins of the municipal water required by the facility, and
    given the city's view of the Aquaria plant as a supplemental
    source of its water needs, the volume required by the PCF might
    come entirely or at least in part from the Silver Lake system.
    Given the evidence that the city's municipal water withdrawals
    continue to have a significant environmental impact on the
    Silver Lake system, the board concluded that Brockton Power had
    not met its burden of proving that the environmental impacts of
    the incremental potable water usage from BMWS had been minimized
    consistent the requirements of § 69J¼, fifth par.
    Brockton Power complains that the board did not analyze
    sufficiently the environmental impacts of the additional
    withdrawals anticipated by the PCF on the Silver Lake system,
    but this appears to have been the result of the position the
    company itself took before the board:   the PCF filing proceeded
    on the assumption that most or all of the increased water
    18
    required by the facility would come from the Aquaria plant.20
    Nevertheless, it is apparent that the board did analyze and
    consider the effect of the proposed water use on the city’s
    traditional water sources, including two studies and expert
    testimony indicating that the city's withdrawals have a
    continued impact on the environment of the Silver Lake system by
    degrading freshwater mussel habitat and increasing environmental
    stress on the Jones River, the major tributary of Silver Lake.
    Moreover, contrary to Brockton Power's assertion, the board
    considered the city's water conservation progress in light of
    continuing environmental challenges to the Silver Lake system
    and the facility's projected water needs.21
    20
    In its PCF decision, the board noted: "The [c]ompany did
    not provide information on or analysis of the different
    environmental impacts on the Silver Lake system that would
    result from the [c]ity's water consumption with the [p]roject's
    use of [Brockton municipal water supply (BMWS)] water as
    compared to the [c]ity's water consumption without the
    [p]roject. Rather the [c]ompany restricted its argument to the
    unsubstantiated and, in fact, highly questionable, claim that
    its cooling tower water would predominately come from Aquaria.
    Without analysis specific to the Silver Lake system, the
    environmental impacts of the [p]roject change cannot be reliably
    assessed."
    21
    Brockton Power's remaining arguments are without merit.
    The board need not address or make findings with respect to all
    the evidence in the record. See Box Pond, 435 Mass. at 418.
    The board's initial approval of 0.257 mgd of BMWS water for
    sanitary and process use by the facility does not compel the
    conclusion that the proposed use of 1.1 mgd for the facility's
    cooling tower minimized environmental impacts as required by
    § 69J¼. Further, the board did not deviate impermissibly from
    its precedent. Although the board previously has granted siting
    19
    Although the board's denial of the PCF with respect to BMWS
    appears to preclude construction of the facility as currently
    proposed, we briefly review the city's appeal of the board's
    approval of the two other proposed changes.22
    3.   Elimination of ULSD capacity.   As initially approved by
    the board, the facility would use ULSD as an alternative fuel
    for up to sixty days per year.   In its PCF filing, Brockton
    Power proposed to construct the facility with natural gas-only
    generators, eliminating the facility's capacity to use ULSD.23
    permits for energy facilities utilizing municipal water for
    their cooling towers, the board's decision on the PCF here
    discussed and distinguished these precedents based on the
    evidence of environmental threats to the Silver Lake system
    contained in the record. See Tofias v. Energy Facilities Siting
    Bd., 
    435 Mass. 340
    , 349 (2001), quoting Robinson v. Department
    of Pub. Utils., 
    416 Mass. 668
    , 673 (1993) ("'reasoned
    consistency' . . . means only 'that any change from an
    established pattern of conduct must be explained'"). Finally,
    Brockton Power asserts also that the board's decision interfered
    with its right to obtain potable water from the BMWS in a
    nondiscriminatory manner. Because of the projected quantity of
    water that Brockton Power will need for the facility's cooling
    tower, discussed infra, the company is not situated similarly to
    other users of the system. See Rounds v. Board of Water & Sewer
    Comm'rs, 
    347 Mass. 40
    , 44 (1964).
