NextEra Energy Resources, LLC v. Department of Public Utilities ( 2020 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    SJC-12886
    NEXTERA ENERGY RESOURCES, LLC vs. DEPARTMENT OF PUBLIC
    UTILITIES & others.1
    Suffolk.       April 9, 2020. - September 3, 2020.
    Present:    Gants, C.J., Gaziano, Lowy, Budd, Cypher,
    & Kafker, JJ.
    Electricity. Electric Company. Public Utilities, Electric
    company, Electrical transmission line, Sale of electric
    power. Administrative Law, Agency's interpretation of
    statute, Agency's interpretation of regulation.
    Civil action commenced in the Supreme Judicial Court for
    the county of Suffolk on July 22, 2019.
    The case was reported by Lowy, J.
    Donald E. Frechette for the petitioner.
    Gerald J. Petros, Special Assistant Attorney General, for
    the respondent.
    Jared S. des Rosiers, of Maine, Andrew O. Kaplan, Joshua D.
    Dunlap, Jed M. Nosal, & Jesse S. Reyes, for Central Maine Power
    Company, intervener, submitted a brief.
    1  Central Maine Power Company, intervener; NSTAR Electric
    Company, doing business as Eversource Energy, intervener;
    Massachusetts Electric Company and Nantucket Electric Company,
    each doing business as National Grid, interveners; and Fitchburg
    Gas and Electric Light Company, doing business as Unitil,
    intervener.
    2
    John K. Habib, Matthew S. Stern, Danielle C. Winter,
    Matthew Campbell, & Patrick H. Taylor, for NSTAR Electric
    Company & others, interveners, submitted a brief.
    Mark C. Kalpin, Brett D. Carroll, & Christopher M.
    Iaquinto, for New England Power Generators Association, Inc.,
    amicus curiae, submitted a brief.
    KAFKER, J.   This case concerns recent legislation intended
    to facilitate the development of hydroelectric and other clean
    energy sources by requiring electricity distribution companies
    in the Commonwealth to contract for the purchase of electricity
    generated through environmentally friendly means.   The
    challenged power purchase agreements (PPAs) would allow
    electricity distribution companies to purchase clean electricity
    generated hydroelectrically by Hydro-Québec Energy Services
    (U.S.), Inc. (HQUS); this electricity would be supplied to New
    England via a transmission line running from Québec to Maine.
    According to the petitioner, NextEra Energy Resources, LLC, the
    PPAs at issue are inconsistent with statutory requirements that
    such agreements provide for "firm service" hydroelectric
    generation -- a term referring to hydroelectric power that is
    provided without interruption -- and that such generation be
    solely hydroelectric.   Additionally, the petitioner objects to
    the PPAs' use of the New England Power Pool (NEPOOL) Generation
    Information System (GIS), a tracking system intended to account
    for each unit of electricity transmitted, claiming the tracking
    system is inadequate to ensure statutory compliance.
    3
    In its order, the Department of Public Utilities
    (department) concluded that the PPAs allowed for electricity
    delivery to be interrupted only in limited circumstances, and
    that provisions requiring HQUS to cure delivery shortfalls or
    pay damages create an appropriate incentive for HQUS to deliver
    energy and fulfill firm service requirements.     Shortfalls were
    carefully circumscribed by the agreements, encompassing only a
    narrow set of circumstances outside HQUS's control.     The
    department also concluded that the PPAs provide for delivery of
    energy generated by sixty-two specified hydroelectric generating
    facilities operated by HQUS, and the NEPOOL GIS tracking system
    was sufficient as it was the industry standard.
    We affirm the department's order approving the PPAs.     We
    conclude that the department reasonably and realistically
    interpreted the firm service requirement.   We also uphold the
    department's conclusions that the PPAs guarantee electricity
    generated solely from hydroelectric generation and that the
    NEPOOL GIS tracking system is an adequate means to ensure the
    required accounting.   These rulings were supported by
    substantial evidence and sufficient rationale.2
    2 We acknowledge the amicus brief submitted by New England
    Power Generators Association, Inc. As is "[u]sually" the case,
    amicus argument "is limited to only those issues addressed by
    the parties" (citation omitted). Teamsters Joint Council No. 10
    v. Director of the Dep't of Labor & Workforce Dev., 
    447 Mass. 100
    , 100 n.2 (2006). We therefore decline to address the
    4
    1.   Background.   In 2008, the Legislature passed St. 2008,
    c. 169, entitled "An Act relative to green communities," to
    "provide forthwith for renewable and alternative energy and
    energy efficiency in the commonwealth."3   In 2016, the
    Legislature passed St. 2016, c. 188, entitled "An Act to promote
    argument that the power purchase agreements (PPAs) did not
    contract for incremental clean energy, i.e., more energy than is
    otherwise available to the market in the Commonwealth, as this
    argument was raised only by the amicus. See Finch v.
    Commonwealth Health Ins. Connector Auth., 
    459 Mass. 655
    , 669
    n.13 (2011); General Mills, Inc. v. Commissioner of Revenue, 
    440 Mass. 154
    , 167 n.7 (2003), cert. denied, 
    541 U.S. 973
     (2004).
    3 The Legislature passed this act the same year that it
    passed St. 2008, c. 298, the Global Warming Solutions Act
    (GWSA). "Each act addresses a separate but related piece of the
    clean energy economy," and both "provide policymakers with a
    broad array of tools, including 'targeted and technology-
    specific policies[,] . . . economy-wide and market-based
    mechanisms,' and renewable energy portfolio standards and energy
    efficiency improvements, to advance a clean energy economy while
    reducing emissions and addressing the unique threats that
    climate change poses to the Commonwealth." Kain v. Department
    of Envtl. Protection, 
    474 Mass. 278
    , 282 (2016), quoting Report
    of the Senate Committee on Global Warming and Climate Change, No
    Time to Waste, at 10 (Feb. 13, 2015); Executive Office of Energy
    and Environmental Affairs, Massachusetts Clean Energy and
    Climate Plan for 2020, Executive Summary, at 7 (Dec. 29, 2010).
    The GWSA was "designed to make Massachusetts a national,
    and even international, leader in the efforts to reduce the
    greenhouse gas emissions that cause climate change," and
    "establishes significant, ambitious, legally binding, short- and
    long-term restrictions on those emissions" (quotation omitted).
    New England Power Generators Ass'n, Inc. v. Department of Envtl.
    Protection, 
    480 Mass. 398
    , 399 (2018). The GWSA mandates a
    twenty-five percent reduction from 1990 greenhouse gas emission
    levels by 2020 and an eighty percent reduction by 2050. G. L.
    c. 21N, §§ 3, 4. Statute 2018, c. 169, and the provisions at
    issue in this case play an essential role in achieving these
    objectives by requiring the generation of clean energy.
