C & R Construction Co. v. City of Boston , 273 Mass. 280 ( 1930 )


Menu:
  • Wait, J.

    The plaintiff, which will hereinafter be called the company, on March 28, 1929, brought an action at law against the city of Boston, hereinafter called the city, to recover a balance due under a contract made in October, 1926, and completed July 19, 1928, for work upon Beacon Street in Boston. The city admitted its liability therefor. The city declared in set-off for the amount paid in settlement of an execution issued upon a judgment entered in December, 1926, upon a verdict against it in favor of one Roewer, recovered by Roewer for damages sustained by him on August 17, 1924, arising out of a defect in Bowker Street, Boston. The company admitted that said suit was brought, and that a verdict was returned against the city in the amount named.

    *282There was evidence that the company in 1924 did certain work for the city in Bowlcer Street under a contract which inter alla provided that it would indemnify and hold the city harmless “ against, all claims for damages to persons or property occasioned by, or resulting from, blasting or other methods or processes in the work of construction, whether such damages be attributable to negligence of the Contractor or his employees or otherwise ”; and which required the company to refill its trench and, after refilling and replacing paving, to maintain it “ in such a condition that traffic may be carried on over the same with safety.” There was evidence tending to show that Roewer was injured in consequence of a defective condition in the paving near the refilled trench, although certain testimony, if believed, would prove that no such defect existed at the time of his injury. There was evidence that the city had made final payment to the company under the 1924 contract, which provided that any balance found as provided in this article [which dealt with payments] shall be deemed the final settlement under the contract.” Such payment, however, was not a bar to the city’s claim for damage resulting from negligence of the contractor; and there was no error in denying the plaintiff’s motion for a directed verdict in its favor on the defendant’s declaration in set-off. The judge admitted, subject to the company’s exception, a notice from the city to the company, dated January 22,1925, that action was pending against the city brought by Roewer claiming damage from a defect in Bowker Street caused by the improper refilling of the excavation. The notice, which was served by an officer, charged the company with responsibility and called upon it to assume defence of the action. The officer’s return showed acceptance of service for the company by its attorney. There was no evidence that it paid any attention to the notice. The ruling was right. It was material to show that the company had been notified of Roewer’s claim and requested to defend against it, if the city wished to establish that the company was bound by the verdict.

    The evidence did not go far enough to show, as matter of *283law, that the defect for which Roewer sued was one that the company was bound to indemnify against and resulted from methods or processes in its work of construction under the contract of 1924, nor that the judgment bound the company. Whether liability rested upon the company was in part matter of fact for a jury. The trial judge, however, directed the jury to find for the city in set-off against the company for the amount paid upon the judgment with interest. In so doing he was in error. It is only when the evidence, as matter of law, requires a particular verdict, or is binding upon a party, so that contradictory evidence cannot control it, that a verdict can be ordered in favor of the party upon whom the burden of proof rests. Lindenbaurn v. New York, New Haven & Hartford Railroad, 197 Mass. 314. Eddy v. Johnston, 250 Mass. 299, 301. Hicks v. H. B. Church Truck Service Co. 259 Mass. 272, 276. The burden rested on the city to prove that the judgment was binding upon the company. Although the evidence might sustain a finding to that effect, it did not require it as matter of law. The company was not bound by any admission which established its liability. Its exception to the direction of the verdict in set-off for the city must be

    Sustained.

Document Info

Citation Numbers: 273 Mass. 280

Judges: Wait

Filed Date: 11/25/1930

Precedential Status: Precedential

Modified Date: 6/25/2022