    22
    The board concluded, "The evidence in this case
    demonstrated that the three proposed [p]roject changes are not
    interrelated in such a way that implementation of one [p]roject
    change without implementation of one, or both, of the other two
    changes is prevented. Accordingly, our findings stated above
    are made considering each proposed change on a stand-alone
    basis."
    23
    The PCF did not propose modifying the facility's use of
    three ULSD-powered "black-start" generators, used for restarting
    the turbine when power is not available.
    20
    According to Brockton Power, a gas-only plant would reduce air
    emissions, visual impacts, most ULSD deliveries, and the
    facility's water requirements, while the expansion of gas
    supplies in the Northeast would guarantee the reliability of the
    facility's energy supply.   The board found that a gas-only plant
    would "reduce the environmental impacts, consistent with the
    minimization of costs associated with the mitigation, control,
    and reduction of the environmental impacts" of the facility, as
    required by § 69J¼, fifth par.
    On appeal, the city primarily asserts deficiencies with
    respect to the air emission findings in the board's original
    final decision.24   As stated previously, in reviewing a PCF, the
    board need not consider issues that have already been decided in
    the original decision.   The board's PCF decision analyzed the
    PCF for accuracy and completeness and "compared the
    24
    For example, the city argues that the board erred by
    relying on the Environmental Protection Agency's National
    Ambient Air Quality Standards (NAAQS) to evaluate the facility's
    estimated emissions, and by using Logan Airport meteorological
    data. We address these issues in Brockton v. Energy Facilities
    Siting Bd. (No. 1), ante     (2014) (Brockon [No. 1]), also
    decided today. In addition, the city alleges that the board
    erred by not considering an alternative turbine and cooling
    tower design. However, the board was under no obligation to
    examine design alternatives in the context of a review of the
    PCF for a facility that it had already approved. See Box Pond,
    435 Mass. at 419-420. Finally, the city argues that the board
    failed to apply the Environmental Justice policy (EJ policy) to
    the PCF. We also discuss the EJ policy in Brockton (No. 1),
    supra. In this appeal, the city does not claim that the board
    failed to implement the procedural protections of the EJ policy
    in relation to the PCF.
    21
    environmental impacts of the facility as originally approved
    with the environmental impacts of the project as changed."       This
    approach is reasonable and consistent with the board's statutory
    mandate.    See Zachs, 
    406 Mass. at 227
     ("administrative agencies
    have broad discretion over procedural aspects of matters before
    them").    Our review of the city's appeal is limited to new
    issues raised by the PCF.    See Box Pond, 435 Mass. at 419-420
    (rejecting attempt to relitigate issues already decided in
    underlying proceeding).    With respect to the elimination of ULSD
    fuel, we conclude that Brockton Power's PCF was accurate and
    complete, and "minimize[d] the environmental impacts consistent
    with the minimization of costs associated with the mitigation,
    control, and reduction of the environmental impacts."    G. L.
    c. 164, § 69J¼, fifth par.
    The record indicates that with the elimination of ULSD, the
    emissions of all criteria pollutants will be reduced from the
    level estimated in the original petition, which the board has
    already approved (and we have upheld).25   Accordingly, there is
    25
    Brockton Power's estimated percentage reductions based on
    a comparison of the emission estimates in the proposal to those
    in the original final decision are as follows:    nitrogen
    dioxide (twenty-nine per cent); carbon monoxide (ten per cent);
    particulate matter up to ten micrometers in diameter (thirty-
    nine per cent); particulate matter up to 2.5 micrometers in
    diameter (PM2.5) (forty-two per cent); sulfur dioxide (twenty-
    three per cent); and volatile organic compounds (thirty-eight
    per cent). A smaller portion of this reduction is due to
    updated estimates (with respect to the proportion of particulate
    22
    no basis upon which the board could have concluded that the PCF
    would not minimize environmental impacts, as required by G. L.
    c. 164, § 69J¼, fifth par.26   The city has not met its burden of
    showing that the board's decision is invalid, unsupported by