    5
    energy diversity,"   which, among other changes, amended St.
    2008, c. 169, by setting up a competitive bidding process for
    contracts to finance the production of clean energy.     St. 2016,
    c. 188, § 12.   This amendment was effectuated by adding §§ 83B
    and 83D to St. 2008, c. 169 (Sections 83B and 83D).    Id.
    Section 83D required electric distribution companies to
    jointly and competitively solicit proposals for eligible clean
    energy generation resources no later than April 1, 2017, and,
    provided reasonable proposals had been received, to enter into
    cost-effective, long-term contracts -- known as PPAs -- to
    facilitate the financing of clean energy generation resources
    equal to approximately 9.45 million megawatt-hours (MWh) per
    year by December 31, 2022.   As required by statute, the
    department must approve a PPA before it can become effective.
    See Section 83D (e); 220 Code Mass. Regs. § 24.03 (2017).
    "Clean energy generation" includes "firm service hydroelectric
    generation," which Section 83B defines as "hydroelectric
    generation provided without interruption for [one] or more
    discrete periods designated in a long-term contract."4     The
    4 Regulations promulgated by the Department of Public
    Utilities (department) define firm service hydroelectric
    generation as "hydroelectric generation provided without
    interruption for one or more discrete periods designated in a
    long-term contract, including but not limited to multiple
    hydroelectric run-of-the-river generation units managed in a
    portfolio that creates firm service though the diversity of
    multiple units." 220 Code Mass. Regs. § 24.02 (2017). That
    6
    phrase "without interruption" is not defined by statute or the
    accompanying regulations.
    On July 23, 2018, NSTAR Electric Company, doing business as
    Eversource Energy; Massachusetts Electric Company and Nantucket
    Electric Company, each doing business as National Grid; and
    Fitchburg Gas and Electric Light Company, doing business as
    Unitil (companies), filed separate petitions with the
    department, pursuant to Section 83D and 220 Code Mass. Regs.
    §§ 24.00 (2017), for approval of individual PPAs for the
    purchase of hydroelectric generation and associated
    environmental attributes from HQUS.   The PPAs were negotiated
    and submitted to the department after the companies and the
    Department of Energy Resources (DOER) selected a project
    submitted jointly by Hydro Renewable Energy, Inc., an HQUS
    affiliate, and Central Maine Power Company (CMP) after a three-
    stage bidding process.5
    Under the PPAs, the power will be delivered to New England
    over a transmission line that starts at a substation in Thetford
    description applies here, as Hydro-Québec Energy Services
    (U.S.), Inc. (HQUS), will provide the energy guaranteed under
    the PPAs from sixty-two specified hydroelectric generating
    facilities.
    5 The three-stage bidding process, initiated by a request
    for proposals, met the requirements of St. 2008, c. 169, § 83D,
    as inserted by St. 2016, c. 188, § 12 (Section 83D), and is not
    at issue in this appeal.
    7
    Mines, Québec, and runs sixty-five miles to the Canada-Maine
    border.   The power would then be transmitted by means of a new
    transmission line owned by CMP, named New England Clean Energy
    Connect, that travels another 145 miles to a substation in
    Lewiston, Maine.   The PPAs specifically provide for a twenty-
    year service term beginning on the commercial operation date.
    The material terms of the three PPAs are nearly identical.
    We describe those terms only as they relate to this appeal.     The
    PPAs provide that HQUS's obligations to sell and deliver
    hydroelectric-generated energy, and the companies' obligations
    to buy the same, "are firm and not subject to interruption
    except to the extent caused by Force Majeure, excused under
    Section 4.2(a)[6] or cured in accordance with Section 4.3(c)
    [governing curable delivery shortfalls]."
    "Curable delivery shortfalls" under section 4.3(c) of the
    PPAs are shortfalls that result from (1) nonexcused outages,
    i.e., outages or reductions in total transfer capacity other
    than outages or reductions caused by force majeure, scheduled
    maintenance, regulatory decisions, or outages in the
    transmission line from Québec to the Canada-Maine border; or
    (2) outages or reductions in that same transmission line due to
    6 Outages or reductions below capacity caused by force
    majeure, scheduled maintenance, regulatory decisions, or outages
    in the transmission line from Québec to the Canada-Maine border
    are referred to as "excused outages" in the PPAs.
    8
    a physical condition affecting its transfer ability.   The PPAs
    allow HQUS to cure these shortfalls by delivering qualified
    shortfall energy7 during the shortfall cure period.8
    Under the PPAs, "uncured delivery shortfalls" are delivery
    shortfalls HQUS has not cured by the delivery of qualified
    shortfall energy.   Shortfalls that are not cured must be
    remedied by cover damages.   These damages include any penalties
    or additional costs incurred by the companies as a result of
    having to purchase replacement energy.   Additionally, under
    section 9.2(f) of the PPAs, if "[t]he aggregate Uncured Delivery
    Shortfalls in any Shortfall Cure Period are more than twenty
    percent (20%) of the Guaranteed Qualified Clean Energy for such
    Shortfall Cure Period (a 'Defaulted Delivery Shortfall')," HQUS
    has defaulted on the PPAs.   Only shortfalls due to transmission
    line failures are counted when calculating the ratio of
    defaulted delivery shortfalls.   In other words, section 9.2(f)
    7 Qualified shortfall energy is hydroelectric energy
    delivered over any transmission line to the companies during the
    twenty-year term of the PPAs. This energy must also be tracked
    in GIS to ensure it is hydroelectric-generated energy.
    8 A shortfall cure period is defined in the PPAs as "the
    same Contract Year in which the Curable Delivery Shortfall
    occurred or in the immediately succeeding Contract Year."
    9
    does not encompass any decision by HQUS to sell the power to a
    third party.9
    The PPAs further provide that HQUS is responsible for
    maintaining participation in NEPOOL GIS "to register, monitor,
    track, and transfer Environmental Attributes" in order to
    demonstrate that the energy delivered is qualified clean energy.
    NEPOOL is an industry association of energy market participants
    in the New England region.     See 310 Code Mass. Regs. § 7.75(2)
    (2020).   NEPOOL GIS is a database and certificate system
    operated by NEPOOL.     See id.; Jones, James, & Huebner, Do You
    Know Who Owns Your Solar Energy?     The Growing Practice of
    Separating Renewable Attributes from Renewable Energy
    Development and Its Impact on Meeting Our Climate Goals, 
    28 Fordham Envtl. L. Rev. 197
    , 216-217 (2017) (Jones).     The NEPOOL
    GIS tracking system has been employed and relied on by State and
    Federal regulators and generators for nearly twenty years to
    track renewable energy generation and its environmental benefits
    in New England.    The system accounts for the environmental
    attributes associated with each MWh of electricity produced.
