    This is an action of contract on an alleged agreement whereby the defendant was to lease certain premises owned by the plaintiffs. The case was referred to an auditor under an agreement of the parties that his findings of fact should be final.

    The auditor found as follows: The plaintiffs are the owners of the property numbered 231 Bedford Street in Fall River. About October 16, 1928, the plaintiffs, the defendant and one Morganstein met in New Bedford and the following agreement was drawn up. ‘ October 16, 1928 H. F. McCormick, New Bedford, Mass. Gentlemen: We hereby agree to give you a lease on the garage located at 231 Bedford Street, Fall River, Mass., showroom and service station .... The lease is to be for two years beginning November 15th, 1928 and to have a two year renewal option at a monthly rental of $280.00 . . . payable in advance on the first day of each month with a ten day grace period. Same to be furnished with heat. It is agreed that the floor to be covered and the showroom also same to be painted to be agreed upon by both parties. Also a partition for the office and another partition for the parts department agreeable to both parties.’ Both copies of this agreement were signed by the plaintiffs but only one [was signed] by the defendant which he . . . retained. No copy signed by the defendant was ever delivered to the plaintiffs. The property was to be ready [for occupancy] by November 15, 1928. The plaintiffs, following the suggestions of defendant, made the necessary changes and alterations at a cost of . . . $1,157.50 .... November 1, 1928, plaintiffs received a letter from defendant stating ‘ Please get *252lease to me at once so that I can take it up with him.’ November 5, 1928, Timothy J. Greany took a lease to defendant. This lease was not signed by any of the parties though the plaintiffs were ready and willing to sign .... This unexecuted lease was left with defendant who said he wanted to look it over and would let them know. Nothing was heard from defendant [by the plaintiffs] until after December 8, 1928, the date of the writ. At which time the defendant wanted to settle the matter because he would not be able to take the lease having lost the agency of the ■ Dodge car. No settlement was arrived at and on December 19, 1928, an agreement for lease was given [by the plaintiffs] to the Mack Truck Company, rent to begin January 1, 1929. After this the defendant told plaintiffs that he would be willing to take the lease.” The auditor further found that the loss by the plaintiffs of rent from November 15, 1928, to January 1, 1929, at the rental stipulated in the agreement, amounted to $420, that the amount expended by them for repairs and alterations was $1,157.50, and that the total of these two items, $1,577.50, was the amount of damage they had sustained. The auditor filed an amended report which is in substance like the first except that it contains the following paragraph: January 1, 1929, the Mack Truck Company lease began at a rental of $400 a month for the entire premises, of which the agreement with defendant was a part. The improvements made for defendant remained although other changes were made for the Mack Truck Company.” The trial judge denied the defendant’s motion for the entry of judgment in his favor, and allowed the plaintiffs’ motion that judgment be entered-in their favor on the findings of the auditor. From the action of the judge upon these motions the defendant appealed.

    The agreement dated October 16, 1928, which was prepared when the parties met on that date, constituted a definite offer on the part of the plaintiffs to lease the premises to the defendant. Upon the findings it could have been further found that, the defendant by his conduct accepted the plaintiffs’ offer and is bound thereby. A contract exists *253if a paper containing its terms is accepted. Although the agreement at its inception is unilateral, upon acceptance it becomes binding upon both parties. Buffington v. McNally, 192 Mass. 198, 201. The fact that the defendant did not sign the offer contained in the paper of October 16, 1928, will not prevent recovery by the plaintiffs where, as here, it might well be inferred that the defendant by conduct assented to its terms. His secret intention not to do so was immaterial. Assent may be indicated by acts as well as by words . . . Williston on Contracts, §§ 90, 91, 91a. Hobbs v. Massasoit Whip Co. 158 Mass. 194, 197. Bohn Manuf. Co. v. Sawyer, 169 Mass. 477, 482. Spencer v. Spencer, 181 Mass. 471, 473. New York Central & Hudson River Railroad v. York & Whitney Co. 230 Mass. 206, 222. Houghton & Dutton Co. v. Journal Engraving Co. 241 Mass. 541, 544. Nickel v. Zeitz, 258 Mass. 282, 285. Hawkes v. First National Bank of Greenfield, 264 Mass. 545, 548.

    There is no error of law in the finding of the auditor on the question of damages. The general rule is that in an action of contract the damages must be the direct, natural result of the breach, and to have been in the contemplation of the parties when the contract was made as the probable result of such breach. Swift River Co. v. Fitchburg Railroad, 169 Mass. 326. John Hetherington & Sons, Ltd. v. William Firth Co. 210 Mass. 8, 21. Jacobs v. Cromwell, 216 Mass. 182, 183. Narragansett Amusement Co. v. Riverside Park Amusement Co. 260 Mass. 265, 280, 281. The loss of rent due to the failure of the defendant to carry out the agreement was a proper element of damages. The necessary changes and alterations in the premises made at the suggestion of the defendant could be found to have been made for his benefit and necessary for the occupation of the leased premises in the conduct of his business. The plaintiffs’ motion filed in this court to increase the ad damnum in the writ to $2,000 is allowed.

    Judgment for the plaintiffs affirmed.