    substantial evidence, or an abuse of discretion.    See Alliance
    I, 448 Mass. at 51.
    The city also argues that the board erred by
    underestimating the carbon monoxide (CO) emissions from the
    facility by basing its analysis on Brockton Power's allegedly
    inaccurate estimates of plant "start-up and shut-down" events.27
    In its PCF decision, the board noted that the city and Brockton
    Power disagreed about the modeling of the CO emissions.   Without
    analyzing the dispute, the board noted Brockton Power's lower
    matter classified as PM2.5) and improved aerodynamic downwash
    resulting from changes in the design features in the PCF. See
    note 26, infra.
    26
    With respect to the NAAQS for annual PM2.5 levels,
    Brockton Power's new estimate, based on a gas-only plant,
    updated projections regarding emissions, and design changes, is
    9.46 micrograms per cubic meter (µg/m3) annual PM2.5. In Brockton
    (No. 1), supra, we affirmed the board's approval of annual PM2.5
    at a level of 10.15 µg/m3.
    27
    Brockton Power estimated that the gas-only facility plant
    would emit 98.5 tons per year (tpy) of CO, a ten per cent
    reduction from 108.9 tpy for the facility approved by the board
    in the original final decision. According to the city's expert,
    the correct estimate for the facility's CO emissions is 138.8
    tpy. The city alleges that the lower figure, accepted by the
    board, is "conveniently below the then-applicable 100 tpy
    threshold for a rigorous review under the [F]ederal Clean Air
    Act's Prevention of Significant Deterioration . . . permitting
    process."
    23
    figures and stated that the facility would be subject to
    "enforceable annual and hourly limits . . . set out in [the
    DEP's] Conditional Air Plan Approval."     Brockton Power's CO
    emissions estimate, 98.5 tpy, represents 8.6 per cent of the
    NAAQS threshold for one-hour CO, and 18.9 per cent of the NAAQS
    threshold for eight-hour CO.   Although the city's estimate of
    138.8 tpy is higher than Brockton Power's, it is still well
    below the NAAQS limit for this pollutant.    The board is entitled
    to rely on the NAAQS thresholds to determine whether a project
    proposal has minimized the environmental impacts pursuant to its
    review.   See Brockton (No. 1), supra at      .   The board did not
    err by concluding that the CO emissions from a gas-only plant
    satisfied the standards of § 69J¼, fifth par.
    4.   Structural design changes.   In the original final
    decision, the board declined to grant Brockton Power's requested
    zoning exemption under G. L. c. 40A, § 3, which would have
    excused the facility from the Brockton zoning ordinance.
    Brockton Power did not appeal this aspect of the board's
    original decision.   In its PCF, however, Brockton Power proposed
    three changes to the facility as approved in the underlying
    decision, which, in its view, would make the facility compliant
    with the city's zoning ordinance.28    Although the board took no
    28
    First, Brockton Power proposed to replace the 130-foot
    building enclosing the heat recovery steam generator with four
    24
    position on whether the modifications would meet the city's
    zoning ordinance, it analyzed the changes with respect to noise
    and visual impacts, and concluded that the changes minimized the
    facility's environmental impacts as required by G. L. c. 164,
    § 69J¼, fifth par.29
    On appeal, the city argues that the board erred by
    approving a project that does not comply with a local zoning
    ordinance.    This argument is without merit.   In contrast to the
    minimization of visual and noise impacts, compliance with local
    zoning is not a precondition for the approval of a siting
    petition under § 69J¼.    The board's determination that zoning
    issues were "outside the scope" of its § 69J¼ review is
    reasonable.
    5.   Conclusion.    We affirm the board's PCF decision in all
    respects.
    So ordered.
    116-foot sound walls. Second, Brockton Power proposed to reduce
    the height of the main power facility building from sixty-four
    to sixty feet. Third, Brockton Power proposed to redesign the
    accessory buildings so that all of them would be under twenty-
    five feet in height.
    29
    At the time of the board's PCF decision, the zoning
    dispute was the subject of a case pending before the Land Court.
    

Document Info

Docket Number: SJC 11405, 11407

Judges: Ireland, Spina, Cordy, Botsford, Gants, Duffly, Lenk

Filed Date: 7/31/2014

Precedential Status: Precedential

Modified Date: 11/10/2024