    Jones, supra.     Those attributes are recorded in the form of a
    certificate, which may be used to substantiate and track
    9 Instead, a decision by HQUS to sell the power to a third
    party would constitute a breach of the agreements, and would not
    constitute a delivery shortfall remediable by cover damages.
    10
    compliance with environmental regulations.10   Id.   See 310 Code
    Mass. Regs. § 7.75(2).
    The department held a joint public hearing and procedural
    conference for the companies' petitions on August 15, 2018.    It
    granted the petitioner's petitions to intervene as a full party
    in each of the three dockets.   The department held joint
    evidentiary hearings on the three dockets in February 2019.    It
    received testimony from fourteen witnesses at the hearings,
    including three witnesses called by the petitioner.
    10These certificates, also referred to as credits, function
    as an independent form of property right and may be sold to
    third parties separately from the electricity to which the
    certificates relate: the certificates have value to these third
    parties because they may use those certificates to comply with
    environmental regulations or qualify for legal benefits. See,
    e.g., Indeck Me. Energy LLC v. Comm'r of Energy Resources, 
    454 Mass. 511
    , 512–513 (2009) (explaining that certificate, "once
    purchased, is counted toward [an] electricity supplier's
    compliance" with environmental laws); Jones, James, & Huebner,
    Do You Know Who Owns Your Solar Energy? The Growing Practice of
    Separating Renewable Attributes from Renewable Energy
    Development and Its Impact on Meeting Our Climate Goals, 
    28 Fordham Envtl. L. Rev. 197
    , 197–198 (2017) (Jones).
    NEPOOL GIS users are bound by a complex set of operating
    rules that, among other things, govern how certificates are
    created, how certificates may be transferred, and how the
    department, DEP, and other regulatory agencies may access
    information on the system's database. See, e.g., New England
    Power Pool Generation System Operating Rules, Rules 2.1, 3.1,
    5.3 (Jan. 1, 2020). The department (formerly the Department of
    Telecommunications and Energy Resources) helped develop these
    rules. New England Generation Information System, D.T.E. 03-62-
    A, at 9, 24 n.14 (2004).
    11
    On June 25, 2019, the department issued its order approving
    the PPAs.   It concluded that the PPAs provide firm service
    hydroelectric generation without interruption from hydroelectric
    generation alone as required by Section 83D.   It further found
    that the PPAs included "a schedule of guaranteed qualified clean
    energy to be delivered from HQUS on a monthly basis for each
    year of the contract term."
    The department determined that the PPAs allowed electricity
    delivery to be interrupted in only three circumstances:     (1)
    force majeure; (2) deliveries excused during negative locational
    marginal pricing (LMP) periods11; and (3) curable delivery
    shortfalls.   The department explained that the provisions in the
    PPAs requiring HQUS to cure delivery shortfalls were consistent
    with Section 83D's firm service requirement.   It reasoned that,
    "[g]iven the nature of electricity transmission, delivery
    11Locational marginal pricing (LMP) is a method of pricing
    electricity based on its value at different times and locations.
    See Sacramento Mun. Util. Dist. v. Federal Energy Regulatory
    Comm'n, 
    616 F.3d 520
    , 524-525 (D.C. Cir. 2010) ("LMP consists of
    three components: [i] the cost of generation; [ii] the cost of
    congestion; and [iii] the cost of transmission losses").
    Negative LMP periods are periods in which the supply of
    electricity is greater than demand. The department concluded
    that the delivery of electricity generated in such periods would
    be wasteful. Cf. Barton Windpower, LLC vs. Northern Ind. Pub.
    Serv. Co., U.S. Dist. Ct., No. 13-CV-5329 (N.D. Ill. June 18,
    2018) ("When the LMP is negative, market participants . . . can
    stop generating power, or they can continue to generate power
    and sell it to [the system operator] at the negative price
    [i.e., pay [the system operator] to take the power]").
    12
    shortfalls will occasionally happen," and therefore "any long-
    term contract for renewable energy generation requires
    reasonable provisions to address them."    The department found
    that the PPAs' curable delivery shortfall provisions
    appropriately "allow HQUS to fulfill its firm delivery
    obligations while reasonably accommodating transmission outages
    that are not within its direct control."
    Relatedly, the department also found that the cover damages
    provisions requiring HQUS to pay damages in the event that it
    fails to cure a shortfall "reasonably support the PPAs' firm
    energy delivery provision by (1) providing an appropriate
    incentive for HQUS to deliver energy during the winter months
    (and otherwise)[12] and (2) making ratepayers financially whole in
    the event that an uncured delivery shortfall should occur."
    The department also concluded that the PPAs require HQUS to
    deliver, and the companies to purchase, energy derived solely
    from hydroelectric generation, as required under Section 83D.
    12The PPAs contain provisions that guarantee energy
    delivery on a year-round basis, including in winter months. The
    department rejected the petitioner's argument that the delivery
    shortfall provisions would allow HQUS to curtail delivery during
    winter months because it found that the PPAs "limit the delivery
    of qualified shortfall energy to the same season-peak period as
    when the curable delivery shortfall occurred, in [either] the
    same year or the immediately succeeding contract year."
    Additionally, the PPAs provide a method for reconciling
    differences in the economic value of the energy that was to be
    delivered when the shortfall occurred and the energy actually
    delivered to cure the shortfall.
    13
    It based this finding on the fact that the PPAs require all
    energy deliveries to derive from "energy produced by a
    hydroelectric generating resource," particularly the sixty-two
    specified hydroelectric generating facilities operated by HQUS.
    Although the PPAs describe these facilities as "consist[ing]
    predominantly of low-carbon and renewable hydro-electric energy"
    (emphasis added), the department dismissed the petitioner's
    argument that the use of the term "predominantly" would leave
    HQUS free to deliver energy from non-hydroelectric sources.     It
    rejected this argument because the PPAs "unambiguous[ly]"
    require that any energy sold be from clean, hydroelectric
    generation.
    Finally, the department concluded that the PPAs provide the
    energy generated must "be tracked in the NEPOOL GIS to ensure a
    unit-specific accounting" of the delivery of qualified clean
    energy (footnote omitted).13   The department therefore concluded
    that the PPAs complied with Section 83D (j)'s requirement of
    unit-specific accounting for clean energy delivery.   The
    department also found that NEPOOL GIS, "a well-established power
    13"Unit energy" is energy imported into New England that is
    generated by specifically identified generation units assigned
    certificates for their respective, specific environmental
    attributes. "System energy," on the other hand, is power
    imported into New England without specifically identifying the
    specific generation unit. For such energy, NEPOOL GIS assigns
    the characteristics of the over-all mix of the fuel source and
    emissions of the source control area.
