Moulton v. McOwen , 103 Mass. 587 ( 1870 )


Menu:
  • Ames, J.

    The two cases between these parties were tried at the same time, and presented in such a manner that the same question arises in each. The matter which was relied upon as a defence in the case of McOwen v. Moulton is put forward as the .ground of a substantive claim of damages in the case of Moulton v. McOwen. It is obvious, that, if this claim should prove to be well founded in law and in fact, the plaintiff in the last named action can avail himself of it, under the operation of the legal provisions for setting off judgments against eacn other in cross actions, quite as well as in any other way. It is unnecessary, therefore, to disturb the verdict in the first named case; and the exceptions are to be considered as applying ex clusivcly to the last named of the two.

    Ir. that action, the plaintiff’s claim is for damages growing *591out of, and resulting directly from, the alleged imperfect and defective execution, on the part of the defendant, of a building contract; and the question is, as to the correctness of the rule of damages laid down at the trial. It was of course a question of fact whether the parties ever entered into the contract declared upon; and also whether, if there was such a contract, the defendant deviated from it in any material respect, and if so, whether such deviation was by the direction or consent of the plaintiff. If all these questions should be determined in favor of the plaintiff, then he would be entitled to recover in this action an amount equal to the difference in value between the work actually done by the defendant and the work which by the terms of the contract he ought to have done. The work was done upon the plaintiff’s land, and made a part of the house which he built. It was of some benefit and use to him. He could not reject it, or refuse to receive it, as if it had been a strictly personal chattel. The cases are presented in such a shape that the defendant is permitted to charge, and has obtained a verdict for, such a sum of money as, with previous payments, amounts to the entire contract price. In order to protect the plaintiff’s rights, he on his part should be allowed to charge such deficiency in the value of what he received, as compared with what by the contract he should have received, as he can show to have resulted from any unauthorized departure from the contract on the defendant’s part. It would be a question for the jury how much in dollars and cents did the work done and materials actually furnished by the defendant fall short in value of the value of the work and materials which by the terms of the contract he should have furnished; and that difference or deficiency would ordinarily be the measure of the plaintiff’s damages. Hayward v. Leonard, 7 Pick. 181. Smith v. First Congregational Meeting-house, 8 Pick. 178. Snow v. Ware, 13 Met. 42. Reed v. Scituate, 5 Allen, 120. Thompson v. Purcell, 10 Allen, 426. Gleason v. Smith, 9 Cush. 484. Bassett v. Sanborn, Ib. 58.

    At the trial in the superior court, certain specific deficiencies in the quality of the materials and in the execution of the wont, *592and in the entire omission of some portions of the work contracted for, were pointed out as items of damage to be considered and allowed for, if made out by the proof. This was correct as far as it went; but the court then proceeded to qualify this genera] instruction in a manner which had a tendency to mislead the jury. The amount expended in supplying defects is far from being necessarily the measure or limit of the plaintiff’s damages. The defect may be of such a nature as not to admit of being supplied by any reasonable expense. A partial repair may still leave the value quite short of the contract standard. To take the case suggested by the presiding judge, the owner may find one side of the building settled to such an extent that he may reasonably, and with good cause, believe that he cannot bring it up to its proper level without cracking the chimney, and rendering it unsafe. It is difficult to see why in that case he should not have some allowance for such a defect, merely because it is substantially irreparable, or in what sense it can be said to be “ not such a proximate damage as can be recovered for.”

    So far as we can judge from the bill of exceptions, the jury were not distinctly instructed to allow the plaintiff for the deficiency in value of the work done as compared with what by the contract should have been done. They may have supposed that no allowance was to be made to him except for the actual cost of supplying deficiencies, and that he could claim no allowance for defects that proved irreparable. In the case of Moulton v. McOwen, therefore, the Exceptions are sustained.

    At the new trial of the first case, after this decision, before Brigham, C. J., the jury returned a verdict for the plaintiff, and the defendant alleged exceptions substantially as follows:

    “ The plaintiff claimed as elements of damage that the cellar was not of the depth agreed upon; that there was no trench drain under the dry wall of the cellar; that the dry wall was not of the agreed thickness, was built of stone of a poor quality, and not built in a workmanlike manner, in consequence of which it fell after the structure was put upon it, injuring the cis*593tern in the cellar, and causing the house to settle so that it could not be restored to a level, but still remains out of level; and that, in consequence of not putting in a trench drain, the plaintiff was obliged to put in other drains, and do other things, to make the cellar dry. Against the defendant’s objection, the plaintiff was allowed to put in evidence of the cost of supplying particular defects, such as raising the building which had settled, repairing the cistern, putting drains into the cellar, and rebuilding the dry wall and mortar wall which had fallen; and also to offer evidence of the injury to the value and use of the structure, including the cellar and foundations, by reason of those irreparable injuries which arose from the negligence and carelessness of the defendant.
    “ Against the defendant’s objection, the plaintiff was allowed to ask John Bagley, (who, to qualify himself, testified that his business had for twenty-five years been that of a journeyman carpenter for wages, under the direction and oversight of house-builders and master workmen, never having himself built a house as a master workman, but who had worked on this building in its erection, and was so working when the wall fell,) what in his opinion was the amount in dollars and cents of the damage to the house above the foundation walls, as affecting its value and uses by reason of the settling of the house ; ’ to which he answered, from $250 to $300.’
    “ The defendant contended, and offered evidence to show, that the plaintiff had the oversight of building the cellar and dry wall, and agreed to the quality of the stone, and that the cellar and walls were constructed and built as he directed and under his oversight; that, when the dry wall was completed and before the mortar wall was put on, the structure, under the direction of the plaintiff, was erected upon the dry wall, resting upon blocks which rested directly upon the dry wall; that the plaintiff used jack screws upon the dry wall carelessly; that the whole work, by request of the plaintiff, was done in the winter, when the ground was frozen and freezing; that, when the dry wall was completed, the plaintiff, with full knowledge of the character of the work in all respects, paid the defendant, on account *594of the work then done, including the dry wall, $120, finding no fault, nearly or quite paying for the work then done, proportionally to the whole; and that, when the mortar wall was completed, he, with the full knowledge of the character of the work, paid the further sum of $70 without finding any fault, on account of the mortar wall, leaving only $30 more due on the job which the plaintiff retained until the dirt should be removed from the cellar. This claim was denied by the plaintiff, who offered evidence tending to show that he had no oversight or superintendence of the work of building the cellar or the walls of the same; that the house frame was placed upon blocks of timber resting on the wall in a proper manner; that the jack screws were only used to raise up the building after it had settled by reason of the defect in the cellar wall, and were then used in a proper manner, and were not placed upon the wall; and that he had no knowledge of the character of the wall when he paid the $120, nor when he paid the $70, at which time the plaintiff owed the defendant money for other work.
    “ The judge, upon the several points, instructed the jury as follows: General payments on account of the work are not to be construed as waiving defects therein, nor as accepting such defective work, unless such defects were known to the plaintiff at the time such payments were made. On perceiving that the defendant was failing to fulfil his contract, the plaintiff might legally and properly pay him the whole price of $220, or he might refuse to make further payments altogether, and rely on an action of tort for damages. The paying or not paying would in and of itself not raise a material inference as tending to show any acceptance of the defendant’s job. If, as the plaintiff claims, the defendant, by his careless and negligent performance of his undertaking to excavate a cellar, and to furnish materials for and build a cellar wall, has injured the plaintiff so that he has been put to labor and cost in reconstructing or repairing the cellar or the building placed upon it, or so that said cellar and building were as to their value or uses defective beyond reparation, or could not be repaired unless by wholly or partially reconstructing the same at a cost greatly disproportionate to theii *595value and uses, the plaintiff may recover the value of the labor and the cost of reconstructing and of repairing said cellar and building, made necessary by the defendant’s negligence and carelessness, and in addition thereto such an amount of money as will indemnify the plaintiff for any injury to him which may be reasonably imputed to the defendant’s careless and negligent performance of said undertaking, in the value and use of said cellar and building, which cannot be remedied by any repair or reconstruction of said cellar and building, unless the same was made at a cost greatly disproportionate to the value and uses of said cellar and building. If, however, as the defendant claims, his undertaking was upon the condition that the plaintiff would supervise, superintend and participate in the excavation, the choice of materials for, or the construction of, the said cellar, and if any defects in the materials and construction of said cellar were caused by a modification of the original undertaking agreed upon by the plaintiff and defendant, required by the plaintiff or acquiesced in by him, or were caused by mistake, errors in judgment, or haste in the construction of said cellar, in which, according to their mutual undertaking, the plaintiff and the defendant participated, the plaintiff cannot recover, nor can he recover for the injury to the cellar and building arising from said defects which is irreparable, or for the labor and cost made necessary to remedy said defects. It was not the plaintiff's duty to supervise, superintend or direct the work which the defendant undertook, in the absence of an agreement to do so; and his failure to do so would not excuse the defendant’s negligence or carelessness in the performance of his agreement; but if, at any time, or in reference to any detail of the work, the plaintiff, having his attention directed to it by the defendant or his servants, expressly or impliedly by his silence acquiesced in a modification of the wall, which ultimately caused a defect in the cellar or affecting the building upon it, he cannot impute such defect to the defendant’s negligence or carelessness, as a ground for recovering in this action, although it was of such a nature that it might reasonably have been imputed to the defendant’s carelessness and neglect. Defects in the cellar and *596the building upon it, which may be reasonably imputed to the season of the year in which the work was undertaken and prosecuted, or to the fact that the building was put upon the cellar before the cellar was completed, and the cellar completed while the building was resting upon it, the plaintiff cannot recover indemnity for in this action; nor is the defendant required to afford any explanation of such defects. Evidence of general payments of money by the plaintiff, without direction, to parts of the wall then done, or payments of money specifically applying to such parts of the work now alleged to have been defective by reason of the defendant’s negligence and carelessness; as well as residence and employment near the cellar; are circumstances to be considered by the jury, tending to show the plaintiff’s acceptance of and acquiescence in the same as well done, if they indicate that such defective condition was apparent or known to the plaintiff, but not otherwise.
    “ The defendant asked the judge to instruct the jury as follows : If the plaintiff, by the exercise of reasonable and ordinary care, might have known the quality of the materials and character of the work, then he was bound to exercise such care; and, neglecting to do so, and not objecting to the work as it was being done, he cannot now complain of the negligence of the defendant. If the plaintiff knew what was being done, while the work was going on, and saw and understood the quality of the materials and the character of the work, and did not object thereto, then this is such an assent thereto and acceptance thereof as relieves the defendant from liability. If the plaintiff, by agreement, took the oversight of the work of constructing the cellar and walls, and took charge of the men while doing the work, then the plaintiff, and not the defendant, is responsible for any defects in the work. But the judge declined to give said instructions, and instructed as above.
    “ The plaintiff, against the defendant’s objections, was al lowed to show the condition of the house in 1869, (the work having been done in the winter of 1867-8,) for the purpose of estimating the damages arising from the defendant’s carelessness. The jury found for the plaintiff, and assessed the damages *597in the sum of $242.02; and they also found, specially, that the amount and value of the labor and cost expended in repairing or reconstructing the cellar and building, to remedy defects therein caused by the defendant’s negligence and carelessness, were $92.02; that the cellar and building were affected, in their value and use, by defects which could not be repaired, and which were caused by the defendant’s carelessness and negligence, to the amount of $150; and that the cellar and building, as affected by the defendant’s carelessness and negligence in the performance of the contract, had a value, less than their value if there had been no neglect or carelessness of the defendant in the performance of the contract, of $242.02. The defendant excepts to the above rulings and refusals to rule.”

