Denham v. Bryant , 139 Mass. 110 ( 1885 )


Menu:
  • Devens, J.

    The plaintiffs sue upon the common counts for goods sold and delivered. The defendants’ answer sets up that the goods were delivered under a special contract, which is set out at length, and alleges that the plaintiffs did not carry out the contract by delivering the goods mentioned in the agreement, and that the defendants have paid all that by said agreement they were bound to pay for such as were delivered. By the terms of the contract, the defendants agreed to take of the plaintiffs mouldings to the value of not less than §15,000, orders to be given at not less than §1000 worth per month, and the whole to be taken by a certain date. The plaintiffs agreed to receive as one fifth payment a certain parcel of land in Cambridgeport.

    It appeared, at the trial in the Superior Court, that the contract had been actually made as alleged in the answer, and that the plaintiffs, after a portion of the goods had been delivered, refused to complete the same, and to take the land which was to be a partial payment. The facts found by the auditor as to the amount of goods delivered by the plaintiffs, and the balance which had not been paid, were not disputed by the defendants. They contended that they had suffered damage by reason of the failure of the plaintiffs to receive the deed of land referred to in the written agreement, and were permitted to introduce evidence that the market value of the land at the time the agreement was made was less than §3000, (which was the price at which it would have been allowed for in the contract had that *111been completed); and also that they were entitled to receive any difference between $3000 and the market value of the land, as the measure of damages suffered by them by reason of the failure of the plaintiffs to take a deed thereof.

    The plaintiffs urged that this evidence was not admissible under the defendants’ answer, as it did not there appear that they made any claim that they had suffered damage by reason of the plaintiffs’ failure to take a deed of the land. To the ruling that it was admissible, the plaintiffs excepted.

    While the defendants’ answer alleged payment, that which the defendants really relied upon was an offset, by way of recoupment, to the plaintiffs’ bill for goods delivered, of the damages which they had themselves sustained by reason of the plaintiffs’ failure fully to complete their contract. A defendant is not compelled to resort to a cross action. Stacy v. Kemp, 97 Mass. 166. Clark v. Russell, 110 Mass. 133. If the defendants had sustained damage by reason of the failure to deliver all the goods contracted for, or by refusal of the plaintiffs to accept a deed of the land, at the price named, to an amount equal to the value of the goods received, they could not therefore allege that these had been paid for. Where there has been a failure to perform a contract fully, as to build a house or to deliver goods, but valuable service has been rendered, materials furnished or goods delivered, it is the right of the plaintiff to recover their value, less the damage which has been occasioned to him by breach of the stipulations contained in the contract. Cullen v. Sears, 112 Mass. 299, and authorities cited. But that a defendant may entitle himself to such damages, he must state what stipulations have been violated, and how damage has been thus occasioned. He cannot properly allege that he has fully paid for that he has received, when he is only entitled to recoup against this value the damages which he has sustained by reason of a violation of the contract in other particulars. Mulry v. Mohawk Valley Ins. Co. 5 Gray, 541. Wheaton v. Nelson, 11 Gray, 15. Canfield v. Miller, 13 Gray, 274.

    In this case, the defendants rely upon substantive facts wholly or partially in avoidance of the plaintiffs’ claim, and these should be set forth distinctly. Pub. Sts. o. 167, § 20. The failure to deliver all the goods contracted for, which is averred in the *112answer, does not convey the information that the defendants rely, in answer to the action, upon the fact that they have thereby been prevented from selling the tract of land which was to be received in partial payment at the price contracted for. Nor is this so, even if the answer refers to, and incorporates, the written contract. There is no allegation that the price there named is above the real value of the land.

    E. S. Mansfield, for the plaintiffs. W W. Blackmar & H. N. Sheldon, for the defendants.

    We are therefore of opinion that the learned judge who presided erred in ruling this evidence to be admissible under the pleadings as they stood.

    But while this is so, it appears to us that the merits of this case have been fully and fairly tried. Where this appears, and where there is a variance between the declaration and proof, it has been properly held that the plaintiff may be allowed, even after verdict, to amend his declaration on terms. Keller v. Webb, 126 Mass. 393. Whitney v. Houghton, 127 Mass. 527. Fenton v. Lord, 128 Mass. 466. By the auditor’s report, which the plaintiffs put in evidence, it was shown that they, and their assignee refused to complete this contract or take this land. They asked no continuance of the cause on the ground of any surprise. We think, therefore, that the defendants should now be allowed to amend their answer, on such terms as appear just to the Superior Court; and, on filing such amendment, the entry will be, Exceptions overruled.

Document Info

Citation Numbers: 139 Mass. 110, 28 N.E. 691, 1885 Mass. LEXIS 36

Judges: Devens

Filed Date: 3/7/1885

Precedential Status: Precedential

Modified Date: 10/18/2024