    14
    generation and associated environmental attribute tracking
    system used in the New England region," adequately ensured that
    "the Companies purchase clean energy generation as defined by
    statute, and not system energy that contains non-clean energy
    generation."
    After the department issued its order, the petitioner
    appealed to a single justice of this court.    The department and
    the intervening parties moved to reserve and report the matter
    to the full court, which the petitioner did not oppose.     The
    matter was reserved and reported to the full court on January
    27, 2020.
    2.   Discussion.   a.   Standard of review.   This court may
    set aside or modify an agency's decision if it violates the
    Constitution, is in excess of the statutory authority or
    jurisdiction of the agency, is based upon an error of law, is
    made upon unlawful procedure, is unsupported by substantial
    evidence, is unwarranted by the facts found on the record as
    submitted, or is arbitrary and capricious, an abuse of
    discretion, or otherwise not in accordance with the law.     G. L.
    c. 30A, § 14 (7).
    To enable this court to carry out its judicial review
    function, the agency must provide adequate subsidiary findings
    and reasoning to support its decision:    although the agency may
    "evaluate evidence in light of its expertise, it cannot simply
    15
    use its expertise as a substitute for evidence in the record"
    (citation omitted).     Fitchburg Gas & Elec. Light Co. v.
    Department of Pub. Utils., 
    460 Mass. 800
    , 812 (2011).
    Nevertheless, the agency decision is supported by substantial
    evidence so long as the record contains "such evidence as a
    reasonable mind might accept as adequate to support a
    conclusion."   
    Id.,
     quoting G. L. c. 30A, § 1 (6).    See G. L.
    c. 30A, § 11 (5) ("Agencies may utilize their experience,
    technical competence, and specialized knowledge in the
    evaluation of the evidence presented to them").
    When reviewing an administrative decision, "we must
    apply all rational presumptions in favor of the validity of the
    administrative action and not declare it void unless its
    provisions cannot by any reasonable construction be interpreted
    in harmony with the legislative mandate."     New England Power
    Generators Ass'n, Inc. v. Department of Envtl. Protection, 
    480 Mass. 398
    , 408 (2018), quoting Consolidated Cigar Corp. v.
    Department of Pub. Health, 
    372 Mass. 844
    , 855 (1977).        In
    analyzing the legislative mandate, we first determine whether
    the Legislature has spoken with certainty on the topic in
    question by using conventional tools of statutory
    interpretation.   New England Power Generators Ass'n, Inc., supra
    at 404.   If the statute is unambiguous, we give effect to the
    Legislature's intent.    Id.   "[I]f the Legislature has not
    16
    addressed directly the pertinent issue, we determine whether the
    agency's resolution of that issue may 'be reconciled with
    the governing legislation.'"   Id., quoting Goldberg v. Board of
    Health of Granby, 
    444 Mass. 627
    , 633 (2005).    In making this
    determination, "we afford 'substantial deference' to agency
    expertise," and will uphold the agency decision "unless a
    statute unambiguously bars the agency's approach."    New England
    Power Generators Ass'n, Inc., supra at 405, quoting Goldberg,
    supra.
    b.   Firm service.   The first issue is whether the PPAs
    include provisions that contradict Section 83D's "firm service"
    requirement.   The petitioner argues that they do, pointing to
    certain clauses in the PPAs that, under the petitioner's
    reading, permit HQUS to interrupt service.     Specifically, it
    points to (1) the contract provision allowing HQUS to cure
    delivery shortfalls; (2) the provision relating to cover
    damages; and (3) the provision allowing HQUS to decline to sell
    electricity during negative LMP periods.     The department and the
    interveners counter that these provisions are necessary to deal
    with unforeseen shortfalls and other developments beyond its
    control, and that including these clauses in the PPAs is
    therefore consistent with the purpose of St. 2016, c. 188.        We
    agree with the interpretation of the department and the
    interveners.
    17
    In reaching this conclusion, we emphasize that an
    interpretation of firm service without interruption to require
    no interruptions whatsoever, even if those interruptions are
    outside the parties' control, would amount to an otherworldly,
    unrealistic interpretation of the statute.    See Wallace W. v.
    Commonwealth, 
    482 Mass. 789
    , 793 (2019).     These are twenty-year
    contracts; some interruptions over twenty years are unavoidable.
    Further, the contingencies in place are reasonable, reflecting
    industry practices and practical realities, including the need
    to provide electricity during periods of inevitable interruption
    and strong disincentives against noncompliance or gamesmanship.
    At issue is the meaning of the phrase "without
    interruption" in Section 83B's definition of firm service.      We
    begin by recognizing that this court gives "great deference" to
    the department's expertise in cases involving "interpretation of
    a complex statutory and regulatory framework."    Alliance to
    Protect Nantucket Sound, Inc. v. Department of Pub. Utils., 
    461 Mass. 166
    , 178 (2011), quoting Cambridge v. Department of
    Telecomm. & Energy, 
    449 Mass. 868
    , 875 (2007).    We must also be
    "careful to 'avoid any construction of statutory language which
    leads to an absurd result, or that otherwise would frustrate the
    Legislature's intent.'"   Wallace W., 482 Mass. at 793, quoting
    Bellalta v. Zoning Bd. of Appeals of Brookline, 
    481 Mass. 372
    ,
    378 (2019).
    18
    While Section 83B defines "firm service," it does not
    define "without interruption."    Here, the department drew on its
    specialized expertise when it explained that, "[g]iven the
    nature of electricity transmission, delivery shortfalls will
    occasionally happen," and as a result, "any long-term contract
    for renewable energy generation requires reasonable provisions
    to address them."   In essence, the department has interpreted
    "without interruption" to mean that energy must have guaranteed
    availability to the maximum extent feasible, with contingencies
    in place to minimize the impact of unavoidable disruptions, as
    opposed to reading the phrase literally to mean without any
    interruption whatsoever for any reason at all, even if outside
    of the parties' control.     The department's interpretation is a
    commonsense reading of the statute:    the real world is
    unpredictable, especially over twenty years, and this court
    properly defers to the department's view that at least some
    shortfalls are inevitable.     "Firm service" (or "firm power") is
    a common term in the energy industry and among regulators:     the
    United States Court of Appeals for the District of Columbia
    Circuit has explained that "[f]irm service is contractually
    guaranteed; non-firm service is scheduled on an 'as available'
    basis and is subject to interruption."     Sacramento Mun. Utils.