    These exceptions were argued at January term 1871, by the same counsel.

    Ames, J. We can see no valid objection to the admission of Bagley as an expert upon the subject matter in relation to which he testified. He was not a master builder; but it is difficult to see why a journeyman carpenter of twenty-five years’ experience, and who was employed on the building in question, should not be as well qualified to judge of the extent of its deficiencies and imperfections, as compared with the requirements of the contract, as if he had been a master builder.

    Upon the question whether the plaintiff directed or consented to the manner in which the work was done, or waived all objection to either the workmanship or materials, the evidence seems to have been conflicting. The facts that the plaintiff lived near the building, that the work was done in the winter, and that payments were made, from time to time, on general account, and without directing them to be applied to certain special items, were all submitted to the jury as circumstances to be taken into consideration and tending to show (if the defective condition of the work was apparent or known to him) his acceptance of and acquiescence in the same as well done; but the court ruled that the mere payment of money, in and of itself, would not raise a material inference as tending to show an acceptance of the work; that is to say, as we understand it, that *598the mere payment of the whole or part of the contract price would not amount to proof of a waiver of objections to the in* perfection of the . work, unless the circumstances under which such payment was made satisfied the jury that such a waiver was intended or ought to be inferred. The defendant has no ground of complaint against this ruling of the court.

    The rule as to the computation of the damages which the plaintiff might recover was also correct. It might perhaps have been stated, with more brevity, as being the amount in dollars and cents in which the value of the cellar and building as left by the defendant fell short of the value which they would have had if they had been finished according to the contract. It was certainly allowable and proper for the plaintiff to make at his own expense such repairs, or furnish such additional labor and materials, as should supply all such deficiencies as could be supplied without disproportionate or unreasonable expense. If, after this was done, there should still remain deficiencies and injuries which could not be repaired except at a cost greatly disproportionate to the value of the building, he would be entitled to have the effect of those deficiencies and injuries in diminishing its value estimated by the jury. They have found that he expended $92.02 in remedying defects, and that after so doing there still remains a loss upon the building of $150, caused by the defendant’s neglect. These two sums together make up the damages according to the rule given in our previous decision in this case. See also Hayward v. Leonard, 7 Pick. 187; Veazie v. Hosmer, 11 Gray, 396; Gleason v. Smith, 9 Cush. 484; Cardell v. Bridge, 9 Allen, 355; Thompson v. Purcell, 10 Allen, 426. Exceptions overruled.

Document Info

Citation Numbers: 103 Mass. 587

Judges: Ames

Filed Date: 1/15/1870

Precedential Status: Precedential

Modified Date: 11/9/2024