    Dist. v. Federal Energy Regulatory Comm'n, 
    428 F.3d 294
    , 295 n.3
    (D.C. Cir. 2005).   See North Star Steel Co. v. United States, 58
    
    19 Fed. Cl. 720
    , 723 n.2 (2003) (firm service means power that is
    guaranteed to always be available, while non-firm service may be
    interrupted for any reason at any time).
    In contrast, it would be absurd, or at least unrealistic,
    to force clean energy providers to guarantee that their service
    will never be interrupted for any reason:    even the petitioner
    acknowledges that "occasional delivery shortfalls may occur in a
    force majeure context."14   Thus, all the parties understand that
    a literal interpretation of "without interruption" is
    inappropriate.
    The question then becomes whether the particular
    contingencies provided in the PPAs to deal with potential
    interruptions facilitate the firm service requirement rather
    than frustrate it.    We examine each in turn.
    i.    Cure of delivery shortfalls.   In ruling that the
    delivery shortfall provisions of the PPAs were consistent with
    Section 83D's firm service requirement, the department focused
    on the fact that the events triggering this clause are outages
    and reductions in transmission capacity outside the parties'
    control.   The department also cited several contract provisions
    that minimize opportunities for HQUS or the companies to profit
    14Force majeure is defined in section 10.1 of the PPAs, and
    includes (among other circumstances) mechanical or equipment
    breakdown caused by hurricanes, floods, blizzards, terrorism,
    and the like.
    20
    from interrupting delivery of electricity through use of the
    shortfall delivery clause.    For example, the PPAs require any
    shortfall deliveries to be made "in the same Contract Year in
    which the Curable Delivery Shortfall occurred or in the
    immediately succeeding contract year," and any shortfall
    occurring in a winter or summer month may only be cured by a
    shortfall delivery in another winter or summer month,
    respectively.15   The PPAs also provide a formula for reconciling
    price differences in the electricity that was supposed to be
    delivered and the electricity that was actually delivered,
    meaning that any profits that could be made through an
    opportunistic breach of the PPAs are likely to be reallocated.
    Together with the exclusivity provision, which bars HQUS
    from selling energy guaranteed to the companies under the PPAs
    to a third party, these requirements restrict the ability of any
    party to the PPAs to take advantage of seasonal or time-of-day
    price differences.     This comports with the department's
    interpretation of the firm service requirement.     The PPAs
    therefore do not contradict the requirement; nor do they create
    a "right" for HQUS to interrupt delivery in any period, as the
    petitioner contends.
    15The PPAs further specify that shortfall energy that was
    to be delivered between 8 A.M. and 11 P.M. must be delivered
    during this same time frame in such a winter or summer month.
    21
    ii.   Cover damages.    Provisions in the PPAs governing cover
    damages also do not permit HQUS to simply not deliver energy and
    pay damages instead, as the petitioner argues.   On the contrary,
    the cover damages clauses provide incentive for HQUS to fulfill
    its firm service requirements and to cure any delivery
    shortfalls.   They are typical of long-term contracts like the
    ones before us, as experts for the companies testified in the
    departmental proceedings.
    Cover damages are triggered by shortfalls outside HQUS's
    control, such as those caused by a physical condition of the
    transmission line.   As the department found in its order, cover
    damages help make the companies whole, and also minimize
    situations in which the companies are in a position where they
    need to purchase power elsewhere.   Cover damages are also not
    only compensatory:   they include penalties.   Thus, even if HQUS
    could theoretically charge a higher price for its energy
    elsewhere, this benefit could be financially outweighed by
    having to pay penalties to the companies on top of the value of
    the electricity HQUS was to deliver.   And as with the shortfall
    delivery clause, this portion of the contract must be understood
    in light of the exclusivity portions of the PPAs, which restrict
    HQUS from selling its hydroelectric generation to other buyers.
    The cover damages provisions thus create a favorable
    economic outcome for the companies, as HQUS is financially
    22
    responsible for any favorable price differences resulting from
    the shortfall and any later make-up delivery.   It is therefore
    unrealistic to assume that HQUS would first commit a breach of
    the agreement by selling the power guaranteed the companies
    elsewhere, charge a higher price to the third-party buyer, and
    still make a profit after both compensating the companies and
    paying them penalties.16   Instead, we conclude that the cover
    damages provisions in the PPAs further guarantee firm service by
    providing a strong incentive for HQUS to deliver energy and
    fulfill firm service requirements.
    The petitioner also argues that section 9.2(f) of the PPAs
    -- which it claims allows for interruptions of up to twenty
    percent of the annually contracted-for energy delivery -- goes
    beyond the occasional outage to which the department referred in
    its order, and cannot comport with the firm service requirement.
    The petitioner contends that the department does not support its
    conclusion that this provision addresses only what the
    department calls "occasional outages" with adequate subsidiary
    findings.
    16Moreover, it is not the role of this court to read a
    contract under the assumption that the parties will shirk their
    respective obligations. See Rigs v. Sokol, 
    318 Mass. 337
    , 343
    (1945) (court's assumption in interpreting contracts is that
    parties ordinarily contemplate contract will be performed and
    provisions for penalties are "intended as security for
    performance and not as a price for the privilege of
    nonperformance").
    23
    The petitioner's interpretation of section 9.2(f) of the
    PPAs is misguided.   The petitioner argues that this provision
    allows for interruption of service for twenty percent of every
    contract year -- i.e., seventy-three days a year for the twenty-
    year term of the PPAs -- so long as HQUS remedies the
    interruption by way of cover damages.   This interpretation reads
    this clause in isolation, ignoring all of the other provisions
    requiring compliance and penalizing noncompliance.   The
    petitioner's interpretation of section 9.2(f) denies the reality
    that HQUS reaps no benefit from having to pay cover damages
    under the agreements, as discussed supra.   The twenty percent
    figure does not identify a target performance measure, but a
    figure identifying a contractual default, triggering all kinds
    of other consequences, including those related to financing.17
    We therefore reject the petitioner's arguments and conclude
    that these provisions are in line with Section 83D's firm
    service requirement.
    17As the department states in its order, "Section 83D
    requires an electric distribution company to demonstrate that
    any proposed long-term contract will facilitate the financing of
    the clean energy generation resource. To satisfy this
    requirement, an electric distribution company need not
    demonstrate that the long-term contract is necessary to secure
    project financing, only that it will assist in securing project
    financing," citing NSTAR Elec. Co., D.P.U. 12-30, at 40 (Nov.
    26, 2012); Massachusetts Elec. Co. & Nantucket Elec. Co., D.P.U.
    10-54, at 52-53 (Nov. 22, 2010).
    24
    iii.   Negative LMP periods.    Finally, the PPA provisions
    allowing HQUS to forgo delivery during negative LMP periods do
    not interfere with or contradict Section 83D's firm service
    requirement.    That is because additional electricity
    transmission would not benefit either party during negative LMP
    periods.
    LMP methodology is "used by electricity market operators
    across the country."     Black Oak Energy, LLC v. Federal Energy
    Regulatory Comm'n, 
    725 F.3d 230
    , 233 (D.C. Cir. 2013).    LMP is a
    way to price a given unit of electricity at a particular time
    and location.    "Under LMP, the price any given buyer pays for
    electricity reflects a collection of costs attendant to moving a
    [unit] of electricity through the system to a buyer's specific
    location on the grid."    
    Id.
     at 233–234.   See Sacramento Mun.
    Util. Dist. v. Federal Energy Regulatory Comm'n, 
    616 F.3d 520
    ,
    524 (D.C. Cir. 2010) ("With an LMP-based rate structure, prices
    are designed to reflect the least-cost of meeting an incremental
    [unit of demand for energy] at each location on the grid, and
    thus prices vary based on location and time").     "The cost of
    generation can be thought of as the 'baseline cost' of serving
    electricity (known in the industry as 'load') to another
    location on the system in a hypothetical, congestion-free
    environment.    Congestion, in turn, drives up costs because it
    requires [electricity providers] to dispatch more expensive
    25
    generators to meet demand.    The cost of congestion results in
    different prices at different nodes of the system, depending on
    how congested the wires leading to those nodes are" (citations
    omitted).   Black Oak Energy, LLC, supra at 234.
    The PPAs specify that, if "the LMP at the Delivery Point is
    negative, or, in the reasonable opinion of [HQUS], is likely to
    become negative, then [HQUS] . . . shall be under no obligation
    to schedule or transfer Deliveries of Qualified Clean Energy to
    the Delivery Point during such period."    Alternatively, Exhibit
    D of the PPAs allows the companies to take a credit against the
    contract price for negative LMP periods.     Given that LMP
    measures the value of an additional unit of electricity at a
    particular time and location, a negative LMP period is one in
    which this value is negative.    In other words, at the relevant
    time and location, the supply of energy exceeds the demand for
    it, and there is a surplus.     In such a scenario, it would be
    wasteful to deliver additional hydroelectric generation.      The
    negative LMP provisions therefore comport with Section 83D's
    requirement that contracts procured be "cost-effective," Section
    83D (d) (5) (iii); see 220 Code Mass. Regs. § 24.03(1), and
    provide a form of price protection for the companies and -- by
    extension -- ratepayers in the Commonwealth.18
    18We disagree with the petitioner's argument that the
    department was required to make some subsidiary finding
    26
    Beyond the fact that such delivery would be cost-
    ineffective, it would also not serve the Legislature's purpose
    in enacting Section 83D.   It was not the purpose of the
    Legislature to require generation of hydroelectric energy for
    its own sake; instead, the purpose was to generate clean
    electricity that meets the energy demands of the Commonwealth,
    thus reducing greenhouse gas emissions and achieving other
    environmental goals.   See St. 2008, c. 169, preamble; Kain, 474
    Mass. at 281-282.   Delivering energy during negative LMP periods
    serves neither the Commonwealth's energy needs nor the
    environmental purposes promoted by Section 83D.
    None of the provisions cited by the petitioner and
    discussed supra permits unilateral interruptions.   They are
    instead aimed at maintaining cost-effectiveness and making the
    companies and their customers financially whole in case of
    interrupted service.   We therefore conclude that the
    department's interpretation of Section 83D's firm service
    requirement was reasonable, and that interpretation was
    regarding its conclusion that delivery of energy in these
    periods would be wasteful. The concept of negative LMP periods
    speaks for itself, and the department's commonsensical
    conclusion is one that is reflected in other PPAs and the rules
    of system operators. See Barton Windpower, LLC, U.S. Dist. Ct.,
    No. 13-CV-5329 (N.D. Ill. June 18, 2018) (explaining custom when
    LMP is negative for market participants to stop generating power
    or to continue to generate power and sell it to system
    operator).
    27
    correctly applied to the PPAs in this case.19   The department's
    conclusions were supported by substantial evidence, adequate
    findings, and sufficient rationale.
    c.   Hydroelectric generation alone.   The next issue is
    whether the department's finding that the PPAs provide the
    delivery of energy produced through hydroelectric generation
    alone was supported by substantial evidence, adequate subsidiary
    findings, and sufficient rationale.   We conclude that it was.
    The record contains "substantial evidence" supporting the
    department's finding that the PPAs provide for hydroelectric
    generation "alone."   For example, the PPAs provide that HQUS is
    "solely responsible" for demonstrating that "the Hydro-Québec
    Power Resources from which the Products are Delivered are
    Qualified Clean Energy Generation Units."   The "Hydro-Québec
    Power Resources" are the sixty-two specified hydroelectric
    19We similarly reject the petitioner's argument that the
    PPAs do not identify one or more discrete periods in which HQUS
    is to deliver firm service. To the extent discrete periods are
    meant to be limited to temporal periods other than the entire
    contractual term, as the petitioner claims, each of the PPAs
    provides a monthly schedule for the entire twenty-year life of
    the agreements that surely meets this requirement. The
    department made such a finding in its order. Additionally,
    provisions in the PPAs requiring HQUS to cure delivery
    shortfalls within a defined shortfall cure period do not invite
    interruptions by allowing HQUS to "defer cure anywhere from
    [twelve] months and [one] day up to a maximum of [twenty-three]
    months and [twenty-nine] days," as the petitioner claims, but
    instead provide a remedy for the inevitable occurrence of
    interrupted service.
    28
    generating stations; "Qualified Clean Energy Generation Units"
    are electricity generating facilities "capable of producing
    Qualified Clean Energy, or Qualified Shortfall Energy"; and both
    "Qualified Clean Energy" and "Qualified Shortfall Energy" are
    defined as energy produced by the "Hydro-Québec Power Resources"
    and tracked by the NEPOOL GIS "to ensure unit-specific
    accounting" of the delivery of hydroelectric energy.    The PPAs
    thus unambiguously require HQUS to make available to the
    companies generation capacity from hydroelectric facilities, and
    to continuously verify this generation through a tracking system
    (NEPOOL GIS).   The PPAs also excuse the companies from accepting
    or paying for any certificate from HQUS that does not evince
    generation from the specified hydroelectric sources.    Beyond
    such contractual clauses, the department also made an undisputed
    subsidiary finding that HQUS's hydroelectric generation
    facilities have adequate capacity to provide the statutorily
    mandated 9.45 million MWh of purely hydroelectric generation.
    The petitioner argues nonetheless that the department's
    reliance on the language of the PPAs and the use of NEPOOL GIS
    tracking was insufficient.   Instead, the petitioner claims that
    the department was required to make a finding that, "under the
    laws of physics," energy delivered by HQUS and flowing through
    the transmission line comes solely from hydroelectric
    generation.   The department rejects the contention that it was
    29
    required to "predict whether HQUS might breach its contractual
    obligation in the future, or expound on 'the laws of physics.'"
    Instead, the department's position is that it was sufficient
    that the PPAs contractually required HQUS to deliver only
    hydroelectrically generated energy.     The department explains
    that this is the "only analysis that it reasonably could
    conduct," because once electricity enters the New England power
    grid, it is impossible to distinguish the source of any given
    unit of energy, unless there is a dedicated power line for a
    given source of electricity.   No such dedicated power line was
    required by the relevant statute or regulations.     Again, we
    conclude that the department's interpretation of the statutory
    and regulatory requirements is reasonable and supported by the
    evidence.
    Although framed by the petitioner as a question about the
    laws of physics or the sufficiency of the evidence, the issue
    whether the PPAs provide for hydroelectric generation "alone" is
    necessarily linked to a question of statutory construction,
    namely, what it means for electricity to come from
    "hydroelectric generation alone."     Under Section 83D, the
    companies were required to enter into "long-term contracts" to
    purchase "hydroelectric generation" deriving "from hydroelectric
    generation alone."   Sections 83B, 83D (a).    See 220 Code Mass.
    Regs. §§ 24.02, 24.03(1).   If the use of the word "alone" is
    30
    important, then the use of the word "generation" -- as opposed
    to "transmission" -- is no less significant.   Both terms clearly
    support the department's interpretation of the statutory and
    regulatory requirements.
    Fortunately (for this court), the laws of physics are not
    in dispute.   Nor is there any inconsistency between the laws of
    physics and the contractual requirements. See Northern Ind. Pub.
    Serv. Co. v. Federal Energy Regulatory Comm'n, 
    954 F.2d 736
    , 737
    (D.C. Cir. 1992) ("When electricity reaches an intersection of
    several alternative transmission paths, it will flow
    along . . . guided by the laws of physics rather than the
    intention of [contractual] parties . . .").    The petitioner and
    the department essentially agree on the physics involved in
    transmitting electricity from Canada to Maine for distribution
    in Massachusetts.
    The department analogizes the physics involved as follows:
    "It is like [forty] people pouring water into an Olympic
    swimming pool.   Someone later drawing water from the pool cannot
    distinguish between the molecules contributed by each person.
    Not surprisingly, the association of market participants in the
    electric grid that helps guide matters affecting the system
    calls itself the New England Power Pool (NEPOOL)."   In the
    Olympic pool analogy, one can identify the individual sources of
    water that are poured into the pool, and can therefore measure
    31
    what each person is contributing to the pool.   One cannot,
    however, trace water that is already in the pool to a particular
    contributor.
    In this vein, the department's order focuses on the fact
    that the PPAs require the generation of the purchased
    electricity to occur at sixty-two specified hydroelectric
    sources.   So long as this generation can be verified and the
    amount that is generated is received by the companies, the
    department does not understand the statute to require that the
    delivery system for this electricity (i.e., the transmission
    lines) be exclusive of other sources.   This is a reasonable
    reading of the phrase "hydroelectric generation alone" (emphasis
    added), particularly in light of the physics involved.    It is
    also unclear why imposing the requirement of a dedicated
    transmission line for hydroelectric generation would serve the
    Legislature's purpose in enacting Section 83D if the fact of
    hydroelectric generation can be verified in other ways,
    particularly given the additional cost and environmental harm
    caused by developing such a line.   Such a requirement is absent
    from the language of Sections 83B and 83D, which refer only to
    hydroelectric generation.20
    20The petitioner argues that without ensuring that the
    transmitted energy is from hydroelectric generation only, the
    Commonwealth would be paying for clean energy that is being used
    elsewhere. However, that is a fiction so long as the
    32
    In sum, the department's construction of the statute and
    the regulations is reasonable and supported by the evidence.      It
    serves the environmental purposes promoted by the act, and is
    consistent with the "laws of physics."
    d.   NEPOOL GIS tracking system.     As discussed supra,
    Section 83D (j) requires PPAs to "utilize an appropriate
    tracking system to ensure a unit specific accounting of the
    delivery of clean energy" to accurately measure progress in
    achieving the Commonwealth's environmental goals.    The purpose
    of Section 83D's tracking requirement is to allow DEP, in
    consultation with DOER, to "accurately measure progress in
    achieving the commonwealth's [emissions-related] goals."
    Section 83D (j).   The NEPOOL GIS tracking system employed in the
    instant case is the industry standard developed for such
    measurement.   It has been developed by regulators, and it has
    been universally accepted by the industry just for such purpose.
    See, e.g., Ferrey, Threading the Constitutional Needle with
    Care:   The Commerce Clause Threat to the New Infrastructure of
    Renewable Power, 7 Tex. J. Oil Gas & Energy L. 59, 62-63 (2011)
    (Ferrey) (explaining how tracking systems for renewable energy
    Commonwealth is paying for what is being generated, what is
    being generated is actually clean energy, and the Commonwealth
    maintains ownership of the environmental attributes associated
    with that energy. See Jones, 28 Fordham Envtl. L. Rev. at 206-
    207.
    33
    certificates are essential to success of -- and operation of --
    renewable portfolio standard [RPS] programs); 
    N.H. Rev. Stat. Ann. § 362
    -F:6 (2014) (mandating electric RPS program to use
    NEPOOL GIS certificate tracking).
    The department provided a relatively short yet sufficient
    explanation of its finding that use of the NEPOOL GIS is
    consistent with Section 83D (j).    The department concluded that
    the use of NEPOOL GIS is "well-established" and that the PPAs
    require HQUS to utilize it "in compliance with all relevant
    NEPOOL GIS operating rules."   The department was entitled to
    draw on its expertise to conclude that the NEPOOL GIS is an
    appropriate tracking system under Section 83D (j).   See New
    England Power Generators Ass'n, Inc. 480 Mass. at 405; Goldberg,
    444 Mass. at 635.   The department's expertise in this arena
    includes knowledge and experience specific to the NEPOOL GIS
    itself, as the department (formerly the Department of
    Telecommunications and Energy Resources) participated in the
    development of NEPOOL GIS's operating rules.   See New England
    Generation Info. Sys., D.T.E. 03-62-A, at 9, 24 n.14 (2004).
    Indeed, the department's role in developing the NEPOOL GIS
    operating rules was to ensure the NEPOOL GIS's efficacy as an
    emissions labeling tool in accordance with the emissions
    labeling statute that the department is charged with
    administering.   See id. at 1; 220 Code Mass. Regs. § 11.06
    34
    (2016).    These operating rules include rules relating to the use
    of certificates for unit-specific tracking of how electricity is
    generated as well as rules for coordinating with the department
    and DEP.   See New England Power Pool Generation System Operating
    Rules, Rule 2.1(a) & Appendix 5.3 (Jan. 1, 2020).    See also
    Alliance to Protect Nantucket Sound, Inc., 461 Mass. at 178
    (describing "great deference" owed to department's expertise in
    cases involving "interpretation of a complex statutory and
    regulatory framework").
    The department also concluded that the PPAs provide
    sufficient protections to ensure adequate tracking of energy
    attributes.   The PPAs define "Certificate" as "an electronic
    certificate generated pursuant to the [NEPOOL] GIS Operating
    Rules . . .   to represent certain generation attributes of each
    [unit of electricity] generated."    The PPAs require HQUS to
    "transfer to [the companies] all of the right, title[,] and
    interest in and to . . . any and all Certificates[] associated
    with Qualified Clean Energy or any Qualified Shortfall Energy."
    Further, as discussed supra, the PPAs require HQUS to "comply
    with all [NEPOOL] GIS Operating Rules including, without
    limitation, such rules relating to the creation, tracking,
    recording and transfer of all Environmental Attributes
    associated with Qualified Clean Energy or Qualified Shortfall
    Energy" purchased under the agreements, where "Environmental
    35
    Attributes" is a defined term that refers to "any Certificates
    issued pursuant to the [NEPOOL] GIS in connection with Energy
    generated by [HQUS's hydroelectric generating systems]."
    The record provides additional support for the department's
    finding.   Specifically, in September 2018, upon request from the
    companies pursuant to 310 Code Mass. Regs. § 2.09 (2004), DEP
    issued an advisory ruling, concluding that NEPOOL GIS tracking
    of energy units and attributes satisfies Section 83D (j)'s
    requirements.   This ruling was in the record before the
    department.   While such rulings are not binding, Massachusetts
    courts give them deference when they relate to a statute that
    the agency is charged with interpreting and applying, and so
    long as they are consistent with the text and purpose of that
    statute.   See Brookline v. Medical Area Serv. Corp., 
    8 Mass. App. Ct. 243
    , 258–259 (1979).   Cf. Sullivan v. Sleepy's LLC, 
    482 Mass. 227
    , 232 n.11 (2019).   It is particularly appropriate to
    give weight to DEP's advisory ruling approving of the use of the
    NEPOOL GIS, as the stated purpose of Section 83D (j)'s tracking
    requirement is to allow DEP to monitor the Commonwealth's
    progress in reducing greenhouse gas emissions.
    A contrary conclusion -- that NEPOOL GIS is not an
    appropriate tracking system for these PPAs -- flies in the face
    of industry practice relying on tracking systems to comply with
    36
    RPS programs.   See New England Generation Info. Sys., D.T.E. 03-
    62-A, at 5-9; Ferrey, 7 Tex. J. Oil Gas & Energy L. at 62-63.
    NEPOOL GIS not only issues and tracks certificates for all
    MWh of generation and load produced in the control area of the
    Independent System Operator for New England (ISO-New England),
    as well as imported MWh from adjacent control areas, but
    provides emissions labeling for the New England load serving
    entities by tracking the emissions attributes for the region's
    generators.   Market participants in New England commonly use and
    rely on NEPOOL GIS to track clean energy generation and its
    associated environmental attributes, and have long done so.21
    Market participants also use NEPOOL GIS to trade renewable
    energy credits, which are vital to enforcing RPS programs.     See
    Ferrey, 7 Tex. J. Oil Gas & Energy L. at 62-63; Jones, 28
    Fordham Envtl. L. Rev. at 216-217 & n.8.
    The NEPOOL GIS tracking system is not just the industry
    standard, but the only mechanism recognized as sufficient to
    identify supplier-specific labeling information for identifying
    resources.    See Massachusetts Elec. Co. & Nantucket Elec. Co.,
    D.P.U. 08-51, at 2 & n.7 (June 13, 2013).    Concluding that
    21DOER relies on NEPOOL GIS to track the Commonwealth's
    renewable energy portfolio standards. 225 Code Mass. Regs.
    § 14.09 (2016); 225 Code Mass. Regs. § 15.09 (2014); 225 Code
    Mass. Regs. § 16.09 (2019). DEP similarly relies on NEPOOL GIS
    to monitor compliance with its clean energy standard. 310 Code
    Mass. Regs. § 7.75 (2020).
    37
    NEPOOL GIS's tracking system does not satisfy Section 83D's
    requirements would require the creation of an entirely new
    system, which is both impractical and incompatible with the
    Commonwealth's goals to advance renewable energy.22
    Because the department's conclusions were supported by
    substantial evidence, and the department relied on its expertise
    and knowledge of the NEPOOL GIS system to conclude that the
    system's tracking mechanism was adequate to "ensure that the
    Companies purchase clean energy generation as defined by
    statute, and not system energy that contains non-clean energy
    generation," we affirm the department's decision.
    3.   Conclusion.   The department applied a reasonable
    interpretation of Section 83D's firm service requirement,
    concluding that the words "without interruption" must
    accommodate the reality of inevitable outages, even while
    delivery of energy must be guaranteed to the maximum extent
    22Any argument that NEPOOL GIS does not physically track
    the energy HQUS will deliver back to the hydroelectric
    generation station is a repeat of the argument addressed supra,
    i.e., that the PPAs do not adequately ensure that HQUS will
    generate and deliver hydroelectric power alone. The
    petitioner's arguments seem to misunderstand how the tracking
    system works: NEPOOL GIS tracks the attributes associated with
    the energy HQUS delivers into the system, while the meters at
    the delivery point measure the quantity of energy. Requiring
    more, i.e., that the parties ascertain the attributes of the
    energy already in the transmission line, or construct a new
    transmission line devoted solely to energy generated by HQUS, is
    at worst an exercise in futility and at best unnecessary and
    cost-ineffective.
    38
    possible.   The provisions allowing HQUS to cure delivery
    shortfalls, pay cover damages for uncured shortfalls, and forgo
    delivery during negative LMP periods all comply with this
    reasonable interpretation of the statute.   The department's
    conclusion in this regard, as well as its conclusions that the
    PPAs provide for the procurement of energy from hydroelectric
    generation alone and that the NEPOOL GIS tracking system is an
    appropriate system to meet Section 83D's requirements, were
    supported by substantial evidence, adequate findings, and
    sufficient rationale.   We therefore affirm the department's
    approvals of the PPAs pursuant to Section 83D.
    So ordered.